MOT_HMA M-19_Maint_Project2023_ssg_230517 (3).docx

DOCX document 67 KB Posted

Attached to
PMC-HMA Repairs Detail 7 M-19 from 31 Mile Rd to Boardman Rd
Solicitation number
RFP - 591 - 230000002506
Issued by
Macomb County, Rochester City, Michigan

About this file

The document provided is a Special Provision for Maintaining Traffic related to a road maintenance project on M-19 within Macomb County and St. Clair County, Michigan. The project includes requirements and restrictions to maintain traffic during the construction, including the use of various traffic control typicals, restrictions on lane closures and work during holiday periods and special events, and specific traffic regulation procedures. The document outlines the Construction Influence Area, traffic restrictions, and details for hot mix asphalt work, traffic control devices, and measurement and payment.

The related state and local contract opportunity is for Hot Mix Asphalt (HMA) repairs on M-19 from 31 Mile Road to Bordman Road, located in Macomb County and the City of Rochester. No additional details regarding pricing, set-asides, funding, or other salient information are provided.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Macomb TSC: SSG 2 of 13 05-17-2023

MICHIGAN

DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR

MAINTAINING TRAFFIC

Macomb TSC: SSG 1 of 7 APPR:MAC:SES Date 5-17-2023

a. Description. This special provision consists of requirements and restrictions to maintain traffic on M-19 in the city of Richmond and Memphis within Macomb County and St. Clair County.

b. General. Maintain traffic throughout the project in accordance with the standard specifications, typicals, and supplemental specifications in the contract and as described on the plans for this project.

c. Construction Influence Area (CIA). The CIA includes the right-of-way of the following roadways, within the approximate limits described below:

1. 0.25 miles South of 31 Mile Rd and 0.25 miles north of Bordman Rd. on NB and SB M-19 (Gratiot Ave, Main St, and Memphis Ridge Rd).

2. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately 1/4 mile in advance of the work zone or as far as the construction or detour signing extends. The roads include but are not limited to 31 Mile Rd., Gratiot Ave, Main St., Division Rd., 33 Mile Rd., Weber Rd., Pratt Rd., Bordman Rd., and Memphis Ridge Rd.

d. Traffic Restrictions. Maintain traffic in accordance with the Maintaining Traffic Typicals contained herein, except as noted below. Changes or adjustments to the Maintaining Traffic Typicals may be necessary to fit field conditions, subject to approval of the Engineer or as determined by the Engineer.

1. Utilize the following Maintaining Traffic Typicals:

A. 100-GEN-KEY

B. 101-GEN-SPACING-CHARTS

C. 102-GEN-NOTES

D. 103-GEN-SIGN

E. 104-GEN-AB

F. 107-GEN-SPEED

G. 110-TR-NFW-2L

H. 111-TR-NFW-2L-RUM

I. 112-TR-CLT

J. 122-NFW-SHL-(R)

K. 130-CLT-1(CLT)

L. 137-CLT-SHIFT-OLC

M. WZD-100-A

N. WZD-125-E

2. Do not work, deliver material, or close lanes during the holiday periods as defined in Table 1.

Table 1: 2023 Holiday Periods

Holiday
Start Date and Time
End Date and Time
Memorial Day
3:00 p.m. Friday, May 26th
6:00 a.m. Tuesday, May 30th
Independence Day
3:00 p.m. Friday, June 30th
6:00 a.m. Wednesday, July 5th
Labor Day
3:00 p.m. Friday, September 1st
6:00 a.m. Tuesday, September 5th

3. Do not work, deliver material, or close lanes during the Special Events as defined in Table 2.

Table 2: 2023 Special Events

Local Event
Start Dates and Time
End Date and Time
Memphis Days Festival
3:00 p.m. Thursday, August 3rd
6:00 a.m. Monday, August 7th
Good Old Days Festival
3:00 p.m. Thursday, September 7th
6:00 a.m. Monday, September 11th

4. Perform work and lane closures within the allowable time frames as shown in Tables below, unless otherwise approved by the Engineer. Traffic switch operations on freeways may take place within the allowable times listed below in the traffic restriction tables and/or as otherwise approved by the Engineer. Additional lane, ramp, and/or roadway closures and shifts may be implemented during maintaining traffic stage and traffic switch operations with prior Engineer approval.

Location: M-19 (Gratiot Ave, Main St, and Memphis Ridge Rd ) from 31 Mile Rd to Bordman Rd

Closure Type
Start Time
End Time
M
Tu
W
Th
F
Sa
Su

Traffic Regulators 2-Lane Undivided Roadway

00:00
05:00
∞
∞
∞
∞
∞
∞
∞
05:00
20:00
0
0
0
0
0
0
0
20:00
24:00
∞
∞
∞
∞
∞
∞
∞

∞ = Closure is allowed, and the frequency is not limited during the project timeframe # = The number of times closures can take place during the project timeframe.

i. Coordinate with any Macomb County and St. Clair County Department of Roads work.

ii. Maintain or coordinate access to buses while work is active.

iii. Lane closures are prohibited during special events listed in this document.

5. Total closure is not allowed on M-19 at any time.

6. No more than one closure is allowed in each direction of travel at the same time.

A. The maximum closure length is 1 mile unless otherwise approved by the Engineer.

7. Close any dedicated lanes (exit, ramp, turn, etc.) prior to the location under construction.

8. Restrict access to M-19 from side roads for short durations at specific locations as the Engineer directs or approves. Where an intersection is closed or partially closed, allow the adjacent intersections one block to the north and south to remain open to traffic, unless otherwise approved by the Engineer.

e. Traffic General.

1. For any lane open to traffic, provide a minimum lane width of 11 feet with 2 feet of shy distance on both sides unless identified otherwise on plans.

2. Do not close lanes or utilize traffic regulation sequences where work can be accomplished with a shoulder closure. Do not occupy any part of the active traffic lane with personnel or equipment when utilizing a shoulder closure. Place lane closures and traffic regulation operations only in areas as show on the plans unless otherwise directed by the Engineer.

3. Prior to shifting traffic onto shoulders or opening any lanes/shoulders and/or ramps, remove, by sweeping all accumulated debris that has collected within the shoulder and/or within the closed lane/shoulder.

4. A speed reduction will be used. Set the work zone speed limit on M-19 to 30 miles per hour (mph) where existing speed is 40 mph and 45 mph where existing speed is 55 mph while traffic regulator is being utilized.

5. Develop and submit to the Engineer an Internal Traffic Control Plan (ITCP) per subsection 104.11.B of the Standard Specifications for Construction. The requirements listed herein are the requirements for a Type A ITCP. Submit the Type A ITCP at the preconstruction meeting. The Engineer will have 7 calendar days to review the ITCP for approval or provide comments for revisions required to obtain approval. Include in the ITCP, at a minimum, the proposed ingress/egress locations for construction equipment and vehicles, traffic control devices that will be utilized to warn the motoring public of ingress/egress locations, and measures that will be taken to ensure compliance with the ITCP. Ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone. No work may begin prior to approval of the ITCP. Additional time required to obtain an approved ITCP will not be cause for delay or impact claims. All costs associated with obtaining an approved ITCP, providing and executing all parts of the approved ITCP including required traffic control devices, or resolving an incomplete or unacceptable ITCP will be borne by the Contractor.

6. Upon approval of the ITCP, complete and submit the “Lane Closure Notification/Request Form or approved equal” to the Engineer for approval prior to the actual closure date. Submit the lane closure request 7 calendar days in advance of the lane closure for approval. This includes all shifts/shoulder/lane/ramp closures as stated per the proposal or any new lane closure requests submitted by the Contractor. The Engineer will have 4 calendar days to review the lane closure request for approval or provide comments for revisions required to obtain approval. Do not implement a lane closure prior to approval by the Engineer. In addition, notify the Engineer when the lane closure is removed or cancelled. See Lane Closure Notification/Request Form contained in the proposal.

7. Protect the work area at the end of each day. Close all open access points on the project to traffic with Type III barricades or other devices approved by the Engineer.

8. The Engineer will be responsible for notifying emergency services, transit agencies, law enforcement and schools prior to any lane closures, detours or major traffic shifts. In addition, the Contractor will be responsible for working with and complying with any coordination that is necessary with the Department and emergency services, transit agencies, law enforcement and schools. All costs associated with these coordination efforts will be considered included in the pay item “Minor Traf Devices”.

9. Obtain all necessary permits from local governments within areas of local jurisdiction, including noise/dust ordinance waivers when required, prior to placing construction signing on local roads.

A. The Department will reimburse permit costs in accordance with subsection 107.02.A of the Standard Specification for Construction. Adhere to all requirements made by local maintaining agencies regarding placement of traffic control devices prior to closing lanes on roadways not under MDOT jurisdiction.

10. Remove all temporary traffic control devices from MDOT right-of-way during any shut down periods unless needed for directly maintaining or channelizing traffic. No additional payment will be made for removal and/or redeployment of these devices except for in the case of an approved extension of time.

11. Cover or remove construction signing that refers to work zone speed when work at a location is planned to be inactive for a period greater than 2 days, unless otherwise specified on the plans or as directed by the Engineer.

12. Once work is initiated that includes any lane restrictions, that work must be continued daily until completed. A lack of work activity for more than 3 days will require the removal of lane closures at no expense to the Department.

f. Traffic Regulator Control.

1. Maintain two-way traffic at all times on M-19 (Gratiot Ave, Main St, and Memphis Ridge Rd.) using traffic regulator control. A traffic regulator sequence is allowed to cover a maximum closure length of 1 mile. Place the arrow panel, signs and channelizing taper for the traffic regulator operation at locations approved by the Engineer for adequate visibility by oncoming traffic.

2. Do not utilize more than 1 traffic regulator operation(s) at one time on M-19 (Gratiot Ave, Main St, and Memphis Ridge Rd.)

3. Crossroads must remain open to traffic at all times. Use intermediate traffic regulators at each intersection approach and commercial driveways within the closure limits, as directed by the Engineer. Use traffic regulator control as directed by the Engineer for cross street traffic while paving through intersections.

4. Follow the Michigan Traffic Regulator’s Instruction Manual for operations at signalized intersections. Contact the MDOT region electrician or applicable maintaining agency prior to work on traffic signals. Only the MDOT region electrician or applicable maintaining agency may make changes to the traffic signal controllers.

g. Hot Mix Asphalt (HMA) Work.

1. Resurface all HMA milled areas the same day as the HMA cold milling operation.

2. Traffic is allowed on the milled surface, for 24 hours unless otherwise directed by the Engineer.

3. Provide transverse and longitudinal HMA tapers at all grade changes greater than 3 inches caused by cold milling and overlay. Place W8-1 (“BUMP”) signs in advance of transverse HMA tapers. Place W8-11 (“UNEVEN LANES”) signs in advance of longitudinal HMA tapers. Place W8-9 (“LOW SHOULDER”) signs in advance of and every mile within the shoulder drop off.

h. Traffic Control Devices. Ensure all traffic control devices are in accordance with the MMUTCD and must meet the “acceptable” criteria as defined in the ATSSA publication entitled “Quality Guidelines for Temporary Traffic Control Devices and Features” at the time of initial deployment and after each major stage change.

1. During non-working periods, place applicable advance signs and channelizing devices at specific locations, as directed by the Engineer, at no additional cost to the Department.

2. Notify the Engineer 24 hours in advance of when traffic control devices are being delivered to the project site, to allow for initial inspection of devices to take place.

3. Remove from the project site all traffic control devices (including detour signing) no longer needed for a particular operation and equipment for construction within 14 calendar days of reopening the shoulder/lane/roadway.

4. Channelizing Devices.

A. Ensure all devices have sufficient ballast to prevent moving or tipping. If moving or tipping occurs, place additional ballast, as directed by the Engineer, at no additional cost to the Department. No more than two ballasts are allowed on each channelizing device.

B. Do not use caution tape on this project.

C. Space channelizing devices at 25’ for tapers and 50’ for tangents or tighter as directed by the Engineer.

5. Temporary Signs.

A. Additional W20-1 (ROAD WORK AHEAD) signs are included in the quantities to be placed on all intersecting or adjacent roads where construction activities may be encountered.

B. Fabricate, install, and remove temporary sign overlays on existing signs with the pay item for Sign, Type B, Temp, Prismatic, Furn. Attach the overlay in accordance with subsection 812.03.D.2 of the Standard Specifications for Construction.

6. Portable Changeable Message Signs (PCMS’s). Use PCMS’s to warn traffic of upcoming and changing traffic control during the life of the project. Obtain approval from the Engineer for all sign locations.

A. Install PCMS’s and make them operational a minimum of 7 calendar days prior to the start of work, unless otherwise directed by the Engineer. Messages displayed on the PCMS’s must conform to MDOT’s policy on PCMS’s. Notify the Engineer if displaying a different message than those listed below for the project.

B. Do not leave PCMS’s with a blank screen within the clear zone of any roadway at any time. Remove the PCMS or display flashing dots in each corner of the screen when there is no message to display. Update the PCMS messages at the end of each work period to reflect current traffic lane restrictions.

C. Display the following two messages greater than 6 days prior to work per applicable locations or as directed by the Engineer.BEGINS

ON

XX/XX

M-19

ROAD

WORK

D. Display the following two messages during the work or when traffic regulator is being utilized or as directed by the Engineer.

STOPPED

TRAFFIC

AHEAD

BE

PREPARED

TO STOP

M-19

ROAD

WORK

_PM

TO

_AM

h. Measurement and Payment. Payment will be in accordance with the standard specifications unless otherwise specified. No additional payment will be made for the following activities:

1. Transporting traffic control items from site to site.

2. Providing sufficient vehicles and staff to make changes as-needed on site during work.

3. Providing sufficient vehicles and staff to remove closures from the roadway.

4. Providing additional traffic control devices required to expedite the construction for the convenience of the Contractor.

V3.3