N00014-15-R-0005 Sources Sought Notice DRAFT RFP Attachments (excluding Attachment 9 to be attached as a separate Excel file)

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This Request for Information (RFI) is for planning purposes only and shall not be construed as a request for proposals, solicitation, and/or commitment on the part of the Government to issue any future solicitation.

The Government will not reimburse any costs associated with the development and/or submission of materials in response to this request.

Navy ManTech Metal Working Center of Excellence

This notice constitutes a Request for Information for the purpose of determining market capabilities of sources, including small business concerns, for the Navy Metal Working Center of Excellence.

Interested parties who believe they can fulfill the requirements in the DRAFT Request for Proposal (RFP) should provide a capabilities summary that shall not exceed one page in length. Capabilities statements may be submitted in contractor’s format.

Interested parties may also provide comments on the DRAFT RFP. Comments should include page numbers and/or attachment numbers. Comments may be provided in the contractor’s preferred format.

Capabilities statements and comments to the DRAFT RFP shall be sent via email to Ms. Mary Helen

Dent Adams, Contracting Officer at mary.dent@navy.mil no later than 1600 EST on 3 Apr 2015 (Friday).

Communications shall be in email only. No phone calls will be accepted regarding this document.

This draft RFP is subject to change and should a formal RFP be issued, it will be posted to FedBizOpps at a later date.

mailto:mary.dent@navy.mil

N00014-15-R-0005

SOLICITATION, OFFER AND AWARD

4. TYPE OF SOLICITATION2. CONTRACT NUMBER 3. SOLICITATION NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO (If other than Item 7)

ORDER UNDER DPAS (15 CFR 700)

6. REQUISITION/PURCHASE NUMBER

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

NEGOTIATED (RFP)

SEALED BID (IFB)

5. DATE ISSUED

1. THIS CONTRACT IS A RATED RATING PAGE OF PAGES

1 44

C. E-MAIL ADDRESS

EXT.NUMBERAREA CODE

B. TELEPHONE (NO COLLECT CALLS)A. NAME

10. FOR

INFORMATION

CALL:

CAUTION: LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

(Date)(Hour) local timeuntildepository located in copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if hand carried, in the

SOLICITATION

9. Sealed offers in original and

PART IV - REPRESENTATIONS AND INSTRUCTIONS

OTHER STATEMENTS OF OFFERORS

EVALUATION FACTORS FOR AWARD

INSTRS., CONDS., AND NOTICES TO OFFERORS

REPRESENTATIONS, CERTIFICATIONS AND

LIST OF ATTACHMENTS

CONTRACT CLAUSES

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

I

J

K

L

M SPECIAL CONTRACT REQUIREMENTS

CONTRACT ADMINISTRATION DATA

DELIVERIES OR PERFORMANCE

INSPECTION AND ACCEPTANCE

PACKAGING AND MARKING

DESCRIPTION/SPECS./WORK STATEMENT

SUPPLIES OR SERVICES AND PRICES/COSTS

SOLICITATION/CONTRACT FORM

PART II - CONTRACT CLAUSESPART I - THE SCHEDULE

H

G

F

E

D

C

B

A

SEC. DESCRIPTION PAGE(S) (X) DESCRIPTION SEC. (X)

11. TABLE OF CONTENTS

18. OFFER DATE17. SIGNATURE

SUCH ADDRESS IN SCHEDULE.

IS DIFFERENT FROM ABOVE - ENTER

15C. CHECK IF REMITTANCE ADDRESS

EXT.NUMBERAREA CODE

15B. TELEPHONE NUMBER

(Type or print)AND

ADDRESS

OF

OFFEROR

CODE FACILITY

16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER15A. NAME

DATEAMENDMENT NO.DATEAMENDMENT NO.

and related documents numbered and dated):

amendments to the SOLICITATION for offerors

(The offeror acknowledges receipt of

14. ACKNOWLEDGEMENT OF AMENDMENTS

CALENDAR DAYS (%)30 CALENDAR DAYS (%)20 CALENDAR DAYS (%)10 CALENDAR DAYS (%)

(See Section I, Clause No. 52.232.8)

13. DISCOUNT FOR PROMPT PAYMENT

designated point(s), within the time specified in the schedule.

by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the

12. In compliance with the above, the undersigned agrees, if this offer is accepted within ______________ calendar days (60 calendar days unless a different period is inserted

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16 , Minimum Bid Acceptance Period.

OFFER (Must be fully completed by offeror)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

28. AWARD DATE

(Signature of Contracting Officer)

27. UNITED STATES OF AMERICA

25. PAYMENT WILL BE MADE BY

26. NAME OF CONTRACTING OFFICER (Type or print)

CODE 24. ADMINISTERED BY (If other than Item 7)

ITEM

(4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN

41 U.S.C. 253 (c) ( 10 U.S.C. 2304 (c) (

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

21. ACCOUNTING AND APPROPRIATION20. AMOUNT19. ACCEPTED AS TO ITEMS NUMBERED

AWARD (To be completed by government)

CODE

X

N00014

Office of Naval Research 875 North Randolph Street Suite 1425 Arlington VA 22203

1400 ET

Mary Helen Dent 703 Mary.Dent@navy.mil

254-7288

X

X

X

X

X

X

X

X

X

X

X

X

X

PAGE(S)

Mary Helen Dent

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is unusable

STANDARD FORM 33 (Rev. 9-97)

Prescribed by GSA - FAR (48 CFR) 53.214(c)

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 44

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

N00014-15-R-0005

(A) (B) (C) (D) (E) (F)

Delivery Location Code: N00014

Office of Naval Research

Attn:

875 North Randolph Street

Suite 1425

Arlington VA 22203

FOB: Destination

0001 The contractor shall operate and manage the Navy

Manufacturing Technology (ManTech) Navy

Metalworking Center (NMC) of Excellence and perform research on approved ManTech and

Non-ManTech Program technical projects in accordance with Section C, and all task orders issued hereunder.

OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

NSN 7540-01-152-8067

N00014-15-R-0005 Navy Metal Working Center DRAFT RFP

SECTION C - Description/Specifications

ONR 0189 Description/Specifications/Work Statement

(1) The work and services to be performed hereunder shall be subject to the requirements and standards contained in the Statement(s) of Work, the Contract Data Requirements Lists (as specified in each

Delivery/Task Order), and the following paragraph(s):

(2) The purpose of CLIN 0001 is to provide for an instrument under which orders can be issued for:

The management, administration and technical oversight of the Navy Manufacturing Technology

(ManTech) Navy Metalworking Center (NMC) of Excellence and the performance of Special Projects, will be awarded as Task Order 000 IAW Section J, Attachment 1, entitled “Navy Manufacturing Technology

(ManTech) Navy Metalworking Center (NMC) of Excellence Statement of Work.”

The development and management of the Navy Manufacturing Technology (ManTech) Navy

Metalworking Center (NMC) of Excellence which will be awarded as Order 0002, per Section J, Attachment 1 entitled “Navy Manufacturing Technology (ManTech) Navy Metalworking Center (NMC) of

Excellence Statement of Work.”

(3) Deliverable data requirements shall be specified on each delivery/task order as applicable.

SECTION D - Packaging and Marking

ONR 0009 Packaging & Marking

Preservation, packaging, packing and marking of all deliverable contract line items shall conform to normal commercial packing standards to assure safe delivery at destination.

ONR 5252.235-9714 Report Preparation

Scientific or technical reports prepared by the Contractor and deliverable under the terms of this contract will be prepared in accordance with format requirements contained in ANSI/NISO Z39.18-2005 (R2010), entitled, "Scientific and Technical Reports - Preparation, Presentation and Preservation".

NOTE: All National Information Standards Organization (NISO) American National Standards are available as free, downloadable pdf(s) at http://www.niso.org/standards/index.html. NISO standards can also be purchased in hardcopy form from the NISO website by clicking on "Link to Buy". NISO is located at 3600 Clipper Mill Road, Suite 302, Baltimore, MD 21211. NISO can be reached by telephone at (301)

654-3600 or by fax at (410) 685-5278.

SECTION E - Inspection and Acceptance

ONR 0045 Inspection and Acceptance

Responsibility for inspection and acceptance of the deliveries and services under this contract and any ensuing order(s) will be accomplished by the Program Officer designated in Section F of this contract or such other Program Officer as may be designated in the individual task order.

ONR 0120 Inspection and Acceptance- Order

Inspection and acceptance of deliveries under this order will be accomplished by the Program Officer designated below, who shall have thirty (30) days after delivery for acceptance.

Office of Naval Research

Attn: Mr. Greg Woods, ONR 03T

875 North Randolph Street

Arlington, VA 22203-1995

Telephone: (703) 696-4788

E-Mail: gregory.woods1@navy.mil

FAR 52.246-5 Inspection of Services - Cost-Reimbursement. (APR 1984)

FAR 52.246-9 Inspection of Research and Development (Short Form). (APR 1984)

SECTION F - Deliveries or Performance

ONR 0166 Period of Performance

1. The ordering period for CLIN 0001 is from the contract award date (Block 28 of the Standard Form 33) through sixty (60) months thereafter. Orders placed within this ordering period may continue until the delivery date/end date specified in the order. Each order shall specifically set forth the items to be delivered, delivery terms, and the delivery date and/or period of performance.

2. Distribution, consignment and marking instructions for all contract line items shall be in accordance with

Enclosure Number 1 of Exhibit A (of the applicable task order). The address for the cognizant Program

Officer is as follows:

Attn: Mr. Greg Woods, ONR 03T

875 North Randolph Street

Arlington, VA 22203-1995

SECTION G - Contract Administration Data

DFAR 252.232-7006 Wide Area WorkFlow Payment Instructions. (MAY 2013)

(a) Definitions. As used in this clause-

Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.

Document type means the type of payment request or receiving report available for creation in Wide Area

Work Flow (WAWF).

Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.

(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment

Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and mailto:gregory.woods1@navy.mil

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based

Training Course and use the Practice Training Site before submitting payment requests through WAWF.

Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data

Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:

(1) Document type. The Contractor shall use the following document type(s).

Invoice/Receiving Report (COMBO).

(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.

To be completed at time of award.

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC To be completed at time of award

Issue By DoDAAC N00014

Admin DoDAAC To be completed at time of award

Inspect By DoDAAC N/A

Ship To Code N00014

Ship From Code N/A

Mark For Code N/A

Service Approver (DoDAAC) For Cost: Admin DoDAAC

Service Acceptor (DoDAAC) N/A

Accept at Other DoDAAC N/A

LPO DoDAAC N/A

DCAA Auditor DoDAAC To be completed at time of award

Other DoDAAC(s) N/A

(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in

DFARS Appendix F, (e.g. timesheets) in support of each payment request.

(5) WAWF email notifications. The Contractor shall enter the e-mail address identified below in the "Send

Additional Email Notifications" field of WAWF once a document is submitted in the system.

To be completed at time of award

(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

For clarification regarding invoicing contact: Navy WAWF Help Line: 1-800-756-4571 (Option 6). For

Payment Issues Only contact: ONR.NCR.BD021.list.All@navy.mil

(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.

(End of clause)

ONR 0021 Incrementally Funded Orders

The Government, at its discretion, reserves the right to incrementally fund any order issued under this contract. If an order is incrementally funded, the order shall specify the total amount of the order, the amount obligated, the estimated performance period based on the amount of available funds, and a statement that the Contractor is not required to perform work nor is the Government obligated to reimburse the Contractor for work performed in excess of the amounts obligated. All incrementally funded cost reimbursement orders will be funded in accordance with the clause FAR 52.232-22, Limitation of Funds, and the following appropriate “Allotment of Funds” clause:

The following is applicable to CPFF Orders (and will be modified depending on order type) to be completed at time of award.

Allotment of Funds

It is hereby understood and agreed that this order will not exceed a total amount of $__; including an estimated cost of $__ and a fixed fee of $__.

The total amount obligated under this order is $__.The total amount presently available for payment and allotted to CLIN 0001 of this order is $__; including an estimated cost of $__ and a fixed fee of $__. It is estimated that the amount allotted of $__ will cover the period from date of award through (insert date).

The following paragraph should be added as many times as necessary when there are multiple funded

CLINs.

The total amount presently available for payment and allotted to CLIN (Insert) of this order is $__;

including an estimated cost of $__ and a fixed fee of $__. It is estimated that the amount allotted of $__ will cover the period from date of award through (Insert).

ONR 0066 Payment of Allowable Costs & Fixed Fee (Cost Type Orders)

As consideration for the proper performance of the work and services required under this contract, the

Contractor shall be paid as follows:

(a) Costs, as provided for under the contract clause entitled "Allowable Cost and Payment," shall not exceed the amount set forth as "Estimated Cost" in each Task Order, and is subject to the contract clause entitled "Limitation of Cost" or "Limitation of Funds" whichever is applicable.

(b) A fixed fee, in the amount set forth as ‘Fixed Fee’ in each Task Order, in accordance with the contract clause FAR 52.216-8 “Fixed Fee”, shall be paid upon completion of the work and services required under this contract and upon final acceptance by the Contracting Officer. However, the Contractor, may bill on each voucher the amount of the fee bearing the same percentage to the total fixed fee as the amount of cost billed bears to the total estimated cost not to exceed the amount set forth as "Fixed Fee" in Section B. The total fixed fee billed, shall not exceed the total fixed fee specified in each Task Order and is subject to the contract clause entitled "Limitation of Cost" or "Limitation of Funds" whichever applies.

(c) In accordance with FAR 52.216-8, “Fixed Fee”, the Administrative Contracting Officer (ACO), in order to protect the Government’s interest, shall withhold 10% of the fixed fee amount set forth in Section B or until a reserve is set aside in the amount of $100,000.00, whichever is less. The fixed fee withhold should be applied to each voucher. The ACO shall release the withholds in accordance with the provisions of FAR

52.216-8.

ONR 0067 Ordering Officer

The Office of Naval Research (ONR) Procuring Contracting Officer (PCO) or his/her duly authorized representative, shall act as Ordering Officer for the contract and is responsible for issuing orders placed hereunder. Orders shall be placed unilaterally or bilaterally by the Ordering Officer by issuance of a DD

Form 1155, Order for Supplies or Services. The ONR PCO retains the unilateral right to update this guidance for the life of the contract. The ONR point of contact information is as follows:

One Liberty Center

875 North Randolph St.

Attn: Ms. Mary Helen Dent Adams

ONR Code 254, ManTech Team

Email: mary.dent@navy.mil

Telephone: 703-254-7288

ONR 0132 Payment of Allowable Costs

As consideration for the proper performance of the work and services required under this contract, the

Costs, as provided for under the contract clause entitled "Allowable Cost and Payment," shall not exceed the amount set forth as "Estimated Cost" in each Task Order, and is subject to the contract clause entitled

"Limitation of Cost" or "Limitation of Funds" whichever is applicable.

ONR 0152 Method of Payment

As consideration for the proper performance of the work and services required under this contract, the

(a) Costs, as provided for under the contract clause entitled “Allowable Cost and Payment”, not to exceed the amount set forth as “Estimated Cost” in Section B, subject to the contract clause entitled

“Limitation of Cost” or “ Limitation of Funds”, whichever is applicable.

(b) A fixed fee, in the amount set forth as ‘Fixed Fee’ in Section B, in accordance with the contract clause FAR 52.216-8 “Fixed Fee”, shall be paid upon completion of the work and services required under this contract and upon final acceptance by the Contracting Officer. However, the

Contractor, may bill on each voucher the amount of the fee bearing the same percentage to the total fixed fee as the amount of cost billed bears to the total estimated cost not to exceed the amount set forth as

"Fixed Fee" in Section B. The total fixed fee billed, shall not exceed the total fixed fee specified in Section

B and is subject to the contract clause entitled "Limitation of Cost" or "Limitation of Funds" whichever applies.

(c) In accordance with FAR 52.216-8, “Fixed Fee”, the Administrative Contracting Officer

(ACO), in order to protect the Government’s interest, shall withhold 10% of the fixed fee amount set forth in Section B or until a reserve is set aside in the amount of $100,000.00, whichever is less. The fixed fee withhold should be applied to each voucher. The ACO shall release the withhold in accordance with the provisions of FAR 52.216-8.

ONR 0168 Procuring Office Representative- Solicitation

(a) In order to expedite administration of this contract, the Administrative Contracting Officer should direct inquiries to the appropriate office listed below. Please do not direct routine inquiries to the person listed in Item 26 on Standard Form 33.

Contract Negotiator – Ms. Mary Helen Dent Adams, ONE 254, ManTech Team, (703) 254-7288, mary.dent@navy.mil

(If initial response to contract negotiator's email goes unanswered after 3 business days or the contractor knows the previous negotiator has left ONR, forward message to brian.kehoe@navy.mil or phil.reens.ctr@navy.mil

Inspection and Acceptance –Mr. Greg Woods, ONR 03T, (703) 696-4788, gregory.woods1@navy.mil

Security Matters – Ms. Diana Pacheco, ONR 43, (703) 696 8177, DSN 426 8177, E-Mail Address:

diana.pacheco@navy.mil

Patent Matters – Mr. John Forrest, ONR 00CC, (703) 696-4000, DSN 426-4000, E-Mail Address john.forrest@navy.mil

(b) The Administrative Contracting Officer will forward invention disclosures and reports directly to

Corporate Counsel (Code 00CC), Office of Naval Research, Department of the Navy, 875 North Randolph

St. Arlington, VA 22203-1995. The Corporate Counsel will return the reports along with a recommendation to the Administrative Contracting Officer. The Corporate Counsel will represent the Contracting Officer with regard to invention reporting matters arising under this contract.

ONR 0188 Technical Projects Approved Under this Contract

(1) One or more Delivery/Task Orders for Navy ManTech Projects may be issued and may include the following table. The Period of Performance (POP) and the Government cost specified below for each project cannot be exceeded without Contracting Officer approval and cannot exceed the funding specified by ACRN shown below for each approved technical project.

Project

Number CLIN Description Participants

Period of

Performance

Government

Cost

Contractor

Cost Cost

Fixed

Fee

Total

Cost

ACRN: _____

(To be completed as technical projects are approved)

(2) One or more Delivery/Task Orders for Non-ManTech Projects may be issued and may include the following table. The Period of Performance (POP) and the Government cost specified below for each project cannot be exceeded without Contracting Officer approval and cannot exceed the funding specified by ACRN shown below for each approved technical project.

Project Number Description Participants Period of

Performance Cost Fixed Fee Total Cost

ACRN: _____

(3) Special Projects and Rapid Response Projects, if approved by the ONR Program Officer, may be mailto:brian.kehoe@navy.mil mailto:phil.reens.ctr@navy.mil mailto:gregory.woods1@navy.mil mailto:diana.pacheco@navy.mil mailto:john.forrest@navy.mil performed under Delivery/Task Order 0001, COE Operations and Management (for Special Projects) and under Delivery/Task Order 0002, Project Development and Management (for Rapid Response Projects), and may include the following table. The Period of Performance (POP) and the Government cost specified below for each project cannot be exceeded without Contracting Officer approval and cannot exceed the funding specified by ACRN shown below for each approved technical project.

Project

Project

Type

(Rapid

Respons e, etc)

Description Participants Period of

Performance

Government

Cost

Contractor

Cost Cost

Fixed

Fee

Total

Cost

ACRN: ___

ONR 0190 Minimum Contract Guarantee and Maximum Potential

(a) This is an Indefinite Quantity contract as contemplated by FAR 16.504. The total minimum dollar amount the Government may order under this contract is $125,000 (one hundred twenty-five thousand dollars). The maximum dollar amount the Government may order under this contract is $45,000,000

(forty-five million dollars).

(b) The Government shall have no obligation to issue delivery orders to the Contractor beyond the total minimum dollar amount specified in paragraph (a) of this clause.

ONR 0191 Task Order Minimum/Maximum Quantity

The minimum order value for any given Task/Delivery Order issued under CLIN(s) 0001 may not be less than $25,000. The maximum order value for any given Task/Delivery Order issued under CLIN(s) 0001 may not be greater than the maximum value stated under each CLIN.

ONR 0192 Type of Contract.

(a) This is an Indefinite-Delivery/Indefinite Quantity (IDIQ) Task/Delivery Order Contract, which allows issuance of orders on a cost-plus-fixed-fee (CPFF) basis, cost (no fee) basis, Cost Share basis.

(b) Delivery/Task orders will be issued on a cost-plus-fixed-fee or cost-share basis, as indicated in each order.

SECTION H - Special Contract Requirements

ONR 0070 Consent to Subcontract and/or Hire Consultants

The services of the following subcontractors and/or consultants have been identified as necessary for the performance of this contract:

To be completed when projects are awarded. Each Identified Consultant and/or Subcontractor will include their Estimated Time; Rate per day; and estimated cost.

The preceding listing of subcontracts were evaluated during negotiations as required by Paragraph (j) of the contract clause at FAR 52.244-2 entitled “Subcontracts" and therefore do not require consent in accordance with paragraphs (c) and (e) of the Subcontracts clause. This consent is based upon the information submitted by the prime contractor in accordance with FAR 52.244-2 (e) (1) (i) through (vii).

For additional subcontracts beyond those listed above, the Contracting Officer’s written consent to subcontract is only required in accordance with Paragraphs (b), (c), and (d) of FAR 52.244-2.

ONR has delegated contract administration to the Administrative Contracting Officer (ACO) at the cognizant Contract Administration Office (Block 7 of this DD Form 1155 or Block 6 of the Standard Form

26). Although ONR has provided authority to subcontract for the preceding list of subcontracts, ONR is not retaining any post award function for the consent of subcontracts in accordance with FAR 42.302(a)

(51). Therefore, any consents to subcontract required in accordance with FAR 52.244-2 after contract award shall be submitted to the ACO for action.

ONR 0169 Invention Disclosures and Reports

The Contractor shall submit all invention disclosures and reports required by the Patent Rights clause of this contract to the Administrative Contracting Officer

ONR 0170 Travel

Travel cost shall be reimbursed in accordance with FAR 31.205-46 at rates not to exceed the maximum locality per diem rates (the combination of lodging, meals and incidentals) in effect at the time of travel, as set forth in the Federal Travel Regulations, Joint Travel Regulation and Standards Regulations, Section

925, as applicable. In the event award is made to an educational institute, travel shall be reimbursed in accordance with OMB Circular A-21.

All air travel must be booked on American-flagged carriers, unless otherwise directed by the Contracting

Officer. Actual modes of transportation and costs shall be agreed to in advance.

ONR 0172 Program Management Review

A Program Management Review (PMR) is defined as any meeting necessary to support or review the work accomplished and to assess whether the Small Business Subcontracting Plan goals are met under this

Contract. PMRs are considered typical in the conduct and review of the contract and will not be separately reimbursed. It is anticipated a PMR will be held at least every three months.

ONR 0173 Cost Sharing Minimum

The Government anticipates cost sharing for the research work to be performed under Navy ManTech

Projects. The parties recognize that the appropriate level of cost share will be negotiated for individual technical projects and will be identified in Section G-ONR 0188.

ONR 0174 Estimated Cost and Cost Sharing

To Be Completed at Time of Delivery/Task Order Award.

(a) It is estimated that the total cost of performing the work under this contract will be

(b) For performance of the work under this contract, the Contractor shall be reimbursed for not more than _______ percent of the costs of performance determined to be allowable under the Allowable

Cost and Payment clause. The remaining _______ percent or more of the costs of performance so determined shall constitute the Contractor’s share, for which it will not be reimbursed by the Government.

(c) For purposes of the FAR 52.232-20, Limitation of Cost, the total estimated cost to the

Government is hereby established as $_________ [insert estimated Government share]; this amount is the maximum Government liability.

(d) The Contractor shall maintain records of all contract costs claimed by the Contractor as constituting part of its share. Those records shall be subject to audit by the Government. Cost contributed by the Contractor shall not be charged to the Government under any other grant, contract, or agreement

(including allocation to other grants, contracts, or agreements as part of an independent research and development program).

ONR 0175 Orders

(a) General

(1) Orders for research, services, or supplies may be issued by the Contracting Officer (CO) for work as specified in Sections B and C of the Schedule at any time during the effective period of this contract. Except as otherwise provided in any order, the Contractor shall furnish all materials and services necessary for accomplishing the work specified in each order issued hereunder. All the provisions in this contract shall be applicable to all orders issued hereunder. To the extent of any inconsistency between any order and this contract, the contract shall control. It is understood and agreed upon that the Government has no obligation to issue any orders beyond paying the contract minimum on demand at the end of the contract period. The Contractor agrees to accept and perform orders issued by the CO within the scope of this contract during the term set forth elsewhere in the schedule.

(2) Task Orders may be placed at any time during the ordering period specified. Completion tasks may continue until the ordered effort is completed. Task Orders may be issued on a Cost-Plus Fixed-

Fee (CPFF), Cost, Cost Share basis as determined by project type and as indicated in each order.

(b) Ordering

(1) Orders and revisions thereto shall be made in writing by the CO.

(2) Each bilateral order shall be binding when executed by both parties.

(3) Each unilateral order shall be binding upon receipt by the Contractor. The Contractor shall acknowledge receipt of the order within five (5) days after receipt thereof. These orders may be issued through facsimile as well as through electronic and regular mail.

(c) Bilateral Orders

With exception to paragraph (d) (below), the Contractor shall not begin any work until a bilateral order is issued by the CO.

(d) Unilateral Orders

(1) Priced: The CO may issue unilateral orders, either fully or incrementally funded, based upon acceptance of the Contractor’s proposals. Upon receipt of a unilateral order, the Contractor shall promptly commence the work specified therein. Unilateral orders are subject to either the “Limitation of

Cost” (when fully funded) or “Limitation of Funds” (when incrementally funded) clause as incorporated into this contract. The Contractor shall acknowledge receipt of the order within five (5) days of receipt.

(2) Unpriced: When determined to be in the best interest of the Government, the CO may unilaterally issue an undefinitized order directing the Contractor to proceed with performance of the work specified therein. The order shall include the clause entitled “Definitization Requirements - Undefinitized

Orders” (see paragraph (g) below), plus a delivery schedule for the work being ordered.

(e) Cost or Pricing Data

Whenever cost or pricing data are required in accordance with FAR 15.403, the Contractor shall submit required data in accordance with FAR 15.408, Table 15-2. If a Certificate of Current Cost or Pricing Data is required, it shall be provided in accordance with FAR 15.406-2.

(f) Definition

The term Contracting Officer as used in this provision includes the Administrative Contracting Officer

(ACO).

(g) Definitization Requirements - Undefinitized Orders

(1) When an undefinitized contract action is issued, the Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive order. The Contractor agrees to submit a proposal and any necessary cost or pricing data to support its proposal.

(2) In accordance with the requirements of DFARS 217.7404-3, the schedule for definitizing any undefinitized order shall be specified in the order and shall include:

a. Submission Due Date of Contractor's Proposal

b. Projected Date for Commencement of Negotiations

c. Target Date for Definitization

(3) If agreement on a definitive order to supersede this undefinitized order is not reached by the target date specified in the definitization schedule, or within any extension thereof granted by the Contracting Officer, the Contracting Officer may, with the approval of the Head of the Contracting Activity, determine a reasonable price or fee in accordance with FAR Part 15, subject to Contractor appeal as provided in the

Disputes clause. In any event, the Contractor shall proceed with completion of the order, subject only to the limitation of Government liability set forth in paragraph (6) below.

(4) The Contractor further agrees that the Government shall not be liable under such definitization for an increase in the estimated cost and fee which combined would cause the definitized price of the order to exceed the ceiling amount specified in the undefinitized order (See DFARS 217.7404-2). The not to exceed price specified is a maximum and shall not be construed as an indication, other than a limit on the amount, if any, of such definitization. Subject to the foregoing, failure to agree to pay any definitization shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled

“Disputes.”

(5) Pending definitization of an order, the estimated cost of efforts performed under this undefinitized order for purposes of the clause of the contract entitled “Limitation of Cost” or “Limitation of Funds”, as appropriate, is the limitation of Government liability set forth in paragraph (6) below. The Contractor shall be reimbursed for the costs of efforts performed under this undefinitized order in accordance with the clause of this contract entitled “Allowable Cost and Payment”, but in no event for an amount greater than the estimated cost of such efforts. The Contractor shall bill no fee against the estimated cost until this order is definitized.

(6) In performing this undefinitized order, the Contractor is not authorized to make expenditures or incur obligations exceeding the amount obligated to the undefinitized order (see DFARS 217.7404-4 for funding limitations). This is the maximum amount, including fee, for which the Government shall be liable if this order is terminated.

(h) Termination of Orders

(1) The Government may terminate performance of work under any order in whole or, from time to time, in part if ---

a. The Contracting Officer determines that a termination is in the Government’s interest; or

b. The Contractor defaults in performing any order and fails to cure the default within 10 days

(unless extended by the Contracting Officer) after receiving a notice specifying the default. “Default” includes failure to make progress in the work so as to endanger performance,

(2) The Contracting Officer shall terminate the order by delivering to the Contractor a Notice of

Termination specifying whether the termination is for default of the Contractor of for Convenience of the

Government, the extent of termination, and the effective date. If, after termination for default, it is determined that the Contractor was not in default or that the Contractor’s failure to perform or to make progress in performance is due to causes beyond the control and without fault or negligence of the

Contractor as set forth in the Excusable Delays clause, the rights and obligations of the parties will be the same as if termination was for the convenience of the Government.

(3) After receipt of a Notice of Termination, and except as directed by the Contracting Officer, the

Contractor shall immediately proceed with the obligations specified in the “Termination (Cost

Reimbursement)” clause.

ONR 0178 Representations, Certifications, and Other Statements of Offerors

The latest version of the ONR Representations and Certifications may be found here:

http://www.onr.navy.mil/Contracts-Grants/submit-proposal/contracts-proposal/~/media/Files/Contracts-

Grants/Forms/15-001-RepsCerts-Fillable.ashx

ONR 5252.237-9705 Key Personnel (DEC 1988)

(a) The Contractor agrees to assign to the contract tasks those persons whose resumes were submitted with its proposal and who are necessary to fulfill the requirements of the contract as "key personnel". No substitutions may be made except in accordance with this clause.

(b) The Contractor understands that during the first ninety (90) days of the contract performance period, no personnel substitutions will be permitted unless these substitutions are unavoidable because of the incumbent's sudden illness, death or termination of employment. In any of these events, the Contractor shall promptly notify the Contracting Officer and provide the information described in paragraph (c) below.

After the initial ninety (90) day period the Contractor must submit to the Contracting Officer all proposed substitutions, in writing, at least 30 days in advance, 90 days if security clearance must be obtained, of any proposed substitution and provide the information required by paragraph (c) below.

(c) Any request for substitution must include a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information requested by the

Contracting Officer. Any proposed substitute must have qualifications equal to or superior to the qualifications of the incumbent. The Contracting Officer or his/her authorized representative will evaluate such requests and promptly notify the Contractor in writing of his/her approval or disapproval thereof.

(d) In the event that any of the identified key personnel cease to perform under the contract and the substitute is disapproved, the contract may be immediately terminated in accordance with the Termination clause of the contract.

The following are identified as key personnel:

To be completed when projects are awarded.

ONR 5252.242-9718 Technical Direction (FEB 2002)

(a) Performance of the work hereunder is subject to the technical direction of the Program

Officer/COR designated in this contract, or duly authorized representative. For the purposes of this clause, technical direction includes the following:

(1) Direction to the Contractor which shifts work emphasis between work areas or tasks, requires pursuit of certain lines of inquiry, fills in details or otherwise serves to accomplish the objectives described in the statement of work;

(2) Guidelines to the Contractor which assist in the interpretation of drawings, specifications or technical portions of work description.

(b) Technical direction must be within the general scope of work stated in the contract. Technical direction may not be used to:

(1) Assign additional work under the contract;

(2) Direct a change as defined in the contract clause entitled "Changes";

(3) Increase or decrease the estimated contract cost, the fixed fee, or the time required for contract performance; or

(4) Change any of the terms, conditions or specifications of the contract.

(c) The only individual authorized to in any way amend or modify any of the terms of this contract shall be the Contracting Officer. When, in the opinion of the Contractor, any technical direction calls for effort outside the scope of the contract or inconsistent with this special provision, the Contractor shall notify the Contracting Officer in writing within ten working days after its receipt. The Contractor shall not proceed with the work affected by the technical direction until the Contractor is notified by the Contracting

Officer that the technical direction is within the scope of the contract.

(d) Nothing in the foregoing paragraphs may be construed to excuse the Contractor from performing that portion of the work statement which is not affected by the disputed technical direction.

ONR 5252.242-9720 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (SEP 1996)

The COR for this contract is:

Attn: Mr. Greg Woods, ONR 03T

875 North Randolph Street

Arlington, VA 22203-1995

Telephone: (703) 696-4788

E-Mail: gregory.woods1@navy.mil

The COR will act as the Contracting Officer's representative for technical matters, providing technical direction and discussion as necessary with respect to the specification or statement of work, and monitoring the progress and quality of contractor performance. The COR is not an Administrative Contracting Officer and does not have authority to take any action, either directly or indirectly, to change the pricing, quantity, quality, place of performance, delivery schedule, or any other terms and conditions of the contract (or delivery order), or to direct the accomplishment of effort which goes beyond the scope of the statement of work in the contract (or delivery order).

When, in the opinion of the contractor, the COR requests effort outside the existing scope of the contract

(or delivery order), the contractor shall promptly notify the contracting officer (ordering officer) in writing.

No action shall be taken by the contractor until the contracting officer (or ordering officer) has issued a modification to the contract (or delivery order) or has otherwise resolved the issue.

In the absence of the COR named above (due to reasons such as leave, illness, official travel), all responsibilities and functions assigned to the COR shall be the responsibility of the alternate COR acting on behalf of the COR.

SECTION I - Contract Clauses

FAR 52.202-1 Definitions. (NOV 2013)

FAR 52.203-3 Gratuities. (APR 1984)

FAR 52.203-5 Covenant Against Contingent Fees. (MAY 2014) mailto:gregory.woods1@navy.mil

FAR 52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006)

FAR 52.203-7 Anti-Kickback Procedures. (MAY 2014)

FAR 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY

2014)

FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014)

FAR 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)

FAR 52.203-13 Contractor Code of Business Ethics and Conduct. (APR 2010)

FAR 52.203-16 Preventing Personal Conflicts of Interest. (DEC 2011)

FAR 52.204-2 Security Requirements. (AUG 1996)

FAR 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011)

FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUL 2013)

FAR 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)

FAR 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (AUG 2013)

FAR 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (JUL 2013)

FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (MAY 2012)

FAR 52.210-1 Market Research. (APR 2011)

FAR 52.215-2 Audit and Records - Negotiation. (OCT 2010)

FAR 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)

FAR 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data. (AUG 2011)

FAR 52.215-12 Subcontractor Certified Cost or Pricing Data. (OCT 2010)

FAR 52.215-14 Integrity of Unit Prices. (OCT 2010)

FAR 52.215-14 Integrity of Unit Prices. (OCT 2010) - Alternate I (OCT 1997)

FAR 52.215-15 Pension Adjustments and Asset Reversions. (OCT 2010)

FAR 52.215-17 Waiver of Facilities Capital Cost of Money. (OCT 1997)

FAR 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions.

(JUL 2005)

FAR 52.215-19 Notification of Ownership Changes. (OCT 1997)

FAR 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or

Pricing Data - Modifications. (OCT 2010)

FAR 52.215-23 Limitations on Pass-Through Charges. (OCT 2009)

FAR 52.216-7 Allowable Cost and Payment. (JUN 2013)

FAR 52.216-8 Fixed Fee. (JUN 2011)

FAR 52.216-22 Indefinite Quantity. (OCT 1995)

(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.

(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the

Schedule as the "maximum." The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum."

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after [insert date].

FAR 52.217-8 Option to Extend Services. (NOV 1999)

FAR 52.217-9 Option to Extend the Term of the Contract. (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 1 day; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 1day before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 60 months.

FAR 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns. (JAN 2011)

FAR 52.219-8 Utilization of Small Business Concerns. (MAY 2014)

FAR 52.219-9 Small business subcontracting plan. (JUL 2013)

FAR 52.219-10 Incentive Subcontracting Program. (OCT 2001)

(a) Of the total dollars it plans to spend under subcontracts, the Contractor has committed itself in its subcontracting plan to try to award certain percentages to small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns, respectively.

(b) If the Contractor exceeds its subcontracting goals for small business, veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business, and women-owned small business concerns in performing this contract, it will receive 0 percent of the dollars in excess of each goal in the plan, unless the Contracting Officer determines that the excess was not due to the Contractor's efforts (e.g., a subcontractor cost overrun caused the actual subcontract amount to exceed that estimated in the subcontracting plan, or the award of subcontracts that had been planned but had not been disclosed in the subcontracting plan during contract negotiations).

Determinations made under this paragraph are unilateral decisions made solely at the discretion of the Government.

(c) If this is a cost-plus-fixed-fee contract, the sum of the fixed fee and the incentive fee earned under this contract may not exceed the limitations in 15.404-4 of the Federal Acquisition

Regulation.

FAR 52.219-16 Liquidated Damages - Subcontracting Plan. (JAN 1999)

FAR 52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013)

FAR 52.222-1 Notice to the Government of Labor Disputes. (FEB 1997)

FAR 52.222-2 Payment for Overtime Premiums. (JUL 1990)

FAR 52.222-3 Convict Labor. (JUN 2003)

FAR 52.222-21 Prohibition of Segregated Facilities. (FEB 1999)

FAR 52.222-26 Equal Opportunity. (MAR 2007)

FAR 52.222-35 Equal Opportunity for Veterans. (JUL 2014)

FAR 52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)

FAR 52.222-37 Employment Reports on Veterans. (JUL 2014)

FAR 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010)

FAR 52.222-50 Combating Trafficking in Persons. (FEB 2009)

FAR 52.222-54 Employment Eligibility Verification. (AUG 2013)

FAR 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)

FAR 52.223-6 Drug-Free Workplace. (MAY 2001)

FAR 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)

FAR 52.224-2 Privacy Act. (APR 1984)

FAR 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)

FAR 52.227-1 Authorization and Consent. (DEC 2007)

FAR 52.227-1 Authorization and Consent. (DEC 2007) -- Alternate I (APR 1984)

FAR 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (DEC 2007)

FAR 52.227-10 Filing of Patent Applications - Classified Subject Matter. (DEC 2007)

FAR 52.227-11 Patent Rights-Ownership by the Contractor. (MAY 2014)

FAR 52.228-7 Insurance - Liability to Third Persons. (MAR 1996)

FAR 52.230-2 Cost Accounting Standards. (MAY 2014)

FAR 52.230-3 Disclosure and Consistency of Cost Accounting Practices. (MAY 2014)

FAR 52.230-6 Administration of Cost Accounting Standards. (JUN 2010)

FAR 52.232-9 Limitation on Withholding of Payments. (APR 1984)

FAR 52.232-17 Interest. (MAY 2014)

FAR 52.232-20 Limitation of Cost. (APR 1984)

FAR 52.232-22 Limitation of Funds. (APR 1984)

FAR 52.232-23 Assignment of Claims. (MAY 2014)

FAR 52.232-25 Prompt payment. (JUL 2013)

FAR 52.232-25 Prompt payment. (JUL 2013) - Alternate I (FEB 2002)

FAR 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)

FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)

FAR 52.233-1 Disputes. (MAY 2014)

FAR 52.233-3 Protest after Award. (AUG 1996)

FAR 52.233-3 Protest after Award. (AUG 1996) - Alternate I (JUN 1985)

FAR 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)