miami-dade CIIS - RPQ - INVITATION TO BID Friday_ October 16_ 2026 - 11_48_53 AM.pdf
PDF 112 KB Posted
- Attached to
- Pump Station 0812 Relocation and Upgrade
- Solicitation number
- MCC 7360 RPQ No P16319
- Issued by
- Miami-Dade County, Florida
About this file
This is a Request for Price Quotation (RPQ) issued by Miami-Dade County, Florida for the relocation and upgrade of Sewage Pump Station No. 0812. The project encompasses the complete demolition of the existing sewage pump station and construction of a new facility at 8401 SW 107th Avenue, Miami, Florida 33173. The scope of work includes excavation, demolition, removal of existing equipment (pumps, motors, valves, piping), installation of two 15 HP submersible pumps, construction of new wet well and valve vault structures, electrical system upgrades, SCADA equipment integration, temporary bypass pumping operations, sewer force main installation, asphalt paving, and landscape restoration. A mandatory pre-bid meeting and site visit are scheduled for October 28, 2026, at 10:00 AM at the pump station location. Electronic bids are due December 1, 2026, at 10:00 AM, submitted through the Trimble Unity Construct portal with a hard copy postmarked within one business day. The anticipated project start date is December 14, 2027, with a completion timeline of 280 calendar days. The contractor must hold a valid Certificate of Competency or State of Florida Construction Industry Licensing Board certification as a General Engineering Contractor, Pipeline Engineering Contractor, or Underground Utility and Excavation Contractor.
The estimated project value is $1,792,605, excluding contingencies and dedicated allowances, with liquidated damages set at $1,000 per day. Bid bonds are required for bids meeting or exceeding $200,000, and performance and payment bonds are mandatory upon award for projects of this value. The contract is classified as a multiple trade project with no primary trade-related work to be subcontracted; only ancillary work may be subcontracted with prior departmental approval. Minimum bidder qualifications require successful completion of at least three sewage pump station projects within the seven years preceding the bid date, with at least one project completed within a private property easement. Bidders must demonstrate full-time personnel experience and provide three references confirming upgraded pump station work. By-pass pumping subcontractors or vendors must have established and successfully operated at least three by-pass pumping operations without spills or overflows. Contractors must comply with E-Verify employment eligibility requirements, maintain workers' compensation insurance, carry commercial general liability coverage of at least $1,000,000 per occurrence and $2,000,000 aggregate, and provide automobile liability insurance of $1,000,000 combined single limit. There are no Davis-Bacon prevailing wage requirements, no apprenticeship investment requirements, and no disadvantaged business enterprise, small business enterprise, or other set-asides applicable to this contract.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Water and Sewer 3071 SW 38 Avenue Douglas Miami Fl 33146
MIAMI-DADE COUNTY, FLORIDA
REQUEST FOR PRICE QUOTATION (RPQ)
Contract No: MCC 7360 Plan RPQ No: P16319
INVITATION TO BID
A RPQ has been issued for the work identified below. If you are interested in submitting a bid for this project, please submit your bid via Electronic Bidding, attention to Jesus Salinas at no later than 12/1/2026 at 10:00 AM. If you have any questions, contact Jesus Salinas at 786-552-8055.
This RPQ is issued under the terms and conditions of the Miscellaneous Construction Contracts (MCC) Program MCC 7360 Plan.
RPQ DETAILED BREAKDOWN
Bid Due Date: 12/1/2026 Time Due: 10:00 AM Submitted Via: Electronic Bidding Estimated Value: $1,792,605 (excluding Contingencies and Dedicated Allowances) Project Name: Pump Station 0812 Relocation and Upgrade Project Location: 8401 SW 107th Avenue, Miami, Florida 33173 License Requirements: Primary: General Building Contractor; General Engineering; Underground Utility / Excavation;
Pipelines Engineering Contractor Sub: Electrical Contractor; Landscape Contractor; Paving Scope of Work: (Contractor must obtain and submit all permits prior to performing any work).
1.04 DESCRIPTION OF WORK
A. The project consists of furnishing all materials, labor and equipment necessary to demolish existing Sewage Pump Station and construct proposed Sewage Pumping Station No. 0812 as indicated on plans, the work includes but it is not limited to, excavation, demolition and modification work; removal of existing pumps, motors, valves, piping and fittings; partially removal and backfilling of existing dry well and wet well structures; removal of wet well and dry well top slabs and access hatches; removal of existing power/control panel and concrete slab; removal of existing telemetry antenna and remote terminal unit equipment; existing electric service to remain, meter and main disconnect;
removal, transport, salvage and legal disposal of demolition material and equipment; transportation and handling costs, including removal of salvaged equipment to a location designated by the Engineer; removal and replacement of existing PVC sanitary sewer main; furnish, install, operate, and remove temporary sewage effluent bypass pumps, equipment and accessories; furnish and install valve vault structure, top slab and access hatch; furnish and install new wet well structure, top slab and access hatch; furnish and install new sanitary manhole structure, frame and cover; furnish and place suitable backfill material; furnish and install two 15 HP submersible pumps and related equipment; furnish and install leveler control system and related equipment;
furnish and install valve vault sump pump and related equipment; furnish and install new water service piping, enclosure and accessories; furnish and install backflow prevention device; coordinate with FPL for installation of electrical service; furnish and install meter and main disconnect; furnish and install the proposed power/control system inclusive of the necessary electrical panel, enclosure, telemetry system and related equipment; install RTU panel and SCADA equipment furnished by the Department; furnish and install RTU and 01 11 00-3 SCADA materials not specifically provided by the Department; electrical work;
mechanical work; furnish all materials, equipment and supplies necessary for pump station startup and testing; furnish and install sewage force main pipe and fittings; connection to existing sewage force main; placing asphalt driveway; furnish and install landscape improvements as indicate on plans;
temporary and permanent replacement of any sod, sidewalk, pavement and/or driveway damaged by construction; site restoration; and other appurtenant and miscellaneous items and work for a complete, satisfactory and functional installation.
Sewage Pump Station 0812 located at 8401 SW 107 Avenue, Miami, Florida 33173, Section 32, Township 54, Range 40.
B. It is the intent of the Department to obtain a complete and working installation under this Project and any items of labor, equipment or materials which may reasonably be assumed as necessary to accomplish this end shall be supplied whether or not they are specifically shown on the Plans or stated herein.
1.07 MINIMUM REQUIREMENTS OF THE BIDDER
A. Qualifications shall be submitted with the Bids. Submit experience history with a minimum of references along with the bid. The work shall have been completed with the Contractor’s own forces or key personnel.
B. The Contractor shall submit to WASD at the time of submitting the bid, name of the Manufactured and the time it takes to create a product and deliver it to the job site, if the Bids submitted without entry the name of Manufactured and the Lead Time, will be considered non-responsive.
(if apply)
For CICC 7040 MCC Contracts - CICC 7360 MCC Contracts - Open Competitive Contracts
A. License Requirements
1. At the time of Bid and pursuant to the requirements of Section 10-3 of the Code of Miami-Dade County, Florida and these Solicitation and
Contract Documents, the Bidder must hold a valid, current, and active:
a. Certificate of Competency from the County's Construction Trades Qualifying Board as a General Engineering Contractor or as a Pipeline Engineering Contractor. The Pipeline Engineering Contractor shall subcontract with a qualified contractor any work which is incidental to the pipeline specialty but is specified in the aforementioned Code as being the work of other than that of the Engineering Specialty for which certified;
or
b. Certification, as a General Contractor or as an Underground Utility and Excavation Contractor, provided by the State of Florida Construction Industry Licensing Board, pursuant to the provisions of Florida Statutes Chapter 489.115.
B. Primary Trade Related Work
1. For a project like a sanitary sewer pump station, the “primary trade related work” is the work directly related to the sanitary sewer system/functionality. Examples of such work would include the installation of gravity sewer mains, manholes, wet wells, valve vaults, force mains, etc. (all underground improvements). “Non-primary trade related work” would include items such as electrical, concrete, asphalt, sodding, fencing, etc.
2. CICC 7040 MCC Contracts - CICC 7360 MCC Contracts:
a. In accordance with "Issuance of Work Under the Contract" and "Subcontracting of Work: Post Award", E., of the "Special Conditions," this Project might be considered a multiple trade project. None of the primary trade related work shall be subcontracted. Only ancillary work required to complete this Project may be subcontracted with prior approval from the Department and the Miami-Dade County Internal Services Department.
3. Open Competitive Contracts:
a. This Project might be considered a multiple trade project. None of the primary trade related work shall be subcontracted. Only ancillary work required to complete this Project may be subcontracted with prior approval from the Department
1.08 MINIMUM CONSTRUCTION EXPERIENCE OF THE CONTRACTOR
A. With his bid, the successful Bidder shall submit proof that his/her firm has at least the minimum successful contract experience as required below for this Contract being bid. Such proof shall consist of a list of projects, completed prior to the bid date, with the names and telephone numbers of the owners or representatives that the OWNER can contact to confirm the listed experience.
B. In addition to submittal requirements stated elsewhere, to qualify for work on this Contract, the Bidder shall be experienced in raw sewage pump station construction, including the installation of submersible pumps, and low voltage electrical power systems.
C. The Bidder must have successfully completed the installation of a minimum of three (3) pump stations within the last seven (7) years, with at least one (1) within a private property easement.
D. The Bidder must demonstrate that it has full-time personnel with the necessary experience to perform the Project’s Scope of Work. The Bidder shall provide a list of no less than three (3) references who can confirm that the bidder has successfully upgraded pump stations. Each reference shall include the following:
contact’s name, telephone number, e-mail address, and location of pump stations.
E. The experience of key senior personnel with other firms may be counted toward the experience requirement, if acceptable to the ENGINEER. Should such evidence not be satisfactory to the ENGINEER, whose decision shall be final.
F. The Bidder or Bidder’s By-pass Pumping subcontractor or vendor shall have established, operated and maintained at least three (3) successful by-pass pumping operations, including at least (1) by-pass pumping operation receiving flows from two different Manholes. The Contractor shall have had primary responsibility for the by-pass operation and the operation shall have been completed successfully without spills or overflow. Submit experience history with the Bid Package. A Prime Contractor may bid the project with a qualified subcontractor that will be responsible for the by-pass pumping operation. The qualifications of the subcontractor shall be submitted with the bid. The Prime Contractor shall be responsible for having the qualified subcontractor for the duration of the project, no change to the qualified subcontractor used for by-pass pumping shall be made without the approval of the Engineer.
G. In the event a firm is established by executives, supervisors and other senior field staff (key employees) that would have met these minimum experience requirements with a prior firm, OWNER reserves the right to qualify the firm based on OWNER''s sole determination and evaluation of the knowledge and prior experience of these key employees employed by the new firm. The experience of key senior personnel with other firms may be counted towards the experience requirement, if acceptable to the ENGINEER. Should such evidence not be satisfactory to the ENGINEER, whose decision shall be final, the bid will be considered non-responsive, and the second lowest bidder will be considered for award. The qualifying proof shall be submitted in a separate sealed envelope with the bid.
H. Experience
1. In addition to the license requirements, the Bidder must have a minimum of three (3) years of experience, under its current business name in the construction of sewer pump station projects of similar scope and scale involving public right-of-way construction, installation/repair/replacement of sanitary sewer collection systems, and maintenance of vehicular traffic, supported by references for three (3) projects completed within the past seven (7) years.
2. The Bidder must demonstrate that it has full-time personnel with the necessary experience to perform the Project's Scope of Work. This experience shall include work in successfully completed projects performed by the identified personnel whose bulk of work performed in the public right-of-way is similar in detail to the Project's Scope of Work described in these Solicitation Documents. Demonstrate the experience requirement by:
a. Providing a detailed description of at least three (3) projects similar in detail to the Project's Scope of Work described in these Solicitation Documents and in which the Bidder's identified personnel is currently engaged or has completed within the past seven (7) years. List and describe the aforementioned projects and state whether the work was performed for the County, other government clients, or private entities.
For each project listed, the pipe installation shall have been completed and accepted by the project owner prior to the bid submittal date.
The description must identify for each project:
1) The identified personnel and their assigned role and responsibilities for the listed project
2) The client name and address including a contact person and phone number for reference
3) Description of work
4) Total dollar value of the contract
5) Contract duration
6) Statement or notation of whether Bidder's referenced personnel is/was employed by the prime contractor or subcontractor, and
7) For completed projects, provide letters of certification of final acceptance or similar project closure documentation issued by the client and available Contractor's performance evaluations.
3. The County reserves the right to request additional information and/or contact listed persons pertaining to bidder's experience.
Document Pickup: Contact: Jesus Salinas Phone No: 786-552-8055 Date: 10/16/2026 Location: Electronic request Trimble Unity Document Portal
Pre-Bid Meeting:: YES Mandatory: YES Date: 10/28/2026 Time: 10:00 AM Location: PS No. 0812 - 8401 SW 107th Avenue, Miami, Florida 33173
Site Meeting: YES Mandatory: YES Date: 10/28/2026 Time: 10:00 AM Location: PS No. 0812 - 8401 SW 107th Avenue, Miami, Florida 33173
Bid shall be submitted to: Contact: Jesus Salinas Address: 3071 SW 38th Ave. Miami, FL 33146 -1st Flr - OCI _Procurment Email: Jesus.Salinas@miamidade.gov FAX # : 571-223-2910
Type of Contract: Multiple Trade Method of Award: Lowest Responsible Bidder Method of Payment: Scheduled Monthly Payments Insurance Required: YES
Additional Insurance Required: NO If Yes - Minimum Coverage:
Performance & Payment Bond Required: YES Bid Bond Required: YES
Davis Bacon: NO Maintenance Wages: NO AIPP: NO Amount:
DBE Participation: NO Percentage: 0.00% DBE Subcontractor Forms Required: NO SBE-S Requirements NO Percentage: 0.00% SBE-Services Commodity Set-Aside NO If Yes, Service = SBE-G Requirements NO Percentage: 0.00% SBE-Goods Commodity Set-Aside NO If Yes, Goods = Liquidated Damages: YES $$ Per Day: $1,000.00 For RPQ's less than $10,000, if no LD rate is specified, the County reserves the right to assess actual damages in lieu of LDs.
Design Drawing Included: YES Shop Drawing Included: YES Specifications Included: YES Anticipated Start Date: 12/14/2027 Calendar Days for Project Completion: 280 Comments: Bid submission must be electronic, through the Trimble Unity Construct (eBuilder) Bid Portal, with a hard copy sent to WASD postmarked within one (1) business day of the bid submittal date, mailed to WASD [3071 SW 38th Avenue, Suite 107, Miami, FL 33146]
The original Bid Security (in the form of a bid bond or cashier’s check) MUST be delivered to WASD, at the address above, BEFORE the bids are opened. Failure to deliver the original will result in the bid submission being rejected as non-responsive.
Invited bidders should have received an Invitation to Bid with an Invitation Key linked to the Invitee’s email address. Upon request, an invitation can be sent to multiple email addresses within the same company. However, if multiple bids are submitted by the same company, ALL submitted bids will be rejected.
The bid set includes electronic bid instructions. Training on electronic bid submission is available every Monday from 9 – 10 and every Wednesday from 1 – 2. Email the Contracting Officer or paul.adams@miamidade.gov for further information or to schedule training on alternative dates.
The RFI cut-off date is no less than five (5) business days prior to the bid due date
Liquidated Damages - $1,000.00 per day.
The contractor must include in their bid package the following documents:
1. Appendix 5A,
2. Quotation Forms Pages & Quotation Bid Item Pages
3. Addendums,
4. Bid Bond - Note: A Bid Bond will be required only if the bid meets or exceeds $200K.
In addition, a Performance and Payment Bond with additional insurance will be required once bid is Awarded and bid meets or exceeds $200K.
5. COA (Certificate of Assurance) form. (Only if project has Goods or Services goals)
SPD department will process it as a “No Measure” ( no SBE Measure)
DISCLOSURE:
• Contractor shall indemnify and hold harmless the County and its officers, employees, agents and instrumentalities from any and all liability, losses or damages, including attorneys’ fees and costs of defense, which the County or its officers, employees, agents or instrumentalities may incur as a result of claims, demands, suits, causes of actions or proceedings of any kind or nature arising out of, relating to or resulting from the performance of this Agreement by the Contractor or its employees, agents, servants, partners principals or subcontractors. Contractor shall pay all claims and losses in connection therewith and shall investigate and defend all claims, suits or actions of any kind or nature in the name of the County, where applicable, including appellate proceedings, and shall pay all costs, judgments, and attorney’s fees which may issue thereon. Contractor expressly understands and agrees that any insurance protection required by this Agreement or otherwise provided by the Contractor shall in no way limit the responsibility to indemnify, keep and save harmless and defend the County or its officers, employees, agents and instrumentalities as herein provided.
The Contractor shall furnish to Water and Sewer, 3071 SW 38 Avenue, Douglas, Miami Fl 33146, Certificate(s) of Insurance which indicate that insurance coverage has been obtained which meets the requirements as outlined below:
A. Worker’s Compensation Insurance for all employees of the Contractor as required by Florida Statute 440.
a. If applicable should include coverage required under the U.S. Longshoremen and Harbor Workers’ Act (USL&H) and/or Jones Act for any activities on or about navigable water.
B. Commercial General Liability in an amount not less than $1,000,000 per occurrence, and $2,000,000 in the aggregate.
Miami-Dade County must be shown as an additional insured with respect to this coverage.
C. Automobile Liability Insurance covering all owned, non-owned and hired vehicles used in connection with the work, in an amount not less than $1,000,000 combined single limit per occurrence for bodily injury and property damage.
*Under no circumstances are Contractors permitted on the Aviation Department, Aircraft Operating Airside (A.O.A) at Miami International Airport without increasing automobile coverage to $5 million. Only vehicles owned or leased by a company will be authorized. $1 million limit applies at all other airports.
VERIFICATION OF EMPLOYMENT ELIGIBILITY (E-VERIFY):
By entering the Contract, the Awarded Bidder becomes obligated to comply with the provisions of Section 448.095, Florida Statute, titled "Verification of Employment Eligibility." This includes but is not limited to utilization of the U.S. Department of Homeland Security’s E-Verify System to verify the employment eligibility of all newly hired employees by the Awarded Bidder effective, January 1, 2021, and requiring all Subcontractors to provide an affidavit attesting that the Subcontractor does not employ, contract with, or subcontract with, an unauthorized alien. Failure to comply may lead to termination of this Awarded Bidder, or if a Subcontractor knowingly violates the statute, the subcontract must be terminated immediately.
Any challenge to termination under this provision must be filed in the Circuit Court no later than twenty (20) calendar days after the date of termination. If this Contract is terminated for a violation of the statute by the Awarded Bidder, the Awarded Bidder may not be awarded a public contract for a period of one year after the date of termination, and the Awarded Bidder may be liable for any additional costs incurred by the County resulting from the termination of the Contract. Public and private employers must enroll in the E-Verify System (http://www.uscis.gov/e-verify) and retain the I-9 Forms for inspection.