Munitions Containers, Handling, and Support Equipment Federal contract opportunity
Solicitation number
FA2487-21-R-MMHE
Issued by
Department of the Air Force Materiel Command Test Center

About this file

This memorandum and sources sought notice outline requirements for an indefinite delivery indefinite quantity contract to manufacture munitions material handling equipment. The Air Force Life Cycle Management Center seeks capabilities statements from manufacturers within 750 miles of Eglin Air Force Base in Florida that can produce prototypes and low-rate production runs from shop drawings or Level III drawings. Responses are due by September 11, 2020 and the contract period of performance will be five years. Manufacturers must demonstrate quality management certification, configuration management compliance, shipping capabilities, and the ability to perform fabrication, assembly, welding, cleaning, painting and other processes on mechanical and electronic items.

View the file

Other files for this federal contract opportunity

Other files attached to Munitions Containers, Handling, and Support Equipment, newest first.
File Type Posted
MMHE IDIQ SOO.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE LIFE CYCLE MANAGEMENT CENTER

EGLIN AIR FORCE BASE FLORIDA

10 August 2020

MEMORANDUM FOR RECORD

FROM: AFLCMC/EBDS

SUBJECT: FY21 MMHE IDIQ Contract Requirements

1. Item Description: MMHE is requesting an IDIQ contract that allows civilian manufacturers the ability to submit correspondence to Request for Information (RFI), Request for Quote (RFQ) and Request for Proposal (RFP) presented from MMHE. On average, MMHE can produce 15 prototypes and some low-rate production assets per year. MMHE RFPs are mostly (85-90%) for a single prototype or a low-rate production run ranging from small hand tools to large pieces of equipment, may be some electronic work. Drawing packages may be shop drawings or Level III drawing packages with a “Distribution C” statement of release. CAD models will be available upon request.

2. Threshold Requirements:

a. Within 750 mile radius of Eglin AFB, FL.:

i. Required for possible Engineer/Project Manager (PM) prototype review/testing

ii. Enables Engineer/PMs to access the machine shop in a reasonable time and with reasonable cost to influence design as necessary.

b. Company must be able to

i. Disassemble

ii. Assemble

iii. fabricate piece parts

iv. weld

v. sand blast

vi. clean

vii. plate

viii. perform surface preparation

ix. paint

x. non-destructive evaluation

xi. quality assurance reports

xii. rework

xiii. store

xiv. Provide test support and handling equipment or associated hardware

c. ISO 9000 Certified

d. Meet Configuration Management Standard EAI649C, dated 7 Feb. 2019

e. Maintain system or controlling government drawings and government furnished equipment (GFE).

f. Provide proof of Quality Assurance processes/practices upon request:

i. Incorporate cost-effective methods and practices

ii. Monitor and control critical processes and product variation

iii. Establish mechanisms for feedback of field product performance

iv. Implement an effective failure modes analysis and corrective action system

v. Promote continuous process improvement

vi. Inspect and document completed deliverables

vii. Verify calibration of precision measurement equipment as required

viii. Records to show objective evidence of inspections and control processes at minimum Certificate of conformance, Certificate of Material Conformance, and Quality Inspection Report (typical manufacturer report template is acceptable).

ix. Welders are certified and procedures written to meet contract requirements

x. Control of purchases orders.

g. Provide shipping to stateside and overseas locations

h. Provide packaging for shipment IAW MIL-STD-2073-1E_Change 4

3. Objective Requirements:

a. No limit on Machine shops within range

b. Within 750 mile radius of Eglin AFB, FL.:

i. Required for possible Engineer/Project Manager (PM) prototype review/testing

ii. Enables Engineer/PMs to access the machine shop in a reasonable time and with reasonable cost to influence design as necessary.

image1.png

File details come from the government source that posted it. Updated .