MIV RCAG Floor Replacement SOW.pdf

PDF 2 MB Posted

Attached to
Floor Replacement & Painting Walls Federal contract opportunity
Solicitation number
2301613
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

View the file

Other files for this federal contract opportunity

Other files attached to Floor Replacement & Painting Walls, newest first.
File Type Posted
Photo Log 11-15-22- Millville (MIV) RCAG Facility Rehabilitation Project.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wilmington System Support Center Abatement of Vinyl Asbestos Tile, Installation of Resilient Floor Tile and Painting of Interior

Walls at the 40’ x 18’ Millville Remote Communication Air to Ground

(RCAG), Millville, NJ

WORK SUMMARY

The work shall include, but is not limited to the following:

Phase I (EQUIPMENT ROOM FLOOR TILE ASBESTOS ABATEMENT PLANNING/DESIGN):

1. Perform Asbestos Abatement Planning and Design (Sampling performed by FAA – results attached) for the removal and disposal of the asbestos containing floor tiles and mastic in the RCAG equipment room.

2. Perform Background Air Sampling as required

3. Provide abatement start/facility shutdown date to FAA a minimum of 45 days in advance.

Phase II shall not start until:

- The asbestos abatement subcontractor submits all documents required by the specifications and New Jersey Department of Health.

- Phase I abatement work plan/design is submitted to the FAA for review.

- Facility shutdown/abatement start date is approved by the FAA.

NOTE: Air sampling procedures (including clearance) shall not be performed by any asbestos contractor involved with the asbestos project, except as follows: The non-abatement asbestos contractor firm that performed the building/structure asbestos survey, or is acting as the project monitor or project designer on the asbestos project, may perform project air sampling and analysis, provided that the individual or firm performing the building/structure asbestos survey or acting as project monitor or project designer, will not perform any asbestos abatement work on the project and has not retained or been retained by the asbestos abatement contractor for work on the asbestos project.

Phase II (EQUIPMENT ROOM ASBESTOS ABATEMENT):

1. Perform Phase IIA, Asbestos Notification/Abatement for the removal of floor tile, mastic and base cove in accordance with New Jersey Department of Health regulations. NOTE: All abatement work must be performed by a State of New Jersey licensed asbestos abatement contractor.

2. Perform Phase IIB, Work Area Preparation for the removal of floor tile, mastic and base cove. NOTE:

Contractor to clean/wipe down, remove and store all items/objects that cannot remain in the work area. All equipment remaining in the work area must be wrapped in poly. Negative air/HEPA filtered exhaust system must be set up in the work area.

3. Perform Phase IIC, Final Cleaning and Clearance Procedures.

NOTE: Air sampling/clearance sampling must be performed after all ACM has been removed by the abatement contractor. Clearance sub-contractor shall perform a “rush” turnaround with the TEM test for the final clearance samples to allow the communication equipment to be returned to service as soon as possible.

4. Perform Phase IID, Final Waste Removal and Disposal from the Site in accordance with New Jersey regulations, US EPA and New Jersey Department of Environmental Protection regulations.

Phase III (LEAD ABATEMENT/PAINTING/FLOOR TILE INSTALLATION):

1. STORAGE ROOM - LEAD BASED PAINT CONDUIT REPLACEMENT: Coordinate the shutdown of the lights and ADS-B equipment located in the storage room. Open each circuit breaker and lockout power for the circuits (2 total) running through painted conduits fastened to the walls and ceiling in the storage room. Pull cables back to the LBs and cap end of each cable. Remove approximately 25 LF of in-use painted conduits, 10 LF of unused painted conduit, 3 junction boxes and one light switch with box with existing power circuits. Dispose of the painted conduit and boxes as hazardous waste (painted LB with lighting circuit to remain). Install approximately 25 LF of new EMT conduit, junction boxes and wall switch (match existing sizes) for the lighting circuts. Reinstall existing wiring and re-energize power circuits. (NOTE: Conduit paint has been tested for lead and found to contain lead – results are attached). Contractor to wear appropriate PPE when removing painted conduit (do not cut conduit), install plastic on the floor beneath the work area, wrap conduit in plastic and properly dispose of all loose paint chips and wrapped conduit as hazardous waste. A copy of the manifests must be provide to the FAA.)

2. PAINT EQUIPMENT AND STORAGE ROOMS DOORS, WALLS AND CEILING: Remove and store all items in the storage room. Protect all operational equipment. Paint interior side of doors, interior walls and ceiling in the equipment room and storage room. New paint color to match existing color. (NOTE:

Interior wall paint has been tested for lead and found to contain low amount of lead – results are attached). Contractor shall not sand or take any other action that would create paint dust). Protect existing equipment racks from paint overspray/drops.

3. INSTALL EQUIPMENT ROOM AND STORAGE ROOM FLOOR TILE: Install 12” x 12” x 1/8” commercial grade asbestos free VCT floor tile in the 16’ x 28’ equipment room and 16’ x 10’ storage room and polish floor tiles. All mastic/adhesive materials used in the new installation must be asbestos free.

Move all items/objects back into the equipment and storage rooms from temporary storage.

SITE LOCATION ADDRESS: 30 Bogden Blvd., Millville, NJ

APPROXIMATE Equipment Room Dimensions: 16’x 28’ APPROXIMATE Storage Room Dimensions: 16’ x 10’

NOTES:

1. CONTRACTOR IS RESPONSIBLE FOR MEASURING EXISTING SHELTER/ROOM DIMENSIONS. NOT ALL EQUIPMENT AND

OBJECTS ARE SHOWN.

2. CONTRACTOR SHALL REMOVE AND STORE ALL OBJECTS (DESKS, STORAGE RACKS, BOXES, ETC) THAT ARE MOVABLE.

ALL REMAINING EQUIPMENT MUST BE WRAPPED IN POLY.

3. CONTRACTOR SHALL REMOVE EXISTING FLOOR TILE AND MASTIC IN THE EQUIPMENT ROOM. ALL MATERIAL IS ASSUMED TO BE ASBESTOS. THE FLOOR TILES BENEATH THE FLOOR MOUNTED EQUIPMENT RACKS WILL REMAIN IN

PLACE AND SHALL BE COVERED BY NEW TILE

4. ALL COMMUNICATION EQUIPMENT MUST BE SHUTDOWN FOR THE DURATION OF THE ASBESTOS ABATEMENT PORTION OF THE PROJECT. THE REQUIRED SHUTDOWN DATES (START AND END) FOR EACH SITE SHALL BE

COORDINATED WITH THE FAA A MINIMUM OF 45 DAYS IN ADVANCE.

5. CONTRACTOR SHALL MOVE ALL OBJECTS REMOVED AND STORED BACK INTO THE BUILDING AFTER THE NEW FLOOR

TILES ARE INSTALLED AND THE PAINTING IS COMPLETE.

DESCRIPTION/SPECIFICATION

SECTION INDEX

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS

Section Title

1-1 Summary of Work 1-2 Construction Limits and Use of Facilities 1-3 Temporary Facilities 1-4 Contract Close-out 1-5 Project Record Documents 1-6 Completion Certificate

DIVISION 2 – SITE WORK

2-1 Demolition

DIVISION 9 - FINISHES

9-1 Flooring 9-2 Painting

DIVISION 16 – ELECTRICAL

16-1 Electrical Material and Installation 16-2 Applicable Documents 16-3 Grounding 16-4 Wire Methods 16-5 Conductors 16-6 Quality Assurance Provisions

APPENDIX

Site Location Map Site Photos

DIVISION 1 - GENERAL REQUIREMENTS

1-1 SUMMARY OF WORK

1-1.1 General

These specifications, together with the referenced specifications, standards and drawings specified in the Contract Documents, cover the requirements of the Federal Aviation Administration, hereinafter referred to as the Government or FAA, for all work associated with the replacement of the floor tile and interior painting at the Millville RCAG, NJ.

1-1.2 Intent of Specifications

This specification identifies all labor, materials and equipment necessary to perform the required work. All material not specifically indicated as furnished by the Government in the List of Government Furnished Materials (GFM) shall be furnished by the Contractor.

1-1.3 Construction Per Drawings

The construction of this facility shall be in accordance with the lines and grade shown on the contract drawings. The Contractor shall verify all distance by measuring in the field.

1-1.4 Contract Duration

The contractor shall have sixty-six (66) calendar days from the notice to proceed (NTP) to complete the project (Phase 1 – 45 days and Phase II and III – 21 days).

1-1.5 Work Hours

Normal work hours are from 7 am to 3:30 pm, Monday through Friday. All work outside of the normal time frame shall be coordinated with the RE a minimum of 48 hours prior.

1-1.6 Health and Safety Plan

The contractor shall submit a health and safety plan for the project prior to the issuance of the notice to proceed.

The plan must contain a specific section to address COVID-19, asbestos abatement and lead abatement

1-1.6.1 Asbestos Free Construction

The contractor shall submit a letter at the end of the project certifying that all materials installed during construction are “asbestos free” in accordance with current OSHA and NJ definitions.

1-1.7 Work Schedule

Contractor shall submit a work schedule prior to the FAA issuing notice to proceed. The schedule shall include all major milestones and cut-overs. NOTE: The navigational and communication equipment in each VOR must be shutdown for the duration of the abatement. The contractor must coordinate the abatement dates with the FAA a minimum of 45 days in advance

1-2 CONSTRUCTION LIMITS AND USE OF FACILITIES

1-2.1 Construction Limits

The Contractor shall confine operations, activities, storage of materials and employee parking within the areas designated by the RE. Any additional space the Contractor deems necessary shall be obtained off the site, at no additional cost to the Government. At no time will the Contractor disturb any of the vegetation at the site unless directed by the RE.

1-2.2 Damage to Site

Damage to existing pavement, landscaping, structures or underground facilities caused by the contractor's activities shall be repaired. All costs of such repairs shall be paid for by the Contractor.

After notice to proceed and prior to commencement of construction, the Contractor and Resident Engineer (RE) shall conduct joint inspections of the existing area. Existing damage or defects shall be noted and will be used as the basis for determination of damages caused by the Contractor's operations.

1-2.3 Contractors' Use of Premises

The Contractor shall have use of the premises within the construction area limits for the execution of his work and shall assume full responsibility for the protection and safekeeping of products and materials stored on the site. This shall include all Government Furnished Equipment (GFE) as provided in this contract.

The Contractor and subcontractors shall maintain the job site in a neat and orderly condition. This includes the daily removal of rubbish, waste, tools, equipment, and materials not required for the work in progress.

1-2.4 Access to Site

The contractor shall be escorted to the site and remain with the FAA each day when working at the site.

1-2.5 Vehicle Marking

All contractor vehicles shall have the company name and/or logo permanently fixed to the vehicle.

1-3 TEMPORARY FACILITIES

1-3.1 General

The Contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work.

1-3.2 Temporary Toilets and Sanitation

The Contractor shall provide ample and suitable on-site sanitary conveniences with proper enclosures for the use of all workers. Such conveniences shall be kept clean, be properly ventilated and shall be installed and maintained in conformity with requirements of all laws and ordinances governing such installation. Locations shall be subject to the RE's approval. After completion of the work, such conveniences shall be removed from the site.

1-3.3 Temporary Electric Lighting and Power

The Contractor shall provide and maintain a temporary lighting and power system for construction and inspection purposes. The Contractor shall make all necessary arrangements for temporary electrical services and shall provide and pay for all temporary work.

1-3.4 Temporary Water

The site does not have a water source available for contractor use. The contractor must make the appropriate arrangements for transporting water to the site.

1-4 CONTRACT CLOSEOUT

General

The Contractor shall require each subcontractor engaged upon the work to bear full responsibility for cleaning up during and immediately upon completion of his work. All rubbish, waste, tools, equipment and other apparatus caused by or used in the execution of the work shall be removed. This shall in no way be construed to relieve the Contractor of his primary responsibility for maintaining the site clean and free of debris, and leaving all work in a clean and proper condition acceptable to the RE.

1-4.1 Rubbish Removal

Immediately after unpacking, all packing material, case lumber, wrappings, or other rubbish, flammable or otherwise, shall be collected and removed from the site and disposed of in accordance with local regulations on a daily basis.

1-4.2 Overall Cleaning

Immediately before the final inspection, the surrounding areas shall be thoroughly cleaned by the contractor, including but not limited to the following:

a) For all construction facilities, debris and rubbish shall be removed from the site.

b) All tools, scaffolding, temporary utility connections or buildings, belonging to the contractor or used under his direction shall be removed from the site.

1-5 PROJECT RECORD DOCUMENTS

1-5.1 Maintenance of Documents

The following documents shall be maintained at the project site:

a) Contract drawings

b) Contract specifications

c) Reviewed shop drawings

d) Change orders

e) Field test reports

f) Project correspondence

g) Current Work Schedule

1-5.2 Submittals

General -- All materials that are to be installed by the Contractor, must be to the RE for approval, prior installation. NOTE: All chemical product submittals must include the Safety Data Sheet (formally known as Material Safety Data Sheet)

1-5.2.1 Procedure – Four (4) complete sets of all shop drawings and/or product data shall be submitted and two sets will be marked and returned to the contractor.

Each shop drawing, submitted for approval, shall have in the lower right hand corner, just above the title block, a 4 inch open space in which the RE can indicate action taken. All submittals shall be accompanied by transmittal letters identifying the contents of the submittal. Transmittal letters shall consist of one original and one copy. A schedule of submittals shall be made 10 days after contract award, showing the dates when all shop drawings and material approvals will be submitted for the entire project. This schedule shall be organized by specification division and shall indicate the referenced division section along with the proposed submittal dates. The FAA review will take (10 calendar days maximum) with possible contractor resubmittal (10 calendar days maximum) and FAA resubmittal review (10 calendar days maximum). Work requiring approval shall not be initiated, fabricated or delivered to the site prior to approval of submittal. Submittals shall be checked by the contractor and coordinated with the work of other trades involved before they are complete, detailed, and assembled in sets. Lack of completeness or inadequate description will be justification for disapproval. Shop drawings shall bear the following information:

Number of contract drawings and latest revision;

Specification page;

Name of project;

Name of subcontractor or supplier;

Clearly identified contents and location of work.

1-5.2.3 By submitting shop drawings, the contractor thereby represents that he has verified the following:

Space limitations; Coordination with equipment furnished under other specifications;

Catalog numbers and similar data; Compliance with requirements of the work and of the contract documents.

1-5.2.4 Shop drawing approval - The checking, marking or approval of the shop drawings and/or product data by the Resident Engineer shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory.

Approval will not relieve the contractor of responsibility for any error which may exist. The contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work.

1-5.2.4.1 Approved as submitted - If "approved as submitted" is marked by the Resident Engineer, each copy of the shop drawings or product data will be identified as having received such approval by being stamped and dated. After submittal has been approved, no substitution will be permitted without written approval by the Resident Engineer.

1-5.2.4.2 Approved as noted - If "approved as noted" is marked by the Resident Engineer, the shop drawings or product data is satisfactory contingent upon contractor acceptance of corrections, notations, or both and, if accepted, does not require resubmittal.

1-5.2.4.3 Approved as noted - resubmission required - If "approved as noted-resubmission required" is marked by the Resident Engineer, the shop drawings or product data may be satisfactory contingent upon contractor resubmission of corrections, notations, or both. The effect of the notations or corrections is such that resubmission is required in order to evaluate the corrected data or drawings. Contractor shall resubmit the corrected material, in the same quantity as specified for the original submittal.

1-5.2.4.4 Not approved - If "not approved" is marked by the Resident Engineer, the shop drawing or submittal data does not meet job requirements and the contractor must resubmit. If shop drawings or submittal data are disapproved, the contractor shall resubmit the corrected material, in the same quantity as specified for the original submittal.

1-5.2.5 Samples - The Government reserves the right to request samples of any products or materials proposed for use on this project. Specific samples currently listed under various sections of this specification will be required.

1-6 COMPLETION CERTIFICATE

When the Contractor considers the work is complete, he shall submit written certification that contract documents have been reviewed; work has been inspected for compliance with contract requirements;

equipment and systems have been tested in the presence of the RE and are operational.

1-6.1 Punch List

The Contracting Officer will furnish the Contractor with a list of discrepancies in the work, material and equipment noted during the final inspection.

DIVISION 2 – SITE WORK

2-1 DEMOLITION

The contractor shall remove all equipment room asbestos containing flooring (tile and mastic) material. All waste shall be disposed of in a legal manner. The shelter has been inspected for asbestos and the 9” x 9” floor tiles and mastic contain asbestos (See testing report).

All existing equipment and battery racks that must remain in-place must be wiped and wrapped in poly prior to the abatement. The contractor shall cut tiles around the equipment that cannot be moved.

All other items/objects (i.e. desks, work benches, cabinets, etc.) shall be wiped down and removed by the contractor. All removed items/objects shall be properly stored and protected in a storage container. The items/objects shall be moved back into the building to their original location after the new tile has been installed and painting has been completed.

2-1.1 Asbestos Abatement

Asbestos abatement to include all applicable notifications to federal, state, and local governmental authorities. This work shall comply with the U.S. Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926.1101, Asbestos Standard for the Construction Industry AND New Jersey State Department of Health regulations

The contractor shall submit abatement plan to FAA prior to scheduling the abatement start dates.

2-1.2 Asbestos Documentation Required.

The contractor shall furnish documentation that the firm and its employees are familiar with the following regulations of the US. Department of Labor, Occupational Safety and Health Administration (OSHA), the U.S. Environmental Protection Agency (US EPA) and New Jersey State Department of Health, relating to the application, removal, disposal and treatment of asbestos:

a. U.S. Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926.1101, Asbestos Standard for the Construction Industry.

b. U.S. Environmental Protection Agency 40 CFR 61, National Emissions Standards for Hazardous Air Pollutants, Subpart M, Asbestos.

c. New Jersey State Department of Health

The contractor shall furnish documentation of worker training and previous abatement work.

The contractor shall furnish proof that employees have had instruction on the dangers of asbestos exposure and decontamination procedures.

The contractor shall furnish asbestos license

The contractor shall furnish copies of all letters of notification of asbestos abatement work to all applicable governmental authorities.

The contractor shall furnish copies of all material, clearance and air sampling results.

Upon disposal of asbestos containing waste, the contractor shall furnish copies of completed waste disposal manifests to the FAA.

DIVISION 9 – FINISHES

9-1 FLOORING

This section covers furnishing and installation of resilient flooring as specified herein and as shown on the project drawings.

9-1.1 Materials

Adhesive: Adhesive for vinyl tile shall conform to manufacturers installation specifications.

Adhesive for the base shall be a water resistant product recommended by the base manufacturer.

Vinyl Tiles: Vinyl tile shall conform to ASTM F 1066, Class 2, 12 inches square by 1/8 inch thick.

Color shall be Charcoal. Approved source: Armstrong, Standard Excelon Imperial Texture.

9-1.2 Installation

Adhesive: Adhesive application and time allowed for setting shall be in accordance with the tile manufacturer's recommendations.

Tile: Tile shall be laid in accordance with the pattern layout as approved by the RE. Undersurface of the tile shall be bonded to the floor slab, with each tile in tight contact with surrounding tiles and with joints aligned.

Surface Preparation: Surfaces to receive flooring shall be cleaned free of dust, foreign matters and materials not compatible with adhesive. Surfaces shall be dry and in suitable condition to receive the flooring. Surface shall be prepared in accordance with the floor manufacturer installation specifications.

Cleaning: Sweep, dust mop or vacuum the finished floor thoroughly to remove all loose dust, dirt, grit and debris. Remove any dried adhesive residue with a clean, white cloth dampened with mineral spirits, carefully following the warnings on the container. Damp mop the floor with a properly diluted neutral (pH 6 to 8) detergent solution such as Armstrong R S-485 Commercial Floor Cleaner.

Protection: Apply a minimum of 3 coats of a high-quality commercial floor polish (such as Armstrong R S-480 Commercial Floor Polish) to protect the floor.

Maintenance Stock: Furnish a minimum of twenty (20) extra vinyl floor tiles for each color or style of tile used in the project.

9-2 PAINTING

9-2.1 General

9-2.1.1 Work Included

Furnish materials and labor necessary to apply paint to specific surfaces and areas, which require field painting.

These areas include the equipment room and storage room interior masonry walls, ceiling and interior face of doors.

9-2.2 Materials

9-2.2.1 General

To the maximum extent practicable, use the materials of one manufacturer throughout the project.

9-2.3 Installation

9-2.3.1 Preparation

a) Surfaces shall be inspected in regard to their suitability to receive a finish. In the event that imperfections due to materials or workmanship appear on surfaces, appropriate corrections shall be made. Damage to painted or decorated finish due to carelessness or negligence of other crafts shall be corrected.

b) Hardware, hardware accessories, plates, lighting fixtures and similar items placed prior to painting shall be removed or protected. Remove protection upon completion.

c) Surfaces to be painted shall be cleaned as required to remove dust and dirt. Sand as necessary to properly prepare surfaces to receive paint. NOTE: Do to trace amounts of lead in the paint, only wet sanding methods are approved. Workers must wear the appropriate PPE and all cleanup will be accomplished with a HEPA vacuum.

d) All metal surfaces shall be washed with benzine or mineral spirits to remove any dirt, oil or grease before applying paint. Where rust or scale is present, wire brush or sandpaper clean before painting.

f) Masonry and concrete surfaces to be painted shall be prepared by removing dirt, dust, oil and grease stains and efflorescence. The method of surface preparation must be per the manufacturer’s specifications and approved by the RE. Damaged concrete block mortar joints shall be re-pointed

9-2.3.2 Application

a) The work of this section shall be coordinated with the work of other trades.

b) Miscellaneous existing materials which have been prime coated shall be touched-up as required where the shop coat has been damaged by welding or abrasion during the handling and erection operations. Also rivets, bolts and welds which are unpainted after assembly and erection shall be primed and painted.

c) Paint shall be applied by a brush, roller or spray in accordance with the manufacturer's directions.

Use the type of brushes best suited for the type of material being applied. For covers on rollers use carpet with velvet back and of high pile sheep's wool or use short hair covers, as best suited for material and texture specified. Apply spray paint uniformly with suitable equipment. Paint shall be applied to a minimum thickness of five (5) mils.

d) Only skilled painters shall be employed. Materials shall be spread evenly and smoothly without runs, sags, or other defects.

e) Exterior paint shall not be applied in damp, rainy weather or until the surface has dried thoroughly from the effects of such weather. The temperature of the surface to be painted and of the surrounding air temperature shall be maintained between 45 degrees F and 95 degrees F during the application and drying period. Surfaces to be painted shall be clean, dry, smooth and adequately protected from dampness. Each coat of paint shall be applied smoothly, worked out evenly and allowed to dry completely before the subsequent coat is applied. Finished work shall be uniform and of the approved color. Paint shall completely cover, be smooth and free from runs, sags, clogging or excessive flooding. Make edge of paint adjoining other materials or colors sharp and clean without overlap. Where high gloss enamel is used, lightly sand undercoat to obtain a smooth finish coat. Painting shall be completed according to the manufacturer's written instructions.

f) Final coats shall not be applied until after other trades, whose operations would be detrimental to finish painting, have finished their work in the areas to be painted and the areas have been approved for painting by the RE.

9-2.3.3 Protection

a) Soiled cleaning rags and waste shall be disposed of daily at the close of each day's work or stored in metal containers with tight fitting covers. Buckets of sand shall be provided at all times for use in the event of fire. "No Smoking" signs shall be posted as required or directed by the RE.

b) The work of other trades shall be protected against damage or injury by use of suitable covering during the progress of the painting and finishing work. Repair any damage done.

c) All floor and wall mounted equipment shall be protected/covered with suitable coverings to prevent paint overspray/drops from damaging the equipment.

9-2.3.4 Schedule of Painting

9-2.3.4.1 Primed Surfaces

All surfaces to receive 1st primer coat

9-2.3.4.2.2 Miscellaneous

Hollow metal doors, frames and steel ductwork shall be painted as follows:

1st Galvanized metal primer 2nd Exterior Metal Paint (Match Existing) 3rd Exterior Metal Paint (Match Existing)

9-2.3.4.3 Interior Surfaces

9-2.3.4.3.1 Concrete Masonry Unit Walls and Bond Beams

1st Concrete block primer 2nd Acrylic Latex, eggshell (Match Existing) 3nd Acrylic Latex, eggshell (Match Existing)

9-2.4 Quality Assurance

9-2.4.1 Environmental Requirements

a) Paint shall not be applied to non-protected surfaces in wet weather or to surfaces on which ice, frost, water, or dampness is visible.

b) Interior paint shall not be applied when the temperature is lower than 60 degrees F or expected to fall below this temperature.

c) Steel which is at a temperature which can cause blistering, porosity, or otherwise be detrimental to the life of the paint shall not be painted. When paint is applied in hot weather or thinned in cold weather, ensure that the specified thickness of paint coating is obtained.

d) Interior paint shall not be applied when satisfactory results cannot be obtained due to high humidity and excessive temperature.

9-2.4.2 Submittals

Submit in accordance with Division 1 the manufacturer's color chips and charts for use in preparation of color schedule. Manufacturer's specifications for application and a chart or drawing indicating where each product will be applied.

9-2.4.3 Delivery and Storage

9-2.4.3.1 Delivery

Products shall be delivered to the job site in their original unopened containers clearly labeled with the manufacturer's name and brand designation, referenced specification number, and type as applicable.

9-2.4.3.2 Storage

Products shall be stored in an approved ventilated dry area, protected from contact with soil and from exposure to the elements. Keep products dry at all times.

9-2.4.3.3 Handling

Handle packaging and containers in a manner that will prevent damage to contents.

9-2.4.4 Identification of Materials

Containers shall have labels with the following information:

Manufacturer's name Type of paint Manufacturer's stock number Color Instructions for reducing, where applicable.

DIVISION 16 - ELECTRICAL

16-1 ELECTRICAL MATERIAL AND INSTALLATION

16-1.1 Work Included

Installation and furnishing of all materials for interior and exterior electrical work.

16-1.2 Installation - General

The rules, regulations and reference specifications enumerated herein shall be considered as minimum requirements and shall not relieve the Contractor from furnishing and installing higher grades of materials and workmanship than are specified herein or when so required by the Contract Drawings.

This specification shall govern when conflicts occur between reference documents and this specification.

16-1.3 Workmanship

All materials and equipment shall be installed in accordance with the Contract Drawings and the recommendations of the manufacturer as approved by the Resident Engineer (RE). The installation shall be accomplished by skilled workmen regularly engaged in this type of work. Where required by local regulations, the workmen shall be properly licensed.

16-1.4 Materials

The Contractor shall furnish all materials required in accordance with contract drawings and specifications. Materials must comply with all contract requirements. Materials to be furnished by the Contractor shall be new, the standard products of the Manufacturer regularly engaged in the production of such materials, and of the specification requirements. Whenever standards have been established by Underwriter's Laboratories, Inc., the materials shall bear the UL label.

16-1.5 Repair of Existing Work

Electrical work shall be carefully laid out in advance. Where cutting, channeling, chasing, or drilling of floors, wall partitions, ceilings, or other surface is necessary for the proper installation, support, or anchorage of the conduit, raceways, or other electrical work, it shall be carefully done. Damage to the building, piping, or equipment shall be repaired by skilled mechanics of the trades involved at no additional cost to the government.

16-2 APPLICABLE DOCUMENTS

The current issues of the following documents in effect on the date of invitation for bids form a part of this specification.

16-2.1 Federal Specifications

J-C-30 Cable and Wire, Electrical (Power, Fixed Installation) W-C-582 Conduit, Raceway, Metal, and Fittings; Surface W-C-586 Conduit Outlet Boxes, Bodies, and Entrance Caps, Electrical: Cast Metal

- For Shore Use W-J-800 Junction Box; Extension, Junction Box: Cover, Junction Box (Steel, Cadmium or Zinc - Coated) W-S-610 Splice, Conductor QQ-W-343 Wire Electrical Uninsulated WW-C-566 Conduit, Metal, Flexible

WW-C-581 Conduit, Metal, Rigid; and Coupling, Elbow, and Nipple, Electrical Conduit: Zinc Coated

16-2.2 Military Documents

MIL-P-15147 Primer and Enamel, Coal Tar MIL-R-21931 Resin, Epoxy

16-2.3 FAA Standards

FAA-STD-019f Lightning Protection, Grounding, Bonding and Shielding Requirements for

Facilities..

FAA-C-1217h Interior, Electrical

16-2.4 National Fire Protection Association (NFPA) Publications

70 National Electrical Code 78 Lightning Protection Code

16-2.5 National Electrical Manufacturers Association (NEMA) Standards

WD1 General Purpose Wiring Devices

16-2.6 Underwriters Laboratories, Inc. (UL) Standards

UL 50 Cabinets and Boxes UL 96A Master Labeled Lightning Protection UL 98 Switch, Box, Surface Mounted UL 870 Wireways, Auxiliary Gutters and Associated Fittings

16-3 GROUNDING

The grounding system for the facility shall be as indicated on the Contract Drawings and as specified herein. The National Electrical Code and FAA Std 19f, except where otherwise indicated shall govern, but in no case shall the code be violated.

16-3.3 Equipment Grounding Conductor

All electrical equipment shall be grounded by means of a separate green insulated ground wire routed within the raceway. The ground conductor shall be connected to the power panel or lighting panel equipment ground bus. Equipment or device mounting shall be bonded to the metal structure by means of metal to metal contact. Conductor shall be sized to match the ungrounded (power) conductors.

16-4 WIRE METHODS

Unless otherwise indicated, wiring shall consist of insulated copper conductors installed in heavy-wall rigid galvanized steel.

16-4.1 Raceway System

Each run shall be complete and shall be fished and swabbed before conductors are installed. Ends of conduit systems not terminated in boxes or cabinets shall be capped. Exposed raceways shall be installed parallel to or at right angles with the lines of the structure. Crushed or deformed raceways shall not be installed. A pull wire shall be installed in all empty tubing and conduit systems. The pull wire shall be No. 14 AWG zinc coated steel, or plastic with a minimum 200 pound tensile strength.

Ten inches of slack shall be left at each end of the pull wire. Where conduit has to be cut in the field, it shall be cut square using a hand or power hacksaw or approved pipe cutter using cutting knives.

The cut ends of the field-cut conduit shall be reamed to remove burrs and sharp edges. Where threads have to be cut on conduit, the threads shall have the same effective length and shall have the same thread dimensions and taper as specified for factory cut threads on conduit. Conduits installed with threads not complying with these requirements shall be removed and replaced with conduits which comply. Minimum diameter of all conduits shall be ¾”.

Elbows, fittings, offsets, etc., shall be pre-formed and similar in materials and construction to the conduit.

Couplings shall be of a type to provide a watertight installation of the conduit system.

All conduits that enter a wireway or junction box from the ground, enter a shelter/building from the exterior or enter an SPD/TVSS must be sealed off with “duct seal”.

16-4.2 Conduit

16-4.2.1 Heavywall Zinc Coated Rigid Steel Conduit

Heavywall zinc coated rigid steel conduit shall conform to Federal Specification WW-C-581. Rigid steel conduit may be used in all locations. Coated rigid steel conduit shall be used for installation below slab or grade, or underground. The conduit shall be factory coated with .04 inch of polyvinyl chloride on the exterior. Any damaged coating shall be repaired in accordance with the manufacturer specifications. All fittings for use with rigid steel conduit shall be of the threaded type of the same materials as the conduit.

Where conduits enter boxes or cabinets without threaded hubs, double locknuts shall be used plus an insulated metallic grounding bushing on the open end.

Where conduit enters exterior boxes watertight grounding type hubs with a grounding bushing shall be used.

16-4.2.2 Electric Metallic Tubing (EMT)

EMT shall conform to Federal Spec. WW-C-563. EMT may be used only in dry interior locations, and where not subject to physical damage. EMT shall not be used on circuits above 600 volts.

Fittings to be used with EMT shall be standard compression fittings designed for use with this type of conduit. Where box fittings are used with only a locknut, a smooth bushing shall be installed on the fitting end.

16-5 CONDUCTORS

16-5.1 Color Coding

All branch circuit and feeder conductors shall be color coded as specified hereinafter. The color coding shall be continuous throughout the facility on each phase conductor to its point of utilization so that the conductor phase connection is readily identifiable in any part of the installation. The equipment grounding conductor shall be as specified herein before. Neutral conductors shall be continuous white unless more than one system is run in the same raceway, box, or other type enclosure. The neutral of the other systems shall be white with identifiable colored tracers (not green).

Where color coding is not available in the larger size conductors, the conductors shall be color coded by use of color coded tape, half lapped for a minimum length of 3 inches. Where conductors are color coded in this manner, they shall be color coded in all junction and pull boxed accessible raceways, panelboards, outlets and switches, as well as at all terminations. Conductors in accessible raceways shall be coded in such manner that by removing or opening any cover, the coding will be visible.

Phase conductors shall be color coded as follows:

Single Phase Three Phase

120/240 Volts 120/208 or 240 Volts

Line A - Black Phase A - Black Line B - Red Phase B - Red Phase C - Blue

Grounded conductors shall be color coded as follows:

Equipment ground – green

16-5.2 Insulated conductors

Unless otherwise indicated, insulated conductors shall be copper with thermoplastic or thermosetting insulation, type THW, THWN, and XHHW for general use, or type THHN for use in dry locations only, all insulated for 600V in accordance with Federal Specification J-C-30. Conductors #10 AWG and smaller shall be solid, and conductors #8 AWG and larger shall be stranded. Minimum branch circuit conductor size shall be #12 AWG. Minimum control wire size shall be #14 AWG unless noted otherwise.

16-5.3 Conductor Identification

In addition to color coding, all line, phase, and neutral conductors shall be identified by plastic-coated, self-sticking printed markers, permanently attached stamped metal fail markers, or equivalent means as approved by the RE. Conductor identification shall be provided at all terminations, and in all junction boxed through which these conductors pass. Conductor identification shall be provided within each enclosure where a tap, splice, or termination is made.

16-5.4 Splices

All splices for power cables shall be by hydraulically crimped barrel that utilize a minimum force of 12 tons. Heavy wall heat-shrink insulation tubing that is UL listed for cable voltage and direct burial shall cover each splice. Wire nuts are acceptable for interior splices of #12 AWG cables.

16-6 QUALITY ASSURANCE PROVISIONS

16-6.1 Submittals

Before installing any materials or equipment, the Contractor shall submit the following to the RE for approval:

a. Conduit and connectors

b. Cable

c. Junction Boxes

d. Grounding

e. Splice

SITE MAPS

Millville RCAG (30 Bogden Blvd., Millville, NJ)

Equipment Room Floor Photo

Equipment Room Wall Photo

Storage Room Photo

Storage Room Painted Conduit