N42 Multimedia Department Statement of Work for Large Format Professional Photo Quality Poster Printers
1.0 SCOPE
1.1 This Statement of Work (SOW) defines the scope of work required to purchase (2) new professional photo quality poster printers and (1) professional photo quality latex poster printer for the Naval Maritime Intelligence Center (NMIC). It includes the installation, set-up, warranty service and training for three (3) devices. Technical/CAD type plotters and printers will not be considered.
2.0 BACKGROUND
2.1 The Multimedia Services Department (N42) operates and maintains graphic, design and printing services providing briefing boards, media display’s, other unique large format production requirements for the Director, Naval Intelligence, Chief of Naval Operations and National Level Consumers.
3.0 REQUIREMENTS
3.1 All equipment provided in support of this SOW shall conform to Executive Order 13423, meet July 2009 Energy Star Requirements, and meet Section 508 Accessibility Standards of the Federal Rehabilitation Act.
3.1.1 The specific areas supported are:
· Administrative & System Support
· System Hardware/Software Specifications
· Security Authorized to Operate (ATO) Support
3.1.2 Equipment in Attachment 1A must be of the same manufacturer to maintain color matching and production run consistency, and for maintaining economical parts/consumable inventory. Equipment in Attachment 1B can be a different manufacturer from 1A if need be due to the Non-Solvent Latex requirement. Contractor technical proposal submissions shall address each section of the SOW and include clear descriptions of the proposed make and model to include all standard features and options that together meet the government stated requirements.
3.2 Administrative & System Support
3.2.1 The contractor shall provide equipment to support the requirements as specified in this SOW.
3.2.2 The contractor shall provide delivery, installation and set-up of equipment (as stated in the chart below) within 90 days after the contract is awarded. Delivery after 90 days is non-negotiable. The contractor shall provide an industry standard machine warranty for every piece of equipment to include but not limited to: service, parts, labor, and travel. The warranty shall not being until all equipment has been delivered and installed. Training shall be provided as described in Section 9.0.
| CLIN # |
| Item Description |
| Delivery Date |
| Quantity Delivered |
| 0001 |
| 60 Inch Postscript Professional Photo Quality Poster Printer |
| 90 days after date of award |
| 2 each |
| 0002 |
| 64 Inch Aqueous Based Latex Professional Photo Quality Poster Printer |
| 90 days after date of award |
| 1 each |
| 0003 |
| Onsite Formal Training at Equipment Location |
| 1-5 business days after date of installation |
| 3 each |
3.2.3 The contractor shall provide a delivery plan NLT 10 business days after contract award that details tasks and timelines for equipment deliveries. Delivery installation and software documentation requirements specific to individual machines shall be delineated in the delivery plan Section 5.0. (CDRL A0001 & A0004)
3.2.4 The contractor shall provide a training plan that details timelines for formal equipment training. Training schedule specific to individual machines shall be delineated in the training plan Section 5.0. (CDRL A0002)
3.2.5 The contractor shall schedule a pre-delivery meeting with the N42 point of contact no later than five-seven business days after contract award for a site visit and to discuss delivery and installation logistics to ensure equipment delivery and installation are agreed to by the government. Point of delivery has restrictions to include but not limited to: advanced delivery date notice, pre-screening of contractor and delivery personnel and pre-entry inspections; that will all be coordinated with the N42 point of contact.
3.3 System Hardware/Software Requirements
The contractor shall provide all equipment as delineated in Attachment 1A and 1B. This SOW is for new equipment only, reconditioned or used equipment will not be considered or accepted.
3.3.1 Salient characteristic requirements of new equipment shall be within the scope as noted in Attachment 1A and 1B.
3.3.2 The contractor shall be responsible to coordinate (in conjunction with the N42 point of contact) all installation procedures and processes with Hopper ISC-O Network administration. Hopper ISC-O points of contact shall be provided no later than seven business days after contract award.
3.4 ONI Enterprise Requirements
Technical proposals that do not contain complete ONI Enterprise Requirements will be eliminated from consideration.
3.4.1 ONI Enterprise Architecture Compliance Requirements
3.4.1.1 If a front end controller (RIP) is required, the contractor shall provide a RIP that is configured with Windows 10 Operating System.
3.4.1.2 The contractor shall be available to perform operating system upgrade(s) as needed to conform to the ONI enterprise operating environment.
3.4.1.3 The contractor shall provide installation support for all units proposed in response to this statement of work. Support shall be coordinated with Hopper ISC-O and N42 Systems Administrator providing oversight.
3.4.1.4 The contractor shall provide, no later than 10 days after award, installation instruction documentation for all units proposed. (CDRL A0004)
3.4.2 ONI Enterprise Security System Requirements (CDRL A0003)
SECNAV Instruction 5239.3B requires all Department of the Navy activities to institute an Information Assurance (IA) policy. IAW ONI IA policy any information technology (IT) asset acquisition shall comply with minimum security standard configuration requirements.
Technical proposals shall contain a Security Concept of Operations (SECONPS) that provides an overview of the System Minimum Configuration Security Requirements identified in Attachment 1C, Table 1. The SECONOPS shall detail how proposed unit features will be implemented and utilized operationally in a secure manner.
The SECONOPS shall be organized by paragraph referencing Table 1 line numbers in order. Security configuration lock-down procedure(s) shall be provided for each line item in the table. If the feature is not applicable or not required it shall be indicated N/A. Features not represented in Table 1 may be added by number and indicated in the SECONOPS as “Additional Item #X.”
Network and host based security scanning tools will be utilized to perform security scans on all systems and devices, if applicable. When/if network scanning produces security findings, the Offeror shall address and mitigate the finding(s). In cases where the findings cannot be resolved, the Offeror shall provide mitigation options along with a plan to resolve the findings.
Proposals that do not address security requirements will be eliminated from consideration.
4.0 GOVERNMENT FURNISHED EQUIPMENT
No government furnished equipment shall support this effort.
5.0 DELIVERABLES
All Contract Data Requirement List (CDRL) deliverables required under this SOW are listed below. All deliverables shall meet approved requirements, comply with Section 6.0 of this SOW and shall be delivered as a Microsoft Office document to the N42 point of contact.
| CDRL |
| TITLE |
| FREQUENCY |
| FORMAT |
| A0001 |
| Delivery Installation Schedule |
| 15 days after contract award |
| Contractor choice |
| A0002 |
| Training Schedule |
| 15 days prior to installation date |
| Contractor choice |
| A0003 |
| Security CONOPS Verification |
| 10 days prior to installation date |
| MS Office 2003 or later. |
| A0004 |
| Software Installation Documentation |
| Electronically submitted 10 days after award. |
| MS Office Word 2003 or later. |
6.0 QUALITY ASSURANCES
The contractor shall ensure quality results by maintaining weekly email communication with the N42 point of contact. Weekly communication shall be conducted each Tuesday or as required beginning with the first Tuesday after award.
7.0 TRAVEL
No travel is anticipated in support of this SOW.
8.0 LOCATION
Equipment installation and service delineated in this SOW shall be rendered by the contractor to the Office of Naval Intelligence, Suitland, Maryland. Assets added to the inventory during the execution period of the contract shall be designated a location at the time of selection.
9.0 TRAINING
The contractor shall provide basic onsite training for the equipment on the day of installation/setup. Basic training should consist of but is not limited to; on/off, loading paper, paper path through machine, simple finishing, menus, auto document feeding, basic RIP functions, etc. Formal training shall be provided onsite within 1-5 business days after equipment installation and shall be prescheduled with the N42 point of contact. Formal training shall consist of but is not limited to; finishing operations, paper libraries, color control, troubleshooting, advanced menu functions, advanced RIP functions, color calibration, etc. Additionally, the contractor will provide one day of formal training in maintenance and troubleshooting the machines within 15 business days of installation.
10.0 SECURITY
10.1 Inspections: All items being carried into and out of the government facility are subject to physical inspection by Government Security Protective Officers.
10.2 Escorting will be provided by ONI personnel for onsite visits. At a minimum, contractor shall provide drivers license and vehicle insurance information, VIN number and tag information upon request.
10.3 No copier parts of any kind shall be removed once installed/setup in the government facility. Under no circumstances will a copier hard drive, circuit board or memory device be removed from the installed equipment by a vendor technician. Copier hard drives, circuit boards and memory boards upon delivery are government owned property and will be disposed of by government personnel after being used and/or replaced.
10.4 Prohibitive Items: The following items are prohibitive and shall not be brought into the government facility. Prohibitive items are subject to permanent confiscation. This list is subject to change and the contractor shall make inquiries with the government point of contact of possible changes prior to entering the government facility.
· Firearms, Knives or Dangerous Weapons
· Laptops
· Ammunition
· MP-3 Players
· Alcohol
· PDAs w/audio or video record capability
· Illegal or Controlled Substances (other than prescription medicine)
· PEDs w/audio or video record capability
· Personal two-way pager
· Explosive or Combustible Materials
· Cameras or Recording Equipment (audio, video, photographic, magnetic, optical, etc)
· Corrosive Chemicals
· Chemical or Biological Materials
· Cellular Telephones
· CD or DVD
· USB, Micro Drive or Thumb Drives
If items from the prohibitive list are required to perform any of the duties during the contract phase, the contractor shall make the government aware prior to contract award. CD, DVD’s and other types of electronic servicing media used by the installation technician are subject to government Systems Security evaluations and guidelines prior to introduction into the government facility. After use, these materials become the property of the Government of the government and cannot be removed from the facility.
UNCLASSIFIED//FOR OFFICIAL USE ONLY 9/6/18
ATTACHMENT 1A
60 INCH POSTSCRIPT PROFESSIONAL PHOTO QUALITY PRODUCTION PRINTER REQUIREMENTS
QUANTITY
· Two (2)
CONNECTIVITY
· Printer Driver Windows 10, Postscript Windows, Mac Drivers with Postscript and PDF capability
· TCP/IP 10/100/1000
· No Bluetooth or WIFI Printing Gigabit Ethernet (1000Base-T)
· If Front End Controller or RIP is required must have Windows 10 OS.
FUNCTIONALITY
· Memory: Minimum 64 GB
· Hard Disk: Minimum 300 GB
· Front Panel Touch Screen
· Print Language’s: Adobe Postscript (PS), PDF, TIFF, JPEG
· Print Resolution: Best Quality 2400x1200 dpi (optimized)
· Ink Type: Pigment-based inks
· Color Configuration: Minimum 8 Ink Configuration
· Embedded Spectrophotometer within the printer
· Operator replaceable print heads and maintenance cartridges
· Color Accuracy: 95% of colors. No color banding and capable of consistent repeat color printing without requiring calibration for each print
· Multiple Print Modes is Desirable
MEDIA
· Media Handling: Roll Feed
· Media Size: up to 60 inch roll width / up to 22 mil thickness / up to 114lb weight pending media type
· Media Types: Must print on uncoated bond, high gloss coated, photographic and proofing paper, backlit, self-adhesive, banner and textile materials (fabric)
· Provide instant dry capability as the printed product exits the machine must be dry and capable of being immediately laminated
· Auto Cutter with Media Catch Bin / Take Up Roll
WARRANTY
· Minimum 1-year manufacturer warranty. 2 or 3-year warranty is desirable.
MAINTENANCE
· No daily maintenance requirements on equipment
ENVIRONMENTAL/SAFETY
· Equipment, cleaning products, and all consumables (ink, maintenance products, etc) must be non-hazardous and pass all U.S. Federal environmental law/regulations and industry certifications for ecological and environmentally green standards
· The equipment and any of the related materials required for the continual use, upkeep, or maintenance of the equipment must not require special ventilation other than normal office working environment
· No hazardous restrictions or labels for operational use, materials, inks, equipment, or cleaning chemicals
· Provide Manufactures Safety Data Sheets (MSDS) for all chemicals, inks, or any products related to this equipment
DELIVERY
· Delivery, training, and installation shall occur no more than 90 days after receipt of award
SECURITY CHECKLIST
· Each of the attached security checklist questions must be answered in order for the offer to be considered
ATTACHMENT 1B
64-INCH NON-SOLVENT BASED LATEX
POSTSCRIPT PROFESSIONAL PHOTO QUALITY PRODUCTION PRINTER
QUANTITY
· One (1)
CONNECTIVITY
· Printer Driver Windows 10, Postscript Windows, Mac Drivers with Postscript and PDF capability
· TCP/IP 10/100/1000
· No Bluetooth or WIFI Printing Gigabit Ethernet (1000Base-T)
· If Front End Controller or RIP is required must have Windows 10 OS.
FUNCTIONALITY
· Memory: Minimum 64 GB
· Hard Disk: Minimum 320 GB
· Front Panel Touch Screen
· Print Language’s: Adobe Postscript (PS), PDF, TIFF, JPEG
· Print Resolution: Native 1200 x 1200 dpi
· Ink Type: Non-Solvent Environmentally Friendly Latex Inks (Aqueous Based)
· Color Configuration: Minimum 7 color print cartridges
· Embedded Spectrophotometer within the printer
· Operator replaceable print heads and maintenance cartridges
· Color Accuracy: 95% of colors. No color banding and capable of consistent repeat color printing without requiring calibration for each print
MEDIA
· Media Handling: Roll Feed
· Media Size: up to 64 inch roll width / up to 22 mil thickness
· Media Types: Self-adhesive vinyl, film, fabric, wall coverings, canvas, synthetics, mesh textiles, various papers
· Provide dry scratch resistant printed products upon machine exit
· Auto Cutter with Take Up Roll / Media Catch Bin
WARRANTY
· Minimum 1-year manufacturer warranty. 2 or 3-year warranty is desirable.
ENVIRONMENTAL/SAFETY
· Equipment, cleaning products, and all consumables (ink, maintenance products, etc) must be non-hazardous and pass all U.S. Federal environmental law/regulations and industry certifications for ecological and environmentally green standards
· The equipment and any of the related materials required for the continual use, upkeep, or maintenance of the equipment must not require special ventilation other than normal office working environment
· No hazardous restrictions or labels for operational use, materials, inks, equipment, or cleaning chemicals
· Provide Manufactures Safety Data Sheets (MSDS) for all chemicals, inks, or any products related to this equipment
DELIVERY
· Delivery, training, and installation shall occur no more than 90 days after receipt of award
SECURITY CHECKLIST
· Each of the attached security checklist questions must be answered in order for the offer to be considered
ATTACHMENT 1C - Enterprise Requirements, each line number must be addressed for the offer to be considered.
Table 1 System Minimum Security Configuration Requirements
| Line Number |
| Technical Requirement/Feature |
| Security Requirement |
| 1.0 |
| USB ports |
| Removed or not present in hardware. If these ports cannot be removed (i.e. they are required for connectivity requirements) procedures to disable them must be provided by the vendor. |
| 2.0 |
| DVD/CD Drives |
| Removed or not present in hardware. If these drives cannot be removed (i.e. they are required to load software), procedures to disable them must be provided by the vendor. |
| 3.0 |
| Wired Networking |
| Networking capabilities (i.e. hostname, IP address, DNS, DHCP) must be securely configurable. |
| 4.0 |
| Wireless Networking |
| Removed or not present in hardware. If wireless network adapters cannot be removed they must be disabled via software configuration. |
| 5.0 |
| User Accounts |
| Accounts on the system must be individually attributable to a specific user; for example there should not be a single shared administrator account. If the system is UNIX based, access to the root account should be disabled or should require logging in as a normal user first to access. Accounts should support or enforce strong password protection rules, i.e. passwords should require uppercase letters, lowercase letters, numbers and special characters, passwords must be longer than 8 characters, passwords must be changed in accordance with security policy (i.e. every 90 days). |
| 6.0 |
| Remote Access Capabilities |
| All remote access capabilities (i.e. SSH, FTP, SMB, web-based login) must be documented. Procedures to disable unnecessary capabilities must be provided. Remote access capabilities must use secure protocols (i.e. SSH or SFTP, not RSH or FTP). |
| 7.0 |
| Web Server |
| If the system’s remote access capabilities include a built-in web server, this server should be removed or disabled. If the web server cannot be disabled (for example it is required for system administration), the type of web server used (i.e. Apache, BEA WebLogic, IIS) should be identified, and procedures to configure the web server securely should be provided. |
| 8.0 |
| Auditing and Logging |
| All access to the system must be logged and auditable. Administrative actions taken on the system must be attributable to individual users. |
| 9.0 |
| Web Browser |
| If the system includes a web browser, it should be removed or disabled. If the browser is a required component, the type of web browser used should be identified, it must require a user login to access, and it should be configured securely. |
| 10.0 |
| Internal Operating System |
| Must be identified. Must be an operating system that is still supported by the original vendor; for example Windows NT would not be acceptable. If possible the operating system should be built to a secure baseline (i.e. DoDIIS Baseline), otherwise the operating system should be configurable to meet DoD 8500.2 security controls for UNCLASSIFIED or SECRET networks, and NIST 800-53 security controls for TOP SECRET/SCI and above networks. If the operating system cannot be reconfigured (i.e. it is built on a read-only drive), it must ship in a secure configuration from the vendor. If the operating system is a vendor-proprietary operating system, or a vendor-customized version of a commercial or open source operating system, the vendor must provide documentation regarding the operating system’s security configuration. |
| 11.0 |
| Email Capabilities |
| Removed or not present. If this capability is needed to support operational requirements, procedures to disable it and to configure it securely when enabled must be provided. |
| 12.0 |
| Patch Management |
| Hardware-specific patches must be provided by the vendor on a regular schedule, and procedures to apply such patches must be documented and provided. Operating system or software-specific patches not released by the vendor must be loadable by the customer. Such patches should be tested by the vendor, and any patches which would damage the system’s functionality should be documented. |
| 13.0 |
| Secure Print |
| The hardware should support secure print job capabilities, including PIN code or password protection for all print jobs. |