RFI Questions and Answers.docx

DOCX document 19 KB Posted

Attached to
F-35 JPO Enterprise Data Science and Analytics Support
Solicitation number
N0001927R0054
Issued by

About this file

This is a Questions and Answers document providing clarification on an RFI (Request for Information) related to F-35 JPO Enterprise Data Science and Analytics Support. The document addresses respondent inquiries regarding the scope, requirements, and submission details for the pre-solicitation activity issued by the Naval Air Systems Command. Key clarifications include guidance on data science and analytics capabilities, enterprise system integration requirements, technical qualifications expected from potential contractors, and administrative details concerning response formatting and submission procedures. The Q&A provides standardized answers to common questions submitted by prospective contractors evaluating their ability to support the F-35 Joint Program Office's data science and analytics initiatives. This resource serves to align contractor understanding of the government's needs and expectations prior to formal solicitation release, helping potential bidders determine their competitive positioning and capability gaps for this opportunity.

View the file

Other files

File Type Posted
PWS F35 JPO - DSaaS - 10 - 22 - 2026.docx DOCX document
DataScience RFI Instructions.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. The instructions limit responses to 20 pages including the cover letter and also limit the capability statement to 5 pages. Please confirm the 5-page limit applies to the capability statement only, and the 20 pages cover the full package.

20 pages is the entire package, ignore the 5-page limit for capability statement.

1. Does the Government anticipate a single-award contract, an IDIQ, or a task order under an existing vehicle? Is there a predecessor or incumbent contract associated with this requirement?

We are conducting market research right now and we are gathering information for this new requirement

1. What contract type is anticipated (FFP, T&M, labor hour, cost reimbursable)? Will a DCAA-approved accounting system be required at award?

FFP. we rely on the vendors system

1. Will key personnel need active TOP SECRET clearances at proposal submission, or at contract start? Is SCI eligibility required?

At proposal submission and SCI eligibility is preferred but not required

1. What DoD cloud Impact Level(s) apply to the hosting environments (e.g., IL4, IL5)?

IL5 and IL6

1. Will the contractor be expected to obtain Platform One / Iron Bank onboarding, or will the Government provide access to existing pipelines?

Contractors may be required to obtain Platform One / Iron Bank onboarding. Government will provide access to existing pipelines within F-35 owned systems

1. Can the Government share an estimated level of effort or number of FTEs?

No, it's a new effort and need industry to provide solutions to the requirement

1. Would the Government consider a WOSB or total small business set-aside if market research shows sufficient capable small businesses?

Yes

1. We'd like to confirm our interest and ask whether the JPO has any additional guidance on the response format or the labor categories it expects to need.

No, this is a new requirement, and we need industry to provide solutions

1. Clearances: RFI Section 3 says personnel "must possess active TOP SECRET clearances," while PWS 11.1 applies the requirement "when identified in the contract." Will Top Secret be required by position, and roughly what share of the work is expected in classified environments?

Top secret clearances will be required for all members of the contract support team.

1. Documents and data: Could you confirm the SAM.gov notice number and that the draft PWS file "PWSF35JPO-DSaaS-10-22-2026" is the current version? Is there a predecessor contract, and will workload data be released before the RFP?

There is no predecessor contract

1. Submission. Is email to both of you acceptable, and do you prefer PDF or Word?

It does not matter if it’s word or pdf.

1. The RFI response instructions state that "Personnel performing under this requirement must possess active TOP SECRET clearances," and Section 4 asks for "Confirmation that the company can provide a team with active Top Secret clearances." The draft Performance Work Statement says something different. Section 9.2 states "The contractor team should have active Top Secret clearances," and Section 10 states "Personnel will be required to possess active TOP SECRET clearance when identified in the contract; such eligibility does not authorize classified performance under this PWS." Does the clearance requirement apply to every team member, or may uncleared personnel perform unclassified work, with Top Secret applying only to the positions the contract identifies?

Top secret clearances will be required for all members of the contract support team to ensure solutions developed in the unclassified space are efficiently deployed in classified spaces.

1. Facility clearance. Will a facility clearance be required at proposal, at award, or before classified performance begins? Would the Government consider sponsoring offerors for facility clearances during the competition, as 32 CFR 117.9(a)(10) allows?

Due to the project schedule, the Government would prefer offerors that possess the required TS FCL at the time of proposal submission. The Government will not delay the procurement or condition award on an offeror’s ability to obtain a TS FCL after sponsorship. Offerors are responsible for ensuring that they meet all applicable facility-clearance requirements by the solicitation’s stated deadline.