This pre-solicitation notice announces the Department of the Navy's intent to solicit and negotiate a sole source contract with Northrop Grumman Systems Corporation for the repair of various electrical components. The five-year requirements contract is estimated to be issued between February and March 2019 and will include items such as inertial measuring units, navigation systems, radar transceivers, batteries, antennas, circuit cards, and computer systems that support various weapon systems. Interested parties may identify their capabilities until the time of solicitation, though the government reserves the right to not compete the proposed contract based on responses to this notice.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

9. Sealed offers in original and one (1) copies for furnishings the supplies or services in the Schedule will be received at the place specified in item 8, or if hand carried, in the depository located in until 03:00 P local time

(Hour) (Date)

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

1 1 . TABLE OF CONTENTS

(X) SEC. DESCRIPTION PAGE(S) (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE PART II- CONTRACT CLAUSES

A SOLICITATION/CONTRACT FORM 1 I CONTRACTCLAUSES 154

B SUPPLIES OR SERVICES AND PRICES/COSTS 2 PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

C DESCRIPTION/SPECS./WORK STATEMENT 123 J LIST OF ATTACHMENTS 164

D PACKAGING AND MARKING 137 PART IV- REPRESENTATIONS AND INSTRUCTIONS

E INSPECTION AND ACCEPTANCE 147

K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTSOFOFFERORS

F DELIVERIES ORPERFORMANCE 148

G CONTRACT ADMINISTRATIONDATA 152 L INSTRUCTIONS, CONDITIONS, AND NOTICESTO OFFERORS 1170

H SPECIALCONTRACT REQUIREMENTS 153 M EVALUATION FACTORS FORAWARD N/A

OFFER (Must be fully completed by offeror)

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

1 2 . In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) 30 CALENDAR DAYS (%) CALENDARDAYS(%)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):

AMENDMENT NO. DATE AMENDMENT NO. DATE

15A. NAME AND

ADDRESS

OFOFFEROR

CODE FACILITY 16. NAME AND THE TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

15B. TELEPHONE NUMBER

15C. CHECK IF REMITTANCE ADDRESS IS

DIFFERENT FROM ABOVE - ENTER SUCH

ADDRESS IN SCHEDULE.

17. SIGNATURE 18. OFFER DATE

AREA CODE NUMBER EXTENSION

AWARD(To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL OPEN COMPET

10 U.S.C. 2304 (c) 41 U.S.C. 3304(

ITION: 23. SUBMIT INVOICES T

(4 copies unless otherwise

a) ( )

O ADDRESS SHOW N IN ITEM

specified)

24. ADMINISTERED BY (If other than Item 7) 25. PAYMENT WILL BE MADE BY CODE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF

(Signatu

AMERICA 28. AW ARD DATE

re of Contracting Officer)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is unusable

STANDARD FORM 33 (REV. 6/2014)

Prescribed byGSA - FAR (48 CFR) 53.214 (c)

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

RATING

DO-A7

3. SOLICITATION NUMBER

N00104-18-R-CC02

5. DATE ISSUED

N00104

1 SOLICITATION, OFFER AND AWARD

2. CONTRACT NUMBER 4. TYPEOF SOLICITATION

SEALED BID (IFB)

8. ADDRESS OFFER TO (If other than item 7)

N0010418U4422M

7. ISSUED BY

NAVSUP Weapon System Support - Mech, Attn: Tracy Hunt P.O. Box 2020, Mechanicsburg, PA 17050

Department of the Navy, NAVSUP Weapon System Support - Mech, Contracting Dept, Code N7, Bldg 312, Bay F-19

5450 Carlisle Pike, Mechanicsburg, PA 17055-0788

10. FOR

INFORMATION

CALL:

A. NAME

Tracy L. Hunt

B. TELEPHONE (NO COLLECT CALLS) C. E-MAIL ADDRESS

Tracy.Hunt1@navy.mil

AREA CODE

NUMBER

EXTENSION

Bldg 312, Bay F19

31 MAY 2019

01 MAY 2019

mailto:Tracy.Hunt1@navy.mil

0242csdd r20021007 wl

SECTION B N00104-18-R-CC02 Page 2

ITEM SUPPLIES / SERVICES QUANTI UNI UNIT AMOUNT

0001 NSN: 7HH 6605 01-495-0012 VN

65 EA

NSP NSP

NOM: INERTIAL MEASURING

P/N: 4300859 RTAT: SEE ATTACHMENT A

FAMILY NSN: 6605 01-470-8747

PACKAGING: SEE STATEMENT OF WORK

0001AA SAME AS ITEM 0001, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0001AB SAME AS ITEM 0001, ESTIMATED REQUIREMENT FOR 53 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0001AC SAME AS ITEM 0001, ESTIMATED REQUIREMENT FOR 88 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0001AD SAME AS ITEM 0001, ESTIMATED REQUIREMENT FOR 88 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0001AE SAME AS ITEM 0001, ESTIMATED REQUIREMENT FOR 88 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0001AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0001AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SEE ATTACHMENT C.

SECTION B N00104-18-R-CC02 Page 3

ITEM SUPPLIES / SERVICES QUANTI UNI UNIT AMOUNT

NSN: 7HH 6605 01-513-6655

EA

NSP

NOM: INERTIAL NAVIGATION

P/N: 1982915 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0002AA SAME AS ITEM 0002, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0002AB SAME AS ITEM 0002, ESTIMATED REQUIREMENT FOR 8 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0002AC SAME AS ITEM 0002, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0002AD SAME AS ITEM 0002, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0002AE SAME AS ITEM 0002, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0002AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0002AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 4

NSN: 7HH 3010 01-413-4654

NOM: CLUTCH ASSEMBLY, FRI

P/N: 1979219 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0003AA SAME AS ITEM 0003, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0003AB SAME AS ITEM 0003, ESTIMATED REQUIREMENT FOR 7 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0003AC SAME AS ITEM 0003, ESTIMATED REQUIREMENT FOR 7 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0003AD SAME AS ITEM 0003, ESTIMATED REQUIREMENT FOR 7 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0003AE SAME AS ITEM 0003, ESTIMATED REQUIREMENT FOR 7 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0003AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0003AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 5

NSN: 7HH 5810 01-600-9931

NOM: RADAR TRANSCEIVER

P/N: 4803910-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0004AA SAME AS ITEM 0004, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0004AB SAME AS ITEM 0004, ESTIMATED REQUIREMENT FOR 4 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0004AC SAME AS ITEM 0004, ESTIMATED REQUIREMENT FOR 5 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0004AD SAME AS ITEM 0004, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0004AE SAME AS ITEM 0004, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0004AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0004AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 6

NSN: 7HH 6140 01-470-8756

NOM: BATTERY ASSEMBLY

P/N: 1981554 RTAT: SEE ATTACHMENT A

FAMILY NSN: 6135 01-580-5726

PACKAGING: SEE STATEMENT OF WORK

0005AA SAME AS ITEM 0005, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0005AB SAME AS ITEM 0005, ESTIMATED REQUIREMENT FOR 31 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0005AC SAME AS ITEM 0005, ESTIMATED REQUIREMENT FOR 48 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0005AD SAME AS ITEM 0005, ESTIMATED REQUIREMENT FOR 48 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0005AE SAME AS ITEM 0005, ESTIMATED REQUIREMENT FOR 48 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0005AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0005AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 7

NSN: 7HH 5840 01-570-0441

NOM: RCVR/ADC ASSY

P/N: 6869010-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0006AA SAME AS ITEM 0006, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0006AB SAME AS ITEM 0006, ESTIMATED REQUIREMENT FOR 1 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0006AC SAME AS ITEM 0006, ESTIMATED REQUIREMENT FOR 4 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0006AD SAME AS ITEM 0006, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0006AE SAME AS ITEM 0006, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0006AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0006AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 8

NSN: 7HH 5998 01-470-8196

NOM: ELECTRONIC COMPONENT

P/N: 4300880-3 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0007AA SAME AS ITEM 0007, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0007AB SAME AS ITEM 0007, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0007AC SAME AS ITEM 0007, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0007AD SAME AS ITEM 0007, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0007AE SAME AS ITEM 0007, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0007AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0007AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 9

NSN: 7HH 5985 01-540-7574

NOM: ANTENNA ASSEMBLY

P/N: 1978835-2 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0008AA SAME AS ITEM 0008, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0008AB SAME AS ITEM 0008, ESTIMATED REQUIREMENT FOR 4 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0008AC SAME AS ITEM 0008, ESTIMATED REQUIREMENT FOR 4 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0008AD SAME AS ITEM 0008, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0008AE SAME AS ITEM 0008, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0008AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0008AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 10

NSN: 7HH 7010 01-600-9928

NOM: COMPUTER SYSTEM, DIG

P/N: 4600994-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0009AA SAME AS ITEM 0009, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0009AB SAME AS ITEM 0009, ESTIMATED REQUIREMENT FOR 8 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0009AC SAME AS ITEM 0009, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0009AD SAME AS ITEM 0009, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0009AE SAME AS ITEM 0009, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0009AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0009AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 11

NSN: 7HH 5985 01-406-8555

NOM: ANTENNA

P/N: 1978835 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0010AA SAME AS ITEM 0010, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0010AB SAME AS ITEM 0010, ESTIMATED REQUIREMENT FOR 4 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0010AC SAME AS ITEM 0010, ESTIMATED REQUIREMENT FOR 4 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0010AD SAME AS ITEM 0010, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0010AE SAME AS ITEM 0010, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0010AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0010AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 12

NSN: 7HH 5998 01-570-2881

NOM: COM FREQ GEN ASSY

P/N: 6868057 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0011AA SAME AS ITEM 0011, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0011AB SAME AS ITEM 0011, ESTIMATED REQUIREMENT FOR 2 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0011AC SAME AS ITEM 0011, ESTIMATED REQUIREMENT FOR 2 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0011AD SAME AS ITEM 0011, ESTIMATED REQUIREMENT FOR 2 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0011AE SAME AS ITEM 0011, ESTIMATED REQUIREMENT FOR 2 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0011AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0011AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 13

NSN: 7HH 5998 01-321-4634 VN

NOM: CIRCUIT CARD ASSEMB

P/N: 1977569 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0012AA SAME AS ITEM 0012, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0012AB SAME AS ITEM 0012, ESTIMATED REQUIREMENT FOR 48 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0012AC SAME AS ITEM 0012, ESTIMATED REQUIREMENT FOR 48 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0012AD SAME AS ITEM 0012, ESTIMATED REQUIREMENT FOR 48 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0012AE SAME AS ITEM 0012, ESTIMATED REQUIREMENT FOR 48 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0012AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0012AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 14

NSN: 7HH 6140 01-513-8204

NOM: BATTERY ASSEMBLY

P/N: 1982847 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0013AA SAME AS ITEM 0013, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0013AB SAME AS ITEM 0013, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0013AC SAME AS ITEM 0013, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0013AD SAME AS ITEM 0013, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0013AE SAME AS ITEM 0013, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0013AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0013AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 15

NSN: 7HH 6130 01-527-1132

NOM: RUGGEDISED AC UNINT

P/N: 4801124 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0014AA SAME AS ITEM 0014, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0014AB SAME AS ITEM 0014, ESTIMATED REQUIREMENT FOR 36 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0014AC SAME AS ITEM 0014, ESTIMATED REQUIREMENT FOR 36 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0014AD SAME AS ITEM 0014, ESTIMATED REQUIREMENT FOR 36 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0014AE SAME AS ITEM 0014, ESTIMATED REQUIREMENT FOR 36 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0014AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0014AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 16

NSN: 7HH 6625 01-557-5363

NOM: TEST SET, TRANSMITTE

P/N: 6869025 RTAT: SEE ATTACHMENT A

FAMILY NSN: 6625 01-522-7686

PACKAGING: SEE STATEMENT OF WORK

0015AA SAME AS ITEM 0015, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0015AB SAME AS ITEM 0015, ESTIMATED REQUIREMENT FOR 1 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0015AC SAME AS ITEM 0015, ESTIMATED REQUIREMENT FOR 1 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0015AD SAME AS ITEM 0015, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0015AE SAME AS ITEM 0015, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0015AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0015AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 17

NSN: 7HH 5895 01-557-5365

NOM: COMPUTER SUBASSEMBL

P/N: 6867882-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0016AA SAME AS ITEM 0016, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0016AB SAME AS ITEM 0016, ESTIMATED REQUIREMENT FOR 1 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0016AC SAME AS ITEM 0016, ESTIMATED REQUIREMENT FOR 4 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0016AD SAME AS ITEM 0016, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0016AE SAME AS ITEM 0016, ESTIMATED REQUIREMENT FOR 4 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0016AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0016AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 18

NSN: 7HH 7045 01-600-9925

NOM: CARD RACK ASSY

P/N: 4803950-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0017AA SAME AS ITEM 0017, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0017AB SAME AS ITEM 0017, ESTIMATED REQUIREMENT FOR 2 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0017AC SAME AS ITEM 0017, ESTIMATED REQUIREMENT FOR 2 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0017AD SAME AS ITEM 0017, ESTIMATED REQUIREMENT FOR 3 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0017AE SAME AS ITEM 0017, ESTIMATED REQUIREMENT FOR 3 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0017AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0017AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 19

NSN: 7HH 7025 01-578-3732

NOM: MONITOR,20.1 INCH

P/N: 4302542-2 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0018AA SAME AS ITEM 0018, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0018AB SAME AS ITEM 0018, ESTIMATED REQUIREMENT FOR 8 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0018AC SAME AS ITEM 0018, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0018AD SAME AS ITEM 0018, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0018AE SAME AS ITEM 0018, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0018AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0018AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 20

ITEM SUPPLIES / SERVICES QUANTI UNI UNIT AMOUNT

0019 NSN: 7HH 6130 01-519-6625

16 EA

NSP NSP

NOM: POWER SUPPLY,UNINTE

P/N: 4801482 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0019AA SAME AS ITEM 0019, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0019AB SAME AS ITEM 0019, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0019AC SAME AS ITEM 0019, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0019AD SAME AS ITEM 0019, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0019AE SAME AS ITEM 0019, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0019AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0019AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 21

NSN: 7HH 6625 01-570-2882

NOM: SYNTHESI ER ASSY.

P/N: 6868058 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0020AA SAME AS ITEM 0020, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0020AB SAME AS ITEM 0020, ESTIMATED REQUIREMENT FOR 3 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0020AC SAME AS ITEM 0020, ESTIMATED REQUIREMENT FOR 3 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0020AD SAME AS ITEM 0020, ESTIMATED REQUIREMENT FOR 3 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0020AE SAME AS ITEM 0020, ESTIMATED REQUIREMENT FOR 3 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0020AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0020AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 22

NSN: 7HH 1285 01-600-9927

NOM: COUPLER,RADAR RECEI

P/N: 4804105-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0021AA SAME AS ITEM 0021, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0021AB SAME AS ITEM 0021, ESTIMATED REQUIREMENT FOR 4 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0021AC SAME AS ITEM 0021, ESTIMATED REQUIREMENT FOR 4 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0021AD SAME AS ITEM 0021, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0021AE SAME AS ITEM 0021, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0021AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0021AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 23

NSN: 7HH 5998 01-532-1151

P/N: 4304600-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0022AA SAME AS ITEM 0022, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0022AB SAME AS ITEM 0022, ESTIMATED REQUIREMENT FOR 2 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0022AC SAME AS ITEM 0022, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0022AD SAME AS ITEM 0022, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0022AE SAME AS ITEM 0022, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0022AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0022AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 24

NSN: 7HH 5895 01-673-5645

NOM: POWER TRAY ASSY

P/N: 4803980-2 RTAT: SEE ATTACHMENT A

FAMILY NSN: 5895 01-600-9932

PACKAGING: SEE STATEMENT OF WORK

0023AA SAME AS ITEM 0023, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0023AB SAME AS ITEM 0023, ESTIMATED REQUIREMENT FOR 5 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0023AC SAME AS ITEM 0023, ESTIMATED REQUIREMENT FOR 5 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0023AD SAME AS ITEM 0023, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0023AE SAME AS ITEM 0023, ESTIMATED REQUIREMENT FOR 5 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0023AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0023AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 25

NSN: 7HH 7025 01-521-2391

NOM: DISPLAY UNIT

P/N: 4301665-1 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0024AA SAME AS ITEM 0024, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0024AB SAME AS ITEM 0024, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0024AC SAME AS ITEM 0024, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0024AD SAME AS ITEM 0024, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0024AE SAME AS ITEM 0024, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0024AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0024AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 26

NSN: 7HH 5998 01-528-8138

P/N: 1981763 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0025AA SAME AS ITEM 0025, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0025AB SAME AS ITEM 0025, ESTIMATED REQUIREMENT FOR 8 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0025AC SAME AS ITEM 0025, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0025AD SAME AS ITEM 0025, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0025AE SAME AS ITEM 0025, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0025AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0025AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 27

NSN: 7HH 5977 01-348-1147

NOM: RING,ELECTRICAL CON

P/N: 1810553-4 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0026AA SAME AS ITEM 0026, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0026AB SAME AS ITEM 0026, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0026AC SAME AS ITEM 0026, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0026AD SAME AS ITEM 0026, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0026AE SAME AS ITEM 0026, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0026AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0026AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 28

NSN: 7HH 5840 01-633-4530

NOM: RECEIVER,RADAR

P/N: 6869010-2 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0027AA SAME AS ITEM 0027, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0027AB SAME AS ITEM 0027, ESTIMATED REQUIREMENT FOR 1 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0027AC SAME AS ITEM 0027, ESTIMATED REQUIREMENT FOR 1 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0027AD SAME AS ITEM 0027, ESTIMATED REQUIREMENT FOR 1 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0027AE SAME AS ITEM 0027, ESTIMATED REQUIREMENT FOR 1 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0027AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0027AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 29

NSN: 7HH 5977 01-348-1146

P/N: 1810553-3 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0028AA SAME AS ITEM 0028, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0028AB SAME AS ITEM 0028, ESTIMATED REQUIREMENT FOR 16 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0028AC SAME AS ITEM 0028, ESTIMATED REQUIREMENT FOR 16 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0028AD SAME AS ITEM 0028, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0028AE SAME AS ITEM 0028, ESTIMATED REQUIREMENT FOR 16 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0028AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0028AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 30

NSN: 7HH 5998 01-330-4809

P/N: 1979348 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0029AA SAME AS ITEM 0029, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0029AB SAME AS ITEM 0029, ESTIMATED REQUIREMENT FOR 8 EA

YEAR TWO (2).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR TWO WILL BEGIN IN

MONTH 13 THROUGH MONTH 24, FOR 365 DAYS.

0029AC SAME AS ITEM 0029, ESTIMATED REQUIREMENT FOR 8 EA

YEAR THREE (3).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR THREE WILL BEGIN IN

MONTH 25 THROUGH MONTH 36, FOR 365 DAYS.

0029AD SAME AS ITEM 0029, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FOUR (4).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FOUR WILL BEGIN IN

MONTH 37 THROUGH MONTH 48, FOR 365 DAYS.

0029AE SAME AS ITEM 0029, ESTIMATED REQUIREMENT FOR 8 EA

YEAR FIVE (5).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR FIVE WILL BEGIN IN

MONTH 49 THROUGH MONTH 60, FOR 365 DAYS.

0029AF CONTRACT DATA REQUIREMENTS LIST 1 LO

TECHNICAL DATA, SEE DD FORM 1423, EXHIBIT A

DATA ITEMS A001 THROUGH A002.

0029AG WEBCAV REPORTING IAW WEBCAV STATEMENT OF WORK 1 LO NSP NSP

SECTION B N00104-18-R-CC02 Page 31

NSN: 7HH 5998 01-470-8750

P/N: 1981559 RTAT: SEE ATTACHMENT A

PACKAGING: SEE STATEMENT OF WORK

0030AA SAME AS ITEM 0030, ESTIMATED REQUIREMENT FOR

YEAR ONE (1).

ACRN: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

PR. NO.: TO BE IDENTIFIED ON INDIVIDUAL ORDER.

THE ORDERING PERIOD FOR YEAR ONE WILL BEGIN FROM

THE DATE OF CONTRACT AWARD FOR 12 MONTHS, OR 365

DAYS.

0030AB SAME AS ITEM 0030,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .