This document appears to be Attachment J-3, which contains figures related to the Statement of Work for the Multi Mission Surface Combatant (MMSC) - Professional Mariner (PM) Crew contract opportunity.
The key details are as follows:
The Naval Sea Systems Command (NAVSEA) intends to issue a solicitation, N00024-25-R-2310, for the operation and maintenance of four MMSC ships during a 14-month Post Delivery (PD) period. The PM Crew, augmented with a detachment from NSWC-PHD, will be responsible for safe operation, navigation, equipment maintenance, shipboard hotel services, and routine upkeep of the MMSC ships during the PD periods, both in-port and at-sea. The PM Crew Contractor will also provide shore services in support of ship operations.
The draft Statement of Work, Draft Instructions, and an Industry Day Questionnaire are available. Interested parties can request additional information, including a draft Contract Data Requirements List (CDRL) package, by submitting a written request with their organization's CAGE code and point of contact by November 15, 2024. The Government requests all feedback on the draft SOW by November 22, 2024. An Industry Day is planned for December 2024, and a Request for Proposal (RFP) is anticipated to be released in fiscal year 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MMSC PM Crew - Industry Day 3 - Q-A.pdf | ||
| MMSC INDUSTRY DAY 2024 ATTACHMENT 1.docx | DOCX document | |
| MMSC Professional Mariner Crew Industry Day 2024 Questionnaire.docx | DOCX document | |
| DRAFT PM Crew SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment J-3 Professional Mariner Crew Figures
Figure 1 MMSC Ship Specifications Sheet
Figure 2 MMSC Post Delivery 12-month Schedule
DRAFT
Figure 3 PMS 525 Post Delivery Organization
Figure 4 Notional PSA Schedule and Milestones
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14
MILESTONES
Start Pre-PSA (T- 4 Days) Start PSA Crew Move Ashore Drydock Ship Undock Ship C/S Support Systems Available Aviation Tech Assist Visit Combat Systems Lightoff Load Fuel Hab Spaces Available Crew Move Aboard Aviation Certification GTG Light-off Complete Machinery Spaces Safe to Steam
MELO
Perform Inclining Dock Trials/Fast Cruis Sea Trial PSA Completion
SEQUENCE
3 Days 17 Days
28 Days 4 Days
7 Days 6 Days
4 Days 1 Day
2 Days
5 Days 2 Days
2 Days 3 Days
4 Days 1 Day
4 Days
DRAFT