STATEMENT OF WORK
Installation of Military Working Dog (MWD) Kennel Exercise Runs
JBSA-LACKLAND, TX
1. PROJECT INFORMATION: Applicable provisions of the contract clauses shall govern work under each section of the specifications.
2. GENERAL: All JBSA-Lackland Whelping clinic, kennel areas, and working MWD facilities require escort and safety training.
3. PROJECT REQUIREMENTS:
The contractor shall install 10 exercise runs adjacent to building 7617 on Lackland AFB with the following specifications:
• use 9-gauge zinc coated GBW chain link with knuckle selvage on all fencing
• mesh openings must not exceed 2”
• each run (lane) enclosure shall consist of a 6’wide x 8’high x 100’long fence run (lane)
• each run shall have one self-latching entry gate installed. Specifications for the latches are as follows:
o self-latching security snap or lock with a fingertip release (latches automatically) o hardware is suitable for right or left handed use
• 1-5/8” top rail along the full length of each run
• 1-5/8” bottom rail along the full length of each run; along the bottom, each end, and each gate
• each bottom rail shall have no more than a 2” clearance above harden ground
• 1-5/8” cross brace attached to the top rail every 10’ (total of 8) to support shade fabric
• shade fabric to cover the entire top length of the runs (securable to the bottom rail)
• plastic privacy slats woven into the fence fabric covering the full length sides and ends of each run
• 8’H and 4” diameter corner post and gate post (12 total)
• use 2-3/8” line post every 8’ (12 total) for runs
• install 275’ of back fence 8’H with line post every 8’ parallel to and 25’ from existing perimeter fence
• contractor shall remove and dispose of existing area boundary fencing and replace the
475’ of exercise run boundary fence with 8’H fence and 8’ line post every 10’
4. SITE CONDITIONS:
The contractor shall furnish and maintain adequate barricades, and warning signs, on the job site.
The construction site shall be kept clean, orderly, and safe for workers at all times.
5. BASE FIRE REGULATIONS:
The contractor shall comply with all JBSA-Lackland Fire Regulations. It is the contractor’s responsibility to obtain an approved welding permit issued by the JBSA-Lackland Fire Department.
All fire and safety regulations shall be enforced. The Government will provide necessary documentation, but it will be incumbent upon the contractor to see approval.
6. CONTRACTOR GENERATED REFUSE:
All contractor generated refuse and waste shall be stored in a waste container provided by the contractor and hauled from the construction site to a disposal area to be selected by the contractor and shall be located outside the physical boundaries of the installation. It is the contractor’s responsibility to tarp and/or protect their dumpsters etc. On-site dumpsters furnished by the contractor shall be coordinated with the Government Inspector. Refuse disposal shall comply with the current JBSA-Lackland disposal environmental requirements.
7. RECORDS MANAGEMENT:
The contractor shall manage all data created for Government use or legally controlled by the Government, in support of the functional activity or required by AF publication, IAW with the AF Records Management procedures in Air Force Instruction (AFI) 33-322 or subsequent replacement Air Force Manual (AFMAN) 33-363 and Air Force Instruction (AFI) 33-364 (or their subsequent replacements)".
8. PLACE AND HOURS OF PERFORMANCE:
When working at Government facilities, work shall be accomplished during normal duty hours (0730-1630), Monday through Friday, unless otherwise approved by the Government Project Manager. The contractor shall not schedule work on Federal Holidays: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. If the holiday falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.
When the contractor desires to work other than standard times, a written request shall be submitted to the Contracting Office for approval. Written approval from the Contracting Officer must be received before proceeding with the work.
APPENDIX A:
END STATEMENT OF WORK
| 6. CONTRACTOR GENERATED REFUSE: |
| All contractor generated refuse and waste shall be stored in a waste container provided by the contractor and hauled from the construction site to a disposal area to be selected by the contractor and shall be located outside the physical boundaries of... |
| 8. PLACE AND HOURS OF PERFORMANCE: |