MUX_Acquisition_Overview_Brief_FBO_04June2018.pdf
PDF 81 KB Posted
- Solicitation number
- N00019-18-NORFP-PMA-266-0126
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MUX_Industry_Day_Q&As.pdf | ||
| Industry_Day_Attendee_List.pdf | ||
| MUX_Industry_Day_USMC_Brief.pdf | ||
| MUX_Technical_Requirements_Brief_FBO_04June2018.pdf | ||
| Updated_MUX_Industry_Day_Agenda_06.01.2018.pdf | ||
| MUX_Industry_Day_Registration_Form_-_20180503.pdf | ||
| MUX_Industry_Day_Agenda_Final_-_FBO_20180425_(2).pdf | ||
| MANGL_Dimensions.xlsx | XLSX spreadsheet | |
| MUX_Updated_tables.pptx | PPTX presentation | |
| MUX_Industry_Q&As.docx | DOCX document | |
| N00019-18-NORFP-PMA-266-0126_MUX_AV_RFI_FINAL_03-08-2018.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Unclassified
MAGTF UAS Expeditionary (MUX) Industry Day Agenda: June 6-7, 2018
Wingate Hotel – Fredericksburg, VA
DAY 1
• 0730-0845: Sign-In
• 0855-0900 Administrative Remarks Marci Spiotta / PMA-266
• 0900-0905 Introduction Col Frey
• 0905-0920 Opening Remarks LtGen Rudder / DCA
• 0920-0935 Opening Remarks LtGen Walsh / MCCDC
• 0935-1005 Marine Corps MUX Concepts & Overview Col Frey / BGen Adams
‒ CONOPS
‒ Requirement
• 1005-1020 MUX Acquisition Overview CAPT Dodge / PMA-266 ‒ Teaming Arrangements / Small Business Opportunities
• 1020-1030 Break
• 1030-1200 Detailed Briefings:
‒ Budget/Schedule Col Frey
• CBA / ICD
‒ Mission Profiles FMID / PMA-266 ‒ Technical Requirements PMA-266
• Aircraft
• Mission Systems
• Control Station / NIOPS
• Systems Engineering Environment
• 1200-1330 LUNCH
• 1330-1630 One-on-One Session 1 – Separately Scheduled Govt./Industry
DAY 2
• 0830-1630 One-on-One Session 2 – Separately Scheduled Govt./Industry
NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
MUX Acquisition Overview
CAPT Dodge, Program Manager
PMA-266
2NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
Program Timeline
• Initial program development FY18-FY20
– Analysis of Alternatives (AoA) and trade studies
– Additional RFI(s) may be released for mission systems, control station, etc.
• Refine the acquisition plan FY19
– Mid-tier rapid prototyping vs. tailored DoD 5000
• MUX acquisition decision FY20
– Commence prototyping and development
– Land-based Early Operational Capability (EOC) within five years of acquisition decision
– Land-based Initial Operational Capability (IOC) within seven years of acquisition decision
– Sea-based IOC within nine years of acquisition decision
3NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
Intellectual Property
• Expect a mix of contracting elements to include
– Limited
– Government Purpose Rights (GPR)*
– Unlimited rights
• Seeking the right balance that supports sustainment, maintenance, and operations
*Government desires the data rights necessary to enable rapid upgrades
NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
Integration Strategy
• The overall system integration strategy remains undecided
– Seeking Industry feedback on effective combinations of Original
Equipment Manufacturer (OEM), Government, and Third Party development and integration
• Intended Government Furnished Equipment (GFE)
– Common Control System (CCS)
– Communication systems (e.g., radios, data link terminals, etc.)
– Weapon systems
• Open Architecture
– Architecture that allows for separation of flight controls and mission systems management
– Use of recognized open standards
– Use of model-based engineering where feasible
5NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
Small Business
• Government desire for rapid delivery presents opportunities for small business participation
• Integration strategy / acquisition strategy being developed with a goal of encouraging / incentivizing small business participation
6NAVAIR Public Release 2018-468. Distribution Statement A - "Approved for public release; distribution is unlimited"
| MAGTF UAS Expeditionary (MUX)�Industry Day Agenda: June 6-7, 2018�Wingate Hotel – Fredericksburg, VA |
| MUX Acquisition Overview ��CAPT Dodge, Program Manager�PMA-266 |
| Program Timeline |
| Intellectual Property |
| Integration Strategy |
| Small Business |