The document provided is the Schedule B.1 - Janitorial Specifications for a Request for Proposal (RFP) No. 230000001925 for Janitorial Services for the Menominee Welcome Center issued by the Michigan Department of Transportation (MDOT). The specifications outline the janitorial requirements for the Welcome Center/Rest Area, including primary cleaning of restrooms, storage/utility areas, general grounds cleaning, maintenance of plastic map and display cases, and sidewalks/walkways/porch areas. The document also details no-snow/growing season services, snow/winter season services, and minor facility maintenance responsibilities. The contract term is 3 years, with two additional 1-year renewal options.
The contractor is responsible for providing all cleaning supplies and equipment, maintaining a two-week supply onsite, and properly storing all supplies and equipment. No additional compensation will be provided for holiday periods or summer weekend coverage, as these costs are to be included in the contract unit price. The contractor must notify the MDOT Program Manager when supply levels are low and perform minor maintenance tasks, while MDOT is responsible for major building repairs and replacements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard Contract Terms MWC.docx | DOCX document | |
| MWC Schedule A.docx | DOCX document | |
| proposal-instructions-confidential-treatment-vendor-questions-worksheet-pass-fail-low-bid.docx | DOCX document | |
| MWC LSS.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan.gov/MiProcurement
SCHEDULE B.1 – JANITORIAL SPECIFICATIONS
Michigan.gov/MiProcurement
SCHEDULE B.1 – JANITORIAL SPECIFICATIONS
Request for Proposal (RFP) No. 230000001925 Janitorial Services for the Menominee Welcome Center
I. WELCOME CENTER/REST AREA JANITORIAL REQUIREMENTS
An attendant must be onsite during the Regular Hours of Staffing as stated in the Specifications on Schedule C – Location Specification Sheet.
1.1. BASIC JANITORIAL SERVICES
A. Restrooms
1. Primary Cleaning of Restrooms. Primary cleaning, specified in the following, shall be completed between the hours of 6:30 A.M. and 9:30 A.M.
a. Close off restroom and place closed sign in front of door while cleaning, if necessary. Restroom shall be closed a maximum of 20 minutes in Rest Areas which only have one men’s and one women’s bathroom. All restrooms shall remain open except during cleaning.
b. Perform cleaning survey of all areas - note problems with lights, faucet leaks, flush valves, floor tiles, drains, etc. Fill out condition report.
c. Replenish supplies (toilet tissue, hand soap, etc.). Do not dilute hand soap with water.
d. Clean and disinfect door, door pulls, window, kick plates, etc.
e. Clean and sanitize baby changing stations. Use an all-purpose or pH-neutral cleaning solution. Clean all touchable areas of the baby changing station, including handles, sides, safety straps and the interior changing surface. After use of cleaning solution, wipe down with clean, wet towel or rinse down with water to ensure removal of any soil or chemical material.
f. Clean and disinfect sanitary napkin receptacle - remove bag, disinfect container, and install new bag.
g. Apply disinfectant to outside of toilets, top and bottom of seats, and flush valves. Do not use acid bowl cleaner.
h. Punch water out of toilet traps.
i. Apply acid bowl cleaner to johnny mop and clean inside of toilet bowl. Pay special attention to under the rim of the bowl.
j. Apply disinfectant to outside of urinals and flush valves. Do not use acid bowl cleaner.
k. Apply acid bowl cleaner to johnny mop and clean inside of urinal bowl.
l. Clean mirrors.
m. Clean and disinfect sinks, countertops, fixtures, and front of vanity.
n. Clean and disinfect hand dryers. For manual dryers, disinfect push buttons and wipe air inlet openings. For automatic dryers, follow manufacturer’s instructions for cleaning and taking care to avoid damage to sensors.
o. Wipe disinfectant from toilets, seats, flush valves, and urinals.
p. Spot clean walls, ceilings, and partitions; remove graffiti.
q. Pick up trash and sweep floor.
r. Empty trash receptacles; clean and disinfect inside and outside of all waste receptacles presenting a soiled or odorous condition. Replace receptacle liners when torn or soiled.
s. Mop floors using liquid detergent disinfectant.
t. Place floor dryers as needed to dry floor prior to re-opening rest room.
u. Report needed repairs to the Program Manager.
2. Disinfect and clean entire walls and partitions.
3. Remove and clean plastic light fixture covers with soap and water.
4. Clean window screens as needed.
5. Scrub tile floors.
a. Close restroom - sign properly displayed.
b. Sweep area thoroughly; remove gum or sticky substances with putty knife.
c. Fill bucket with carefully measured 20-36% E.P.A. registered phosphoric acid-based solution.
d. Place wet floor signs in area.
e. Liberally apply cleaning solution to floor with wet mop.
f. Allow solution to dwell five minutes.
g. Scrub corners and areas machine will not reach with manual swivel scrub brush.
h. Pickup scrubbing solution with wet mop.
i. Empty bucket - refill with clean rinse water.
j. Rinse floor and corners thoroughly - change water often.
k. Pickup rinse water with dry mop.
l. Dry mop, allow to dry, remove wet floor signs.
6. Wash restroom walls, partitions, toilets, and urinals with portable pump-up sprayer.
a. Close restroom.
b. Remove all paper products.
c. Trip the circuit to hand dryers, and electrical outlets.
d. Cover all hand dryers, and electrical outlets with plastic duct tape.
e. Wear gloves and eye protection and any other PPE prescribed by the SDS for the cleaning product being used.
f. Prepare detergent-disinfectant solution according to manufacturer’s directions.
g. Apply cleaning solution to walls and partitions. (DO NOT SPRAY CEILING).
h. Wash toilets, urinals, flush valves.
i. Allow solution to dwell 10 minutes.
j. Rinse thoroughly with clean, warm water.
k. Wipe down walls, toilets, and urinals with clean cloth.
l. Dry mop floor.
7. Clean drains with approved disinfectant.
8. Completely clean ceiling vent covers.
9. Turn off ceiling heaters (if present) and clean panels.
B. Storage/Utility Areas
1. Keep storage area neat and tidy.
a. Pick up litter.
b. Dispose of empty containers and supplies/materials/equipment no longer used or are damaged.
c. Keep walkways clear of obstruction.
2. Visually inspect all equipment (water heaters, pipes, furnace, etc.) for possible leaks.
3. Sweep, mop floor and wipe equipment.
4. Clean drains with approved disinfectant cleaner.
C. General Grounds Cleaning
1. Pick up litter and debris, including paper, food/drink waste, cigarette butts, sticks, and animal droppings, from the grounds and all parking lots. Properly dispose of debris.
2. Sweep curb.
3. Empty recycle bins, replace liners and clean barrels as necessary.
4. Clean cigarette snuffers and/or ash receptacles. Remove cigarette butts from containers.
5. Clean park benches and picnic tables with detergent/disinfectant and rinse.
6. Sweep concrete slabs beneath park benches and picnic tables.
7. Remove/dispose of ashes and clean picnic grills/stoves.
D. Plastic Map and Display Cases
1. Clean plexiglass with a mild soap and water. Do not use harsh chemicals or abrasive materials – DO NOT scratch plexiglass.
2. Remove graffiti using appropriate product for surface.
3. Remove cobwebs in and around structures.
E. Sidewalks, Walkways, and Porch Areas
1. Sweep all sidewalks, walkways, and porch area pavement surfaces clean of debris.
2. Wash exterior of front porch once a month during the months of June, July and August.
1.2. NO-SNOW and/or GROWING SEASON SERVICES
F. General Grounds Cleaning
1. Water new landscape plantings as needed or as directed by Program Manager.
2. Weed all landscaped beds, flowerbeds and mulch/wood chip covered areas.
G. Sidewalks, Walkways and Porch Areas
1. Remove weeds/grass growing in concrete cracks.
2. Remove gum by spraying with gum remover.
H. Annual Flower Beds
1. Water as often as needed.
a. Do not allow soil to dry out.
b. Water in the morning.
c. Water thoroughly, with water hose, allowing the water to penetrate down to a depth of four to six inches to encourage deep root growth. Probe the soil to determine when the water has reached these depths.
2. Remove weeds daily as needed. Weeds must be removed either by hand pulling or lightly scratching the surface with a hoe to cut weeds off just below the soil level.
3. Remove (deadhead) faded flowers. Deadheading is necessary to keep the plants attractive, from going to seed and to prevent diseases. Remove faded flowers as needed according to the maintenance level throughout the entire season.
a. Low Maintenance - Faded flowers fall cleanly from the plant and do not need removing.
1) Alyssum
2) Basil
3) Begonias
4) Coleus
5) Dahlberg daisy
6) Dusty Miller
7) Flowering cabbage and kale
8) Impatiens
9) Vinca
b. Semi-Low Maintenance - Shear back once in mid-July. Shearing back is another form of deadheading. Only enough growth is sheared to remove the flower heads. No more than 33% - 50% of the plants’ top growth should be removed.
1) Lobelia
2) Petunia
c. Medium Maintenance - Deadhead at least twice a week or as blossoms die. Pinch off faded flowers with fingers just below the flower head or pinch off complete stems depending on the particular plant. Be sure to remove the seedpod also.
1) Brachycome (Swan River Daisy)
2) Cosmos
3) Dianthus
4) Geraniums
5) Marigold
6) Pansies
7) Rudbeckia
8) Salvia
9) Snapdragon
10) Strawflower
11) Verbena
1.3. SNOW and/or WINTER SEASON SERVICES
I. Sidewalks, Walkways and Porch Areas
1. Shovel/sweep as often as needed to remove snow and ice; the full width of sidewalks, walkways and porch areas must be kept free of snow and ice at all times.
2. Apply deicer chemicals/sand after snow/ice removal is complete.
3. Remove, as often as needed, any snow left between the parking area (curbside) and the sidewalk. All curb cuts must be kept clear of snow and ice.
4. To avoid snow being pushed onto walkways during plowing, snow must be cleared along the curbs adjacent to the walkways in the parking lot areas in front of and in back of the Welcome Center/Rest Area building. The cleared area must be at least the width of a snowblower or 24” wide and the length of the walkways.
5. When snow is not present, sweep excess deicer chemical from sidewalks/walkways/porch areas after clear and dry.
1.4 FACILITY MAINTENANCE
J. Minor Maintenance The Contractor must perform the following minor maintenance:
1. Tighten loose screws in partition doors, door closures, etc.
2. Plunge plugged toilets and urinals or rod if necessary.
If a problem cannot be fixed by minor maintenance, turn off water supply to fixtures, electric supply to dryers, lights, or heaters; place temporary "out of order" sign on stall; and notify the Program Manager immediately. The Program Manager may give further instructions for temporary closing part or all of the Welcome Center/Rest Area.
The Contractor shall notify the Program Manager of any conditions that are deemed hazardous or may be questionable and of Welcome Center/Rest Area damage that requires more than minor maintenance.
The Contractor must contact the Program Manager immediately for necessary repairs and replacements, or of any warning lights in the maintenance room or outside on Welcome Center/Rest Area grounds.
The Contractor must not adjust or tamper with controls regulating water treatment equipment, or HVAC equipment. Temperatures in the Rest Area will be maintained at 68 degrees Fahrenheit.
K. MDOT Responsibility
1. Major building repairs and replacement of fixtures will be done by MDOT as required, unless specified as the Contractor's responsibility.
2. MDOT is responsible for the general maintenance of their facilities and all other maintenance not specifically required of the Contractor under the Contract. Maintenance performed by MDOT includes:
a) Water conditioning equipment
b) Building structures or shelters
c) Trees and shrubs, placing and planting, trimming and removal
d) Heating and plumbing systems, unless specified as the Contractor's minor maintenance
e) Fences
f) Lagoons, tile fields and septic tanks
g) Electrical equipment
h) Utility bills
II. HOLIDAYS AND ADDITIONAL COVERAGE
Holiday periods and Summer weekends may require additional hours of coverage. See Schedule C, tab 1 Service Specifications for additional coverage hours and requirements. No additional compensation will be provided; coverage costs for these periods are to be included in the Contract unit price.
III. REFUSE DISPOSAL
A. Contractor Responsibilities
1. Garbage and recycling shall be placed on the curb by 7:00 am. on Tuesday’s.
2. SUPPLIES REQUIREMENTS
A two-week supply of all replenishable materials and products must be stored at the Welcome Center. Vendor is responsible to notify MDOT Program Manager when supplies are low. All supplies and materials must be properly stored in the Storage Room areas.
B. Cleaning Supplies – To Be Provided
IV. EQUIPMENT
A. Equipment Requirements – To be Provided
V. SUPPLIES AND EQUIPMENT STORAGE
All supplies and equipment must be stored within the confines of the assigned storage/utility area.
1. Storage/utility areas must be clean and orderly.
2. All boxes and supply items that may be damaged by water must be stored on shelves; these items cannot be stored on the floor.
3. Items are stored in a manner consistent with the fire code and Safety Data Sheet requirements. Aisles/walking areas are wide and free from obstructions or obstacles.
4. No used equipment parts or broken equipment and/or equipment parts will be stored in the storage/utility areas. Old or broken equipment or equipment parts must be removed from the facility.
image1.png
File details come from the government source that posted it. Updated .