USS_BOXER_Q&A_1_finale.xlsx
XLSX spreadsheet 492 KB Posted
- Attached to
- USS BOXER (LHD 4) Fiscal Year (FY) 20 Docking Selected Restricted Availability (DSRA) RFP
- Solicitation number
- N00024-19-R-4416
About this file
This document contains a question and answer set regarding a solicitation for the USS BOXER (LHD 4) Fiscal Year 2020 Docking Selected Restricted Availability.
The solicitation seeks offers to perform dry-docking maintenance, pier-side maintenance, repair, and alterations for the LHD 4 beginning in January 2020 and completing in April 2021. The work includes items such as hull preservation, preservation of masts and kingposts, cable management planning, machinery repairs, and structural repairs. Offerors were able to inspect the reference ship USS ESSEX from September to December 2019. Questions were due by November 13, 2019 with responses providing clarification but no amendments to the solicitation. The contracting agency is the Department of the Navy Naval Sea Systems Command. The anticipated contract type is firm-fixed price.
USS BOXER Q&A#1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N0002419R4416 A0002 Conformed.pdf | ||
| S-7 Proposal Assessment LHD 4 REV 1.xlsx | XLSX spreadsheet | |
| N0002419R4416 A0002 Executed.pdf | ||
| N0002419R4416_AMD_1_Nonconformed.pdf | ||
| N0002419R4416_AMD_1_Conformed.pdf | ||
| S-3_PPI_Form_-_USS_BOXER_1APR19.docx | DOCX document | |
| S-1__Manpower_Utilization_Data_Sheet_-_rev1.xlsx | XLSX spreadsheet | |
| S-2_Past_Performance_Questionnaire_USS_BOXER_15AUG19.docx | DOCX document | |
| S-8_Pier_and_Drydock_Graphical_Representation_Template.xlsx | XLSX spreadsheet | |
| S-5_Eligibility_Criteria_Data_Sheet_BOXER_FY20_DSRA_12SEP19.docx | DOCX document | |
| S-7_Proposal_Assessment_LHD_4_12SEP19.xlsx | XLSX spreadsheet | |
| S-9_PP_CPARS_Reference_List_BOX_12SEP19.docx | DOCX document | |
| S-6_(BOXER)_Value_Adjusted_Total_Evaluated_Price_-_29AUG19.xlsx | XLSX spreadsheet | |
| S-4__Manpower_Plan_to_Actual_Data_Sheet.xlsx | XLSX spreadsheet | |
| USS_BOXER_N0002419R4416.pdf | ||
| USS_BOXER_13AUG19.docx | DOCX document | |
| Sources_Sought_-_USS_BOXER_(LHD_4)_FY20_DPMA.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QA1
USS BOXER (LHD 4) DSRA Pre-Proposal Information (PPI) Questions
| Solicitation #: | N00024-19-R-4416 | Phone | ||
| TPPC | Michelle Wogu, Michelle.wogu@navy.mil | 202-781-4230 | ||
| Martha Bello, Contracting Officer, martha.bello@navy.mil | 202-781-3864 | |||
| The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation. | ||||
| To request references, drawings, RLARs, and Erratas being provided under this Solicitation Question & Answer Set, |
please contact the NAVSEA POCs.
| Q # | Work Item No. | Document Number/Title | Question | Government Response |
| 001 | RFP | Pg 103 | On page 103 of 189 of the Solicitation the Contractor notes the Governments inclusion of C-211-H016 SPECIFICATION AND STANDARDS (NAVSEA) (Oct 2018): |
(a) Definitions.
(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).
(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.
(b) Requirements.
All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only.
CONTRACTOR QUESTION:
It is the Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references. However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate the reference and only use it to aid in the development of an estimate of references that are to be accomplished.
1) Please concur or advise on this interpretation.
| Please estimate the reference. | |||
| 002 | RFP | Pg 88 | On Page 88 of 189 the Solicitation states, |
NOTE F: SPECIAL AGREEMENT FOR GROWTH WITH A PRICE OF $25,000 OR LESS
1. To make administration of small dollar value changes more efficient and less costly, both parties (Government and Contractor) agree to a pre-priced value for individual growth items with an estimated price of $25,000 or less. The Contract will include a firm fixed price for growth valued at $25,000.00 or less. Zero-dollar changes and administrative contract changes (for example, drawing revision change where no additional work is required) shall not be executed using the Small Dollar Value Growth procedures, but will follow the change process.
In NOTE F, will the Government clearly identify changes in drawings when they have determined that "no additional work is required"?
| Drawing changes that require no additional work will be identified on a case basis in the event the contractor requests a small dollar value change. | ||
| 003 | RFP | CONTRACTOR QUESTION: |
1) Since the ship was last painted in a US Shipyard, has there been any paint applied outside of the United States?
2) If so, verify that all paint applied outside of the United States met NAVSEA Standard Item FY20, 009-32, table 1 thru 8 requirements?
| No Paint applied Outside of the US to the Port Engineers and Project Managers Knowledge. | |||
| 004 | RFP | pg 152 | The following document(s), exhibit(s), and other attachment(s) also form a part of this solicitation and will form a |
part of the contract resulting from this solicitation:
Attachment J-1 Specification Package TPPC-LHD4-SWRMC20-CN01 Attachment J-2 Work Item Plans, Drawings, and Other References Attachment J-3 Execution Milestones and Key Event Dates Attachment J-4 Pricing Workbook Attachment J-5 Quality Assurance Surveillance Plan Attachment J-6 Subcontracting Plan (to be incorporated upon award) Attachment J-7 Schedule Model Review
Will the Government issue J-1 through J-7?
| Local Pick up information regarding J-1 and J-2 were emailed to offers who requested and attachements J-3, J-4, J-5 and J-7 were sent to intreasted offers in the form of email. | |||
| 005 | N/A | J-1 & J-4 | The following Work items are listed on the J-4 Pricing Work Book but not provided on the CD picked up on 10/02/19. |
Work Item 242-12-002 Propulsion Shafting Waterborne Port Inspect and Repair.
Work Item 252-11-001 Forward Throttle Control Console (TCC) Temperature Monitoring Panel Repair.
Work Item 511-11-005 Laaundry Press Steam Supply and Condenate Drain Piping Replace.
Will the Government provide the three work items or issue an Amendment and cancelling and remove them from the J-4? PM has reviewed both the J-4 and the CD's received and the Work Items Work Items 243-12-002 Propulsion Shafting Waterborne Port Inspect and Repair.
252-11-001 Forward Throttle Control Console (TCC) Temperature Monitoring Panel Repair. 511-11-005 Laaundry Press Steam Supply and Condenate Drain Piping Replace. Work Items ARE on the CD
| 006 | Solicitation N00024-19-R-4416 | |
| Page 90 | Category I NAVSEA FY20 Standard Items identified under Attachment J-1 are applicable to all items without further reference. |
Contractor notes NAVSEA Standard Items FY-20 has 2 Changes.
| Will the Government please clarify the correct FY NAVSEA Standard Items that the contractor shall use? | Use the one titled FY20 CH-1 NAVSEA Standard Items | ||||
| 007 | RFP Section B CLIN 0011 | CLIN 0011 is titled, "Multiple Out of Homeport Items." Please confirm this CLIN is to be priced only by out of homeport area Offerors. | Concur. | ||
| 008 | RFP Attachment J-1 | RFP Attachment J-1 (specifications), page 2, NAVSEA Standard Item Catogory 1 Index, states, "Items that are struck out in this index do not apply to this contract. There are no items struck out. However, several items such as 009-34, 009-40, 009-109, 009-110, 009-111, 009-118 that probably do not apply to this contract. Please review and advise. | Do not Estimate NSI that are not applicable. PM has accomplished strike thrus | ||
| 009 | RFP Attachment J4 | RFP Attachment J-4, "Total Proposed Evaluated Price", line 10 description is "Dock Differential Reduction for "Fewer Dock Days Proposed." There isnt a corresponding evaluation factor in Section M of the RFP for proposing a reduction for fewer dock days. Please clarify. | Add to Section M Factor 4 - Price, para 2: "g) As applicable, the value of the dock differential (as identified in Section L of this solicitation)." | ||
| 010 | 321-90-001 | Paragraph 4.1 states that the references will be issued 9/27/19 per the Planning Yard and that the work item is to be estimated as is until issuance of drawings. As of 10/4/19 these drawings have not been received. Without the references the work item can't be estimated as is. Please advise. | Drawings were provided to potential offerors on 10/16/2019. | ||
| 011 | 663-90-001 | Paragraph 4.1 states that not all drawings listed in 2.0 have been issued as of 8/2/19 and that the work item is to be estimated as is until issuance of drawings. As of 10/4/19 several of the required drawings have not been received. Without the references the work item can't be estimated as is. Please advise. | Drawings were provided to potential offerors on 10/16/2019. | ||
| 012 | 631-21-001 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 013 | 980-00-001 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 014 | 980-80-001 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 015 | 980-80-002 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 016 | 980-80-003 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 017 | 980-80-004 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 018 | 980-90-003 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 019 | 980-90-004 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 020 | 980-90-005 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 021 | 980-90-007 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 022 | 980-90-008 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 023 | 980-90-009 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 024 | 980-90-010 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 025 | 980-90-011 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 026 | 980-90-012 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 027 | 980-90-013 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 028 | 980-90-014 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 029 | 980-90-015 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 030 | 980-90-016 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 031 | 980-90-017 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 032 | 980-90-018 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 033 | 980-90-019 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 034 | 980-90-023 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 035 | 980-90-025 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 036 | 997-11-002 | Please review the mast preservation date of 20 August 2020 stated in paragraph 4.1. This doesn’t appear to be a valid date. | 20 August 20 is a Valid Date. All Mast Work will start upon completion of Mast Preservation | ||
| 037 | 321-90-001 | ShipAlt LHD1-71492K, HESS (400Hz) Line Voltage Regulator; | |||
| accomplish | Paragraph 3.1 states, "Accomplish the requirements of 2.2 through 2.9. (See Note 4.1)" and Note 4.1 states "Drawings listed in 2.2 through 2.9 will be issued 9/27/19 per Planning Yard" |
Contractor notes that 9/27/19 has pasted and references 2.2 through 2.9 have not been issue to all bidders.
Question: Will the Customer provide the missing references to all bidder?
| Drawings were provided to potential offerors on 10/16/2019. | |||
| 038 | 663-90-001 | ShipAlt LHD1-82483K, Capstone Space Arrangement; accomplish | |
| accomplish | Paragraph 3.1 states, "Accomplish the requirements of 2.2 through 2.54. (See Note 4.1)" and Note 4.1 states "Not all drawings listed in 2.0 have been issued as of 8/2/19." |
Contractor notes that 8/2/19 has pasted and references 2.2 through 2.54 have not been issue to all bidders.
Question: Will the Customer provide the missing references to all bidder?
| Drawings were provided to potential offerors on 10/16/2019. | |||
| 039 | 541-11-001 | Fuel Oil Stripping Piping; replace | Paragraph 3.2 states, “Remove existing piping, associated fitting and retain existing valves, fit and install new, piping listed in 1.3 and associated fitting listed in attachment B, reinstall existing valves as designated by the SUPERVISOR, using 2.3 through 2.10 for guidance". |
Contractor notes that Attachment B was not provided with the specification.
Question: Will the Customer provide the missing Attachment B to all bidder?
| Attachment Will be provided on the Disk with Drawings for 321-90-001 and 663-90-001 Work Items. | |||
| 040 | N/A | J-4 Pricing Work Book | The Attachment J-1 Specification Package TPPC-LHD4-SWRMC20-CN01 identifies Work Items 980-90-003 and 980-90-023 as Option Items in their titles. |
Contractor notes that both of these work items are listed as Basic on the J-4 Pricing Work Book and not as being Option Item's.
Question: Can the Customer provide clarification as to the disparitiy with Work Items 980-90-003 and 980-90-023 being listed as Basic and not Option Items on the J-4 Pricing Work Book?
| These work items are part of the Basic package. The J 4 Pricing Work Book is correct. | |||
| 041 | 897-11-004 | Cable Management Plan; provide | 1) Pargraph 3.1 states, "Conduct an applicability ship check within 30 days of avail start to validate and document existing cable way conditions". |
Contrator notes that the reference provided in 2.2 through 2.7 are insuficient to provide and acurate estimate of labor or material for paragraph 3.1.1 through 3.5.
Contractor notes that there are no quaunities of false floor plates, cableways, Overhead sheathing, deck covereing, battle lanterns and operating lights, or a list of applacable AIT SCD SID cable installation references.
Contractor notes that prior to paragraph 3.6 there are no Directed Labor or Material pools established to accomplish 3.1.1 through 3.5
Question: Can the Customer provide clarification as to the disparities identified regarding paragraphs 3.1.1 through 3.5, and will an Errata be issued for this specification?
A “Like Ship” (LHD 2) is made available. A ship check will provide accurate layout and configuration of quantities, square footage, number of operating lights and battle lanterns, etc listed in paragraph 3.1.1, 3.1.2, 3.1.3, 3.1.4, 3.1.5 and 3.1.5.1.
WRT paragraph 3.1.4, Request the contractor estimate tiered cableways located under false deck floor plates using the Cableway and Cable Routing list (8770810) reference included in the bidder’s package and estimate for approximately 7000 cables to be removed and 6000 of various sizes to be installed.
No Errata will be issued, anything in addition to the above quantities will be addressed via RCC.
| 042 | N/A | Solicitation N00024-19-R-4416 | |
| Section L, Page 167 of 189, Item 8 Government provided pier differential | The solicitation includes the provision for a Government Provided Pier Differential for offerors relying on the Government to supply the required pier space. |
The solicitation includes the following value for the Government provided pier differential; Location, San Diego, CA. Differential, $4,892,958
| Question: Bidder requests clarification of the cost elements included in the above depicted Gov't pier differential value? Bidder requests a detailed list of Gov't provided pier and facility related efforts that will be provided by the Navy customer? Bidder requests detailed information regarding Gov't provided pier and facility related costs that bidder is responsible for, and as such must include in its proposed bid price? | The pier differential covers all costs associated with typical ship berthing requirements including potable water, electricity, sewage, etc. These typical services will be provided if the Navy pier is utilized. | |||
| 043 | N/A | Solicitation N00024-19-R-4416, Section L - Instructions, Conditions and Notices to Bidders, Page(s) 160 - 161 of 189, | Introduction Item C. states, "To ensure the Government is able to adequately address and respond to offeror pre-proposal information (PPI) via amendment, it is requested questions be submitted no later than 13 November 2019 at 3:00 pm, local time, Washington DC". |
GENERAL INFORMATION A. states, "The USS BOXER (LHD 4) will not be available for ship check prior to the proposal submission due date. Instead, potential offerors may inspect the USS ESSEX (LHD 2) in San Diego, CA from 30 September 2019 to 6 December 2019".
Contractor notes that the PPI's are required to be submitted no later than 13 November 2019 and ends prior to the Ship Check period that ends 6 December 2019 and does not allow time to submit question that will arise from ship checks conducted after 13 November 2019.
Question (1): Can the Customer provide clarification as to the disparities identified regarding the PPI submital date of 13 November 2019 and the end date of 6 December 2019 to complete ship checks and will an ammedment be issued extending the period to submit pre-proposal information (PPI) questions?
| Please refer to N00024-1-R-4416 Ammendment 0001 | ||
| 044 | 120-11-002 | Item 120-11-002 paragraph 1.3.1 states; "Quantity (One SF) Vent Trunk (Inboard Plate) for Supply System S4-78-1 S(199), from 2 Inch below 2nd Deck, and from 18 Inch between Fwd and Aft Trunk Plate, Fr 77 to 80, Steel, Sheet 10, Detail 5-A of 2.6" |
There is no detail 5-A on Sheet 10 of 2.6.
| Please provide correct detail or advise. | Should have been Detail 5-A of 2.4 vice 2.6. Errata work Spec to be written and issued. | ||
| 045 | 130-11-007 | Item 130-11-007, location of work from 1.2.1 states "Troop Water Closet (01-34-2)"; |
| Contractor notes this is an incomplete compartment number, please provide with correct full number. | Correct Space should be "(01-33-0-L)" Erratta Work spec written | ||||
| 046 | 110-11-002_2.4 | 100-5862395-J | Incorrect SWBS number, refer to SWBS 110 as per drawing title | SWBS Will not change-Contractor to estimate scope | |
| 047 | 130-11-003_2.5 | 185-5862480-F | Incorrect SWBS number, refer to SWBS 136 as per drawing title | SWBS Will not change-Contractor to estimate scope | |
| 048 | 321-90-001_2.4 | 670-8770603 | Missing reference from CD received on October 02, 2019. | Drawings were provided to potential offerors on 10/16/2019. | |
| 049 | 555-12-010_2.3 | 555-6125902-F | Incorrect SWBS number, refer to SWBS 505 as per drawing title | SWBS Will not change-Contractor to estimate scope | |
| 050 | 122-21-001 | Transverse, Longitudinal Structural; repair | Paragraph 3.2.4 states, "Remove existing and install new (2 EA) preheater listed in 1.3.5 and 1.3.6 in accordance with 2.6 for guidance". |
Contractor notes both preheaters identified in 1.3.5 and 1.3.6 to be replaced state to use reference 2.6, however reference this drawing 137-5862468 Rev F, is a structural drawing and does note list or identfy these items.
Question: Can the Customer provide clarification as to the disparity between the equipment identified in 1.3.5 and 1.3.6 and reference 2.6 and will an Errata be issued for this specification?
Should have been Reference 2.5 vice 2.6. Errata work spec written image1.jpeg image2.png