B2.03 Sec J Attachment 10 Q_A.pdf

PDF 213 KB Posted

Attached to
Navy ManTech - Composites Manufacturing Center (CMC)
Solicitation number
N0001420R0007
Issued by

About this file

This document contains a question and answer file related to a solicitation for the Composites Manufacturing Center. The solicitation is seeking a contractor to operate the Composites Manufacturing Center of Excellence to develop and demonstrate manufacturing technology solutions for identified Navy composites manufacturing requirements. Key details include that the solicitation number is N0001420R0007, issued by the Office of Naval Research within the Department of the Navy Secretary's office. The Composites Manufacturing Center will help key Navy acquisition programs like aircraft carriers, destroyers, and submarines achieve affordability goals by transitioning manufacturing technologies that reduce costs. The Center will develop cost reduction portfolio and projects, and provide consulting services and facilitate implementation of technologies for naval industrial activities and industry.

View the file

Other files

File Type Posted
B2.03 A0001.pdf PDF
B2. 01RFP Sec J Attachment 5 PPIF.docx DOCX document
B2. 01RFP Exhibit A CoE Level CDRLS.docx DOCX document
B2. 01RFP Exhibit B Project CDRLS.docx DOCX document
B2. 01RFP Sec J Attachment 6 PPQ.docx DOCX document
B2.01 N00014-20-R-0007.pdf PDF
B2. 01RFP Sec J Attachment 4 COR.docx DOCX document
B2. 01RFP Sec J Attachment 3 Report Format.doc DOC document
B2. 01 ENCLOSURE NUMBER 1.docx DOCX document
B2. 01RFP Sec J Attachment 1 SOW CMC.docx DOCX document
B2. 01RFP Sec J Attachment 2 Key Personnel.doc DOC document
B2. 01RFP Sec J Attachment 7 Price Information.docx DOCX document
B2. 01RFP Sec J Attachment 8 CE Summary.xlsx XLSX spreadsheet
B2.01 Sec J Attachment 9 ONR Reps_Certs.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Composites Manufacturing Center (CMC) Attachment 10 Q&A Solicitation No. N00014-20-R-0007 As of Amendment 0001

# Document Page Section Question KO Response 1 Solicitation 1 SF33 Blocks 7 and 10 On the Standard Form (SF) 33 of the solicitation, there are two different phone numbers listed for the Office of Naval Research (ONR) solicitation Point of Contact, Ms. Dent in Blocks 7 and 10. Is there a preferred number to use in the event communications via phone are necessary?

Please use 850-276-2279.

2 Solicitation 2 Section C On Page 2 of the solicitation, ONR - Statement of Work, Paragraph (2), can you confirm “Electronics” is to read “Composites”? This should read as Composites.

3 Solicitation 3 Section C On page 3 of the solicitation, Section C, ONR - Acknowledgement of Sponsorship, can you confirm “(252.204-7000)” is a DFARS clause? Yes, 252.204-7000 is a DFARS clause.

4 Solicitation 7 Section G On page 7 of the solicitation, Section G, ONR- Incrementally Funded Orders, Allotment of Funds provision, first paragraph, can you confirm “order” and “estimate” after each “$” is to be a fill in blank?

This clause will be placed in each resultant Task Order. This will be filled out at time of Task Order award.

5 Solicitation Section G Reference Section G of the solicitation. Based on previous ONR Requests for Proposals (RFPs), XXX expected to see ONR - Travel Costs provision in Section G as follows: “Travel may be required to support this Statement of Work. For profit Contractor’s travel costs shall be reimbursed in accordance with FAR 31.205-46 at rates not to exceed the maximum locality per diem rates (the combination of lodging, meals and incidentals) in effect at the time of travel, as set forth in the Federal Travel Regulations, Joint Travel Regulation and Standards Regulations, Section 925, as applicable.

For educational Contractor’s, travel shall be reimbursed in accordance with OMB Circular A-21. All Contractor travel arrangements including: clearance requests, hotel accommodations, travel orders, and visa/passport requirements, are the Contractor’s responsibility.” Will ONR include this provision in the solicitation and/or resultant contract?

Yes 6 Solicitation Section G Reference Section G of the solicitation. Based on previous ONR Requests for Proposals (RFPs), XXX expected to see ONR- Payment of Allowable Cost provision in Section G as follows: “As consideration for the proper performance of the work and services required under this contract, the Contractor shall be paid as follows: Costs, as provided for under the contract clause entitled “Allowable Cost and Payment”, not to exceed the amount set forth as “Estimated Cost” in Section B, subject to the contract clause entitled “Limitation of Cost” or “ Limitation of Funds”, whichever is applicable.” Will ONR include this provision in the RFP and/or resultant contract? No, this is on page 7 of the original solicitation.

7 Solicitation 12 Section H On Page 12 of the solicitation, Section H, ONR –

Orders, Paragraph (d), does this provision apply to ONR’s issuance of unilateral orders only on XXX proposals whose subcontractors’ proposal validity date has not expired?

ONR's award of the Task Order/modificaiton to the Task Order is to the prime. As ONR does not have a relationship with the subcontractor(s), it is up to the prime to make sure the subcontractors proposal does not 1) exceed bid validity or 2) the subcontractor(s) will extend their bid validity. Yet, the clause states "may" and the ONR PCO uses the Changes Clause to award and/or modify a project where a subcontractor would have bid validity. The changes clause requires a bilateral action.

8 Solicitation 15 Section H On Page 15 of the solicitation, Section H, ONR- Organizational Conflict of Interest. The following statement appears to be a missing before the first paragraph based on previous ONR solicitations: "If required, the below language as it pertains to Conflicts of Interest will be inserted into the resultant IDIQ award:" Will ONR consider adding this statement to the solicitation and/or resultant contract?

This is an oversight but this clause will be included in the award as COI may occur prior to, or during, the IDIQ award.

9 Solicitation 17 Section I On Page 17 of the solicitation, Section I, will ONR consider adding FAR 52.215-23 ALT I (OCT 1997) to the solicitation and/or resultant contract, if determined to be applicable? Yes, this is applicable and will be added via amendment.

PCO Note: XXX denotes the offerors name who asked the question.

10 Solicitation 18 Section I On Page 18 of the solicitation, Section I, will ONR consider adding FAR 52.227-14 (MAY 2014) and FAR 52.227-16 (JUN 1987) to the solicitation and/or resultant contract, if determined to be applicable? Yes, this is applicable and will be added via amendment.

11 Solicitation 19 Section I On Page 19 of the solicitation, Section I, will ONR consider adding DFARS 252.227-7039 (APR 1990) to the solicitation and/or resultant contract, if determined to be applicable? Yes, this is applicable and will be added via amendment.

12 Solicitation Section I Reference Section I of the solicitation, will ONR consider adding FAR 52.211-15 (APR 2008) in full text or by reference to the solicitation via amendments and/or resultant contract, if determined to be applicable? Yes, this clause should have been in the original award.

13 Solicitation 62 Section L On Page 62 of the solicitation, Section L 1 General

Instructions for Submission of Proposals, Paragraph (J)

– due to potential delays in mail delivery due to the US presidential election and potential COVID-19 impacts, would ONR consider receipt of hard copies postmarked by the proposal due date on time?

No, hard copies should be submitted before the due date/time.

14 Solicitation 69 Section L On Page 69 of the solicitation, Section L, 2 Preparation of Technical Proposals, Paragraph (C), Factor 3: Key Personnel and Staffing, Subparagraph (c ) Staffing, Subparagraph 4 - can you confirm "advanced manufacturing" should be revised to read "composite manufacturing"? This should read as Composites.

15 Solicitation 88 Section M On Page 88 of the solicitation, Section M, 2 Evaluation of Technical Proposals, Technical Factor 1, Paragraph 5, after the italicized statement "The Government will evaluate the following:" - can you confirm "naval metal working" should be revised to read "composite manufacturing"? This should read as Composites.

16 Solicitation 88 Section M On Page 88, Section M, 2 Evaluation of Technical Proposals, Paragraph (9) – can you confirm that “electro optics” should read “composites”?

This should read as Composites.

17 Solicitation 90 Section M On Page 90 of the solicitation, Section M, Technical

Factor 3, Paragraph 2 and Paragraph 4 after the italicized statements "The Government will evaluate the following:" - can you confirm "advanced manufacturing" should be revised to read "composite manufacturing"? This should read as Composites.

Solicitation Change?

Yes

Yes

No

No

Yes

No

No

No

Yes

No

Yes

Yes