This document is a Statement of Work (SOW) for the procurement of Microwave Absorber Brazements for the Material Plasma Exposure (MPEX) experiment at Oak Ridge National Laboratory (ORNL). The SOW covers the brazing, testing, inspection, packaging, and delivery of the Microwave Absorber Brazements, which are in-vessel components that accept high heat loads and are part of the vacuum envelope of the MPEX device.
The SOW outlines the specific performance requirements, including the development of a quality plan and project schedule, drawing and specification review, manufacturing review, fabrication, and final delivery. It also details the project management requirements, such as communications protocol, schedule and milestones, reporting, and quality assurance. Key deliverables include the quality assurance program documentation, a list of proposed deviations, manufacturing review reports, and the final factory acceptance test report. The SOW is associated with a federal contract opportunity (Solicitation Number: PR325497) issued by the Department of Energy for the MPEX Microwave Absorber Brazements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MPEX-05-SOW-002_High Heat Flux Brazed Components.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MPEX-05-SOW-003 R0
STATEMENT OF WORK FOR
MPEX MICROWAVE ABSORBER BRAZEMENTS
MATERIAL PLASMA EXPOSURE EXPERIMENT
(MPEX)
Prepared by
OAK RIDGE NATIONAL LABORATORY
Oak Ridge, TN 37831-6283
Managed by
UT-BATTELLE, LLC
For the
US DEPARTMENT OF ENERGY
under contract DE-AC05-00OR22725
This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof. The views and opinions of the authors expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.
MPEX-05-SOW-003 R0 Page 2 of 15
Material Plasma Exposure Experiment Oak Ridge National Laboratory
Statement of Work for MPEX Microwave Absorber Brazements for the
Material Plasma Exposure Experiment Project
MPEX-05-SOW-003
Reviewers:
Matt Dessel, Engineer Date
Misty Magill, Procurement Officer Date
Milena Keys, Quality Assurance Representative Date
Aftab Hussain, MPEX Lead Engineer, TPO Date
Craig Deibele, MPEX Operations Lead
Approver: Date
Adam Aaron, CAM, In Vessel Components Date
Distribution:
John Sanseverino, MPEX Interim Project Director Robyn Rose, MPEX Project Manager
MPEX-05-SOW-003 R0 Page 3 of 15
Revision History
Revision Date DESCRIPTION OF CHANGE
REVISION TYPE
Major Minor
0 October, 2024 Initial Issue ☒ ☐
MPEX-05-SOW-003 R0 Page 4 of 15
CONTENTS
ACRONYMS
1. INTRODUCTION
2. SCOPE
3. APPLICABLE DOCUMENTS
4. PERFORMANCE REQUIREMENTS
4.1 TASK 1: QUALITY PLAN AND PROJECT SCHEDULE
4.2 TASK 2: DRAWING AND SPECIFICATION REVIEW
4.3 TASK 3: MANUFACTURING REVIEW
4.4 TASK 4: HIGH HEAT FLUX BRAZED COMPONENTS FABRICATION
4.5 TASK 5: DELIVER HIGH HEAT FLUX BRAZED COMPONENTS
5. PROJECT MANAGEMENT
5.1 LANGUAGE
5.2 COMMUNICATIONS PROTOCOL
5.3 KICKOFF MEETING
5.4 SCHEDULE AND MILESTONES
5.5 MONTHLY REPORTS
5.6 VARIANCE REPORTING
5.7 PERIODIC COMMUNICATIONS
6. QUALITY ASSURANCE
6.1 QUALITY PROGRAM
6.2 ACCESS FOR SOURCE SURVEILLANCE INSPECTIONS
6.3 SUSPECT/COUNTERFEIT ITEMS PREVENTION
6.4 SELLER REQUESTED DEVIATIONS
6.5 NON-CONFORMANCES
6.6 MEASUREMENT AND TEST EQUIPMENT
MPEX-05-SOW-003 R0 Page 5 of 15
7. TRANSPORTATION
8. DELIVERABLES
MPEX-05-SOW-003 R0 Page 6 of 15
ACRONYMS
MPEX Material Plasma Exposure Experiment
TPO Technical Project Officer
ISO International Organization for Standardization
NIST National Institute of Standards and Technology
NQA ASME Nuclear Quality Assurance
QAP Quality Assurance Program
SOW Statement of Work
STEP Standard for the Exchange of Product Data
PMI Plasma Material Interaction
COTS Commercial Off the Shelf
DAP Delivered at Place
FAT Factory Acceptance Test
POC Point of Contact
PO Procurement Officer
ORNL Oak Ridge National Laboratory
CMM Coordinate Measuring Machine
VCR Swagelok VCR® Metal Gasket Face Seal Fitting
SCI Sensitive Compartmented Information
MPEX-05-SOW-003 R0 Page 7 of 15
1. INTRODUCTION
The Material Plasma Exposure eXperiment (MPEX), a superconducting magnet, steady-state plasma device, is being built at Oak Ridge National Laboratory (ORNL) to address the harsh conditions inside a fusion reactor. This device, as designed, will have the unique feature of being able to conduct accelerated lifetime tests of plasma-facing components, including those that have experienced neutron damage. The in-vessel components are plasma-facing components that accept high heat loads and are part of the vacuum envelope of the MPEX Device. The brazements in this procurement are used to build the Microwave Absorber, an in-vessel component.
2. SCOPE
This Statement of Work (SOW) applies to the brazing, testing, inspection, packaging, and delivery of the Microwave Absorber Brazements in Table 1.
Table 1.
In-Vessel Components MPEX Drawing Number Rev Order Qty
Notes
Microwave Absorber MPEX-05-DES-03-A003 0 14 ORNL is responsible for machining of all components except interstitial layer parts
(MPEX-05-DES-03-A009).
Seller is responsible for finished interstitial layers
(MPEX-05-DES-03-A009)
and brazing of interstitial layers and AlN tiles to explosion bonded plate.
Microwave Absorber MPEX-05-DES-03-A004 0 2 ORNL is responsible for machining of all components except interstitial layer parts
(MPEX-05-DES-03-A009).
Seller is responsible for finished interstitial layers
(MPEX-05-DES-03-A009)
and brazing of interstitial layers and AlN tiles to explosion bonded plate.
MPEX-05-SOW-003 R0 Page 8 of 15
3. APPLICABLE DOCUMENTS
Table 2
Document Revision
MPEX-00-ENG-002 MPEX Vacuum Handbook [1] 0
Quality Assurance Plan for the MATERIAL PLASMA EXPOSURE EXPERIMENT [2] 0
4. PERFORMANCE REQUIREMENTS
4.1 TASK 1: QUALITY PLAN AND PROJECT SCHEDULE
The seller shall prepare a quality plan and a project schedule for the manufacture, test, and delivery of the Microwave Absorber Brazements. The quality plan shall address how the seller's Quality Program will be applied to the work in this SOW, and identify procedures and other documentation for all special processes, measurements, etc. The quality plan shall also identify the planned work to be outsourced, list the planned or expected subcontractors and suppliers, and address how the quality requirements of this SOW will be flowed down to these subcontractors and suppliers.
The project schedule shall contain sufficient detail so that ORNL may track procurement, fabrication, testing, and shipping activities. The seller shall propose milestones for tracking progress and payments based on the Tasks outlined here in Section 4 and the activities and milestones listed in Section 5.4 that will require ORNL approval.
For this task, the seller shall provide the ORNL with:
• Quality plan
• Project Schedule
• Factory Acceptance Test Plan
4.2 TASK 2: DRAWING AND SPECIFICATION REVIEW
The seller shall review the MPEX drawings identified by the part number awarded to the seller in Table 1, the specifications of the vacuum components found in [1], and the quality guidelines and requirements outlined in [2]. The seller can propose deviations or changes to these specifications.
ORNL will review these change requests. The specified braze alloy shall be discussed to ensure the seller is qualified to perform braze using indicated material. Seller may specify alternative alloy for review by ORNL.
Proprietary seller manufacturing processes that are different from the drawing specifications or requirements of [1] shall be identified and reviewed with ORNL. The seller is responsible for documenting any deviation from the Microwave Absorber Brazements drawings.
MPEX-05-SOW-003 R0 Page 9 of 15
Any deviation request shall be submitted by the seller and approved by ORNL for all process or specification deviations and then must be maintained under revision control after ORNL approval.
The seller shall provide ORNL with all released documents.
4.3 TASK 3: MANUFACTURING REVIEW
With the completion of Task 2 and with authorization from ORNL, the seller shall prepare a manufacturing plan to demonstrate how the design specifications given in the drawings and [1] and [2] are satisfied. The seller shall prepare a report and participate in a manufacturing review.
The Manufacturing review will be held by videoconferencing or at the seller's site based on an agreement between the seller and ORNL. The seller shall prepare written meeting minutes and submit them to ORNL for review within 3 working days after the meeting. Completion of the Manufacturing review and closure of all action items shall constitute a project milestone.
The Manufacturing Review and Report shall include:
• Component fabrication plan, including all purchased and outsourced components.
• Review of materials and processes to be used for brazing, including brazing alloys.
• A project plan summary of how compliance with all MPEX requirements and specifications will be achieved.
4.4 TASK 4: MICROWAVE ABSORBER BRAZEMENTS FABRICATION
After completion of Task 3 and with approval of ORNL, the seller shall provide an updated manufacturing schedule and begin construction. The seller and ORNL shall establish a recurring fabrication update meeting not to exceed 1 month between meetings. The seller shall prepare a current manufacturing status report and identify any fabrication issues or logistics that will affect the agreed-upon delivery date. ORNL will review and generate actionable items for the seller or ORNL. Status shall be reviewed at all fabrication status meetings. Fabrication status meetings shall be held by videoconferencing or at the seller's site based on an agreement between the Seller and ORNL. The seller shall prepare written meeting minutes and submit them to ORNL for review within 3 working days after each meeting. Meeting minutes can be used to supplement the monthly reporting requirements of Section 5.5.
At a minimum, the meeting minutes shall include:
• Project schedule update o Component brazing status o Delivery status
• Quality plan update o Quality Control Inspection reports o Non-conformance reports
• Status of old action items
MPEX-05-SOW-003 R0 Page 10 of 15
• New action items
• Report any variances or deviations from the agreed-upon specifications
• Summary of main discussion topics
• Summary of decisions and agreements between the seller and ORNL.
4.5 TASK 5: DELIVER MICROWAVE ABSORBER BRAZEMENTS
Upon successful completion of Task 4 and with authorization of ORNL, the seller shall perform factory acceptance testing, generate quality plan compliance documentation, and deliver the high heat flux brazed components following the approved approach from Task 3 meeting the drawings requirements and specifications in [1] and [2].
Final acceptance of the high heat flux brazed components will occur upon successful completion of the site acceptance tests at ORNL’s facility.
5. PROJECT MANAGEMENT
5.1 LANGUAGE
All communications and documentation shall be in English.
5.2 COMMUNICATIONS PROTOCOL
The seller shall designate an official single Point of Contact (POC) to interface with ORNL. The interface will be made via ORNL’s designated Technical Project Officer (TPO).
Only ORNL’s Procurement Officer (PO) can authorize changes to the price, statement of work, or work scope.
Problems encountered or anticipated shall be communicated as soon as practical.
5.3 KICKOFF MEETING
The kickoff meeting will be scheduled at a mutually agreed time as soon as practical after the award of the subcontract. The seller is responsible for recording meeting minutes and submitting them to ORNL within 3 working days after the meeting.
The primary purpose of the kickoff meeting is to confirm that the project participants understand the terms and conditions of the subcontract, SOW, drawings requirements and specifications in [1] and [2], and work activities.
The following topics will be discussed:
1. Flow down of requirements.
2. Work activities, schedules, and deliverables
MPEX-05-SOW-003 R0 Page 11 of 15
3. Expectations for satisfying quality standards and documentation
The seller should be prepared to review Tasks 1 and 2 during the kickoff meeting.
5.4 SCHEDULE AND MILESTONES
At a minimum, the schedule shall include the following activities or milestones:
• Kickoff meeting
• Quality Plan
• Manufacturing Review
• Resolution of deviation requests and approval for construction
• Materials ordered or fabrication started
• Individual brazements complete
• Factory Acceptance Tests
• Approval of Shipping Plan
• Prepare for shipment
• Customer onsite final acceptance tests
• Complete and submit final documentation
5.5 MONTHLY REPORTS
Monthly reports shall be submitted by the third calendar day of each month or on the seller’s usual reporting schedule as mutually agreed between ORNL and the seller’s POC.
Monthly report data shall include actual schedule progress, milestones reached, corrective actions needed, display of the present critical path for the seller’s work, and a brief narrative describing the status of work, significant accomplishments, actual and potential problems, and risk mitigations or corrective actions.
5.6 VARIANCE REPORTING
The seller shall notify ORNL (TPO and PO) immediately in writing when it is determined the actual cost may exceed the Agreement price. In no case shall the seller continue work without authorized funding if it is determined that the actual cost may exceed the agreement price.
5.7 PERIODIC COMMUNICATIONS
The seller shall participate in a bi-weekly (every other week) meeting (or as agreed to in 5.3) to be held with ORNL to discuss any technical issues and schedule, personnel, and any other items pertinent to the work activities. The bi-weekly phone conference will serve as a mechanism to get early visibility of potential problems and issues arising during the performance of this subcontract.
MPEX-05-SOW-003 R0 Page 12 of 15
The seller shall prepare written meeting minutes and submit these to ORNL within 3 working days after the meeting.
6. QUALITY ASSURANCE
6.1 QUALITY PROGRAM
The seller shall have a Quality Assurance Program (QAP) that, at a minimum, is ISO 9001 certified, but preferably compliant with NQA-1 2008/2009a or equivalent. The seller shall be able to demonstrate that it can fulfill the quality assurance requirements in this. At a minimum, the prospective supplier shall have an established, documented, and effectively implemented quality assurance program describing controls for work processes (controlled by instructions/procedures), personnel training and qualification, document and records control, design, procurement, inspection, and testing; including the use of measuring and test equipment when used, corrective action, and assessments (audits).
Before the subcontract award, the seller’s QAP shall be evaluated to determine the degree of effective implementation of the quality program. Deficiencies, if any, identified during the evaluation shall be addressed and corrected to the satisfaction of ORNL and shall occur before award.
All suppliers/sub-suppliers, subcontractors, and fabricators (as applicable) shall have a Quality Assurance Program that meets or exceeds the requirements listed above.
6.2 ACCESS FOR SOURCE SURVEILLANCE INSPECTIONS
As part of the ORNL’s quality assurance program, ORNL reserves the right to perform source surveillance activities which may be conducted at the seller’s facility or any sub-tier seller facility that the ORNL determines necessary to ensure that quality objectives are met.
6.3 SUSPECT/COUNTERFEIT ITEMS PREVENTION
The Seller’s QAP must include a Sensitive Compartmented Information (SCI) Program that is compliant with DOE O 414.1D, Quality Assurance, or approved equivalent. Although there is a provision in the contract describing SCI prevention; we have found many vendors don’t focus on the details of SCI nor the impact long-term of counterfeit items prevention.
6.4 SELLER REQUESTED DEVIATIONS
The seller shall propose any deviations to the specifications, drawings, or other technical requirements during the Review of Specifications per Section 4.2 and obtain ORNL’s approval before invoking the deviation. Any deviation requests arising from the fabrication phase shall adhere to the seller's quality program procedure and must be approved by ORNL.
MPEX-05-SOW-003 R0 Page 13 of 15
6.5 NON-CONFORMANCES
When a nonconformance is identified, the seller shall notify ORNL to determine the required actions and document the nonconformance following the seller's quality program procedure. All nonconformances shall be summarized in the final report. Items that do not conform to specified requirements shall be controlled to prevent inadvertent installation or use. Controls shall provide for identification, documentation, evaluation, segregation when practical, disposition of the nonconforming items, and for notification to ORNL.
6.6 MEASUREMENT AND TEST EQUIPMENT
Tools, gages, instruments, and other measurement and test equipment used for activities affecting quality shall be controlled, calibrated at specified periods, adjusted, and maintained to required accuracy limits.
Measurement and test equipment used by the Seller to perform work under this Statement of Work must be calibrated and traceable to NIST standards. Calibrations must be current. Calibration records must be provided to ORNL.
7. TRANSPORTATION
The equipment shall be packaged according to [1], section 3.10 and in a manner that protects the equipment from damage and facilitates movement, loading, and unloading by fork truck or crane.
Any special lifting fixtures or related hardware that are required to move, load, or unload the equipment shall be considered part of the equipment. Incoterms: Delivered at Place (DAP) (ORNL Facility – Oak Ridge TN).
8. DELIVERABLES
The seller shall supply the following:
Deliverable 1 – Within 2 weeks of subcontract award, provide to ORNL the seller's quality assurance program documentation and a project specific quality plan.
Deliverable 2 – At the kickoff meeting defined by 5.3,the seller shall provide to ORNL a list of proposed deviations to any requirements specified in the drawings of the awarded Microwave Absorber Brazements or governed by MPEX documents [1] and [2].
Deliverable 3 – Manufacturing review shall be held no more than 8 weeks after subcontract award and shall include the following documents:
• Manufacturing review report
• Presentation slides and documents
• Action item resolution documentation
• Fabrication procedures for all brazing processes
MPEX-05-SOW-003 R0 Page 14 of 15
Deliverable 4 – Microwave Absorber Brazements shall be delivered with the following:
• Quality inspection data required for all components
• Test data required for all components
• Completed factory acceptance test report shall include as a minimum o Material certifications (brazing alloys) o Critical dimension report
MPEX-05-SOW-003 R0 Page 15 of 15
REFERENCES
[1] MPEX-00-ENG-002 Vacuum Handbook [2] MPEX-12-PLAN-001 Quality Assurance Plan for the MATERIAL PLASMA EXPOSURE
EXPERIMENT
| 2024-10-03T14:15:04-0400 | |
| MATTHEW DESSEL |
| 2024-10-03T14:20:55-0400 | |
| Misty Magill |
| 2024-10-04T08:52:26-0400 | |
| Milena Keys |
| 2024-10-04T09:09:14-0400 | |
| Muhammad Aftab Hussain |
| 2024-10-04T09:13:59-0400 | |
| Craig Deibele |
| 2024-10-04T09:17:07-0400 | |
| Aaron, Adam |
File details come from the government source that posted it. Updated .