B2. 01RFP Sec J Attachment 3 Report Format.doc
DOC document 48 KB Posted
- Solicitation number
- N0001420R0007
About this file
This document outlines reporting requirements and deliverables for a Navy Manufacturing Technology contract opportunity. The successful offeror will be required to submit quarterly Center Operations and Management reports including a Center Status section with activities, financials, and planned work as well as a Project Status section for each active project covering technical details, schedules, costs, and implementation progress. A final report summarizing all work under the contract is also required. Project Final Reports for individual efforts must include background, objectives, technical approach, results, benefits analysis, implementation status, conclusions and recommendations. Standard government report formats are acceptable unless otherwise specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B2.03 A0001.pdf | ||
| B2.03 Sec J Attachment 10 Q_A.pdf | ||
| B2. 01RFP Sec J Attachment 5 PPIF.docx | DOCX document | |
| B2. 01RFP Exhibit A CoE Level CDRLS.docx | DOCX document | |
| B2. 01RFP Exhibit B Project CDRLS.docx | DOCX document | |
| B2. 01RFP Sec J Attachment 6 PPQ.docx | DOCX document | |
| B2.01 N00014-20-R-0007.pdf | ||
| B2. 01RFP Sec J Attachment 4 COR.docx | DOCX document | |
| B2. 01 ENCLOSURE NUMBER 1.docx | DOCX document | |
| B2. 01RFP Sec J Attachment 1 SOW CMC.docx | DOCX document | |
| B2. 01RFP Sec J Attachment 2 Key Personnel.doc | DOC document | |
| B2. 01RFP Sec J Attachment 7 Price Information.docx | DOCX document | |
| B2. 01RFP Sec J Attachment 8 CE Summary.xlsx | XLSX spreadsheet | |
| B2.01 Sec J Attachment 9 ONR Reps_Certs.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Naval Composites Manufacturing Center (CMC) Report Formats
10 Jan 2020 Note to all offerors: The following reports are required to be submitted as part of contract performance.
The resultant First and Second Task Orders will include each of the deliverables below in the Contract Data Requirements List (CDRL).
Distribution instructions for the following reports will be contained in Enclosure Number 1 of Exhibit A for Each Task Order: Contract Data Requirements List, Instructions for Distribution.
Note: CoE = Center of Excellence.
First Task Order – Center Operations and Management See Attached DD 1423 for deliverables.
COE Quarterly Report The COE Quarterly Report shall contain two sections, Center Status and Project Status sections as shown below.
1. Center Status
a. Cover Page (with COE, Quarter / Dates Covered)
b. Table of Contents
c. Executive Summary
d. Center Activities Report (include accomplishments and recommendations based on independent analyses/assessments)
e. Status of Program Planning
1. Current Fiscal Year (FY) Program Planning Status
2. Next Fiscal Year Program Planning Status
3. Current Projection of New Start Funds for Next Fiscal Year
f. Center Financial Status
1. ManTech: operations and management activities’ costs report detailed by expense element including: direct labor hours, direct salaries, overhead hours & costs, facilities maintenance, facilities purchased or leased, travel, materials, subcontracts/consultants, and other direct/indirect costs.
2. Non-ManTech (if applicable)
3. ODC Itemized List: ODC, description/purpose, date of purchase, quantity, unit cost, and total cost.
g. Major Activities Planned for the Next Quarter
h. Status of Technical Project Reports: Include table (project number, title, status, end date, due date, submittal date) for i) all projects that the work has been completed, but whose Technical Project Report has yet to be published, and ii) all projects with projected end dates within the next quarter.
2. Project Status (for each Active ManTech Project, Special projects, and Non-ManTech projects)
a. Cover Page (with Order Number, ManTech Project Number, PDR Number, COE Project Number (if applicable), Project Title, and Quarter/Dates Covered by this report)
b. Period of Performance – include any contract modifications, extensions, etc.
c. Project Participants
d. Stakeholder, including POC info (name, title, address, phone, e-mail)
e. Technical Assistant POC info (if applicable)
f. Navy Technical Authority POC info (if applicable)
g. Responsible COE Project Manager POC info
h. Background/Problem Statement
i. Objective
j. Overall Project Status (Green/Yellow/Red)
1. Technical
2. Schedule
4. Cost
Note:
Green – good/on track
Yellow – minor deviation (explain)
Red – major deviation (explain)
k. Project Financial Status (include total and FY planned/actual/forecast)
Include project budget (total budget and amount through reporting period; total expenditures, expenditures for report period; cost share). Break out expenditures by Performing Activity (in house vs. subcontracted activities/purchased services).
l. Significant Past Activity
m. Significant Activity/Accomplishments for Reporting Quarter, Overall, and by Phase and Task
n. Plans for Next Quarter
o. Issues/Problems/Workarounds (if applicable)
p. Project Schedule Update
1. Milestone/Deliverable Table (FY Deliverables; Date Due; Deliverable; Status)
2. Gantt Chart showing Schedules/Progress (if required by contract)
q. Implementation Status/Update
If determined applicable by the Program Officer, an Implementation Report section shall be included in the Project Status section of the Quarterly Project Status/Financial Report. The Implementation Status shall outline the necessary events for successful transition into the Navy and the necessary resources to ensure transition. The following items shall be reported under the Implementation Report:
1. Primary and secondary weapons systems targeted for implementation of technology developed.
2. Implementing organization.
3. Identification of organization/personnel responsible for major milestones leading to full implementation. Identification of the appropriate Navy Technical Authority.
4. Remaining tasks required to implement improved manufacturing technologies in a production environment.
5. Summary of interactions held with the Navy Technical Authority and/or the implementing program office to ensure the project remains on track with the platform’s needs, requirements, and schedule.
6. Estimated funding/source of funding required for implementation.
7. Implementation timeline for transition of resultant technology to production floor. The tasks identified in Item 4 (above) shall be clearly delineated in the timeline. The timeline shall include major milestones for Government and/or Design Agent certification/qualification of improved process.
8. Is the project on schedule to meet the transition window? If not, explain why and what needs to be done to recover.
9. Associated designs and materials, as applicable.
r.
Remarks/Recommendations (if applicable)
Final Report Contractor format is acceptable as approved by the ONR Program Officer. Report shall provide a summary of all work completed during the entire contract period.
All other ManTech Program deliverables as required
Contractor format is acceptable, unless ONR Program Office format specified with applicable data call.
Second Task Order – Project Development and Management
See Attached DD 1423 for deliverables.
Project Final Report 1.
Cover Page (Title, Date, Project Number, Performing Activity, Project Team Members and Contact information)
2. Executive Summary/Abstract
3. Table of Contents
4. Background/Problem Statement
5. Objective(s)
6. Technical Approach (by task)
7. Technical Activities Performed
8. Results and Discussions
9. Benefits Analysis
a. Categorize and prioritize project’s accomplishments in one or more of the following areas and include quantifiable data to support benefit analysis:
• Warfighter readiness
• Improved performance
• Cost avoidance/savings
• New product/process development to meet critical performance requirements
• Environmental compliance
10. Implementation Report (Transition / Deployment Progress / Status)
If determined applicable by the Program Officer, an Implementation Report section shall be included in the Technical Project Report. The following items shall be reported under the Implementation Report section:
a. Primary and secondary weapons systems targeted for implementation of technology developed.
b. Implementing organization.
c. Identification of organization/personnel responsible for major milestones leading to full implementation. Identification of the appropriate Navy Technical Authority.
d. Description of how the new technology and/or processes were implemented into the targeted platform/system.
e. Implementation timeline for transition of resultant technology to production floor. The timeline shall include major milestones for Government and/or Design Agent certification/qualification of improved process.
f. Associated designs and materials, as applicable.
g. Identification of other platforms, systems or services that have interest in the new technology and will take the lessons learned to further develop the technology to their own specific needs.
11. Conclusions and Recommendations
Recommendations shall be based on independent analyses/assessments conducted by the Navy Composites Manufacturing Center (NCMC) COE (Contractor).
12. References
( Contractor/Program Office report format is acceptable for Non-ManTech reports, such as Special Projects or Non-ManTech Projects.
All Other ManTech Program Deliverables as required
Contractor format is acceptable, unless ONR Program Office format specified with applicable data call.