Attachment 1 Frequently Asked Questions.pdf
PDF 25 KB Posted
- Attached to
- Request for Information (RFI) for Silent Anvil Air-Launched Torpedo (SAA-LT) Standoff Delivery Solutions Federal contract opportunity
- Solicitation number
- N00019-27-RFI-PMX201-SILENTANVIL
About this file
This is a Frequently Asked Questions document for the SAA-LT (Small Aircraft Agility-Long Endurance Technology) federal contract opportunity. The document addresses four key inquiries from prospective vendors regarding proposal submission requirements and technical specifications.
The FAQ clarifies that Alternative Positioning, Navigation, and Timing (Alt PNT) with GPS-denied navigation capability is not currently planned as an initial threshold requirement. Regarding submission format, vendors responding with solutions for both design options are limited to a maximum of 15 pages, and the Government has no preference whether vendors submit independent responses for each option or present Option 2 (wing-kit-only) as a subsystem within Option 1 using a combined narrative approach. Additionally, the document confirms that no presentations or slides from the SAA-LT Industry Day will be released, as the event is briefed at the Controlled Unclassified Information (CUI) classification level.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N00019-27-RFI-PMX201-SILENTANVIL RFI (Updated 9-28).pdf | ||
| N00019-27-RFI-PMX201-SILENTANVIL RFI (Updated 9-24).pdf | ||
| Attachment 1 Frequently Asked Questions (Updated 9-24-2026).pdf | ||
| N00019-27-RFI-PMX201-SILENTANVIL RFI (Updated 9-16).pdf | ||
| N00019-27-RFI-PMX201-SILENTANVIL RFI.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Frequently Asked Questions
Q1: Is there a requirement for Alt PNT/ GPS Denied navigation?
A1: Alt PNT/GPS Denied navigation is currently not planned to be an initial threshold requirement.
Q2: Will there be any slides or presentations released from the SAA-LT Industry Day?
A2: Industry Day will be briefed at the CUI level. There are no plans release presentations at this time.
Q3: Can the Government clarify the maximum page count for a response providing a solution for both design options?
A3: The maximum number of pages when providing a response for both solutions is 15.
Q4: Is there a preference for independent responses covering each option, or can vendors treat the wing-kit-only option 2 as a subsystem of option 1 and present a combined narrative?
A4: There is no preference.