QA-16-23_July26.docx

DOCX document 15 KB Posted

Attached to
Solicitation for NAVAIR-HQ's requirement for Commercial Common Initial Spares for the P-8A Aircraft
Solicitation number
N0001912R3001
Issued by

About this file

Q A 16-23

View the file

Other files

File Type Posted
Amendment0004_Aug0612.doc DOC document
QA-24 Aug2.docx DOCX document
Spares List 02 Aug 2012 final.xlsx XLSX spreadsheet
Amendment0003Aug2.doc DOC document
Amendment0002_72512_Final.docx DOCX document
Final Commercial Common Spares 25 July 2012 final bnf.xlsx XLSX spreadsheet
Spares_List_11 July 2012.xlsx XLSX spreadsheet
Amendment0001_0717.doc DOC document
Q A_0716.docx DOCX document
Solicitation_Final_RemovedWatermark.pdf PDF
Solitiation_0621_FINAL.doc DOC document
Final Commercial Common Spares 20 Jun 12.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 25, 2012: Question and Answers 16-23

16. What is the per day liquidated damages rate?

A: The per day liquidated damages rate is .05% of the delayed CLIN’s value, per day.

17. Will the Government split awards based on different part numbers?

A: No. The Government does not intend to split awards based on different part numbers.

18: Will the Government extend the solicitation due date by one week?

A: Yes. The date has been extended to 6 August 2012.

19: The specific instructions for the Technical Volume states that “This volume shall not contain any reference to cost of price aspects of the offer”; however, Paragraph F instructs the Offeror to include the SB Subcontracting Plan in this volume. Should the SB Subcontracting Plan be included in Volume IV- Price Proposal because it contains reference to the price of the offer?

A: No, the SB Subcontracting Plan should be included in the Technical Volume. As it contains prices, offerors shall make it as an Annex so that it can be separately evaluated outside of the other technical factors. Please refer to the amended Section L, Addendum to 52.212-1.

20: Please confirm that the vast majority of spare parts are required for Pax River with a delivery date of 6/1/2014 as shown in Attachment 1 and SECTION F.

A: Please see the updated Section F and Attachment 1.

21: Please provide alignment of delivery date requirements of Attachment 1 with SECTION F or modify Section B and SECTION F to eliminate blocks and use only locations for CLIN designations.

A: Please see the updated Section F and Attachment 1

22. Will the Government update part numbers if they have been found to be superseded/rolled?

A: The Government does not intend to update the part numbers.

23: Can the Representations and Certifications from the Volume I be exempt from the page count?

A: Yes. Please refer to the amended Section L, Addendum to 52.212-1.