N0010419RF004_-_Exhibit_A_CDRLs.pdf
PDF 535 KB Posted
- Attached to
- Basic Ordering Agreement for Propulsion Shafts Federal contract opportunity
- Solicitation number
- N0010419RF004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N0010419RF004.U0002.pdf | ||
| N0010419RF004_-_Attachment_1.docx | DOCX document | |
| N0010419RF004.U0001.pdf | ||
| N0010419RF004.pdf | ||
| N0010419RF004_-_Exhibit_B_NIIN_List.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
TDP X TM OTHER
D. SYSTEM/ITEM
ITEM INSPECTION AND REPAIR
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
CONTRACTOR’S PROGRESS, STATUS AND MANAGEMENT REPORT
3. SUBTITLE
N/A
17. PRICE GROUP
4. Authority (DATA Acquisition document No.)
DI-MGMT-80227
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NAVSUP WSS N743 (N00104)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
B
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
LT MTHLY 30DAC
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
N/A Draft Final
A N/A Reg Repro
16. REMARKS ELECTRONIC
COPY
BLOCK 4: IN LIEU OF THE PREPARATION REQUIREMENTS SPECIFIED IN
DI-MGMT-80227, UTILIZE THE FOLLOWING FORMAT. THE REPORT
SHALL BE PROVIDED ELECTRONICALLY IN MICROSOFT EXCEL, 2003
VERSION. THE REPORT FORMAT AND INSTRUCTIONS ARE AVAILABLE
ELECTRONICALLY FROM NAVICP OR AT http://www.dcma.mil/npp/. THE
STATUS REPORT SHALL BE SUBMITTED ELECTRONICALLY VIA
ELECTRONIC MAIL ON A MONTHLY BASIS. THE REPORT SHALL
CONTAIN STATUS BASED ON THE FIRST WORKING DAY OF THE
MONTH REPORTED. ITEMS SHIPPED SHALL REMAIN ON THE REPORT
FOR ONE ADDITIONAL MONTH AND THEN DELETED.
BLOCK 10: STATUS REPORT SHALL BE SUBMITTED MONTHLY BY THE
FIFTH WORKING DAY OF EACH MONTH BY ELECTRONIC MAIL.
BLOCK 12: THE FIRST SUBMISSION SHALL BE WITHIN 30 DAYS OF
CONTRACT AWARD.
BLOCK 13: SUBSEQUENT SUBMISSIONS SHALL BE SUBMITTED
MONTHLY BY THE FIFTH WORKING DAY OF EACH MONTH.
BLOCK 14: DISTRIBUTION SHALL BE MADE BY ELECTRONIC MAIL.
ADDRESSES FOR REPORT DISTRIBUTION SHALL BE OBTAINED FROM
NAVSUP WSS N743.
DCMA ACO 0 1 0
DCMA QAR 0 1 0
NAVSUP WSS
N743
0 1 0
NSWCPD 423 0 1 0
NSWCPD 427 0 1 0
NAVSUP WSS
END ITEM
MANAGERS
0 1 0
15. TOTAL 00 06 00
G. PREPARED BY
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
J. DATE
07 FEB 2017
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page 1_ of 14_ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
B. EXHIBIT
A
A002
2. TITLE OF DATA ITEM
INSPECTION SYSTEM PROGRAM AND TEST PLAN
3. SUBTITLE
DI-QCIC-81110
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
B
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SS ONE/R 60 DAC
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
ASREQ Draft Final
A N/A Reg Repro
BLOCK 4: PLAN SHALL INCLUDE THE CONTRACTOR’S QUALITY
SYSTEM PROCEDURES THAT MEET THE REQUIREMENTS OF ASQ-
9002.
ADDITIONALLY THE CONTRACTOR SHALL SUBMIT INSPECTION AND
TEST PROCEDURES FOR THE INSPECTION AND TESTING OF
PROPULSION SHAFT PLUG OR RING GAGES, OTHER INSPECTION
FIXTURES OR TOOLS, JIGS AND OTHER SHAFT RELATED ITEMS IN
ACCORDANCE WITH CONTRACT REQUIREMENTS.
BLOCK 8: APPROVAL WILL BE BASED ON COMPLIANCE WITH
CONTRACT SPECIFICATIONS. GOVERNMENT REQUIRES 45 DAYS
REVIEW TIME.
BLOCK 12: DRAFT COPY SHALL BE SUBMITTED FOR GOVERNMENT
REVIEW NO LATER THAN 60 DAYS AFTER BOA AWARD. FINAL
APPROVAL COPY INCORPORATING ANY GOVERNMENT REVIEW
COMMENTS SHALL BE SUBMITTED 30 DAYS AFTER RECEIPT OF
GOVERNMENT REVIEW COMMENTS.
BLOCK 13: SUBSEQUENT SUBMISSION TO BE SUBMITTED WITHIN 30
DAYS UPON DEVELOPMENT OR REVISION OF THE QUALITY SYSTEM
MANUAL OR INSPECTION AND TEST PROCEDURES OR AFTER
NOTIFICATION BY THE GOVERNMENT THAT A NEED FOR A REVISION
IS REQUIRED. THIS CDRL DOES NOT NEED TO BE SUBMITTED FOR
EACH DELIVERY ORDER.
THE CONTRACTOR SHALL DOCUMENTATION IN ADOBE ACROBAT,
VERSION 7.0 OR LATER IN WAWF.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE
FOLLOWING DODAACS:
INSPECT BY : S4306A
SHIP TO: N64498
ACCEPT BY: S4306A
DCMA QAR 1 1 0
NSWCPD 427 0 1 0
NSWCPD 423 0 1 0
15. TOTAL 01 03 00
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page _ of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
B. EXHIBIT
A
A003
2. TITLE OF DATA ITEM
WELD PROCEDURES AND QUALIFICATION TEST REPORT
3. SUBTITLE
DI-MISC-80876
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
B
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SS ONE/R 60DAC
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
ASREQ Draft Final
A N/A Reg Repro
BLOCK 4: SUBMIT COPIES OF ALL APPROVED WELDING PROCEDURE
QUALIFICIATION TEST REPORTS OR ASSOCIATED APPROVAL
LETTERS, AND APPLICABLE QUALIFIED WELDING PROCEDURES
NECESSARY TO PERFORM PRODUCTION WELDING.
BLOCK 8: APPROVAL WILL BE BASED ON COMPLIANCE WITH
CONTRACT SPECIFICATIONS. GOVERNMENT REQUIRES 45 DAYS
REVIEW TIME.
BLOCK 12: DRAFT COPY SHALL BE SUBMITTED FOR GOVERNMENT
REVIEW NO LATER THAN 60 DAYS AFTER BOA AWARD. FINAL
APPROVAL COPY INCORPORATING ANY GOVERNMENT REVIEW
COMMENTS SHALL BE SUBMITTED 30 DAYS AFTER RECEIPT OF
GOVERNMENT REVIEW COMMENTS.
BLOCK 13: SUBSEQUENT SUBMISSION TO BE SUBMITTED WITHIN 30
DAYS UPON DEVELOPMENT OR REVISION OF THE QUALITY SYSTEM
MANUAL OR INSPECTION AND TEST PROCEDURES OR AFTER
NOTIFICATION BY THE GOVERNMENT THAT A NEED FOR A REVISION
IS REQUIRED. THIS CDRL DOES NOT NEED TO BE SUBMITTED FOR
EACH DELIVERY ORDER.
THE CONTRACTOR SHALL PROVIDE DOCUMENTATION IN ADOBE
ACROBAT, VERSION 7.0 OR LATER IN WAWF.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE
FOLLOWING DODAACS:
INSPECT BY: S4306A
SHIP TO: N00167
DCMA QAR 1 1 0
NSWCPD 427 0 1 0
15. TOTAL 01 04 00
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
0001, 0002, 0003, 0004, 0006
B. EXHIBIT
A
A004
2. TITLE OF DATA ITEM
REQUEST FOR DEPARTURE FROM SPECIFICATIONS
3. SUBTITLE
DI-CMAN-80640C
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
LT ASREQ ASREQ
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
N/A Draft Final
A N/A Reg Repro
BLOCK 10: THIS DATA ITEM SHALL BE SUBMITTED FOR ALL OUT OF
TOLERANCE CONDITIONS WHETHER PRE-EXISTING OR FOUND AFTER
THE COMMENCEMENT OF WORK. FORMAT AND CONTENT SHALL BE IN
ACCORDANCE WITH MIL-STD-973, APPENDIX "E", SHORT FORM IN LIEU
OF DI-CMAN-80640C.
THE CONTRACTOR SHALL UTILIZE DD FORM 1694 FOR SUBMISSION OF
ALL REQUESTS.
A COPY OF THE SIGNED DEPARTURE SHALL BE INLCUDED IN THE FINAL
REPAIR REPORT (A012) FOR THE ITEM, EVEN IF APPROVAL WAS
PREVIOUSLY GRANTED.
BLOCK 8: APPROVAL WILL BE BASED UPON IMPACT ON ITEM FORM, FIT
OR FUNCTION. GOVERNMENT REQUIRES 30 DAYS (TOTAL) REVIEW
TIME. ALL DEPARTURES SHALL BE FORWARDED TO DCMA QAR FOR
REVIEW AND COMMENT. THE DCMA QAR WILL FORWARD DEPARTURES
WITH COMMENTS ON DD FORM 1998 DIRECTLY TO NSWCPD 427 WITH A
COPY OF THE DEPARTURE TRANSMITIAL TO NAVSUP WSS N743 FOR
REVIEW AND DISPOSITION.
THE CONTRACTOR SHALL PROVIDE A COPY OF THE DEPARTURE IN
ADOBE ACROBAT, VERSION 7.0 OR LATER.
SUPPORTING DATA, SUCH AS DRAWINGS, SKETCHES, PHOTOGRAPHS,
CALCULATION, FINANCIAL ANALYSIS OR OTHER ATTACHMENTS THAT
WILL CLARIFY OR JUSTIFY THE REQUESTS FOR DEPARTURE SHALL BE
INCLUDED.
DCMA QAR 01 01 00
NAVSUP WSS
N743
00 01 00
NSWCPD 427 00 01 00
NSWCPD 423 00 01 00
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
B. EXHIBIT
A
A005
2. TITLE OF DATA ITEM
EQUIPMENT DAMAGE AND REFURBISHMENT REPORT
3. SUBTITLE
VISUAL PRESERVATION INSPECTION
(VPI)
DI-NDTI-80809B
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SS ASREQ SEE BLOCK 16
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
SEE BLOCK 16 Draft Final
A NA Reg Repro
BLOCK 4. USE THE FOLLOWING REQUIREMENT IN LIEU OF THE SPECIFIED
DATA ITEM DESCRIPTION. PRESERVATION, PACKAGING, PACKING, MARKING
AND TRANSPORTATION DEFICIENCIES OF ALL GOVERNMENT FURNISHED
MATERIAL SHALL BE DOCUMENTED ON A SF 364 AND SUBMITTED AND IN
ACCORDANCE WITH SECNAVINST 4355.18A. THE COGNIZANT GOVERNMENT
QUALITY ASSURANCE REPRESENTATIVE (QAR) SHALL VERIFY THE ACCURACY
AND ADEQUACY OF THE REPORT. A COPY OF THE APPROPRIATE VISUAL
PRESERVATION INSPECTION (VPI) REPORT AND PHOTOGRAPHS, WHERE
APPROPRIATE, SHALL BE ATTACHED TO THE SF 364.
FOR PROPULSION SHAFT PLUG AND RING GAGES, A VISUAL PRESERVATION
INSPECTION REPORT, FORM 9243/2 SHALL BE COMPLETED.
FOR PROPULSION SHAFTS, A VISUAL PRESERVATION INSPECTION REPORT,
FORM 9243/5 SHALL BE COMPLETED.
FOR OTHER GOVERNMENT FURNISHED MATERIAL, THE REPORT SHALL BE IN
THE CONTRACTOR’S FORMAT.
BLOCK 12: INTIAL VISUAL PRESERVATION INSPECTION REPORT SHALL BE
SUBMITTED WITHIN 14 DAYS OF RECEIPT OF THE ASSET.
BLOCK 13: FINAL VISUAL PRESERVATION INSPECTION REPORT SHALL BE
SUBMITTED WITHIN 14 DAYS OF COMPLETION OF FINAL PACKAGING PRIOR
TO FINAL DELIVERY. A HARD COPY OF THE FINAL VPI REPORT SHALL BE
SHIPPED WITH THE ASSET FOR FINAL DELIVERY.
BLOCK 8: APPROVAL WILL BE BASED UPON THE ACCURACY, ADEQUACY AND
COMPLIANCE WITH TECHNICAL REQUIREMENTS. ALLOW 10 DAYS FOR
GOVERNMENT REVIEW AND ACCEPTANCE.
THE CONTRACTOR SHALL SUBMIT A COPY OF THE REPORT IN ADOBE
ACROBAT, VERSION 7.0 OR LATER IN WAWF.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE FOLLOWING
DODAACS:
INSPECT BY : S4306A
DCMA QAR 01 01 00
NSWCPD 427 00 01 00
NSWCPD 423 00 01 00
HARD COPY
EQUIPMENT 00 01 00
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
B. EXHIBIT
A
A006
2. TITLE OF DATA ITEM
EQUIPMENT DAMAGE AND REFURBISHMENT REPORT
3. SUBTITLE
PRE-REPAIR INSPECTION REPORT
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD ASREQ SEE BLOCK 16
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
NA Draft Final
A NA Reg Repro
BLOCK 4: THE FOLLOWING REQUIREMENTS SHALL BE FOLLOWED IN
LIEU OF THE SPECIFIED DATA ITEM.
FOR PROPULSION SHAFTS, REPORT FORMAT AND CONTENT SHALL
COMPLY WITH THE REQUIREMENTS OF THE APPLICABLE TECHNICAL
REPAIR STANDARD, NAVSEA S9243-AW-TRS-011/SHAFT AND THE
TECHNICAL DATA PACKAGE.
CHANGES SHALL NOT BE MADE TO THE INSPECTION FORM FORMAT
WITHOUT PRIOR APPROVAL OF NSWCPD 427. ADDITIONAL
INFORMATION AND PHOTOGRAPHS SHALL BE PROVIDED IF REQUIRED.
A WRITTEN DESCRIPTION IN THE CONTRACTOR’S FORMAT OF
RECOMMEDED REPAIRS AND OR ITEMS NOT ANTICIPATED TO BE
REPAIRED WITH APPROPRIATE JUSTIFICATION SHALL BE INCLUDED
WITH THE PRE-REPAIR INSPECTION REPORT.
BLOCK 8: APPROVAL WILL BE BASED UPON THE ACCURACY,
ADEQUACY AND COMPLIANCE WITH TECHNICAL REQUIREMENTS.
ALLOW 45 DAYS FOR GOVERNMENT REVIEW AND APPROVAL.
BLOCK 12: THE PRE-REPAIR INSPECTION REPORT SHALL BE
SUBMITTED WITHIN 90 DAYS OF RECEIPT OF THE ASSET.
THE CONTRACTOR SHALL PROVIDE A COPY OF THE REPORT IN
ADOBE ACROBAT, VERSION 7.0 OR LATER IN WAWF.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE
FOLLOWING DODAACS:
INSPECT BY : S4306A
ACCEPT BY: N64498
NSWCPD
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
0004, 0006
B. EXHIBIT
A
A007
2. TITLE OF DATA ITEM
PRODUCTION RADIOGRAPHY
3. SUBTITLE
DI-MISC-80678
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SS SEE BLOCK 16 SEE BLOCK 16
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
N/A Draft Final
A N/A Reg Repro
BLOCK 4: PARAGRAPHS 10.2.2, 10.2.3, 10.2.4, AND 10.3 OF DI-MISC-
80678 DO NOT APPLY.
AFTER RADIOGRAPHIC INSPECTION OF THE SLEEVE BUT PRIOR TO
ITS INSTALLATION, THE SLEEVE MANUFACTURER SHALL PROVIDE RT
CERTIFICATION OF COMPLIANCE TO NAVSEA TECHNICAL
PUBLICATION T9704-AS-GIB-010/271 AND S9074-AR-GIB-010/278 TO THE
CONTRACTOR. THE SLEEVE MANUFACTURER SHALL RETAIN RT
DOCUMENATION IN ACCORDANCE WITH NAVSEA TECHNICAL
PUBLICATION S9074-AR-GIB-010/278 REQUIREMENTS. THE
CONTRACTOR SHALL SUBMIT A GOVERNMENT APPROVED
RADIOGRAPHIC SHOOTING SKETCH (RSS), PROCEDURE, FILM AND ALL
CORRESPONDING SUPPORT DOCUMENTATION TO THE COGNIZANT
DCMA QAR AT THE SLEEVE MANUFACTURER'S FACILTIY FOR
VERIFICATION OF ACCOMPLISHMENT. RADIOGRAPHY SHALL BE IN
ACCORDANCE WITH THE SAME TECHNIQUE THAT WAS USED IN THE
PREVIOUSLY APPROVED RSS AND FILM.
DEVIATIONS FROM A PREVIOUSLY APPROVED RSS, EXCEPT AS
NOTED BELOW, SHALL BE RESUBMITTED TO THE NAVSEA
AUTHORIZED REPRESTATIVE FOR APPROVAL.
. CHANGES IN SLEEVE WALL THICKNESS, AS LONG AS
PENETRAMETER REMAINS THE SAME AS APPROVED
. INNER OR OUTER DIAMETER CHANGES, AS LONG AS THE
NUMBER OF EXPOSURES USED AROUND THE CIRCUMFERENCE
REMAINS THE SAME AS APPROVED
. SOURCE TYPE; ANY SOURCE MAY BE SUBSTITUTED FOR THAT
SHOWN ON THE RSS PROVIDED THE MATERIAL THICKNESS VERSUS
ENERGY RANGES USED ARE CONSISTENT WITH THOSE
RECOMMENDED BY NAVSEA TECHNICAL PUBLICATION T9074-AS-GIB-
010/271, FIGURES 1, 2, AND 3. HOWEVER, IF THE APPROVED RSS
ALLOWS 2-4T SENSITIVITY, THIS QUALITY LEVEL DOES NOT APPLY TO
THE SOURCE SUBSTITUTED IF 2-2T IS REQUIRED.
. SOURCE SIZE
01 01 00
NSWCCD
. SOURCE STRENGTH (CURIES OR KV)
. SOURCE-TO-FILM DISTANCE
. PENETRAMETER OR BLOCK MATERIAL GROUP (ONLY LOWER
GROUP THAN APPROVED)
. PENETRAMETER SIZE (ONLY SMALLER THAN APPROVED)
. PENETRAMETER PLACEMENT (RELOCATING PENETRAMETERS
FROM THE PART TO A REPRESENTATIVE BLOCK OF EQUAL OR
GREATER THICKNESS, OR FROM A BLOCK TO THE PART)
. FILM SIZE, TYPE, AND QUANTITY
. TOTAL NUMBER OF EXPOSURES DUE TO LENGTH OF SHAFT
SLEEVE
IF NO GOVERNMENT APPROVED RADIOGRAPHIC SHOOTING SKETCH
AND PROCEDURE EXISTS OR IF DEVIATIONS OUTSIDE OF THOSE
LISTED ABOVE ARE PRESENT, THE CONTRACTOR SHALL SUBMIT
NEW SHOOTING SKETCH, PROCEDURES, AND FILM TO THE NAVSEA
AUTHORIZED REPRESENTATIVE BELOW FOR APPROVAL PRIOR TO
FULL SLEEVE RADIOGRAPHY.
NSWCCD WEST BETHESDA
9500 MACARTHUR BLVD
BETHESDA, MD 20817
ATTN: ASHLEE FLOYD, CODE 6110
ALLOW 45 DAYS FOR GOVERNMENT REVIEW.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE
FOLLOWING DODAACS:
INSPECT BY: S4306A
15. TOTAL 01 02 00
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contract ing Officer
0004, 0005, 0006
B. EXHIBIT
A
A008
2. TITLE OF DATA ITEM
EQUIPMENT DAMAGE AND REFURBISHMENT REPORT
3. SUBTITLE
FINAL REPAIR REPORT
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD ASREQ ASREQ
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
N/A Draft Final
A N/A Reg Repro
BLOCK 4: THE FOLLOWING REQUIREMENTS SHALL BE FOLLOWED IN LIEU OF
THE SPECIFIED DATA ITEM.
FOR PROPULSION SHAFTS, REPORT FORMAT AND CONTENT SHALL COMPLY
WITH THE REQUIREMENTS OF THE APPLICABLE TECHNICAL REPAIR
STANDARD, NAVSEA S9243-AW-TRS-011/SHAFT AND THE TECHNICAL DATA
PACKAGE.
CHANGES SHALL NOT BE MADE TO THE INSPECTION FORM FORMAT WITHOUT
PRIOR APPROVAL OF NSWCPD 427. ADDITIONAL INFORMATION AND
PHOTOGRAPHS SHALL BE PROVIDED IF REQUIRED.
THE CONTRACTOR SHALL SUBMIT ALL MAGNETIC PARTICLE (MT)
INSPECTION REPORT/RESULTS DOCUMENTATION, ALL LIQUID PENETRANT
(PT) INSPECTION REPORT/RESULTS DOCUMENTATION, AND ALL ULTRASONIC
TEST (UT) INSPECTION REPORT/RESULTS DOCUMENTATION ACCOMPLISHED
ACCORDINGLY.
THE ONE-TIME IN-SERVICE UT OF THE ENTIRE SHAFT SHALL ONLY BE
ACCOMPLISHED IF THERE IS EVIDENCE OF SEAWATER INTRUSION AND/OR
CORROSION IN THE SHAFT BORE. ALL WELD REPAIRED AREAS EXCEEDING
ONE LAYER ALWAYS REQUIRE UT INSPECTION.
RT CERTIFICATION OF COMPLIANCE SHALL BE INCLUDED IN THE FINAL
REPAIR REPORT.
BLOCK 8: APPROVAL WILL BE BASED UPON THE ACCURACY, ADEQUACY AND
COMPLIANCE WITH TECHNICAL REQUIREMENTS. ALLOW 45 DAYS FOR
GOVERNMENT REVIEW AND APPROVAL.
BLOCK 12: THE FINAL REPAIR REPORT SHALL BE SUBMITTED WITHIN 14 DAYS
OF COMPLETION OF ALL REPAIRS.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE FOLLOWING
DODAACS:
INSPECT BY : S4306A
ACCEPT BY: N64498
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer
0004, 0005, 0006
B. EXHIBIT
A
A009
2. TITLE OF DATA ITEM
CERTIFICATION DATA REPORT
3. SUBTITLE
DI-MISC-80678
5. CONTRACT REFERENCE
SEE SECTION C
6. REQUIRING OFFICE
NSWCPD 427 (N64498)
18. ESTIMATED
TOTAL PRICE
7. DD 250 REQ 9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SS ASREQ ASREQ
a. ADDRESSEE
b. COPIES
8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION
NA Draft Final
A NA Reg Repro
BLOCK 4: DI-MISC-80678 IS TAILORED AS FOLLOWS:
FOR PROPULSION SHAFTS, A CERTIFICATION DOCUMENT IN
ACCORDANCE WITH NAVSEA S9243-AW-TRS-011/SHAFT SHALL BE
COMPLETED AFTER THE APPROVAL OF THE FINAL INSPECTION
REPORT.
REPORT FORMAT SHALL BE AS PROVIDED FOR ON THE INSPECTION
FORMS. CHANGES SHALL NOT BE MADE TO THE INSPECTION FORM
FORMAT WITHOUT PRIOR APPROVAL FROM NSWCPD 427.
FOR OTHER GOVERNMENT FURNISHED EQUIPMENT, THE REPORT
SHALL BE IN THE CONTRACTOR’S FORMAT.
CERTIFICATION DOCUMENTS SHALL BE SIGNED BY THE COGNIZANT
DCMA QUALITY ASSURANCE REPRESENTATIVE (QAR).
BLOCK 12: SUBMISSION SHALL BE MADE NO LATER THAN 5 DAYS
AFTER SIGNATURE OF THE DCMA QAR.
A HARD COPY OF THE CERTIFICATION DATA REPORT SHALL BE
PACKAGED WITH THE ASSET FOR FINAL DELIVERY.
IN ADDITION TO HARD COPY FORMAT, THE CONTRACTOR SHALL
PROVIDE A COPY OF THE REPORT IN ADOBE ACROBAT, VERSION 7.0
OR LATER IN WAWF.
DOCUMENTS SHALL BE SUBMITTED IN WAWF UTILIZING THE
FOLLOWING DODAACS:
INSPECT BY : S4306A
HARD COPY
EQUIPMENT 00 01 00
NICOLE ELIA, NSWCPD 423
H. DATE
23 AUGUST 2016
I. APPROVED BY
KEVIN FAUVELL, NSWCPD 423
DD FORM 1423-1, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page of _ Pages