QA-16-23_July26.docx
DOCX document 15 KB Posted
- Attached to
- Solicitation for NAVAIR-HQ's requirement for Commercial Common Initial Spares for the P-8A Aircraft
- Solicitation number
- N0001912R3001
About this file
Q A 16-23
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment0004_Aug0612.doc | DOC document | |
| QA-24 Aug2.docx | DOCX document | |
| Spares List 02 Aug 2012 final.xlsx | XLSX spreadsheet | |
| Amendment0003Aug2.doc | DOC document | |
| Amendment0002_72512_Final.docx | DOCX document | |
| Final Commercial Common Spares 25 July 2012 final bnf.xlsx | XLSX spreadsheet | |
| Spares_List_11 July 2012.xlsx | XLSX spreadsheet | |
| Amendment0001_0717.doc | DOC document | |
| Q A_0716.docx | DOCX document | |
| Solicitation_Final_RemovedWatermark.pdf | ||
| Solitiation_0621_FINAL.doc | DOC document | |
| Final Commercial Common Spares 20 Jun 12.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
July 25, 2012: Question and Answers 16-23
16. What is the per day liquidated damages rate?
A: The per day liquidated damages rate is .05% of the delayed CLIN’s value, per day.
17. Will the Government split awards based on different part numbers?
A: No. The Government does not intend to split awards based on different part numbers.
18: Will the Government extend the solicitation due date by one week?
A: Yes. The date has been extended to 6 August 2012.
19: The specific instructions for the Technical Volume states that “This volume shall not contain any reference to cost of price aspects of the offer”; however, Paragraph F instructs the Offeror to include the SB Subcontracting Plan in this volume. Should the SB Subcontracting Plan be included in Volume IV- Price Proposal because it contains reference to the price of the offer?
A: No, the SB Subcontracting Plan should be included in the Technical Volume. As it contains prices, offerors shall make it as an Annex so that it can be separately evaluated outside of the other technical factors. Please refer to the amended Section L, Addendum to 52.212-1.
20: Please confirm that the vast majority of spare parts are required for Pax River with a delivery date of 6/1/2014 as shown in Attachment 1 and SECTION F.
A: Please see the updated Section F and Attachment 1.
21: Please provide alignment of delivery date requirements of Attachment 1 with SECTION F or modify Section B and SECTION F to eliminate blocks and use only locations for CLIN designations.
A: Please see the updated Section F and Attachment 1
22. Will the Government update part numbers if they have been found to be superseded/rolled?
A: The Government does not intend to update the part numbers.
23: Can the Representations and Certifications from the Volume I be exempt from the page count?
A: Yes. Please refer to the amended Section L, Addendum to 52.212-1.