J-1_PH_EDSRA_Specification_Work_Package.pdf

PDF 13 MB Posted

Attached to
USS PAUL HAMILTON (DDG 60) EDSRA
Solicitation number
N00024-16-R-4400
Issued by

About this file

Attachment J-1 USS PAUL HAMILTON EDSRA Specification Package No. TPPC-DDG60-SSSD16-CN01

View the file

Other files

File Type Posted
N55236_170001_FBO.pdf PDF
N00024_170014_FBO.pdf PDF
N00024_170015_FBO.pdf PDF
N00024_170024_FBO.pdf PDF
N00024_170017_FBO.pdf PDF
N00024_170016_FBO.pdf PDF
N000024_170012_FBO.pdf PDF
N00024_170013.pdf PDF
N55236_170025_FBO.pdf PDF
JA_222N_redact.pdf PDF
JA_270N_redact.pdf PDF
JA_3_REDAC6.pdf PDF
JA_4_REDACT.pdf PDF
Redacted_Hamilton_JA2.pdf PDF
JA_PAUL_HAMILTON_REDACT.pdf PDF
DDG-60_RFP_Q_AND_A_-_FINAL.docx DOCX document
Amend_0010_conformed.pdf PDF
Amendment_0009.pdf PDF
Amend_0009.pdf PDF
Amend_0009_conformed.pdf PDF
Amend_0008.pdf PDF
J-3_Execution_Milestones_(Amend_0008).xlsx XLSX spreadsheet
N00024-16-R-4400-0007_Released.docx DOCX document
DDG-60_Mod_Critical_Path_Turnover_Schedule.pdf PDF
SI_Index_0204.pdf PDF
DDG-60_RFP_Q_AND_A_-___250_-_345.pdf PDF
DDG_60_AC_Conversion_POAM_plants__1_and__4.mpp MPP file
Amend_0006_Conformed.pdf PDF
Amend_0006.pdf PDF
J-7_Quality_Assurance_Surveillance_Plan_Amend_0005.pdf PDF
DDG-60_RFP_Q_AND_A_-___98_-_249_FBO.pdf PDF
Amend_0004.pdf PDF
Amend_0004_conformed.pdf PDF
J-3_Execution_Milestones_(Amend_0003).xlsx XLSX spreadsheet
Amend_0003_conformed.pdf PDF
J-7_Quality_Assurance_Surveillance_Plan_(Amend_0003).pdf PDF
J-5_Award_Fee_Intra_Availability_(Amend_0003).pdf PDF
Amendment_0002_Conformed.pdf PDF
J-4_Pricing_Spreadsheet_for_Amendment_0002.xlsx XLSX spreadsheet
Amendment_0002.pdf PDF
DDG-60_RFP_Q_AND_A_-___1-_27.pdf PDF
RFP-IFB_Amend__1.pdf PDF
S-5_Eligibility_Criteria_Data_Sheet.docx DOCX document
Exhibit_C.pdf PDF
J-5_Award_Fee_Intra_Availability.docx DOCX document
S-4_PP_Reference_List.docx DOCX document
Exhibit_A.pdf PDF
S-2_Past_Performance_Questionnaire.docx DOCX document
Exhibit_B.pdf PDF
Synopsis_-_PAUL_HAMILTON_(DDG_60)_Final_(10-1-15).docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED

SPECIFICATION NUMBER:

SHIP CHARACTERISTICS

FEET INCHESLENGTH OVERALL

FEET INCHESMAX. BEAM AT DESIGN WATERLINE

FEET INCHESEXTREME BEAM INCLUDING APPENDAGES

FEET INCHESDRAFT (MAX. NAVIGABLE) (FWD.)

FEET INCHESDRAFT (MAX. NAVIGABLE) (AFT.)

LONG TONLIGHT DISPLACEMENT

LONG TONFULL LOAD DISPLACEMENT

INCHESFEETHEIGHT OF MAST ABOVE DESIGN WATERLINE

INCLUDES ALL CHANGES THROUGH 12/15/2015

INDEX

SHIP: USS PAUL HAMILTON (DDG 60) TPPC-DDG60-SSSD16-CN01

ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.

CATEGORY I. FY-16 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.

ITEM_NO. TITLE DATE

009-01 General Criteria; accomplish 07/18/2014

009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 07/18/2014

009-03 Toxic and Hazardous Substances; control 07/18/2014

009-04 Quality Management System; provide 07/18/2014

009-05 Temporary Accesses; provide 07/18/2014

009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;

accomplish

07/18/2014

009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 07/18/2014

009-08 Fire Protection at Contractor's Facility; accomplish 07/18/2014

009-10 Shipboard Asbestos-Containing Material (ACM); control 07/18/2014

009-18 Magnetic Material; control 07/18/2014

009-19 Provisioning Technical Documentation (PTD); provide 07/18/2014

009-20 Government Property; control 07/18/2014

009-21 Logistics and Technical Data; provide 07/18/2014

009-23 Interferences; remove and install 07/18/2014

009-24 Authorization, Control, Isolation, Blanking, and Tagging Requirements; accomplish 07/18/2014

009-28 Fire Prevention Requirements; accomplish 06/10/2014

009-29 Asbestos-Free Pipe Hanger Liner Material; install 07/29/2004

009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/17/2013

009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish

07/18/2014

009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component; provide

07/19/2007

009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish

07/18/2014

009-59 Organotin Antifouling Material; control 07/29/2011

009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;

provide and manage

07/18/2014

009-61 Shipboard Use of Fluorocarbons; control 07/18/2014

009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 07/18/2014

009-65 Polychlorinated Biphenyls (PCBs); control 07/29/2011

009-67 Integrated Total Ship Testing; manage 07/18/2014

009-69 Heavy Weather/Mooring Plan; provide 07/18/2014

009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish

07/18/2014

009-72 Physical Security at Private Contractor's Facility; accomplish 07/18/2014

009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install 07/18/2014

009-74 Occupational, Safety and Health Requirements; accomplish 07/18/2014

009-77 Cofferdam Requirements; accomplish 07/18/2014

009-79 Government Owned Material (GOM); status reporting 07/18/2014

Page 1 of 14 EXECUTING WORK

ITEM_NO. TITLE DATE

009-80 Ship's Facilities; provide 07/18/2014

009-81 Compartment Closeout; accomplish 07/18/2014

009-82 Data Requirements When Installing an Equal Component Vice Specified Component;

provide

07/29/2011

009-83 Wire Rope Fitting Verfication; provide 01/17/2013

009-84 Accountability of Temporary Fasteners; provide 07/18/2014

009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish

08/01/2008

009-87 Chemical disinfection Procedures; accomplish 07/18/2014

009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify

07/18/2014

009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;

accomplish

07/29/2011

009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide

07/18/2014

009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/17/2013

009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 07/18/2014

009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide

01/17/2013

009-99 Ship Departure Report; provide 07/18/2014

009-100 Ship's Stability Process Control Procedure (PCP); maintain 07/18/2014

009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish 07/18/2014

009-102 Alteration Verification; provide 07/29/2011

009-103 Weight and Moment Change Data; provide 07/18/2014

009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/06/2014

009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish

07/18/2014

009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;

accomplish

07/18/2014

009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 07/18/2014

009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration;

provide and manage

07/18/2014

009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 07/18/2014

009-118 CG Deck Loading; accomplish 07/18/2014

009-120 Fact Finding and Critique of Unplanned Events; manage 07/18/2014

009-121 Ship Assessment/Inspection Requirements; provide 07/18/2014

Page 2 of 14 EXECUTING WORK

DATETITLEITEM NO.

CATEGORY II. FY-16 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER

009-09 Process Control Procedure (PCP); provide and accomplish 07/18/2014

009-12 Welding, Fabrication, and Inspection Requirements;

accomplish

09/01/2015

009-12 Welding, Fabrication, and Inspection Requirements;

accomplish

07/18/2014

009-12 Welding, Fabrication, and Inspection Requirements;

accomplish

07/18/2014

009-13 Meters; repair and certify calibration 07/18/2014

009-14 Gages, Switches, and Thermometers; repair and certify calibration

07/18/2014

009-15 Rotating Machinery; balance 01/17/2013

009-16 Electronic Equipment; repair 07/29/2011

009-17 Rotating Electrical Equipment; repair 07/18/2014

009-22 Shipboard Electric Cable; test 07/18/2014

009-25 Structural Boundary Test; accomplish 07/18/2014

009-26 Deck Covering Requirements; accomplish 07/18/2014

009-32 Cleaning and Painting Requirements; accomplish 07/10/2015

009-32 Cleaning and Painting Requirements; accomplish 11/07/2013

009-36 Controller; repair 07/18/2014

009-43 Engineering Plant Production Completion Date (PCD), Light-Off Assessment (LOA) Support; provide

07/18/2014

009-55 Regulating/Reducing Valve; repair 07/30/2010

009-57 Reduction Gear Security Requirements; accomplish 07/18/2014

009-58 Pump and Driver Shaft Alignment; accomplish 07/18/2014

009-58 Pump and Driver Shaft Alignment; accomplish 09/01/2015

009-63 Lubricating Oils and Hydraulic Fluids; analyze 07/18/2014

009-71 Testing Requirements for Piping Systems; accomplish 07/18/2014

009-71 Testing Requirements for Piping Systems; accomplish 07/10/2015

009-76 Waveguide and Transmission Line Temporary Lay-Up, Pressurization, and Purging; accomplish

07/29/2011

009-78 Passive Countermeasures System (PCMS) Material Repair/Installation Requirements; accomplish

11/07/2013

009-90 Technical Representative; provide 07/18/2014

009-92 Resilient Mount; remove and install 07/18/2014

009-98 Monel Fasteners; inspect 07/18/2014

009-104 Vibration Testing and Analysis; accomplish 07/18/2014

009-107 Piping System Cleanliness (Non-Nuclear); accomplish 07/18/2014

Page 3 of 14 EXECUTING WORK

009-113 Rotating Electrical Equipment with Sealed Insulation Systems (SIS); rewind

07/18/2014

Page 4 of 14 EXECUTING WORK

ITEM NO. TITLE

Work Package Execution Review; accomplish042-11-001

Accountability of Manhour and Material Reservation; accomplish042-27-001

Hazardous Waste Produced on Naval Vessels; control077-01-001

Underwater Hull; inspect110-11-001

Bulkhead and Overhead Plating; repair110-21-001

Machinery Space Bilge Drain Well; repair113-11-001

Sonar Passage Drain Well; replace113-11-002

Sonar Cooling Equipment Room Sump; repair113-11-004

Machinery Room Structural Repair; accomplish120-11-001

Main Engine Room No. One Structural Repair; accomplish120-11-002

Auxiliary Machinery Room Number One and 2 Structural Repair;

accomplish

120-11-003

Fuel Oil Tanks, Group 3 and 4; inspect and preserve123-11-001

Fuel Service Tank; repair123-11-003

Contaminated Oil Tank; repair and preserve123-17-001

AER 84650D, Escape Trunk Manhole and Cover; install123-80-001

Flight Deck Tiedown Fitting; replace130-11-001

AER 83007D, Increase Deck Plate Thickness Modifications(Partial);

accomplish

130-80-001

Bulkhead and Scupper; repair and preserve150-11-001

Bridge Wing Repair; accomplish150-11-002

SLQ-32 Antenna Platform and Step Platform; preserve and replace150-11-003

04 Level Deck; repair and preserve150-11-004

Deck Edge Waterway Bar; replace150-11-005

03 Level Structural Repair; accomplish150-11-006

02 Level Bulkhead and SRBOC Deck; repair150-11-007

02 and 03 Level Structural Repair; accomplish150-11-008

05 Level Deck; repair150-11-009

Main Deck Bulkhead; repair150-11-010

CIWS Weapon Group Mount 21 Deck; repair150-11-011

CIWS Weapon Group Mount 22 Deck; repair150-11-012

Page 5 of 14 EXECUTING WORK

06 Level Director Maintenance Deck; repair150-11-013

05 Level Structural; repair150-11-014

Weather Deck Corrosion Repairs; Accomplish150-11-015

Harpoon Stowage Foundation; replace150-11-017

Flight Deck; repair150-11-018

01 Level Superstructure; repair150-11-019

01 Level Bulkhead; repair150-11-020

Passage Structural; repair150-11-021

ShipAlt DDG51-64156D, Harpoon Blast Pad Corrosion Modification;

accomplish (Option Item)

150-80-001

03 Level Deck; repair154-11-001

03 Level Deck; repair154-11-002

Forward Stack; repair and preserve162-11-001

Aft Stack; repair and preserve162-11-002

Sea Chest; inspect163-11-001

Waster Sleeve; replace163-11-002

Sonar Dome Rubber Window (SDRW); inspect and repair165-11-001

Lower Sonar Dome Access Scuttle; repair165-11-002

Upper Sonar Dome Access Scuttle; repair165-11-003

ShipAlt DDG51-83678D, Sonar Dome Air Flow Meter Replacement;

accomplish

165-80-001

Bolted Equipment Removal Plate (BERP) Repair; accomplish167-11-001

Watertight Scuttle; replace167-11-002

Hatch and Scuttle; repair167-11-003

Bolted Equipment Removal Plate (BERP) Repair (Option Item);

accomplish

167-11-004

Bolted Equipment Removal Plate (BERP) Repair (Option Item);

accomplish

167-11-005

No. 2A GTM Bolted Equipment Removal Plate (BERP) Repair;

accomplish (OPTION ITEM)

167-11-006

No. 2B GTM Bolted Equipment Removal Plate (BERP) Repair;

accomplish (OPTION ITEM)

167-11-007

Watertight Scuttle and Hatch; replace167-11-008

Watertight Scuttle; repair167-11-009

No. 1A GTM Bolted Equipment Removal Plate (BERP) Repair;

accomplish (OPTION ITEM)

167-11-010

ShipAlt DDG51-77228D (Partial), Watertight Door; replace167-80-004

Page 6 of 14 EXECUTING WORK

Cargo Door; replace168-11-001

Structural Door Assembly; replace168-11-002

Remove and Overhaul the Actuator; accomplish168-12-001

ShipAlt DDG51-64233, Improved Fan Room Access Modification;

accomplish

168-80-001

ShipAlt DDG51-78049D, Install Bridge Wing Void Manholes; accomplish168-80-002

Main Reduction Gear No. 2 Input Shaft Seal; replace241-11-001

Stern Tube Shaft Seal; overhaul243-11-001

Propulsion Shafting; inspect, repair and align243-11-002

ShipAlt DDG51-73395D, Bulkhead Shaft Seal Upgrade Modification;

accomplish

243-80-001

Outboard Propulsion Shafting, Bearing Clearance Measurement;

accomplish

244-12-001

Controllable Pitch Propeller (CPP) Blade; inspect and repair245-11-001

Controllable Pitch Propeller (CPP) Oil Sump Tank Heater Element;

inspect and clean

245-11-002

Controllable Pitch Propeller (CPP) Oil Distribution Box; replace245-12-001

Controllable Pitch Propeller (CPP) System, Propeller Hub; replace245-12-002

Controllable Pitch Propeller (CPP) Prairie Air Tube, and Valve Rod Assembly; repair and test

245-12-003

Moisture Separator Assembly Mounting Flange; repair251-11-001

Air Intake and Exhaust Louver and Screen; remove, crate and install251-31-001

Ship Service Gas Turbine Generator (SSGTG) Number One Generator Intake; repair and preserve

251-31-002

Forward Intake Repair; accomplish251-31-004

Forward Intake/Uptake Engine Room Number One Repair; accomplish251-31-005

Forward Intake (Clean Side) Repair; accomplish251-31-006

SSGTG No. 3 Generator Exhaust Trunk; repair and preserve251-31-007

Forward Mixing Room Repair; accomplish251-31-008

Ships Service Gas Turbine Generator (SSGTG) Number One Intake;

repair

251-31-009

Ships Service Gas Turbine Generator (SSGTG) Intake Trunk; preserve251-31-011

Intake/Uptake Engine Room No. 2; repair251-31-012

Ships Service Gas Turbine Generator No. 3 (SSGTG) Intake Trunk; repair251-32-001

Ship Service Gas Turbine Generator (SSGTG) Number 2 Intake (Dirty Side); repair

251-32-002

Engine Room No. 2B Intake; repair251-32-003

Engine Room No. 2A Intake; repair251-32-004

Page 7 of 14 EXECUTING WORK

Seawater Service Piping; replace256-11-001

Ship Service Gas Turbine Generator (SSGTG) Lube Oil Cooler Sea Water Piping; repair

256-11-002

Seawater Air Cooler Piping; replace256-61-001

ShipAlt DDG51-64250D Ship Service Gas Turbine Generator (SSGTG) Emergency Seawater Cooling System Modification; accomplish

256-80-001

Gas Turbine (GTRB) Exhaust Duct Collector; repair259-11-001

SSGTG Exhaust Trunk No. One and No 2; repair and preserve259-11-002

Forward Gas Turbine Exhaust Duct Lagging and Insulation; replace259-11-003

Uptake, Manhole Cover; replace259-11-004

Aft Gas Turbine Exhaust Duct Lagging and Insulation; replace259-11-005

Number 3 Ship Service Gas Turbine Generator (SSGTG) Exhaust Anchor Flange; repair / replace

259-11-006

Gas Turbine Module 1A Exhaust Gasket and Lagging; replace259-11-007

Uptake Engine Room Exhaust Flange Fasteners and Anchor Flange;

replace / repair

259-11-009

No. 2A Propulsion Gas Turbine Exhaust Duct Internal Insulation Sheathing Tabs; replace

259-11-010

Ship Service Gas Turbine Generator (SSGTG) Uptake Trunk No. One and No. 2; repair and preserve

259-11-011

2B Gas Turbine Module (GTM) Duct Lagging; replace259-11-012

No. 2 Ship Service Generator Gas Turbine Exhaust Duct; repair259-11-013

No.2 Ship Service Gas Turbine Generator (SSGTG) Exhaust Flange;

repair

259-11-014

Uptake Deck; repair and preserve259-11-015

ShipAlt DDG51-76087D, Gas Turbine (GTRB) and Ship Service Gas Turbine Generator (SSGTG) Boundary Layer Infrared Suppression System (BLISS) Cap Modification; accomplish

259-80-001

Fuel Riser Mounting Bracket; replace261-11-001

Number One Main Reduction Gear (MRG) Lube Oil Cooler; repair262-11-001

Lube Oil Temperature Regulating Valve; repair262-11-002

Number 2 Main Reduction Gear (MRG) Lube Oil Cooler; repair262-12-001

Lube Oil Settling Tank Heater Element; inspect and clean262-21-001

Lube Oil Settling Tank Heater Element; inspect and clean262-22-001

Electric Driven Lube Oil Pump; repair262-41-001

ShipAlt DDG51-76253K, Install Lube Oil Coalescing Filter; accomplish262-90-001

Number One Lube Oil Purifier Heater Shell; replace264-11-001

ShipAlt DDG-51-85973K, Lube Oil Purifier Heat Exchanger Modifications;

accomplish

264-90-001

Page 8 of 14 EXECUTING WORK

ShipAlt DDG51-64208D, SSGTG Emergency Cooling Water Activation Modification; accomplish

310-80-001

Electrical Receptacle Replacement; accomplish321-11-001

01 Level Weatherdeck Electrical Equipment, Electromagnetic Pulse (EMP) Conduit, Stuffing Tubes and Method Mount Foundations; replace

321-11-003

Weatherdeck Electrical Equipment, Electromagnetic Pulse (EMP) Conduit and Stuffing Tube; replace

321-11-004

01 Level Weatherdeck Lighting and Bulkhead; repair321-11-005

Stuffing Tube, Conduit and Dimmer Switch Replacement; accomplish321-11-006

Flight Deck Electrical Equipment; replace321-11-007

Running Lights Telltale Panel; replace324-11-001

ShipAlt DDG51-77427K, DDGM Digital Indicators Installation: accomplish411-90-001

ShipAlt DDG51-73088K, Gigabit Ethernet Data Multiplex System (GEDMS) Upgrade; accomplish

431-90-001

ShipAlt DDG-51-83419D, Removal Halocarbon Monitoring System;

accomplish

436-80-001

ShipAlt DDG51-77829K, Installation of Radar and Time Domain Reflectrometer (TDR), Tank Level Indicator (TLI) for Diesel Fuel Marine (DFM), JP-5 and Potable Water Tanks; accomplish

437-90-001

ShipAlt DDG51-77269K, Installation of Redundant Tank Level Indicators (TLI) on Generator Head Tanks; accomplish

437-90-002

ShipAlt DDG51-71604K, DDG Mod MCS/DCS Upgrades, Single Central Control Station (CCS) Watchstander; accomplish

438-90-001

ShipAlt DDG51-71726K, DDG Mod Full IBS Upgrade, Single Bridge Watchstander; accomplish

438-90-002

ShipAlt DDG51-80612K, Backfit ICAS Installation (ICAS); accomplish438-90-003

ShipAlt DDG51-80897K, Navy Multiband Terminal (NMT) AN/WSC-9(V)2 Q/KA/X/GBS Installation; accomplish

441-90-001

ShipAlt DDG-51-01100K, NTWK Build, PEOC4I INC 1, Consolidated Afloat Network and Enterprise Services (CANES), PEOC4I ADNS AN/USQ-144K(V)2 W/SP 1/2 and PEOC4I Naval Modular Automated Communications System (NAVMACS) Tech Refresh; accomplish

441-90-002

ShipAlt DDG51-74283K, AEGIS Ballistic Missile Defense (BMD) 4.0 Installation; accomplish (OPTION ITEM)

450-90-002

ShipAlt DDG51-79322K, AEGIS Ballistic Missile Defense (BMD) 4.0.1 Installation; accomplish (OPTION ITEM)

450-90-003

ShipAlt DDG51-74012K, BMD VLS Magazine Ventilation Upgrade;

accomplish (OPTION ITEM)

450-90-004

OrdAlt 75920 and AER 66030, Electronic Equipment Water Cooler A-Style Bonnet and Titanium Tube Bundle Installation; accomplish

456-90-001

ShipAlt DDG51-84530K, AWS: Peripherals Upgrade to SPRS Installation;

accomplish (OPTION ITEM)

456-90-002

SCD 85218K, AN/SQQ-89A(V)15 Tech Refresh with TI-12 Plus Hardware; accomplish

468-90-001

ShipAlt DDG51-86644 K USW-DSS AN/UYQ-100(V)3 to AN/SQQ-89(V)15 Interface; install

468-90-002

OrdAlt-80831 Guided Missile Director AS-3444/SPG-62, Passive Countermeasures System (PCMS) Material; install

472-90-001

Silicon Aluminum Bronze (SAB) Union Fittings; inspect and replace505-11-001

Page 9 of 14 EXECUTING WORK

Collective Protection System (CPS) Clean Side Access Plate; remove512-11-001

Supply Ventilation; replace512-11-004

Ventilation Ducting; replace512-11-005

Vaneaxial Fan; repair512-11-006

Ventilation Diffuser; install512-11-007

Cooling Coil Condensate Drain Piping; install512-11-008

ShipAlt DDG51-77419K, Textile Duct Installation; accomplish512-90-001

Chilled Water Piping Bulkhead Penetration; replace514-11-001

Air Conditioning Plant Resilient Mount; replace514-24-001

ShipAlt DDG51-76721, TOTS Valve Installation; accomplish514-80-001

ShipAlt DDG51-76648K, Refrigeration Plant Overboard Pressure Relieving Modification; accomplish

516-90-001

Sea Valve; repair and replace520-11-001

Firemain Valve and Piping; replace521-11-002

Number 5 Fire Pump Class B Overhaul; accomplish521-21-001

ShipAlt DDG51-73738, Installation of Additional Bulkhead Cutout Valves;

accomplish

521-80-001

ShipAlt DDG51-75829D, Firemain Regulator Strainer, Cord Piping and Structural Modifications; accomplish

521-80-002

ShipAlt DDG51-82474D, Relocation of CIWS, Torpedo and DLS Magazine Gauges (Partial); accomplish

522-80-001

Fan Room Deck Drain; replace526-11-001

Deck Drain; replace526-11-002

Deck Drain; replace528-11-001

Deck Drain Piping; replace528-11-002

Plumbing Valve Remote Operator Deck Box Cover; replace528-11-003

Deck Drain Piping; replace528-11-004

Main Eductor Overboard Discharge Valve Teleflex Cable; replace529-11-001

Electronic Cooling Water (ECW) Flow Switch; replace532-11-001

Machinery Space Structural Repairs and Preservation; accomplish533-11-001

ShipAlt DDG51-70403K, Digital Fuel Control System Installation;

accomplish

541-90-001

ShipAlt DDG51-76034K, Modify JP-5 Piping to Allow Emergency JP-5 Supply to Number 3 Gas Turbine Generator Head Tank and ML;

accomplish

542-90-001

Anti-Icing Hanger and Bellow; replace551-11-001

Number One High Pressure Air Compressor (HPAC) Class B Overhaul;

accomplish

551-51-001

Page 10 of 14 EXECUTING WORK

Number 2 High Pressure Air Compressor (HPAC) Class B Overhaul;

accomplish

551-52-001

ShipAlt DDG51-64209D, Anti-Icing Piping Hot Hanger Modifications (Partial); accomplish

551-80-001

Halon Actuator Tubing Assembly; replace555-31-001

Steering Gear Hydraulic Power Unit (HPU) Number 1A Axial Piston Pump Class B Overhaul; accomplish (Option Item)

561-11-001

Rudder Stock Bearing; inspect562-11-001

Rudder Bearing Seal and Rudderstock Seal; repair562-11-002

Anchor and Anchor Chain Inspection and Preservation; accomplish581-11-001

Boat Handling and Stowage System; repair583-11-001

Vacuum, Collection, Holding and Transfer (VCHT) Piping System;

chemical cleaning

593-11-001

Plumbing Drain Tank; preserve593-11-002

Vacuum, Collection, Holding and Transfer (VCHT) System Piping, replace593-11-003

ShipAlt DDG51-73622, Installation of H2S Detectors in VCHT Rooms;

accomplish

593-90-001

Portable J-Bar Davit; replace611-11-001

Reversible Deck Socket and Bolt; repair and replace612-11-001

ShipAlt DDG51-64223D, CIWS Grating and Corrosion Modifications;

accomplish

622-80-001

Inclined Ladder Grating Platform; replace623-11-001

ShipAlt DDG51-64213D, Vertical Ladder Corrosion Modification (Partial);

accomplish

623-80-001

Balanced Joiner Door; remove, store, repair and install624-11-001

VCHT Room No. 2 Bilge; inspect and preserve631-11-001

Generator Room Bilge; repair and preserve631-11-003

Collective Protection System (CPS) Zone 2 Fan Room; repair631-11-004

Fan Room; repair and preserve631-11-005

Vacuum Collection Holding Tank (VCHT) Room Bilge; preserve631-11-006

Fan Room; preserve631-11-009

Chain Locker; inspect and repair631-13-001

Mast Preservation; accomplish631-21-001

Antenna Platform Structure and Plating; inspect and preserve631-21-003

Underwater Hull; preserve631-31-001

Freeboard Preservation; accomplish631-41-001

Impressed Current Cathodic Protection (ICCP) System; inspect and repair

633-11-001

Page 11 of 14 EXECUTING WORK

Scullery Deck Covering; replace634-11-002

Flight Deck Nonskid; replace634-21-001

Sonar Dome Hull Damping; preserve and replace636-11-001

ShipAlt DDG51-86249D, Removal of Overhead Sheathing in Battle Dressing Stations; accomplish

637-80-001

ShipAlt DDG51-64194D, Composite Radar Cross Section (RCS) Plating Installation; accomplish

639-80-001

Berthing Habitability Projects (BENL-S4329) Installation; accomplish643-11-001

Crew Messroom Renovation; accomplish643-11-003

Sanitary Space Habitability Project (HENL-S4330) Installation;

accomplish

644-11-002

ShipAlt DDG51-71605K, DDG Mod Advance Galley Inst; accomplish651-90-001

Vertical Launch System (VLS) Flush; accomplish721-31-001

Vertical Launch System (VLS), MK 41 Launcher Top and Uptake Hatch;

preserve

721-31-002

MK 41 Vertical Launching System (VLS) Uptake Hatch; replace721-31-003

Vertical Launching System (VLS) Cell Hatch; replace721-31-004

Torpedo Handling Transfer Station Chock Plate and Protective Screw;

replace

752-11-001

AEGIS Light-Off (ALO) Compartment Release Schedule; provide813-11-001

Production Planning and Estimating, On-Site Planning and Support Services (NAVSEA); provide

813-11-002

Production Planning and Estimating, On-Site Planning and Support Services (TYCOM); provide

813-11-003

Compartment Closeout Schedule; provide813-11-004

Antenna Photographs; provide837-11-001

Personnel Berthing Barge Support; provide857-11-001

TYCOM and SWRMC Office Space; provide980-11-001

Industrial Support Services, Hygienist; provide980-11-002

Light-Off Discrepancy Correction Assistance; provide980-11-003

Local Area Network (GIG-E LAN) Support Service; provide980-11-004

ShipAlts 70403K, 71604K, 71615K, 71726K, 73088K and 77829K Naval Surface Warfare Center (NSWC-CD) SSES Alteration Installation Team (AIT) Production, Test Sequence, Coordination and Testing Services;

provide

980-90-001

NAVSEA (PHD) Office Space; provide980-90-002

ShipAlt DDG51-00151.02K, Air Conditioning Plants No. One and 4 Upgrade Industrial Support; provide (OPTION ITEM)

980-90-003

ShipAlt DDG51-80897K, NMT AN/WSC-9(V)2 Q/KA/X/GBS Installation, Alteration Installation Team (AIT) Support Service; provide

980-90-004

Page 12 of 14 EXECUTING WORK

ShipAlt DDG-51-83940K, Video Distribution System (VDS) Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION

ITEM)

980-90-005

ShipAlt DDG-51-01100K, NTWK Build, Alteration Installation Team (AIT) Support Service; provide

980-90-006

OrdAlt 83135, CIWS Cable Reliability, Alteration Installation Team (AIT) Support Service; provide

980-90-007

ShipAlt EC 70619K Alteration Installation Team (AIT) Support Service;

provide

980-90-008

Digital Video Surveillance System (DVSS), 1MC Announcing System Upgrade, Moriah HW for DDG, EM Log Replace AN/WSN-9(V)1 DHYSL and SIWCS, Alteration Installation Team (AIT) Support Service; provide

980-90-009

SHIPALT DDG-51-70403K, 71604K, 71726K, 73088K, 77427K and 77829K DDG MOD CORE Alteration Installation Team (AIT) Support Services

980-90-010

SHIPALT DDG51-70403K, 71604K, 71726K, 73088K, 77829, 71615

Asset Recovery; provide.

980-90-011

ShipAlts 74283K BMD 4.0 Program ORTS Display Upgrade and 79322K BMD-DDG 4.0.1 Ship Impact, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

980-90-012

ShipAlts 70403K, 71604K, 71615K, 71726K, 73088K and 77829K, Naval Surface Warfare Center (NSWC-CD) SSES Alteration Installation Team (AIT) Office Space; provide

980-90-013

ShipAlt DDG-51-77333K, CKT 3TV COTS Upgrade, Alteration Installation Team (AIT) Support Service; provide

980-90-014

OA and SA 79362 AWS Seawater Flow Meter Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

980-90-017

ShipAlt DDG51-84530K, AWS: Peripherals Upgrade to SP, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

980-90-018

ShipAlt DDG51-85218 K AN/SQQ-89A(V)15 Tech Refresh Alteration Installation Team (AIT) Support Services; provide

980-90-019

OA 82668, COTS, Upgrade, Alteration Installation Team (AIT) Support Service; provide

980-90-020

Dock Trial, Fast Cruise and Sea Trial; accomplish982-31-001

Engineering Plant Production Completion and Requirement for Light-Off Assessment (LOA); provide

982-31-002

Temporary Service; provide992-11-001

Temporary Flammable Liquid Storage and Hazardous Material Storage Unit, 640 Square Feet; provide

992-11-002

Pierside T-1 Line; provide992-11-003

Crew Transportation; provide992-11-004

Ship's Force Parking; provide992-11-005

Temporary Air Conditioning; provide992-11-006

Fuel Assistance and Towboat Service for Fuel Barge; provide992-11-007

Temporary Refrigerated Storage Facility, 7,000 Cubic Feet; provide992-11-008

Oil Spillage and Floating Sandblasting Debris Boom; install992-11-009

Small Boat Storage and Repair Facility for Ship's Force Use; provide992-21-001

Page 13 of 14 EXECUTING WORK

Cleaning and Pumping; accomplish992-31-001

Demineralized Water; provide992-31-002

NAVSEA Cleaning, Pumping and Gas Free; provide992-90-003

Ship's Force Warehouse Storage Space; provide993-11-001

Pressurized Waveguide and Transmission Line Dry Air Lay-Up;

accomplish

993-11-002

Rigging, Crane and Forklift Service; provide993-11-003

Rigging, Crane and Transportation Service; provide993-21-001

Temporary Deck Covering; install993-31-001

Temporary Main Reduction Gear (MRG) Dehumidifier System; provide993-31-002

AN/SPY-1D Antenna Protective Cover; install993-31-003

Drydocking and Undocking; accomplish997-11-001

Page 14 of 14 EXECUTING WORK

SHIP: USS PAUL HAMILTON (DDG 60) ITEM NO: 042-11-001

COAR: 16 PCN: EXSY-ZA50

SWT FILE NO: 042-002 CMP: NONE

REVISED: 23 Jan 2015 PLANNER: BRITT, BROOKS

SSP: TPPC-DDG60-SSSD16-CN01 1 of 2 ITEM NO: 042-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Work Package Execution Review; accomplish

1.2 Location of Work:

1.2.1 Not Applicable

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Schedule and chair a Work Package Execution Review (WPER) meeting 30 days prior to availability start. The purpose of this meeting is to review with all activities accomplishing work during the availability, the integrated work production schedule required by NAVSEA Standard Item 009-60. This is the final opportunity to resolve any work interface or production support issues between the various activities before actual production work begins.

Report: Meeting Minutes Date: + 3

3.1.1 Record the minutes of the meeting and submit one legible copy in approved transferrable media to the SUPERVISOR within 3 working days after the meeting. All action items, responsible activity, and proposed date for resolution, shall be included in the report.

3.1.2 In addition to the requirements of 009-60 the following applies:

3.1.2.1 For availabilities greater than 120 days in duration, the production schedule shall be provided no later than 25 days after contract award in lieu of 30 days.

4. NOTES:

4.1 Work Package Execution Review. A meeting that takes place at A-30 for CNO availabilities. There should be representation from all the organizations that are accomplishing work during the scheduled CNO availability. The purpose of this meeting is to review the intergrated work production schedule that has been prepared by the executing activity. This is the final opportunity to resolve any work interface or production support issues between the different activities before actual production work begins.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

SHIP: USS PAUL HAMILTON (DDG 60)

SSP: TPPC-DDG60-SSSD16-CN01 2 of 2 ITEM NO: 042-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

SHIP: USS PAUL HAMILTON (DDG 60) ITEM NO: 042-27-001

COAR: 16 PCN: EXSY-ZA15

SWT FILE NO: 042-001 CMP: NONE

SSP: TPPC-DDG60-SSSD16-CN01 1 of 4 ITEM NO: 042-27-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Accountability of Manhour and Material Reservation;

accomplish

1.2 Location of Work:

1.2.1 Not Applicable

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 None

3. REQUIREMENTS:

3.1 Accomplish the following, in addition to the specific requirements of the Job Order, for Work Items which identify reservation of manhours or material dollars.

3.2 Identify task/discrepancies and initiate an estimate of manhours and material dollars on Reservation Task Request/Control Form (Attachment A) for each discrepancy or task identified to be accomplished under a reservation item or reservation paragraph, entering the date and estimate of labor and material, and deliver the estimate to the SUPERVISOR.

3.2.1 Reservation taskings shall not be used to accomplish work outside the scope of the specific Work Item identifying a reservation work paragraph.

3.3 The SUPERVISOR shall review the estimate submitted and if in agreement, shall sign the "RMC/NSA Authorization Agreement to Quote" blank, authorizing the work at the manhour and material dollars quoted.

The contractor shall then sign the "Contractor Obligation/Agreement to Quote" blank and enter the estimated start date. The RMC/NSA contracts representative shall initial the form in the blank provided.

3.3.1 If there is a difference of opinion in the estimate provided by the contractor and RMC/NSA, the manhours and material dollars shall be negotiated immediately to resolve the difference. The negotiated manhour and material dollars shall then be entered in the provided "Revised Estimate" blocks with the required signatures as indicated in 3.3.

3.4 The Contractor shall enter the work completion date, sign and date the control form, and submit to the SUPERVISOR within two (2) days after completion of the tasking authorized.

Report: Weekly Manhour and Material Reservation Date: + 0

3.5 Submit one legible copy, in approved transferrable media, of a weekly report listing all Work Items with manhour and material reservation paragraphs identified to the SUPERVISOR.

SSP: TPPC-DDG60-SSSD16-CN01 2 of 4 ITEM NO: 042-27-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

3.5.1 The report shall contain the following: Work Item number, reservation control form serial number, reservation paragraph number, total original manhours and material dollars allocated in each paragraph, the manhour and material dollars negotiated for each authorized tasking, and the remaining balances of manhour and material dollars.

Report: Weekly Report - Final Date: + 5

3.6 Submit one legible copy, in approved transferrable media, of a final report no later than five days after completion of the availability to the SUPERVISOR.

3.6.1 The report shall contain the same information specified in 3.5.1.

3.7 The reservation manhours and material dollar requirements listed in the individual Work Items are a part of this contract under the original solicitation and award. Therefore they are subject to the provisions, terms, conditions and clauses of this contract job order and the Master Ship Repair Agreement (MSRA)/The Agreement for Boat Repair (ABR).

3.7.1 The manhour reservation shall include both prime contractor and sub contractor efforts.

3.8 The balance of hours remaining in the reservation items after negotiations have concluded, and it is evident that no additional work will be tasked, is subject to a decrease change order.

3.9 Only actual production manhours expended will be considered towards the contractors obligation to provide the defined reservation manhour effort. While supervision, quality assurance, and other nonproductive labor should be included in the pricing for reservation items in the original bid, they shall not count towards satisfying the contractors obligation to provide reserved manhours. The production manhour reservation shall not include any allowance for technical representatives or for any other Government directed source unless specifically addressed in the individual Work Item.

3.10 Material dollars shall be based on actual costs to the Contractor of acquiring the materials provided. Material dollars may include freight or duties which would be reflected on the invoice for the material. The Contractor shall not be allowed to add material handling charges, overhead (including G & A), or profit into the actual cost of materials expended toward the reservation.

4. NOTES:

4.1 The information received in the consolidated final report of 3.6 will be used by the Contracting Officer in the issuance of one contract modification, which will be a final settlement for all reservation Work Items.

4.2 The reservations listed in the individual Work Items are not to be considered Time and Material or a Level of Effort. Once the scope of work for a task has been listed and a mutually agreeable number of manhours or materials has been agreed to, neither party will be entitled

SSP: TPPC-DDG60-SSSD16-CN01 3 of 4 ITEM NO: 042-27-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

to an adjustment based on actual manhours or material dollars required.

4.3 Each task shall not exceed 25 mandays without approval of the Project Manager.

4.4 The SUPERVISOR will serialize each reservation control form.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SSP: TPPC-DDG60-SSSD16-CN01 4 of 4 ITEM NO: 042-27-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

ATTACHMENT A

SHIP: USS PAUL HAMILTON (DDG 60) ITEM NO: 077-01-001

COAR: 16 PCN: EXSY-ZA46

CSWT FILE NO: 077-003 CMP: NONE

SSP: TPPC-DDG60-SSSD16-CN01 1 of 5 ITEM NO: 077-01-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Hazardous Waste Produced on Naval Vessels; control

1.2 Location of Work:

1.2.1 Throughout the Ship

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Resource Conservation and Recovery Act (RCRA)

2.2 49 U.S.C 5103, Federal Hazardous Materials Transportation Act

2.3 Applicable Hazardous Waste Manifest Form

2.4 10 U.S.C. 7311, Repair and Maintenance of Naval Vessels - Handling of Hazardous Waste

3. REQUIREMENTS:

3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.

3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.

3.1.2 Manage and transport for Navy disposal, Navy-generated

hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.

3.1.3 Submit one legible copy, in hard copy or approved

transferrable media, of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.

3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.

3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor shall obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) shall bear a generator identification

SSP: TPPC-DDG60-SSSD16-CN01 2 of 5 ITEM NO: 077-01-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

number issued to the contractor pursuant to applicable law.

Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator number issued to the contractor.

3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste shall bear a generator identification number issued to the contractor and shall also cite in the remarks block a generator identification number issued to the Navy. The contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor shall obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Manifests prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.

3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.

3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:

AMOUNT

TYPE NAVY CO-GENERATED CONTRACTOR

Acid Solutions (may include _____ ____________ __________ spent sulfamic, citric, chromic, nitric, sulfuric, SSP: TPPC-DDG60-SSSD16-CN01 3 of 5 ITEM NO: 077-01-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

hydrochloric, etc.)

Ethylene Glycol (Antifreeze) 20 GAL 30 GAL 50 GAL

Sodium Hydroxide 50 GAL 50 GAL 50 GAL

Cleaning Solvents _____ ____________ __________

Sodium Phosphates (Tri, Bi, _____ ____________ __________ or Mono)

Fluorocarbons _____ ____________ __________

Morpholine _____ ____________ __________

Sodium Chromates _____ ____________ __________

Hydrazine _____ ____________ __________

Methyl Ethyl Ketone 10 GAL 10 GAL 10 GAL

Spent Abrasive Blast Material 500 LB 500 LB 200 TON

(contaminated with a known hazardous waste)

Trichloroethane 20 GAL 20 GAL 20 GAL

Miscellaneous Chemicals 20 GAL 20 GAL 20 GAL

(Ignitable)

Miscellaneous Chemicals 20 GAL 20 GAL 20 GAL

(Corrosive)

Miscellaneous Chemicals 20 GAL 20 GAL 20 GAL

(TCLP Toxic)

Miscellaneous Chemicals _______ _______ _______

(Reactive)

Oil (Synthetic) 10 GAL 10 GAL 10 GAL

Paints (Enamel, Latex, 26 GAL 350 GAL 150 GAL

Epoxy, thinners, oil based, rubber paint, non-skid, lacquer, remover, varnishes)

Paints (May include lead, 10 GAL 10 GAL 20 GAL cadmium, or chrome)

Paint Strippers (phenols, 10 GAL 10 GAL 10 GAL lead, chromium)

Sludge (Contaminated with 100 GAL 5000 GAL 500 GAL a known hazardous waste)

Wool Felt (contaminated _____ ____________ __________

SSP: TPPC-DDG60-SSSD16-CN01 4 of 5 ITEM NO: 077-01-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

with chromium and PCB's)

Petrolatum 0 GAL 0 GAL 330 GAL

3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.

3.7 Submit one legible copy, in hard copy or approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the SUPERVISOR.

3.7.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.

3.7.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assurance programs.

3.7.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.

3.8 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.

4. NOTES:

4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to Paragraph (b) of 2.4. The contractor is expected to use best management practice to identify and dispose of all hazardous waste. Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of 2.1. Inclusion of these substances in the waste listed in

3.5 does not preclude the contractor from taking action consistent with

2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.

Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.

4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.

4.2 Hazardous wastes are determined by one or more of the following methods:

4.2.1 Chemical analysis which shows that the material

characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed

SSP: TPPC-DDG60-SSSD16-CN01 5 of 5 ITEM NO: 077-01-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

the limits for that material in 40 CFR 261.20 Subpart C.

4.2.2 Reference to a Material Safety Data Sheet (MSDS).

4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.

4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

DRYDOCK REQUIRED

SHIP: USS PAUL HAMILTON (DDG 60) ITEM NO: 110-11-001

COAR: 16 PCN: ER01-ZA98

ER01-ZA90

CSWT FILE NO: 110-004 CMP: NONE

REVISED: 23 Jan 2015 PLANNER: DENNIS, SHAUN

BRITT, BROOKS

ZAYAS, ALBERTO

SSP: TPPC-DDG60-SSSD16-CN01 1 of 5 ITEM NO: 110-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Underwater Hull; inspect

1.2 Location of Work:

1.2.1 Underwater Hull, Sides and Stern

1.2.2 Bilge Keel, Port and Starboard

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Standard Items

2.2 100-6218906 Rev AA, Unit Structural Arr Dwg-Assy Unit 1410

2.3 100-6218911 Rev U, Unit Structural Arr Dwg-Assy Unit 2110

2.4 100-6218916 Rev V, Unit Structural Arr Dwg-Assy Unit 2210

2.5 100-6218917 Rev Y, Unit Structural Arr Dwg-Assy Unit 2220

2.6 100-6218921 Rev U, Unit Structural Arr Dwg-Assy Unit 2310

2.7 100-6218922 Rev AB, Unit Structural Arr Dwg-Assy Unit 2320

2.8 100-6218926 Rev AB, Unit Structural Arr Dwg-Assy Unit 2410

2.9 100-6218927 Rev U, Unit Structural Arr Dwg-Assy Unit 2420

2.10 100-6218931 Rev W, Unit Structural Arr Dwg-Assy Unit 3110

2.11…

This is the start of the file's text. The full file is on GovTribe.