Text version

SIMPLIFIED ACQUISITON PROCEDURES (SAP)

Justification for Urgent Acquisitions Over $3,500 But Not Exceeding the Simplified Acquisition Threshold

URGENT REQUESTS ARE FOR SUPPLIES OR SERVICES THAT WILL RESULT IN WORK STOPPAGE OR ARE MISSION ESSENTIAL AND NORMAL PROCESSING TIMES WILL RESULT IN INJURY TO THE GOVERNMENT. THIS JUSTIFICATION MUST BE SUPPORTED BY THE REQUESTOR. THE REQUEST MUST DESCRIBE THE COMPELLING NATURE OF THE URGENCY, HOW THE GOVERNMENT WILL BE SERIOUSLY INJURED AND WHAT THE FINANCIAL IMPLICATIONS MIGHT BE. STATEMENTS SUCH AS "EMPLOYEES WILL BE SENT HOME" OR "THE LINE WILL GO DOWN" ARE INADEQUATE TO SUPPORT AN URGENT PURCHASE. THE CUSTOMER SHALL PROVIDE THE

FOLLOWING INFORMATION:

1. PURCHASE REQUEST OR REQUISITION NUMBER 2. PROJECT/TASK NUMBER 3 ESTIMATED AMOUNT

4. BRIEF DESCRIPTION OF SUPPLIES OR SERVICES REQUIRED AND THE INTENDED USE.

5. PROVIDE EXPLANATION, DATA, ESTIMATED COSTS OR OTHER RATIONALE AS TO THE NATURE AND EXTENT OF HARM THE

GOVERNMENT WILL EXPERIENCE, FINANCIAL OR OTHERS, IF THE AWARD WERE DELAYED.

6. PROVIDE THE REQUIRED DELIVERY SCHEDULE AND MANUFACTURING LEAD-TIME INVOLVED.

7. PLEASE PROVIDE THE DATE THE REQUIREMENT WAS FIRST KNOWN TO EXIST.

8. PROVIDE A STATEMENT OF ACTIONS, IF ANY, THE GOVERNMENT MAY TAKE TO REMOVE OR OVERCOME ANY BARRIERS TO

COMPETITION BEFORE FUTURE ACQUISITIONS ARE REQUIRED.

9A. OFFICE SYMBOL 9B. TELEPHONE NUMBER 9D. DATE

10A. OFFICE SYMBOL 10B. TELEPHONE NUMBER 10D. DATE

MCAAP Form 715-25, February 2016

Quantity 2 - Flexicon TIP-TITE high lift drum dumpers, Model DDT-C2HE-P120-X with a of 70” and a 750 lb capacity. The dumper shall be capable of having the drum loaded into it from floor level via drum dolly. The dumper shall retain the dolly during operation. All product contact surfaces will be type 316L stainless steel. Dumper shall use a hydraulic power system with pneumatic motor and rotates drum to 60 degrees beyond horizontal. Quantity 5 - Drum Dolly's shall be included.

MCAAP the responsibility for designing and defining a new aluminum dumping process . MCAAP is currently incurring down time and must install a new process that allows us to process the aluminum powder safer and cleaner. MCAAP must have the new system installed in order to stop incurring down time. The current system specified will take about 16 weeks after award to build. If this system is not awarded ASAP MCAAP will be at risk as they will not be able to process powder and the complete line will remain shut down and left idle. Any delays will result in lost revenue and negatively effect our ability to support the mission.

MCAAP must have the new system installed as soon as possibe. The current system specified will take about 16 weeks after award to build. If this system is not awarded ASAP MCAAP will be at risk as they will not be able to process aluminum powder for the mixing operation and a complete line will remain shut down and left idle. MCAAP currently has a plan and design to install the drum dumpers, but if they are not here in an urgent fashion we will assume mission failure.

MCAAP Design Engineering Branch has been in the develop phase of this system for about 1 month, leaving the initial start date of design to be early October. Engineering had to develop the design forward from that point. Due to events that occurred on November 2, 2021, and leaving the production line down, this requirement has been drastically elevated.

If the current request is not action as stated, MCAAP will incur more cost to the current explosive mixing program at B194B and incur more down time. The deadline for this project is as soon as possible due to the event occurring on November 2, 2021.

854-18823 & 854-24453

11/03/2021

11/03/2021