Meriden_Columbus_Ave_Cul-de-sac_2025-06-24.pdf
PDF 2 MB Posted
- Attached to
- B026-42 Columbus Avenue Cul-de-sac
- Solicitation number
- B026-42
- Issued by
- New Haven County, Connecticut
About this file
This is a civil engineering design document prepared by Loureiro Engineering Associates for the City of Meriden, Connecticut, detailing the construction plans for a new multi-use path and cul-de-sac project at 380 Columbus Avenue in Meriden. The project involves constructing a 48-foot radius cul-de-sac at the south end of Columbus Avenue and an 8-foot wide stone dust multi-use path connecting Columbus Avenue to Marina Court. Construction work includes removal of existing pavement, site regrading, installation of full-depth bituminous concrete pavement (10,600 square feet), concrete curbing (384 linear feet), concrete sidewalk repairs, a concrete block retaining wall (60 linear feet), chain link fencing (48 inches high), and associated stormwater infrastructure including catch basin modifications and storm sewer connections. The site plan indicates approximately 0.58 acres of land disturbance. The project is anticipated to commence in Spring 2026, with the selected contractor required to prepare a detailed construction schedule for presentation at a pre-construction meeting and coordinate temporary access provisions with affected homeowners to minimize disruption.
The design plans include comprehensive erosion and sedimentation control measures, dust control specifications, and site stabilization requirements in accordance with Connecticut Guidelines for Soil Erosion and Sediment Control (effective March 30, 2024). Key specifications address utility location verification through "Call Before You Dig" procedures, tree removal notifications to the City's Parks Department for trees exceeding 10 inches in diameter, and protection of existing site improvements during construction. The contractor is responsible for field verification of property lines, utility locations, and existing conditions, with discrepancies to be reported to the engineer before proceeding. Permanent seeding of disturbed areas must be completed between April 15 and June 15 or August 15 and September 15, with temporary seeding required if work suspends for longer than 30 days. Construction entrance controls, catch basin inlet protection, silt fencing, and compost filter socks are specified as minimum erosion control measures, with additional measures required as conditions dictate throughout the construction duration.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
X
X
X
X
X
X
CONCRETE WALK
C O
LU
M
B U
S A
V E
M A
R
IN
A C
T
PARKVIEW ST
SP
RIN
G S T
380 COLUMBUS AVE
MERIDEN, CT 06450
JUNE 18, 2025
NEW MULTI-USE PATH AND CUL-DE-SAC
V
C T\
M
ER
ID
EN
\C O
LU
M
B U
S A
V E-
0\
D W
G S \C
IV
IL
\C O
V
ER
.D W
G
Ta b:
C O
V
ER
S av ed
6/
/2
2:
P
M P ap er
S iz e:
4" x
6"
Pl ot te d:
/1 8/
:1
PM
SHEET
NO.
NO. OF
SHEETS1 5
PREPARED BY:
ENGINEER:
NEW MULTI-USE PATH
AND CUL-DE-SAC
Loureiro Engineering Associates, Inc.
100 Northwest Drive · Plainville, Connecticut 06062 Phone: 860-747-6181 · Fax: 860-747-8822 An Employee Owned Company · www.Loureiro.com
Loureiro
LOCATION MAP
SCALE: 1"=50'
PROPERTY OWNER:
CITY OF MERIDEN
142 EAST MAIN ST
MERIDEN, CT 06450
PROJECT LOCATION
LEA COMMISSION NUMBER 051PL5.03 068
DRAWING INDEX
SHEET NO. DRAWING TITLE
1 - COVER SHEET
2 EC-1 EXISTING CONDITIONS
3 C-1 SITE LAYOUT PLAN
4 C-2 DETAILS -1
5 C-3 DETAILS - 2
5'
5" R
CP
R=30'
68' - 15" HDPE STORM SEWER
14' LIMIT OF CLEARING
IN WOODED AREAS (TYP)
X
X
REMOVE WOOD
GUARD RAIL
ASSEMBLY AND
TURN OVER
TO CITY
TO BE RELOCATED AT THE
DIRECTION OF THE CITY
TC=BC=281.80 (EX)
282.30 (EX)
282.36
TC=270.90
BC=270.40
10' ACCESS EASEMENT IN FAVOR OF CITY OF
MERIDEN W/ TEMPORARY GRADING RIGHTS
PER VOLUME 4980, PAGE 134
20' WATER EASEMENT IN FAVOR OF CITY OF
MERIDEN W/ TEMPORARY GRADING RIGHTS
PER VOLUME 4980, PAGE 134
N/F
CITY OF MERIDAN
OPEN SPACE
VOLUME 4980, PAGE 134
201 PROSPECT AVE
WETLANDS AS FLAGGED BY JAMES SIPPERLY,
SOIL SCIENTIST DECEMBER 28, 2004
WETLANDS AS FLAGGED BY SOIL RESOURCE
CONSULTANTS DAVID LORD, SOIL SCIENTIST
OCTOBER 2003 - MAY 2004
N/F
CITY OF MERIDEN
VOLUME 3646, PAGE 193
380 COLUMBUS AVE
N/F
HENRY K. & HANNA M.
LEMMER
VOLUME 4443, PAGE 296
378 COLUMBUS AVE
N/F
CARLOS CHAIRES RIVERA
VOLUME 5476, PAGE 621
383 COLUMBUS AVE
N/F
ANDREW MAY
VOLUME 2695, PAGE 97
381 COLUMBUS AVE
N/F
GAIL R. & PAUL D.
HENNESSY
VOLUME 2583, PAGE 167
379 COLUMBUS AVE
N/F
SHAMARA BURTON
VOLUME 5460, PAGE 523
373 COLUMBUS AVE
N/F
JASON CHRISTOPHER KOVACH
VOLUME 4609, PAGE 26
VOLUME 4609, PAGE 30
367 COLUMBUS AVE
N/F
FRANK J. & LINDA M.
MILANO
VOLUME 939, PAGE 22
374 COLUMBUS AVE
N/F
WILLIAM R. AITKEN
VOLUME 4895, PAGE 239
362 COLUMBUS AVE
N/F
DEAN & RICHARD
SMART
VOLUME 4233, PAGE 19
166 PARKVIEW ST
N/F
SARAH FREEMANTLE
VOLUME 5380, PAGE 451
180 PARKVIEW ST
N/F
N/F
STEVEN D. & ROBERTA A.
LASEK
VOLUME 781, PAGE 247
387 SPRING ST
N/F
DAVID MOZDZIAK
VOLUME 5438, PAGE 488
379 SPRING ST
N/F
GERALDO O. & LYNN A. DEAN
VOLUME 5399, PAGE 971
83 MARINA CT
N/F
PROSPECT AVE ESTATES LLC
VOLUME 3646, PAGE 193
79 MARINA CT
N/F
DENNEHY, GEOFFREY C. DENNEHY
& LAUREN YONUS
VOLUME 5379, PAGE 958
78 MARINA CT
N/F
DELBUONO CONSTRUCTION
& DESIGN LLC
VOLUME 4580, PAGE 77
72 MARINA CT
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
APPROXIMATE
LOCATION OF
UTILITY POLE
PAVED DRIVEWAY
PAVEDDRIVEWAY
HYDRANT
PAVED DRIVEWAY
SANITARY MANHOLE
TF=276.10
PAVED DRIVEWAY
PAVED DRIVEWAY
PROPERTY LINES SHOWN ARE
APPROXIMATE. FIELD LOCATE ALL
PROPERTY LINES WITHIN OR ADJACENT
TO WORK PRIOR TO CONSTRUCTION
SIGNS, "DEAD END", LITTERING,
"NO PARKING ANY TIME"
WOOD GUIDE RAIL
WOOD STOCKADE FENCE
BLOCK
RETAINING
WALL
CHAIN LINK FENCE
STOCKADE FENCE
CHAIN LINK FENCE
0'
U
PL
AN
D
R
EV
IE
W
A
RE
A
FR
O M
W
ET
LA
N D
CONCRETE CURB
CONCRETE WALK
TREE LINE
(FROM AERIAL)
C O
LU
M
BU
S
AV
EN
U E
M
AR
IN
A
CO
UR
T
APPROXIMATE LOCATION
OF GAS MAIN
60' RADIUS
253'±
146'±
4'
1'
54'±
214'±
25' RIGHT OF WAY
10' WIDE SANITARY
SEWER EASEMENT
TC=BC=270.50
273273
328328
.5
' M
IN
16' M
IN
PROPERTY LINE SHOWN IS APPROXIMATE. FIELD
LOCATE PROPERTY LINES WITHIN OR ADJACENT
TO WORK PRIOR TO CONSTRUCTION.
PROPERTY LINE SHOWN IS
APPROXIMATE. FIELD LOCATE
PROPERTY LINES WITHIN OR ADJACENT
TO WORK PRIOR TO CONSTRUCTION.
4" Ø STEEL REMOVABLE BOLLARD
CONCRETE CURB (311 LF)
CONCRETE CURB (73 L F)
FULL DEPTH BITUMINOUS
CONCRETE PAVEMENT (10,600 SF)
FRAISER FUR B&B 2" CAL (TYP OF 2)
4" STEEL REMOVABLE BOLLARD
CT DOT TYPE 1 CURB RAMP
WITH BOLT-ON DETECTABLE WARNING SURFACE
(DO NOT INSTALL PRESS-IN DWS)
FRAISER FUR B&B 2" CAL (TYP OF 6)
8' WIDE STONE MULTI-USE TRAIL (SEE DETAILS AND NOTES)
APPROXIMATE LIMITS OF WORK.
EXISTING BITUMINOUS DEBRIS ON
CUL-DE-SAC PAVEMENT TO BE REMOVED
TEMPORARY FILTER SOCK,
RELOCATE AS NECESSARY
TEMPORARY FILTER SOCK,
RELOCATE AS NECESSARY
REPLACE PORTION OF CONCRETE SIDEWALK
REMOVE PORTION OF CONCRETE CURB
REDI-ROCK OR APPROVED EQUAL
CONCRETE BLOCK RETAINING WALL
60 LF 48" HIGH CHAIN LINK FENCE ANCHORED
TO CONCRETE BLOCK RETAINING WALL
CLEAR WITHIN LIMITS OF MULTI-USE PATH (SEE NOTES)
LOAM AND SEED ALL DISTURBED
VEGETATED AREAS (TYP)
REMOVE SEGMENT OF FENCE TO NEAREST POST.
MIN 2' CLEAR FROM PATH
CONCRETE SIDEWALK
REPAIR / REPLACE SEGMENT OF MISSING FENCE
TEMPORARY SILT FENCE, RELOCATE AS
NECESSARY, REMOVE ONCE ALL UPSTREAM
AREAS ARE STABILIZED
REMOVE EXISTING
BITUMINOUS CURB (TYP)
CB TYPE 'C'
TF=270.00
INV OUT=265.76 15" HDPE
INLET PROTECTION (TYP)
2' EARTH BERM WITH
WOOD CHIP MULCH (TYP)
REBUILD TYPE 'C' CB AS NEEDED. INSTALL NEW "TYPE C" TOP
INV IN (NE)=269.76 (15" RCP)
INV OUT (S)=269.26 (15" RCP)
RESET TOPS AND REPAIR EXISTING
DOUBLE CB AS NEEDED
TF=269.75
EX INV IN(N)=264.46 (15" RCP)
NEW INV IN(E)=264.46 (15" HDPE)
EX INV OUT=264.25 (15" RCP)
2' CURB TAPER AT
END OF CURB
2' CURB TAPER AT END OF
CONCRETE CURB (TYP)
SAWCUT EXISTING PAVEMENT (TYP)
NEW PAVEMENT TO MEET EXISTING FLUSH WITH NOT TRIPPING HAZARD
SAWCUT EXISTING PAVEMENT (TYP)
NEW PAVEMENT TO MEET EXISTING
FLUSH WITH NOT TRIPPING HAZARD
2' TRANSITION OF CONCRETE CURB FROM BITUMINOUS
CURB AT BEGINNING OF CONCRETE CURB
2' CURB TAPER AT BEGINNING
OF CONCRETE CURB
SAWCUT EXISTING PAVEMENT,
NEW PAVEMENT TO MEET
EXISTING FLUSH WITH NOT
TRIPPING HAZARD (TYP)
2' CURB TAPER AT END OF CONCRETE CURB (TYP)
CT DOT TYPE 1 CURB RAMP
WITH BOLT-ON DETECTABLE WARNING SURFACE
(DO NOT INSTALL PRESS-IN DWS)
271.00
271.08
' M
IN
T O C
UR
B
48' RADIUS CUL-DE-SAC
8" Ø DIP PIPE FOR DRAINAGE AS NEEDED (TYP AT LOW SPOTS)
SEE DETAIL FOR CROSS
SECTION A-A'
BASED ON ACTUAL PROPERTY LINE LOCATIONS
AS STAKED IN THE FIELD, ADJUST NEW
DRIVEWAY APRON LOCATIONS AND ASSOCIATED
CURBING TO MEET DESIGN INTENT. MAINTAIN
DESIGN RADIUS OF CUL-DE-SAC AND CURBING
WHEN MAKING ADJUSTMENTS. (TYP)
A
A'
TOPSOIL AND
SEED AREA TO
BE VEGETATED
TOPSOIL AND SEED AREA TO BE VEGETATED
M
AR
IN
A
CT
C O
LU
M
BU
S
AV
E
TEMPORARY SILT FENCE, RELOCATE
AS NECESSARY, REMOVE ONCE ALL
UPSTREAM AREAS ARE STABILIZED
Lo u re ir o En g in ee ri n g
A ss oc ia te s, I n c
N or th w es t
D ri ve ai nv ill e, C on ne ct ic ut
Ph on e:
-7
-6
Fa x:
-7
-8
A n
Em pl oy ee
O w ne d
C om pa ny w w w .L ou re ir o.
co m
ES
F
/1
8/
K A P
/1
8/
V
C T\
M
ER
ID
EN
\C O
LU
M
B U
S A
V E-
0\
D W
G S \C
IV
IL
\S
IT
E
LA
YO
U
T.
D
S
IT
E
LA
YO
U T
S av ed
6/
/2
2:
P
M b y
TC
G R A M
M A
TI
C O
Pa pe r
S iz e:
4" x te d:
/1 8/
:1
PM
PR
EP
A R
ED
F O
R
DRAWING
D R A W
N B
Y D
A
TE
A
PP
R O
V
ED
B Y
S C A
LE
C O
M M
N
O
D A
TE
S
TA
M P
SHEET
NO.
NO. OF
SHEETS
Lo ur ei ro
D
ES
C R
IP
TI
O
N O
F R
EV
IS
IO
N R
EV
D
A
TE
A
PP
R
C-1
1P
L5 .0
3 5
S
IT
E
LA
Y O
U T
P
LA
N
N
EW
M U
LT
I-
U S
E P
A
TH
A N
D C
U L-
D E-
S A
C
C O
LU
M
B U
S A
V E, M
ER
ID
EN
C
T
C
IT
Y O
F M
ER
ID
EN
E A
S T
M A
IN
S
T, M
ER
ID
EN
C T
Lo ur ei ro E ng in ee ri ng
A ss oc ia te s, I nc
A ll
R ig ht s
R es er ve d
A s R ev is ed
1"
SCALE IN FEET
10 10 20 300
THE CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UTILITIES
IN THE FIELD BEFORE BEGINNING ANY EXCAVATION. CALL AT
LEAST 72 HOURS IN ADVANCE FROM ANYWHERE IN THE STATE
OF CONNECTICUT, "CALL BEFORE YOU DIG": 1-800-922-4455
LEGEND
PROPERTY LINE
STORMWATER INLET STRUCTURE
STORMWATER PIPE
GAS PIPE
MAJOR CONTOUR
MINOR CONTOUR
LIMITS OF WORK
STONE WALKING PATH
NEW FULL DEPTH BITUMINOUS
CONCRETE PAVEMENT
SITE PLAN NOTES:
1. MARK ALL TREES GREATER THAN 10-INCHES DBH THAT ARE TO BE REMOVED FOR
CONSTRUCTION AND PROVIDE 10 BUSINESS DAY MINIMUM ADVANCED NOTICE TO
CITY OF MERIDEN PARKS DEPARTMENT. DO NOT CUT ANY TREES GREATER THAN
10-INCHES DBH WITHOUT APPROVAL. REVIEW PROPOSED TRAIL LOCATION AND
MARKED TREES WITH CITY OF MERIDEN AND ADJUST TRAIL ALIGNMENT, IF
REQUESTED, TO AVOID TREES DESIRED TO REMAIN.
2. CONTRACTOR SHALL NOTIFY “CALL BEFORE YOU DIG” (1-800-922-4455) AND VERIFY
UTILITY MARK-OUT WITH THE CITY OF MERIDEN PRIOR TO THE INITIATION OF ANY
SITE DISTURBANCE.
3. THE CONTRACTOR IS SOLELY RESPONSIBLE FOR VERIFICATION OF THE LOCATION
AND NATURE OF ALL SUBSURFACE UTILITIES AT THE PROJECT WHICH MAY BE
AFFECTED BY THE WORK. COORDINATE WITH RESPECTIVE UTILITY OWNERS AND
PERFORM VERIFICATION OF TYPE, LOCATION AND INVERTS AS REQUIRED.
4. THE CONTRACTOR SHALL NOTIFY THE ENGINEER OF ANY AND ALL DISCREPANCIES
BETWEEN EXISTING CONDITIONS AND THE CONTRACT DOCUMENTS BEFORE
PROCEEDING WITH THAT PORTION OF THE WORK.
5. THE LOCATIONS OF EXISTING SITE FEATURES AS SHOWN HAVE BEEN OBTAINED
FROM MAPS, SURVEYS, FIELD INSPECTIONS, AND OTHER AVAILABLE INFORMATION.
THEY MUST BE CONSIDERED APPROXIMATE BOTH TO LOCATION, SIZE, AND AS-BUILT
CONDITION AND ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THE
CONTRACTOR IS SOLELY RESPONSIBLE FOR DETERMINING ACTUAL FIELD
CONDITIONS.
6. ENGAGE A CONNECTICUT-LICENSED LAND SURVEYOR TO PERFORM LAND-SURVEYING
SERVICES REQUIRED, INCLUDING, BUT NOT LIMITED TO VERIFICATION AND LAYOUT
OF PROPOSED IMPROVEMENTS, DIMENSIONS, AND ELEVATIONS. REPORT
DISCREPANCIES TO THE ENGINEER.
7. MAINTAIN ACCESS TO RESIDENTIAL PROPERTIES AT ALL TIMES. IF ACCESS TO A
RESIDENTIAL PROPERTY WILL BE AFFECTED AT ANY TIME DURING CONSTRUCTION,
PROVIDE THE CITY WITH 3 BUSINESS DAY'S ADVANCED NOTICE AND DETAIL THE
NATURE OF THE PROPOSED ACTIVITY.
8. DURING SITE DEMOLITION, PAVEMENT REMOVAL, OR PAVEMENT RECLAIM
OPERATIONS, PROTECT ALL ADJACENT CURBING, SIDEWALKS, RAMPS, ABOVE-GRADE
AND BELOW-GRADE UTILITIES, DRAINAGE STRUCTURES, LIGHT BASES, AND OTHER
IMPROVEMENTS POTENTIALLY AFFECTED BY THE WORK. CLEARLY DELINEATE THE
LIMITS OF WORK AND MARK, BARRICADE, OR OTHERWISE IDENTIFY THOSE
IMPROVEMENTS THAT ARE TO BE PROTECTED AND/OR AVOIDED. ANY IMPROVEMENT
WHICH IS DAMAGED SHALL BE REPAIRED OR REPLACED IN-KIND TO THE OWNER'S
SATISFACTION.
9. PROVIDE CLEAN SAW-CUT AT THE LIMITS OF BITUMINOUS OR CONCRETE PAVEMENT
DEMOLITION. FOR CONCRETE SIDEWALKS, THE LIMIT OF DEMOLITION SHALL BE AT
THE NEAREST CONSTRUCTION OR CONTROL JOINT AT OR BEYOND THE REQUIRED
LIMIT OF DEMOLITION.
10. PROVIDE PAVEMENT SAW-CUT AT THE EDGE OF EACH PAVEMENT REMOVAL OR
PAVEMENT RECLAIM AREA TO ESTABLISH A CLEAN EDGE WHERE NEW WORK WILL
MEET EXISTING PAVEMENT. SAW CUT SHALL BE A MINIMUM OF 12 INCHES FROM
EDGE OF PAVEMENT REMOVAL OR PAVEMENT RECLAIM AREA.
11. CURB RAMPS SHALL COMPLY WITH CT DOT STANDARDS. GRADING CONTOURS AND
SPOT GRADES INDICATE DESIGN INTENT. CONFIRM THE GRADE AND SLOPE OF NEW
WORK BASED ON ACTUAL FIELD CONDITIONS BEFORE PROCEEDING WITH
INSTALLATION. BRING ALL DISCREPANCIES TO THE ATTENTION OF THE ENGINEER
BEFORE PROCEEDING.
12. UNLESS OTHERWISE INDICATED, ALL DISTURBED AREAS SHALL BE RESTORED WITH
SIX (6) INCHES OF LOAM, SEEDED, FERTILIZED, AND MULCHED. PROVIDE
ADDITIONAL EROSION CONTROLS AS REQUIRED. BLEND RESTORED AREAS INTO
ADJACENT UNDISTURBED AREAS.
MASK MASKEROSION AND SEDIMENTATION (E&S) CONTROL PLAN:
A. GENERAL NOTES
1. THE EROSION AND SEDIMENT CONTROL MEASURES SPECIFIED HEREON ARE THE
MINIMUM REQUIREMENTS FOR E&S CONTROL AND ARE SHOWN IN GENERAL SIZE
AND LOCATION ONLY. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING
THAT ALL E&S CONTROL MEASURES ARE CONFIGURED AND CONSTRUCTED IN A
MANNER THAT WILL MINIMIZE EROSION OF SOILS AND PREVENT THE TRANSPORT
OF SEDIMENTS AND OTHER POLLUTANTS TO ANY RESOURCE AREAS. PROVIDE
ADDITIONAL E&S MEASURES AS REQUIRED TO CONTROL EROSION AND
SILTATION THROUGHOUT THE DURATION OF THE CONSTRUCTION AS
CONDITIONS DICTATE AND/OR AS DIRECTED BY THE OWNER OR THE ENGINEER.
2. MONITOR AND INSPECT ALL E&S MEASURES IN AN ONGOING MANNER
THROUGHOUT THE WORK AND TAKE CORRECTIVE MEASURES, AS REQUIRED, TO
MINIMIZE EROSION OF SOILS AND PREVENT THE TRANSPORT OF SEDIMENTS AND
OTHER POLLUTANTS TO ANY RESOURCE AREAS.
3. ANY STOCKPILED MATERIAL SHALL BE SUBJECT TO EROSION CONTROL MEASURES
THAT INCLUDE A MINIMUM OF SILT FENCE OR HAY BALE BARRIER COVER
STOCKPILES IF SIGNIFICANT RAINFALL IS PREDICTED.
4. ANY EROSION AND SEDIMENTATION MEASURE IMPLEMENTED BEYOND THAT
SHOWN HEREON SHALL CONFORM TO APPLICABLE SECTIONS OF THE STATE OF
CONNECTICUT'S “CONNECTICUT GUIDELINES FOR SOIL EROSION AND SEDIMENT
CONTROL", EFFECTIVE DATE MARCH 30, 2024.
B. NARRATIVE
1. THE FOLLOWING EROSION AND SEDIMENTATION CONTROL (E&S) NOTES APPLY
TO THIS PROJECT. THE PROJECT INCLUDES CLEARING A PATH FOR
CONSTRUCTION OF AN 8' WIDE STONE MULTI-USE TRAIL AND CUL-DE-SAC. SITE
IMPROVEMENTS WILL INCLUDE REGRADING TO ACCOMMODATE THE NEW PATH
AND CUL-DE-SAC, NEW STORMWATER COLLECTION, PEDESTRIAN
ACCESS/SIDEWALKS, LANDSCAPING, AND APPURTENANT SITE IMPROVEMENTS.
2. SOILS THROUGHOUT THE SITE CONSIST PRIMARILY OF LUDLOW SILT LOAM AND
PARTLY WETHERSFIELD LOAM.
3. THE PROJECT WILL REQUIRE DISTURBANCE OF APPROXIMATELY 0.58 ACRES OF
LAND AREA.
C. SCHEDULE OF OPERATIONS
1. CONDUCT A PRE-CONSTRUCTION MEETING WITH THE TOWN, ENGINEER, AND
CONTRACTOR(S) PRIOR TO ANY CONSTRUCTION ACTIVITY.
2. INSTALL CONSTRUCTION ENTRANCE(S); INSTALL CATCH BASIN INLET
PROTECTION; AND INSTALL SILT FENCE AND WATTLE PERIMETER E&S CONTROLS.
3. FOLLOWING THE ENGINEER’S APPROVAL OF INSTALLED EROSION AND
SEDIMENTATION CONTROLS, COMMENCE CONSTRUCTION OPERATIONS.
A. COMPLETE REQUIRED CLEARING AND GRUBBING. CHIP BRUSH AND
STOCKPILE CHIPS FOR FUTURE USE IN DESIGNATED AREAS FOR EROSION
CONTROL OR REMOVE OFF-SITE. NO STUMP DISPOSAL ON SITE IS
PERMITTED.
B. REMOVE AND STOCKPILE ALL TOPSOIL AND PROVIDE EROSION CONTROL
MEASURES THAT INCLUDE A MINIMUM OF SILT FENCE AND WATTLE. SEED
STOCKPILE WITH PERENNIAL RYEGRASS AT A RATE OF 40 POUNDS PER ACRE
AND MULCH WITH HAY OR STRAW. IF OUTSIDE THESE PERIODS, AREAS
SHALL BE STABILIZED WITH STRAW OR HAY MULCHING AT A RATE OF 90
POUNDS PER 1000 SQUARE FEET.
C. CONDUCT EARTHWORK OPERATIONS TO ACHIEVE REQUIRED SUBGRADES
FOR PAVEMENT AND OTHER SITE IMPROVEMENTS.
D. NO ROCK CRUSHING AND/OR BLASTING IS PROPOSED.
E. INSTALL SUBGRADE UTILITIES AND OTHER SUBGRADE IMPROVEMENTS.
F. INSTALL STORMWATER MANAGEMENT SYSTEMS IN ACCORDANCE WITH THE
PLANS. WHERE CONNECTIONS ARE MADE TO EXISTING SYSTEMS, ENSURE
NO SILT LADEN STORMWATER ENTERS THE SYSTEM UNTIL FINAL
STABILIZATION. INSTALL INLET PROTECTION IMMEDIATELY AFTER CATCH
BASIN INSTALLATION.
G. PATH AND CUL-DE-SAC CONSTRUCTION MAY PROGRESS CONCURRENTLY.
H. FOLLOWING COMPLETION OF SUBGRADE CONSTRUCTION, PROVIDE FINAL
BACKFILL, GRADING, AND PLACEMENT OF BASE MATERIALS TO
ACCOMMODATE SURFICIAL IMPROVEMENTS.
I. INSTALL SURFICIAL IMPROVEMENTS SUCH AS CURBS, WALKS, RAMPS,
PAVEMENTS, ETC.
J. ALL DISTURBED AREAS NOT COVERED BY SURFICIAL IMPROVEMENTS,
PAVEMENTS, SIDWALK, AND SIMILAR IMPROVEMENTS SHALL BE FINE
GRADED AND STABILIZED WITH A MINIMUM OF 4-INCHES OF TOPSOIL
SEEDED. APPLY COOL WEATHER SEED MIX.
K. AT THE CONCLUSION OF CONSTRUCTION, COMPLETE THE INSTALLATION OF
POST-CONSTRUCTION SITE STABILIZATION MEASURES.
D. EROSION AND SEDIMENTATION CONTROL PROCEDURES
1. ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL CONFORM TO
APPLICABLE PLANS HEREIN AND THE STATE OF CONNECTICUT’S “CONNECTICUT
GUIDELINES FOR SOIL EROSION AND SEDIMENT CONTROL", EFFECTIVE DATE
MARCH 30, 2024.
2. DEVIATIONS FROM THE EROSION AND SEDIMENTATION CONTROL PLAN SHALL BE
COORDINATED WITH THE ENGINEER. DEVIATIONS FROM THE EROSION AND
SEDIMENTATION CONTROL PLAN MAY BE SUBJECT TO CITY FOR APPROVAL.
3. DO NOT PROCEED WITH THE WORK UNTIL ALL EROSION AND SEDIMENTATION
CONTROL MEASURES CONTROL MEASURES DOWNSTREAM OF THE WORK ARE IN
PLACE. ACCOMMODATE ANY INSPECTIONS BY THE CITY
4. MONITOR AND INSPECT ALL EROSION AND SEDIMENTATION CONTROL MEASURES
IN AN ONGOING MANNER THROUGHOUT THE WORK. TAKE CORRECTIVE
MEASURES, AS REQUIRED, TO MINIMIZE EROSION OF SOILS AND PREVENT THE
TRANSPORT OF SEDIMENTS AND OTHER POLLUTANTS TO ANY RESOURCE AREAS.
NO RUNOFF SHALL BE ALLOWED TO ENTER ANY STORMWATER SYSTEM OR EXIT
THE SITE PRIOR TO TREATMENT FOR SEDIMENT REMOVAL.
5. ANY STOCKPILED MATERIAL SHALL BE SUBJECT TO EROSION CONTROL MEASURES
THAT INCLUDE A MINIMUM OF SILT FENCE OR WATTLE BARRIER; COVER
STOCKPILES IF SIGNIFICANT RAINFALL IS PREDICTED.
6. TEMPORARY SEEDING – PROVIDE TEMPORARY SEEDING ON ALL EXPOSED SOIL
AREAS WHERE WORK WILL BE SUSPENDED FOR LONGER THAN 30 DAYS. APPLY
SEED AND MULCH WITHIN THE FIRST 7 DAYS OF SUSPENDING WORK. WHEN
SEEDING IS NOT POSSIBLE DUE TO SEASONAL WEATHER CONDITIONS OR OTHER
FACTORS, PROVIDE TEMPORARY STRUCTURAL SOIL PROTECTION SUCH AS
MULCH, WOODCHIPS, EROSION CONTROL MATTING, OR COMPOST.
7. PERMANENT SEEDING - COMPLETE PERMANENT SEEDING BETWEEN APRIL 15TH
THROUGH JUNE 15TH AND AUGUST 15TH THROUGH SEPTEMBER 15TH. APPLY
PERMANENT SOIL STABILIZATION MEASURES TO ALL GRADED AREAS WITHIN 7
DAYS OF ESTABLISHING FINAL GRADE.
8. ALL TEMPORARY SLOPES IN EXCESS OF 3 (HORIZONTAL) TO 1 (VERTICAL) SHALL
BE STABILIZED WITH EROSION CONTROL MATTING OR APPROVED EQUIVALENT.
9. THE CONTRACTOR SHALL MAINTAIN A CLEAN CONSTRUCTION SITE AND SHALL
NOT ALLOW THE ACCUMULATION OF RUBBISH OR CONSTRUCTION DEBRIS. ALL
TRASH SHALL BE CLEANED ON A DAILY BASIS AND THE SITE SHALL BE LEFT IN A
NEAT CONDITION AT THE END OF EACH WORK DAY.
10. SWEEP ADJACENT ROADWAYS IF MUD OR SOIL IS TRACKED ON TO THEM, OR AS
DIRECTED BY THE ENGINEER. SHOULD THE CONSTRUCTION ENTRANCE FAIL TO
PREVENT THE TRACKING OF SOILS OR SEDIMENT OFF OF THE PROJECT SITE, A
WASHING RACK SHALL BE INSTALLED ALONG WITH APPROPRIATE MEASURES TO
COLLECT RESULTING WASTEWATER.
11. CATCH BASIN INLET PROTECTION SHALL BE INSTALLED AND CLEANED/CHANGED
PER THE MANUFACTURER’S RECOMMENDATIONS. UNITS SHALL BE INSTALLED
COMPLETELY AROUND INLETS OF EXISTING AND PROPOSED DRAINAGE
STRUCTURES SUCH THAT NO RUNOFF IS ALLOWED TO ENTER DRAINAGE SYSTEMS
WITHOUT FILTERING THROUGH THE DEVICE. PRIOR TO A FORECAST RAINSTORM
EVENT AND FOLLOWING ANY RAINSTORM EVENT, ALL CATCH BASIN INLET
PROTECTION SHALL BE INSPECTED FOR SEDIMENT AND DEBRIS AND CLEANED OR
REPLACED AS REQUIRED TO ENSURE FREE FLOW OF STORMWATER.
12. TAKE ALL NECESSARY PRECAUTIONS TO AVOID THE SPILLAGE OF FUEL OR OTHER
POLLUTANTS AND ADHERE TO ALL APPLICABLE POLICIES AND REGULATIONS
RELATED TO SPILL PREVENTION, CONTROL, AND RESPONSE.
13. REMOVE TEMPORARY CONTROL MEASURES ONLY AFTER FINAL SITE
STABILIZATION HAS BEEN ACHIEVED.
DUST CONTROL NOTES:
1. PROVIDE BEST MANAGEMENT PRACTICES TO CONTROL THE GENERATION OF FUGITIVE DUST
DURING ALL PHASES OF THE WORK. PRIOR TO THE INITIATION OF CONSTRUCTION ACTIVITIES, IDENTIFY ALL POTENTIAL FUGITIVE DUST SOURCES AND MEANS AND METHODS FOR
CONTROL.
2. IMPLEMENT FUGITIVE DUST MONITORING IN ACCORDANCE WITH APPROVED PLANS AND
PROTOCOLS. MAINTAIN DUST MONITORING DURING ALL ACTIVITIES THAT HAVE THE
POTENTIAL TO GENERATE FUGITIVE DUST.
3. CONSTRUCTION SEQUENCING SHALL BE ORGANIZED AND CONDUCTED IN A MANNER TO
LEAVE EXISTING PAVEMENT OR GROUND COVERINGS IN PLACE UNTIL JUST PRIOR TO EARTH
EXCAVATION.
4. SWEEP PAVED SURFACES WHERE SOIL MATERIALS HAVE BEEN DEPOSITED TO PREVENT IT
FROM BECOMING AIRBORNE VIA WIND OR VEHICLE MOVEMENTS.
5. UTILIZE DUST CONTROL/SUPPRESSION MEASURES THAT INCLUDE, BUT ARE NOT LIMITED TO, THE FOLLOWING:
A. MINIMIZE DISTURBED AREAS TO THE EXTENT POSSIBLE.
B. AVOID DUST-GENERATING WORK ON HIGH WIND DAYS.
C. STABILIZE DISTURBED AREAS AS SOON AS PRACTICABLE.
D. APPLY WATER DURING ACTIVE DEMOLITION ACTIVITIES IN FINE SPRAY OR MIST. DO NOT
APPLY AT RATES THAT WILL CAUSE PONDING OR RUNOFF.
E. APPLY WATER IN FINE SPRAY OR MIST TO THE EXTENT TO DAMPEN EXPOSED SOILS. DO
NOT APPLY AT RATES THAT CAUSE OVER SATURATION OF SOILS, PONDING OR RUNOFF.
F. APPLY CALCIUM CHLORIDE, ASTM D98, ONLY AT LOCATIONS THAT WILL NOT BE
ADVERSELY AFFECTED BY THE APPLICATION AT A UNIFORM RATE AS INDICATED BY THE
MANUFACTURER’S INSTRUCTIONS.
G. APPLY SOIL TACKIFIERS SUCH AS ACRYLIC CONTROL POLYMERS, SYNTHETIC
COPOLYMER DISPERSIONS, BOTANICAL SOLUTIONS INDIVIDUALLY OR IN CONCERT WITH
MULCHES.
H. STOCKPILES: DURING HIGH WIND CONDITIONS, APPLY WATER, SOIL TACKIFIERS OR
COVERINGS TO CONTROL THE GENERATION OF WIND-DERIVED DUST.
6. NO ASPHALT OR PETROLEUM-BASED PRODUCTS MAY BE UTILIZED FOR DUST SUPPRESSION.
7. MONITOR AND MANAGE DUST CONTROL/SUPPRESSION MEASURES AT ALL TIMES AND ADAPT
SUCH MEASURES TO EVOLVING SITE CONDITIONS THROUGHOUT THE PROGRESS OF THE
WORK.
8' u re ir o En g in ee ri n g
A ss oc ia te s, I n c
N or th w es t
D ai nv ill e, C on ne ct ic ut
Ph on e:
-7
-6
Fa x:
-7
-8
A n
Em pl oy ee
O w ne d
C om w w .L ou re ir o.
co m
ES
F
/1
8/
K A P
/1
8/
V
C T\
M
ER
ID
EN
\C O
LU
M
B U
S A
V E-
0\
D W
G S \C
IV
IL
\D
ET
A
IL
S .D
S
IT
E
S av ed
6/
/2
2:
P
M b y
TC
G R A M
M A
TI
r
S iz e:
4" x te d:
/1 8/
:1
PM
PR
EP
A R
ED
F O
R
DRAWING
D R A W
N B
Y D
A
TE
A
PP
R O
V
ED
B Y
S C A
LE
C O
M M
N
O
D A
TE
S
TA
M P
SHEET
NO.
NO. OF
SHEETS
Lo ur ei ro
D
ES
C R
IP
TI
O
N O
F R
EV
IS
IO
N R
EV
D
A
TE
A
PP
R
C-2
1P
L5 .0
4 5
D
ET
A
IL
S
N
EW
M U
LT
I-
U S
E P
A
TH
A N
D C
U L-
D E-
S A
C
C O
LU
M
B U
S A
V E, M
ER
ID
EN
C
T
C
IT
Y O
F M
ER
ID
EN
E A
S T
M A
IN
S
T, M
ER
ID
EN
C T ur ei ro E ng in ee ri ng
A ss oc ia te s, I nc
A ll
R ig ht s
R es er ve d
A s R ev is ed
N O
T
TO
S C A
LE
STREET CROSS SECTION
(CITY OF MERIDEN ENGINEERING DETAIL)
NOT TO SCALE
PAVEMENT RESTORATION DETAIL
(CITY OF MERIDEN ENGINEERING DETAIL)
NOT TO SCALE
POURED IN PLACE CONCRETE CURB DETAIL
(CITY OF MERIDEN ENGINEERING DETAIL)
NOT TO SCALE
MULTI-USE TRAIL CROSS-SECTION
NOT TO SCALE
4" Ø REMOVABLE BOLLARD
NOT TO SCALE
NOTE:
INSTALLATION TO BE COMPLETED IN ACCORDANCE WITH MANUFACTURER'S
SPECIFICATIONS.
ELEVATION VIEW TOP VIEW, COVER CLOSED
LOCK PROVIDED BY CITY
24"
4" Ø STEEL BOLLARD
MATERIAL GRADATION:
STONE DUST:
CTDOT No. 8 STONE (M.01.02-2)
SQUARE MESH SIEVE % PASSING BY WEIGHT
1/2 INCH 100
3/8 INCH 85-100
No. 4 10-30 No. 8 0-10 No. 16 0-5
GRADED AGGREGATE BASE COURSE:
CTDOT GRANULAR FILL (M.02.01; GRADING "A" M.02.06)
SQUARE MESH SIEVE % PASSING BY WEIGHT
3 1/2 INCH 100
1 1/2 INCH 55-100
1/4 INCH 25-60
No. 10 15-45 No. 40 5-25 No. 100 0-10 No. 200 0-5
4'
FINISH
GRADE
4' CHAIN LINK FENCE NOTES:
1. INSTALL ALL FENCE FABRIC ON PATH SIDE OF POSTS.
2. ALL CHAIN LINK FENCE SHALL BE GROUNDED PER CHAIN LINK MANUFACTURERS RECOMMENDATIONS.
3. FENCE FABRIC - GALVANIZED, PVC-COATED BLACK, ASTM F668.
4. POSTS - 2 7/8" SCH 40 TUBE, POWDER COATED BLACK. POST LENGTH BASED ON FENCE HEIGHT AND MOUNTING CONFIGURATION.
5. ALL HARDWARE AND FITTINGS TO BE GALVANIZED AND POWDER COATED BLACK.
6. POST ANCHORAGE TO TOP OF WALL – OPTION 1: CORE AND GROUT. CORE 8-INCH-DEEP (MIN) HOLE, 1/2 INCH (MIN) LARGER THAN POST DIAMETER
AND SECURE POST WITH NON-SHRINK, NON-METALLIC GROUT, ASTM C1107. OPTION 2: SURFACE MOUNT. PROVIDE POSTS WITH SHOP WELDED 4 x 4 x 1/4 INCH STEEL PLATE, ASTM A36, WITH FOUR HOLES AT CORNERS, FULL ASSEMBLY POWDER COATED AFTER FABRICATION. MOUNT TO WALL ON NEOPRENE PAD, AASHTO M 251 UNDER PLATE SIZED TO MATCH, WITH 3/8 X 4 INCH STAINLESS STEEL WEDGE ANCHORS x 4. INCLUDE STAINLESS STEEL WASHER AND NUT. GRIND EXPOSED THREADS SMOOTH AND PEEN BOLT FOR TAMPER-PROOF ASSEMBLY.
1-7/8 INCH
TOP RAIL
POST CAP
STRETCHER BAR
(END POSTS ONLY)
STRETCHER BAR BANDS
12" O.C.
2" MESH, 9 GAUGE,
TOP AND BOTTOM
SELVAGE KNUCKLED
1-7/8 INCH
BOTTOM RAIL
FASTENERS 18" O.C. AT
ALL HORIZONTAL RAILS
FASTENERS 18" O.C.
AT LINE POSTS
4' CHAIN-LINK FENCE
NOT TO SCALE
POSTS ANCHORAGE TO WALL
(SEE NOTE 6)
A-A' TYPICAL SECTION A-A'
NOT TO SCALE
NOTES:
1. BLOCK TYPE, SIZE, AND CONFIGURATION WILL VARY BASED ON SITE-SPECIFIC CONDITIONS AND WALL HEIGHT.
2. INSTALLATION TO BE COMPLETED IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATIONS.
3. MAKE ADJUSTMENTS TO WALL INSTALLATION IN CONCERT WITH THE ENGINEER BASED ON ACTUAL FIELD
CONDITIONS.
NON-WOVEN GEOTEXTILE FABRIC
EX
PO
S
ED
W A
LL
H
EI
G H
T V A R
IE
S
MULTI-USE TRAIL SURFACE (SEE CROSS SECTION)
LEVELING PAD, CTDOT M.01.02 GRADING No. 3
PERVIOUS STRUCTURE BACKFILL, CTDOT M.02.05
CHAIN LINK FENCE POST
PROPERTY LINE
HEAVYWEIGHT INTERLOCKING
CONCRETE BLOCK GRAVITY WALL,
MINIMUM 2,200 LB BLOCK WEIGHT
8"
COLOR: YELLOW
ALL POSTS
6' SPACING (TYP)
FULL ADHESIVE BOND ON ALL CAP STONES
ENSURE FIRM STABLE SUBGRADE PRIOR TO INSTALLING LEVELING PAD.
REPLACE UNSTABLE, SOFT, OR YIELDING SOILS WITH LEVELING PAD MATERIAL.
RETAINED SOIL
u re ir o En g in ee ri n g
A ss oc ia te s, I n c
N or th w es t
D ai nv ill e, C on ne ct ic ut
Ph on e:
-7
-6
Fa x:
-7
-8
A n
Em pl oy ee
O w ne d
C om w w .L ou re ir o.
co m
ES
F
/1
8/
K A P
/1
8/
V
C T\
M
ER
ID
EN
\C O
LU
M
B U
S A
V E-
0\
D W
G S \C
IV
IL
\D
ET
A
IL
S .D
D
R A
IN
A G
E S av ed
6/
/2
2:
P M b y
TC
G
R A M
M A
TI
r
S iz e:
4" x te d:
/1 8/
:1
PM
PR
EP
A R
ED
F O
R
DRAWING
D R A W
N B
Y D
A
TE
A
PP
R O
V
ED
B Y
S C A
LE
C O
M M
N
O
D A
TE
S
TA
M P
SHEET
NO.
NO. OF
SHEETS
Lo ur ei ro
D
ES
C R
IP
TI
O
N O
F R
EV
IS
IO
N R
EV
D
A
TE
A
PP
R
C-3
1P
L5 .0
5 5
D
ET
A
IL
S
N
EW
M U
LT
I-
U S
E P
A
TH
A N
D C
U L-
D E-
S A
C
C O
LU
M
B U
S A
V E, M
ER
ID
EN
C
T
C
IT
Y O
F M
ER
ID
EN
E A
S T
M A
IN
S
T, M
ER
ID
EN
C T ur ei ro E ng in ee ri ng
A ss oc ia te s, I nc
A ll
R ig ht s
R es er ve d
A s R ev is ed
N O
T
TO
S C A
LE
TYPICAL TRENCH SECTION
(CITY OF MERIDEN ENGINEERING DETAIL)
NOT TO SCALE
CATCH BASIN FRAMES AND GRATES
NOT TO SCALE
SILT FENCE DETAIL
NOT TO SCALE
NOTES:
1. ALL SILT FENCES SHALL BE INSPECTED DAILY BY THE CONTRACTOR AND CLEANED & MAINTAINED A MINIMUM OF ONCE
PER MONTH OR WITHIN 48 HOURS OF A SIGNIFICANT STORM EVENT.
2. THE FILTER CLOTH SHALL BE CLEANED IN A MANNER WHICH ENSURES THAT ALL SEDIMENT COLLECTED REMAINS
ON-SITE.
3. ALL SILT FENCING & ALTERNATIVE FILTERS SHALL BE FURNISHED, INSTALLED AND MAINTAINED IN ACCORDANCE WITH 2002 CT GUIDELINES FOR SOIL EROSION AND SEDIMENT CONTROLS, AS AMENDED AND PER MANUFACTURERS
INSTRUCTIONS.
FLOW
2" WOOD POST
(POST TO BE ANGLED 10° UPSLOPE
FOR STABILITY & SELF CLEANING)
SILT FENCE
FINISH GRADE
12"
6"
COMPACTED BACKFILL
MAX
HEIGHT
30"
COMPOST / MULCH SOCK NOTES:
1. A TEMPORARY SEDIMENT BARRIER CONSISTING OF A MULCH-FILLED TUBE OF FLEXIBLE
NETTING MATERIAL. COMMON TYPES OF FILTER SOCKS INCLUDE STRAW WATTLES,
COMPOST FILTER SOCKS, AND FIBER ROLLS.
2. TRENCHING IS NOT REQUIRED. COMPOST FILTER SOCK SHALL BE PLACED OVER THE
TOP OF GROUND. HEAVY VEGETATION SHALL BE CUT DOWN OR REMOVED, AND
EXTREMELY UNEVEN SURFACES SHALL BE GRADED TO ENSURE THE COMPOST FILTER
SOCK UNIFORMLY CONTACTS THE GROUND.
3. THE ENDS OF THE FILTER SOCK SHALL BE DIRECTED UPSLOPE, TO A HEIGHT AT LEAST
THE HEIGHT OF THE FILTER SOCK, TO PREVENT STORMWATER FROM FLOWING
AROUND THE END OF THE SOCK.
4. ALL COMPOST MULCH SOCKS SHALL BE FURNISHED, INSTALLED AND MAINTAINED IN
ACCORDANCE WITH MANUFACTURERS RECOMMENDATIONS AND WITH THE 2024 CT
GUIDELINES FOR SOIL EROSION AND SEDIMENT CONTROL, AS AMENDED.
5. COMPOST FILTER SOCK MATERIALS AND COMPOST MATERIALS SHALL BE IN
ACCORDANCE WITH AASHTO DESIGNATION: MP 9-06. COMPOST MATERIAL SHALL
MEET ALL APPLICABLE FEDERAL AND STATE REGULATIONS.
6. FILTER MEDIA TO BE DISPERSED ON SITE, AS DETERMINED BY ENGINEER. FILTER
SOCK NETTING MAY BE CUT OPEN AND MULCH SPREAD OUT OR USED ELSEWHERE.
STRAW WATTLES AND FIBER ROLLS ARE USUALLY LEFT ALONG SLOPES AND ARE
BIODEGRADABLE.
MAINTENANCE
7. INSPECT FILTER SOCKS AT LEAST ONCE A WEEK AND WITHIN 24 HOURS OF THE END
OF A STORM THATGENERATES A DISCHARGE.
8. SEDIMENT REMOVAL AND DISPOSAL ARE STILL REQUIRED IN AREAS WHERE SEDIMENT
ACCUMULATES TO AT LEAST ONE-HALF THE DISTANCE BETWEEN THE TOP OF THE
COMPOST FILTER SOCK AND THE GROUNDSURFACE.
9. REMOVE SEDIMENT THAT BUILDS UP BEHIND THE SOCK BEFORE IT INTERFERES WITH
THEFUNCTIONALITY OF THE SOCK. DEPOSIT THE REMOVED SEDIMENT WITHIN THE
PROJECT LIMITS ORDISPOSE OF LEGALLY SO THAT THE SEDIMENT IS NOT SUBJECT TO
EROSION BY WIND OR BY WATER.
10. REPAIR OR REPLACE SPLIT, TORN, OR UNRAVELING SOCKS. REPLACE BROKEN OR
SPLIT STAKES. SAGGINGOR SLUMPING COMPOST SOCKS MUST BE REPAIRED WITH
ADDITIONAL STAKES OR REPLACED.
11. REPAIR OR REPLACE AT LOCATIONS WHERE RILLS AND OTHER EVIDENCE OF
CONCENTRATED RUNOFF HAVEOCCURRED BENEATH THE SOCKS
12. IF THE FILTER SOCK WAS OVERTOPPED DURING A STORM EVENT, THE OPERATOR
SHALL CONSIDER INSTALLING AN ADDITIONAL FILTER SOCK ON TOP OF THE
ORIGINAL, PLACING AN ADDITIONAL FILTER SOCK FURTHER UP THE SLOPE, OR USING
AN ADDITIONAL MEASURE IN CONJUNCTION WITH THE FILTER SOCK(S).
FILTER SOCK
NOT TO SCALE
FLOW
WORK AREA
WORK AREA
FLOW
PERVIOUS SURFACE DETAILS
PLAN SECTION
FILTER SOCK
1" SQ WOODEN STAKES PLACED MIN 10' OC
12 MIN12 MIN
FLOW
WORK AREA
FLOW
IMPERVIOUS SURFACE DETAILS
PLAN SECTION
FILTER SOCK
PAVEMENT OR
IMPERVIOUS
SURFACE
WORK AREA
FILTER SOCK
AREA TO BE
PROTECTED
AREA TO BE
PROTECTED
CONCRETE BLOCKS
OR SAND BAGS AS
NEEDED (MIN 10' OC)
AREA TO BE
PROTECTED
AREA TO BE
PROTECTED
NOTES:
1. MINIMUM CONCRETE COMPRESSIVE STRENGTH = 4,000 PSI.
2. CATCH BASIN TOPS SHALL CONFORM TO CTDOT STANDARD SPECIFICATION FORM 819 AND CTDOT STANDARD DETAIL
HW-507-07.
3. STEEL REINFORCEMENT SHALL CONFORM TO ASTM A615, GRADE 60 AND HAVE A MINIMUM CLEAR COVER OF 2".
4. FRAMES AND GRATES SHALL BE STEEL, GALVANIZED IN ACCORDANCE WITH CTDOT M.06.03.
5. ALL METAL UNITS SUBJECT TO MANUFACTURING TOLERANCES.
6. ONLY LOW HYDROGEN ELECTRODES SHALL BE USED.
7. DIMENSIONAL TOLERANCES MEY BE +/- 1
16".
8. ALL WELDING IN ACCORDANCE WITH CTDOT STANDARDS.
9. ALL BARS SHALL BE WELDED AT ALL INTERSECTIONS.
TOP VIEW
WELDED STUD ANCHOR DETAILS STEEL FRAME
BITUUMINIOUS CURB "BC" TYPE
BITUUMINIOUS CURB "BC" TYPE
CATCH BASIN GRATE
| Sheets and Views |
| 1 COVER SHEET |
| 2 EXISTING CONDITIONS |
| 3 SITE LAYOUT PLAN |
| 4 DETAILS - 1 |
| 5 DETAILS - 2 |
File details come from the government source that posted it. Updated .