12) Response to Questions 1 - RFP MG 06112024.pdf

PDF 83 KB Posted

Attached to
SR Flanged BPM Buttons
Solicitation number
MG-06112024
Issued by

About this file

This document is a response to questions received by Lawrence Berkeley National Laboratory (LBNL) regarding RFP MG-06112024 for the procurement of Storage Ring (SR) Flanged Beam Positioning Monitor (BPM) Buttons.

The key details are:

  • The RFP requires submission of the ALS-U Supplier Quality Evaluation Survey AL-1208-0209 with the technical proposal by the due date of July 12, 2024. This document cannot be submitted after award.
  • Regarding the SR Flanged BPM Button Engineering Specification AL-1745-1941, the supplier is not required to measure the full electromagnetic properties, as LBNL will conduct this testing on the first article or samples. The supplier must optimize the design to meet the specified electrical requirements.
  • The federal contract opportunity has a solicitation number of MG-06112024, is being issued by the Department of Energy, and has a proposal due date of July 12, 2024.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LBNL Response to Questions 01 Re: LBNL RFP MG-0611024 – 06/24/2024

1. AL-1208-0209 Revision: C (ALS-U supplier quality evaluation survey)

Does this document have to be submitted as a part of the proposal by 7/12 or, is it acceptable to submit it after winning the bid?

LBNL Response: Please refer to RFP Factor 4

"Evaluation of Factor 4 is based on the completion of the ALS-U Supplier Quality Evaluation Survey AL-1208-0209 (Must be submitted with the Technical Volume)".

It must be submitted with the supplier’s proposal.

2. AL-1745-1941 Revision: B (SR Flanged BPM Button Engineering Specification)

• 8.2 BPM connector type

• 8.3 Electromagnetic properties

From 8.2 and 8.3, it is required for the supplier to meet the specifications as “Must” but we have to say that it is challenging to verify them ourselves in such a short period.

LBNL Response: The supplier is not required to measure the full electromagnetic properties. LBNL is able to measure the full electromagnetic properties on the first articles or samples delivered by the supplier. The supplier must be able to optimize the design to meet the stipulated electrical specifications.