Att_5_-_DRAFT Delivery Schedule.XLS
XLS spreadsheet 35 KB Posted
- Attached to
- OSR OP Skimmer Federal contract opportunity
- Solicitation number
- N00024-22-R-2287
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Att_4_-_Unique_Item_Identification_(UID).doc | DOC document | |
| Att_6_-_Warranty Terms.doc | DOC document | |
| Att 3 DRAFT 30OP Skimmer Initial Spares.xlsx | XLSX spreadsheet | |
| Att_7_- Technical Data Rights Assertion.doc | DOC document | |
| Att 1 NAVFAC Skimmer Specification 02FEB2022.pdf | ||
| Att 8 FPSL Past Performance and Experience.doc | DOC document | |
| Solicitation.docx | DOCX document | |
| Att 2 DRAFT NAVFAC 30OP Skimmer Specification Response Matrix.xlsx | XLSX spreadsheet | |
| Draft Solicitation 12-16-21.docx | DOCX document | |
| DRAFT_Att1_2020-006 NAVFAC Skimmer Specification_10DEC2021.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Delivery Schedule
| ATTACHMENT 5 | ||||
| Proposed Delivery Schedule Form | ||||
| ORDERING PERIOD 1 | ||||
| DELIVERY ORDER 1 | ||||
| Craft No. | Destination | Notional Delivery Schedule | Proposed Delivery Schedule | |
| Boat 1 | TBD | 330 DAYS AFTER ORDER | ||
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT | ||
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT | ||
| DELIVERY ORDER 2+ | ||||
| Craft No. | Destination | Notional Delivery Schedule | ||
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boat 1+ | TBD | 30 DAYS AFTER LAST BOAT | |
| DELIVERY ORDER 2+ | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 1 | TBD | 330 DAYS AFTER ORDER | |
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT | |
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT | |
| ORDERING PERIOD 2 | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boat 1+ | TBD | 30 DAYS AFTER LAST BOAT | |
| Craft No. | Destination | Notional Delivery Schedule | |
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 1 | TBD | 330 DAYS AFTER ORDER | |
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT | |
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT | |
| ORDERING PERIOD 3 | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boat 1+ | TBD | 30 DAYS AFTER LAST BOAT | |
| Craft No. | Destination | Notional Delivery Schedule | |
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 1 | TBD | 300 DAYS AFTER ORDER | |
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT | |
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT | |
| ORDERING PERIOD 4 | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boat 1+ | TBD | 30 DAYS AFTER LAST BOAT | |
| Craft No. | Destination | Notional Delivery Schedule | |
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 1 | TBD | 330 DAYS AFTER ORDER | |
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT | |
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT | |
| ORDERING PERIOD 5 | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boat 1+ | TBD | 30 DAYS AFTER LAST BOAT | |
| Craft No. | Destination | Notional Delivery Schedule | |
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 1 | TBD | 330 DAYS AFTER ORDER |
| Boat 2 | TBD | 60 DAYS AFTER LAST BOAT |
| Boat 3+ | TBD | 30 DAYS AFTER LAST BOAT |
| DEFINITIONS: | ||
| BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 April 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 300 days after placement of new Delivery Order) | ||
| NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order. (Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 April 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019) |
&RN00024-21-R-2270
Page &P of &N