Summary
This is a rebid specification and bidding document for rehabilitation work on the Mercer County Parking Garage at Market and Cooper Streets in Trenton, New Jersey, issued by the County of Mercer Department of Engineering. The primary work includes removing a portion of the existing overlay and protective membrane, performing repairs to concrete waffle slabs, and constructing a new membrane and overlay. The project will be awarded to a single prime contractor on a base bid with one additive alternate. The site visit is scheduled for October 8, 2026, at 10:00 A.M. at 209 South Broad Street, Trenton, NJ, though attendance is recommended but not mandatory. The deadline for submitting questions is October 8, 2026, at 12:00 P.M. via email to imaldonado@mercercounty.org or through the BidNet Direct Portal. Electronic sealed bids must be uploaded to BidNet Direct at https://www.bidnetdirect.com/new-jersey/mercercounty and will be opened publicly on October 16, 2026, at 11:30 A.M. Work shall commence within ten calendar days of receiving written Notice to Proceed and be substantially completed within 45 calendar days thereafter. Liquated damages of $2,000.00 per day may be assessed for contract violations or failure to perform.
All bids must be accompanied by a certified check, cashier's check, or bid bond equal to ten percent of the bid price but not exceeding $20,000.00, made payable to the County of Mercer. Bidders must also submit a Consent of Surety form confirming availability of Performance and Payment Bonds. The County of Mercer is exempt from sales and excise taxes; contractors must obtain applicable permits and licenses. Contractors must comply with the New Jersey Prevailing Wage Act and submit certified payroll records within ten days of wage payment through the New Jersey Wage Hub. All bidders and named subcontractors must be registered with the New Jersey Division of Revenue prior to bid submission. Contractors must provide three verifiable references for similar construction projects and shall comply with all federal, state, and local safety regulations, including submission of a written safety program for County approval at the preconstruction meeting. Payment will be made within 30 calendar days of bill receipt if work is approved and certified by the County's representative, with billing deemed approved after 20 days unless the County provides written notice of withholding.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
County of Mercer
McDade Administration Building, 640 South Broad Street, Third Floor, P.O. Box 8068, Trenton, NJ 08650-0068
SPECIFICATIONS FOR BID
SPECIAL PROVISIONS/SUPPLEMENTARY SPECIFICATIONS
FOR
REHABILITATION OF THE MERCER COUNTY PARKING GARAGE
AT MARKET AND COOPER STREETS
LOCATED IN
CITY OF TRENTON, MERCER COUNTY
Prepared By:
COUNT
ME
RC
ER
NEW JERSE
To Be Received On
October 16, 2026, at 11:30 А.M
County of Mercer, New Jersey Department of Engineering
Bo Basit A. Muzaffar, P.E., Mercer County Engineer New Jersey Professional Engineer
New Jersey License Number 24GE04281800
AB2026-33B
10/5/2022 Date
Table of Contents
REBID REHABILITATION OF THE MERCER COUNTY PARKING GARAGE
AT MARKET AND COOPER STREETS
DIVISION 00 - CONTRACT AND BIDDING DOCUMENTS
Advertisement and Notice to Bidders Section 1 – Introduction and General Information Section 2 – Instructions to Bidders and Statutory Requirements Appendix A – Bid Document Checklist and Forms Appendix B – Technical Specifications
INDEX
Division 01 Section 011000 - Summary Section 012100 - Allowances Section 012200 - Unit Prices Section 012300 - Alternates Section 012500 - Substitution Procedures Section 012600 - Contract Modification Procedures Section 012900 - Payment Procedures Section 013100 - Project Management and Coordination Section 013200 - Construction Progress Documentation Section 013233 - Photographic Documentation Section 013300 - Submittal Procedures Section 014000 - Quality Requirements Section 014200 - References Section 015000 - Temporary Facilities and Controls Section 016000 - Product Requirements Section 017700 - Closeout Procedures
Division 02 Section 024116 - Demolition
Division 03 Section 030130 - Concrete Repair and Reinforcement
Division 32 Section 321216 - Asphalt Paving
Appendix C – Drawings
Sheet Drawing Number Sheet Title
1 G-001 Title Sheet
2 S-001 General Notes, Legend and Abbreviations
3 S-101 Ceiling and Roof Plan
4 S-501 Sections and Details
ADVERTISEMENT AND NOTICE TO BIDDERS
Notice is hereby given that on October 16, 2026 at 11:30 A.M. (Prevailing time), electronically sealed bids will be opened and conducted in electronic platform in accord with N.J.A.C. 5:34-1 et. Seq., on BidNet Direct at https://www.bidnetdirect.com/new-jersey/mercercounty at which time and place the sealed bids will be opened publicly and read via live-stream by the Purchasing Agent in the Mercer County McDade Administration Building, 640 S outh Broad Street, Room 321 Third Floor, Trenton, New Jersey for:
AB2026-33B
REBID OF REHABILITATION OF THE MERCER COUNTY PARKING GARAGE AT MARKET AND COOPER
STREETS
NOTE:
It is the bidder’s responsibility to ensure that the bid package is uploaded through the BidNet Direct portal by the bid opening date and time. Bid responses received after the deadline established by the Department of Purchasing will not be accepted, regardless of the method of del ivery. B id documents may be obtained f rom the bid platform BidNet Di rect at https://www.bidnetdirect.com/new-jersey/mercercounty .
BID SUBMISSIONS:
Bids shall be electronically uploaded. NO physical bids shall be received, opened or honored. Please contact BidNet for any questions or assistance with electronic bid submission 1800-835-4603 Option 2.
BID OPENING INFORMATION
Webinar link/password for the live stream bid opening will be posted in a timely manner on the Mercer County Procurement website https://www.mercercounty.org/departments/purchasing/bidding-opportunities prior to the bid opening date.
During the bid opening process, the bidders will be announced as well as bid amounts. A bid review providing unit prices will not take place at the openings.
BID GUARANTEE
Bid proposals must be accompanied by a certified check, cashier's check, or bid bond in the amount of a ten percent (10%) of the bid price but not in excess of $20,000.00 and made payable to the County of Mercer. If bids are to be submitted electronically in accord with this notice, then the bidder shall submit a copy of the bid guarantee with electronic submittal, and mail (ensuring receipt PRIOR to electronic bid opening) the original to the Department of Purchasing, 640 S. Broad Street, Room 321, Trenton, New Jersey 08611. The bid guarantee may also be provided in certified check and cashier’s check in accord with provisions within general requirements of this bid.
Any Bid Addenda will be issued on the BidNet website https://www.bidnetdirect.com/new-jersey/mercercounty and processed in accordance with N.J.S.A. 40A:11-23(c)(2). All interested bidders should check the website from now through bid opening.
Bidders are required to comply with the requirements of N.J.S.A.10:5-31 et seq. and N.J.A.C. 17:27-1 et seq.
COUNTY OF MERCER, NEW JERSEY
Purchasing Department 609 989 6710
Release Specifications:
Site-Visit:
October 5, 2026 October 8, 2026 at 10:00 A.M. at at 209 South Broad Street, Trenton NJ, 08650
The site-visit is not a mandatory requirement, but it is highly recommended.
Deadline for all questions: October 8, 2026 at 12:00 P.M.
E-mail questions to: imaldonado@mercercounty.org or via the BidNet Direct Portal
QUESTIONS SUBMITTED AFTER THE DEADLINE SHALL HAVE NO BEARING ON THE PROJECT
Bid Opening: October 16, 2026 at 11:30 A.M
AB2026-33B
REBID OF REHABILITATION FOR THE MERCER COUNTY PARKING GARAGE AT MARKET AND COOPER STREETS
SECTION 1 – GENERAL INFORMATION
INTENT
The County of Mercer requests bids for Rehabilitation for the Mercer County Parking Garage at Market and Cooper Streets, located in the City of Trenton, Mercer County. The project will be constructed under a single prime contract and awarded to one contractor. There is a base bid and one (1) alternate.
SCOPE OF WORK
The PRIMARY WORK to be performed under this contract includes, but is not limited to:
• Remove a portion of the existing overlay and protective membrane
• Perform repairs to the concrete waffle slabs
• Construct a new membrane and overlay.
• The extent of the work is shown on the drawings and specifications.
Perform all work in accordance with the project documents issued and any addenda.
BASE BID
Refer to the technical specifications and drawings for the base bid and add alternate.
BRAND OR EQUIVALENT
All references to Product names in the specifications shall be interpreted as “or equal”.
EXPERIENCE
Bidders and subcontractors shall have similar project experience. Bidders must provide three (3) verifiable references for construction as the contractor with their bid response on form attached
SCHEDULE AND COMPLETION REQUIREMENTS
Project Substantial Completion: Work will commence within Ten (10) Calendar Days after receipt of written "Notice to Proceed" and be substantially completed within 45 calendar days from the receipt of the Notice to Proceed. Pursuant to N.J. S.A 40A:11-19, liquated damages in the amount of $2,000.00 may be assessed for the violation of any of the terms of the contract, the failure to perform the contract in accordance with its terms and conditions and/or terms and conditions of N.J.S.A 40A:11-1,et seq.
WARRANTIES
As specified in section 108.21 of the supplementary specifications.
ALLOWANCE
There is a general allowance. Refer to Bid Forms and Specifications.
NJ WORKPLACE ACCOUNTABILITY IN LABOR LIST (WALL)
Any business whose name appears on the WALL is prohibited from public contracting under N.J.S.A. 34:1A-1.16, the law establishing the WALL.
NEW JERSEY PREVAILING WAGE ACT AND PUBLIC WORKS CONTRACTOR REGISTRATION ACT
Bidders shall comply with and adhere to all requirements of the New Jersey Prevailing Wage Act and Public Works Contractor Registration Act. In accordance with N.J.S.A. 34:11-56.27 and 56.28 the County of Mercer may terminate work if workers are paid less than such prevailing wage.
In the event it is found that any worker, employed by the contractor or any subcontractor covered by said contract, has been paid a rate of wages less than the prevailing wage required to be paid by such contract, the public body, the lessee to whom the public body is leasing a property or premises or the lessor from whom the public body is leasing or will be leasing a property or premises may terminate the contractor's or subcontractor's right to proceed with the work, or such part of the work as to which there has been a failure to pay required wages and to prosecute the work to completion or otherwise.”
N.J.S.A. 34:11-56.27 requires a contractor submitting the lowest bid for a contract that is subject to the Prevailing Wage Act, if that bid is 10 percent or more lower than the next lowest bid, to certify to the public body that the prevailing wage rates required by the Act shall be paid. If the bidder does not provide the certification prior to the award of the contract, the public body shall award the contract to the next lowest responsible and responsive bidder.
CERTIFIED PAYROLLS
The contractor shall submit certified payroll records to the County Engineer within ten (10) days of the payment of wages and uploaded via the New Jersey Wage Hub https://njwages.nj.gov/.
The contractor is responsible for obtaining and submitting all subcontractors' certified payroll records within the aforementioned time period to the County designee. It is the contractor's responsibility to obtain any additional copies of the certified payroll form to be submitted by contacting the New Jersey Department of Labor and Workforce Development, Division of Workplace Standards.
NEW JERSEY BUSINESS REGISTRATION
Bidders and named subcontractors shall be registered through the New Jersey Division of Revenue, Department of the Treasury, at the time of or prior to the date for submission of bids. Prior to the contract award, a copy of the New Jersey Business Registration for the general contractor and any named Subcontractors must be provided.
RENTED EQUIPMENT OR PROVISION BY THE COUNTY
For rented equipment, an hourly rental rate will be used which will be determined by using the monthly rental rates taken from the current edition of the Rental Rate Blue Book for Construction Equipment and dividing it by 176. The contractor will be allowed 65 percent of the rental rate on contractor-owned equipment. The County reserves the right to provide equipment to the contractor.
PRE-CONSTRUCTION AND CONSTRUCTION MEETINGS
The contractor shall report to the County’s representative Engineering and or Architectural Firm or the County’s designee to deliver a project that meets the County’s objectives. The Contractor and construction team will report directly to the County’s representative Firm. A preconstruction meeting will be scheduled along with weekly or bi-weekly construction meetings or as decided upon by the A/E Firm. All communication shall be directed to the County’s Engineering and or Architectural Firm and all communication and minutes shall be memorialized and distributed.
PROMPT PAYMENT
In compliance with N.J.S.A. 2A:30A-1 et seq., the County of Mercer shall impose the following payment process:
The County of Mercer shall pay the submitted bill not more than 30 calendar days after the receipt of the bill by the Owner’s Representative if the contractor has performed in accordance with the contract and the work has been approved and certified by the Owner’s Representative. The billing shall be deemed “approved” and “certified” 20 calendar days after the owner’s representative receives it, unless the Owner’s Representative provides, before the end of the 20-day period, a written statement of the amount withheld and the reason for withholding payment.
SAFETY PROGRAM:
Observe all rules and regulations of the Federal, State, and local health officials, including regulations concerning construction safety and health standards. At the preconstruction meeting, submit to the County for approval a written safety program that meets or exceeds the minimum requirements of the Contract and applicable State or Federal regulations. Include at a minimum the following:
1. Description. Describe in detail how the safety program is implemented and monitored.
Provide guidelines for protecting personnel from hazards associated with project operations and activities. Establish the policies and procedures for safety practices that are necessary for the Work to be in compliance with the requirements of OSHA and other State and Federal regulatory agencies with jurisdiction, rules, regulations, standards, or guidelines in effect at the time the Work is in progress.
2. Certification, Responsibility, and Identification of Personnel. Identify the qualified safety professional responsible for developing the safety program and provide that person's qualifications for developing the safety program including, but not be limited to, education, training, certifications, and experience in developing this type of safety program. Provide a certification, executed by the qualified safety professional that developed the safety program, stating that the safety program complies with the rules, regulations, standards, and guidelines in effect at the time the Work is in progress, of OSHA, and other applicable Federal, State, and local regulatory agencies having jurisdiction.
Identify a safety officer and designate the on-site supervisory-level personnel responsible for implementing and monitoring the safety program until Acceptance and having the authority to take prompt corrective measures to eliminate hazards, including the authority to stop work. Include documentation of training provided to the on-site supervisory-level personnel. For work that requires a competent person as defined by OSHA, ensure that the person is capable of identifying existing and predictable hazards and has the authority to take prompt corrective measures to eliminate the hazards, including the authority to stop work. Include documentation of the qualifications of such competent persons identified, including certifications received.
The contractor is responsible for implementing, monitoring, updating, and revising a safety program through the term of the contract. Submit updates and revisions to the safety program to the County for approval when new information, new practices or procedures, or changing site and environmental conditions necessitate modifications to protect site personnel. Maintain a copy of the updated safety program, including the appropriate documentation associated with each element, within the project limits so that it is available to workers and other authorized persons entering the project limits. Provide program updates to County.
The contractor is responsible for safety in all aspects, and as set forth in the Insurance and Indemnification requirements t, shall defend and indemnify the County for any failure or breach to comply with the rules, regulations, standards, and guidelines in effect at the time the Work is in progress, of OSHA, and other applicable Federal, State, and local regulatory agencies having jurisdiction pertaining to the Contractor's safety program.
CHANGE ORDERS:
All change order requests shall be submitted by the contractor to the Owner’s Representative or County Project Manager. Changes must be reviewed and authorized in accordance with, N.J.S.A. 40A: 11-16.7 et seq., as applicable, N.J.A.C. 5:30– 11through 11.3 et seq., N.J.S.A. 40A:11- 13g; and N.J.S.A. 40A:11-23.1(a). The following rates shall apply in computing indirect costs and profit for adjustments in situations not involving differing or changed conditions covered by N.J.S.A.
40A: 11-16.7 et seq. When the contract time is increased as a result of a change, the resulting change in contract amount will include the indirect impact cost of extended performance, computed in accordance with the terms of this article, and no further consideration of such costs arising from the specific modification will be given. The percentages for overhead and profit shall be negotiated and may vary according to the nature, extent and complexity of the work involved. The percentages shall be applicable for deleted work as well as additional work.
When a change consists of both added and deleted work, the applicable percentages shall be applied to the net cost or credit. In any event, the percentages shall not exceed the following:
a. Overhead will be the sum of:
(1) 15 percent of direct labor costs. NOTE: For the purpose of this article, the term "direct labor" shall include all foremen, equipment operators and skilled, semi-skilled and common laborers directly assigned to the specified operation. The term "direct labor costs" shall consist of the contract or actual payroll rate of wage per hour and fringe benefits paid for each and every hour that such employees are actually engaged in the performance of the work.
(2) 15 percent of direct material costs. NOTE: For the purpose of this article, the term "direct material costs" shall consist of the actual costs of the materials including applicable tax and transportation charges.
b. For rented equipment, an hourly rental rate will be used which will be determined by using the monthly rental rates taken from the current edition of the Rental Rate Blue Book for Construction Equipment and dividing it by 176. An allowance will be made for operating costs for each and every hour the equipment is actually operating in accordance with the rates listed in the aforesaid Rental Book. The contractor will be allowed only 65 percent of the rental rate on contractor-owned equipment. The County reserves the right to provide equipment to the contractor.
c. Bond premiums, insurance, payroll taxes, and travel subsistence, if applicable, will be allowed at actual cost for the equitable adjustment allowed.
d. The contractor's profit on the subcontractor's work will be six percent of the subcontractor's costs. Subcontractor indirect costs will be computed in the same manner as for the prime contractor. The prime contractor agrees to incorporate this article in each of its subcontracts. NOTE: When more than one tier of subcontractors exists, for the purpose of markups, they shall be treated as one subcontractor.
e. A profit of six percent, where profit is allowable by the terms of the applicable contract provision, shall be added to the contractor's total cost for the equitable adjustment allowed. Indirect costs will not be duplicated in direct costs.
f. The General Contractor shall bill unit costs based upon the unit cost proposal provided with the bid.
N.J.S.A 40A:11-16.7 Changed conditions clauses for certain local public contracts
1. All construction contracts issued by a contracting unit for bids which were advertised on or after the effective date of P.L.2017, c.317 (C.40A:11-16.7 et seq.) shall include the changed conditions contract provisions set forth in this section, which provisions shall be deemed to be a part of any such contract even if not expressly incorporated therein, and which provisions may not be modified in any manner by the contracting unit.
a. A contract subject to this section shall include the following differing site conditions provisions:
(1) If the contractor encounters differing site conditions during the progress of the work of the contract, the contractor shall promptly notify the contracting unit in writing of the specific differing site conditions encountered before the site is further disturbed and before any additional work is performed in the impacted area.
(2) Upon receipt of a differing site conditions notice in accordance with paragraph (1) of this subsection, or upon the contracting unit otherwise learning of differing site conditions, the contracting unit shall promptly undertake an investigation to determine whether differing site conditions are present.
(3) If the contracting unit determines different site conditions that may result in additional costs or delays exist, the contracting unit shall provide prompt written notice to the contractor containing directions on how to proceed.
(4) (a) The contracting unit shall make a fair and equitable adjustment to the contract price and contract completion date for increased costs and delays resulting from the agreed upon differing site conditions encountered by the contractor.
(b) If both parties agree that the contracting unit's investigation and directions decrease the contractor's costs or time of performance, the contracting unit shall be entitled to a fair and equitable downward adjustment of the contract price or time of performance.
(c) If the contracting unit determines that there are no differing site conditions present that would result in additional costs or delays, the contracting unit shall so advise the contractor, in writing, and the contractor shall resume performance of the contract, and shall be entitled to pursue a differing site conditions claim against the contracting unit for additional compensation or time attributable to the alleged differing site conditions.
(5) Execution of the contract by the contractor shall constitute a representation that the contractor has visited the site and has become generally familiar with the local conditions under which the work is to be performed.
(6) As used in this subsection, "differing site conditions" mean physical conditions at the contract work site that are subsurface or otherwise concealed and which differ materially from those indicated in the contract documents or are of such an unusual nature that the conditions differ materially from those ordinarily encountered and generally recognized as inherent in the work of the character provided for in the contract.
b. A contract subject to this section shall include the following suspension of work provisions:
(1) The contracting unit shall provide written notice to the contractor in advance of any suspension of work lasting more than 10 calendar days of the performance of all or any portion of the work of the contract.
(2) If the performance of all or any portion of the work of the contract is suspended by the contracting unit for more than 10 calendar days due to no fault of the contractor or as a consequence of an occurrence beyond the contracting unit's control, the contractor shall be entitled to compensation for any resultant delay to the project completion or additional contractor expenses, and to an extension of time, provided that, to the extent feasible, the contractor, within 10 calendar days following the conclusion of the suspension, notifies the contracting unit, in writing, of the nature and extent of the suspension of work. The notice shall include available supporting information, which information may thereafter be supplemented by the contractor as needed and as may be reasonably requested by the contracting unit.
Whenever a work suspension exceeds 60 days, upon seven days' written notice, either party shall have the option to terminate the contract for cause and to be fairly and equitably compensated therefor.
(3) Upon receipt of the contractor's suspension of work notice in accordance with paragraph
(2) of this subsection, the contracting unit shall promptly evaluate the contractor's notice and promptly advise the contractor of its determination on how to proceed in writing.
(4) (a) If the contracting unit determines that the contractor is entitled to additional compensation or time, the contracting unit shall make a fair and equitable upward adjustment to the contract price and contract completion date.
(b) If the contracting unit determines that the contractor is not entitled to additional compensation or time, the contractor shall proceed with the performance of the contract work, and shall be entitled to pursue a suspension of work claim against the contracting unit for additional compensation or time attributable to the suspension.
(5) Failure of the contractor to provide timely notice of a suspension of work shall result in a waiver of a claim if the contracting unit can prove by clear and convincing evidence that the lack of notice or delayed notice by the contractor actually prejudiced the contracting unit's ability to adequately investigate and defend against the claim.
c. A contract subject to this section shall include the following change in character of work provisions:
(1) If the contractor believes that a change directive by the contracting unit results in a material change to the contract work, the contractor shall so notify the contracting unit in writing. The contractor shall continue to perform all work on the project that is not the subject of the notice.
(2) Upon receipt of the contractor's change in character notice in accordance with paragraph (1) of this subsection, the contracting unit shall promptly evaluate the contractor's notice and promptly advise the contractor of its determination on how to proceed in writing.
(3) (a) If the contracting unit determines that a change to the contractor's work caused or directed by the contracting unit materially changes the character of any aspect of the contract work, the contracting unit shall make a fair and equitable upward adjustment to the contract price and contract completion date. The basis for any such price adjustment shall be the difference between the cost of performance of the work as planned at the time of contracting and the actual cost of such work as a result of its change in character, or as otherwise mutually agreed upon by the contractor and the contracting unit prior to the contractor performing the subject work.
(b) If the contracting unit determines that the contractor is not entitled to additional compensation or time, the contractor shall continue the performance of all contract work, and shall be entitled to pursue a claim against the contracting unit for additional compensation or time attributable to the alleged material change.
(4) As used in this subsection, "material change" means a character change which increases or decreases the contractor's cost of performing the work, increases or decreases the amount of time by which the contractor completes the work in relation to the contractually required completion date, or both.
d. A contract subject to this section shall include the following change in quantity provisions:
(1) The contracting unit may increase or decrease the quantity of work to be performed by the contractor.
(2) (a) If the quantity of a pay item is cumulatively increased or decreased by 20 percent or less from the bid proposal quantity, the quantity change shall be considered a minor change in quantity.
(b) If the quantity of a pay item is increased or decreased by more than 20 percent from the bid proposal quantity, the quantity change shall be considered a major change in quantity.
(3) For any minor change in quantity, the contracting unit shall make payment for the quantity of the pay item performed at the bid price for the pay item.
(4) (a) For a major increase in quantity, the contracting unit or contractor may request to renegotiate the price for the quantity in excess of 120 percent of the bid proposal quantity. If a mutual agreement cannot be reached on a negotiated price for a major quantity increase, the contracting unit shall pay the actual costs plus an additional 10 percent for overhead and an additional 10 percent for profit, unless otherwise specified in the original bid.
(b) For a major decrease in quantity, the contracting unit or contractor may request to renegotiate the price for the quantity of work performed. If a mutual agreement cannot be reached on a negotiated price for a major quantity decrease, the contracting unit shall pay the actual costs plus an additional 10 percent for overhead and an additional 10 percent for profit, unless otherwise specified in the original bid; provided, however, that the contracting unit shall not make a payment in an amount that exceeds 80 percent of the value of the bid price multiplied by the bid proposal quantity.
(5) As used in this subsection, the term "bid proposal quantity" means the quantity indicated in the bid proposal less the quantities designated in the project plans as "if and where directed."
SECTION 2 - INSTRUCTIONS TO BIDDERS AND STATUTORY REQUIREMENTS
SUBMISSION OF BIDS
A. Electronically sealed bids shall be received by the County of Mercer in accordance with public advertisement as required by law, with a copy of said notice being attached hereto and made a part of these specifications.
B. Bids shall be electronically uploaded. NO physical bids shall be received, opened or honored. Electronically sealed bids will be opened and conducted in electronic platform in accord with N.J.A.C. 5:34-1 et. Seq., on BidNet Direct at https://www.bidnetdirect.com/new-jersey/mercercounty
C. It is the bidder's responsibility that bids are presented to the County on the date and time specified.
D. Once bids have been opened, they shall remain firm for a period of sixty (60) calendar days.
E. All prices and amounts must be written in ink or type in bid forms. Bids containing any conditions, omissions, unexplained erasures or alterations, items not called for in the bid proposal form, attachment of additive information not required by the specifications, or irregularities of any kind, may be rejected by the County. Any changes, whiteouts, strikeouts, etc. in the bid must be initialed in ink by the person signing the bid.
F. Each bid proposal form must give the full business address, business phone, fax, e-mail ,the contact person of the bidder, and be signed by an authorized representative as follows:
• Bids must furnish the full name of all partners and must be signed in the partnership name by one of the members of the partnership or by an authorized representative, followed by the signature and designation of the person signing.
• Bids by corporations must be signed in the legal name of the corporation, followed by the name of the State in which incorporated and must contain the signature and designation of the president, secretary or other person authorized to bind the corporation in the matter.
• Bids by sole-proprietorship shall be signed by the proprietor.
• When requested, satisfactory evidence of the authority of the officer signing shall be furnished.
G. Bidder should be aware of the following statutes that represent “Truth in Contracting” laws:
• N.J.S.A. 2C:21-34, governs false claims and representations by bidders. It is a serious crime for the bidder to knowingly submit a false claim and/or knowingly make material misrepresentation.
• N.J.S.A. 2C:27-11 provides that a person commits a crime if said person offers a benefit to a public servant for an official act performed or to be performed by a public servant, which is a violation of official duty.
• N.J.S.A. 2C:27-11 provides that a bidder commits a crime if said person, directly or indirectly, confers or agrees to confer any benefit not allowed by law to a public servant.
• Bidder should consult the statutes or legal counsel for further information.
H. Contract shall be awarded to the lowest responsible bidder as declared by the County of Mercer. The contract awarded between the County of Mercer and the successful bidder establishes the contractual obligation regarding specific items, specifications and services to be provided to the county.
I. Contractor shall not assign, transfer, convey sublet or otherwise dispose of the contract or any part thereof to anyone without the written consent of the County of Mercer.
Additionally, no contractor may contract with any subcontractor, who was not named prior to the award of the contract, without the written consent of the County of Mercer and should be given to the county prior to commencement of any work . The addition and/or approval of a subcontractor by the County shall not provide any basis for a change order or any increase in cost.
J. The contractor agrees that he will make no claim for additional payment or any other concession because of any misrepresentation or misunderstanding of the contract on their part, or of any failure to fully acquaint himself with any conditions relating to the contract.
K. If the request for bid involves the use of equipment or machinery, bidder shall submit a list of same owned by the bidder necessary to perform the work being completed prior to contract award.
L. The bidder, if awarded a contract, agrees to protect, defend and save harmless the County of Mercer against any damage for the payment for the use of any patented material process, article or device that may enter into the manufacture, construction or form a part of the work covered by their contract, and he further agrees to indemnify and save harmless the County of Mercer from suits or actions of every nature and description brought against it, for or on account of any injuries or damages received or sustained by any parties, by, or from any acts of the contractor, his servants or agents.
M. Bidder must provide Certificate of insurance in a form and amount acceptable to the County of Mercer including General Liability, Automobile, Workman’s Compensation and such other coverage as may be deemed necessary by the County of Mercer for the work, services or goods being bid. The Certificate of Insurance will be due at time of contract award.
N. BIDDERS SHALL PROVIDE TRADE SECRET OR PROPRIETARY INFORMATION UNDER SEPARATE
COVER WITH THE BID RESPONSE; HOWEVER, ALL INFORMATION IS PUBLIC AT THE TIME OF
THE BID OPENING.
O. SOURCE OF SPECIFICATIONS/BID PACKAGES: This official County bid package is available only through the County of Mercer BidNet Portal. Potential bidders are cautioned that they are bidding at their own risk if a third party supplied the specifications that may or may not be complete. As such, the County is not responsible for third party supplied specifications nor is the County responsible to forward addenda to vendors supplied with specifications from a third party.
P. CAUSES FOR REJECTING BIDS
Bids may be rejected for any of the following reasons in accordance with N.J.S.A.
40A:11-13.2
1. A contracting unit may reject all bids for any of the following reasons:
2. The lowest bid substantially exceeds the cost estimates for the goods or services.
3. The lowest bid substantially exceeds the contracting unit's appropriation for the goods or services.
4. The governing body of the contracting unit decides to abandon the project for provision or performance of the goods or services.
5. The contracting unit wants to substantially revise the specifications for the goods or services.
6. The purposes or provisions or both of P.L.1971, c.198 (C.40A:11-1 et seq.) are being violated.
7. The governing body of the contracting unit decides to use the State-authorized contract pursuant to section 12 of P.L.1971, c.198 (C.40A:11-12).
INTERPRETATIONS AND ADDENDA
The bidder understands and agrees that its bid is submitted on the basis of the specifications prepared by the County. The bidder accepts the obligation to become familiar with these specifications.
Bidders are expected to examine the specifications and related documents with care and observe all their requirements. Ambiguities, errors, or omissions noted by bidders should be promptly reported in writing to the Purchasing Agent. In the event the bidder fails to notify the County of such ambiguities, errors or omissions, the bidder shall be bound by the bid.
No oral interpretation of the meaning of the specifications will be made to any bidder. Every request for an interpretation shall be in writing, addressed to the Purchasing Agent. In order to be given consideration, written requests for interpretation must be received at least (10) calendar days prior to the date fixed for the opening of the bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications, and will be distributed to all prospective bidders, in accordance with N.J.S.A. 40:11-23(c)(2). All addenda so issued shall become part of the contract documents and shall be acknowledge by the bidder in the bid. The County's interpretations or corrections thereof shall be final.
If the amount shown in words and its equivalent figures do not agree, the written words shall be binding. Ditto marks are not considered writing or printing and shall not be used bidder as it can deem the contractor unresponsive. In the event that there is a discrepancy between the unit prices and the extended totals, the unit prices shall prevail. In the event there is an error of the summation of the extended totals, the computation by the County of the extended totals shall govern.
CHALLENGE TO SPECIFICATIONS
Any prospective bidder who wishes to challenge a bid specification shall file such challenges in writing with the contracting agent no less than three business days prior to the opening of the bids.
Challenges filed after that time shall be considered void and having no impact on the contracting unit or the award of contract.
BRAND NAMES, STANDARDS OF QUALITY AND PERFORMANCE (BIDDING PROPRIETARY SYSTEM)
Brand names and/or descriptions used in these specifications are to acquaint bidders with the types of goods and services desired and will be used as a standard by which goods and services offered as equivalent will be evaluated. Variations between the goods and services described and the goods and services offered are to be fully identified and described by the bidder on a separate sheet and submitted with the bid proposal form. Vendor literature WILL NOT suffice in explaining exceptions to these specifications. In the absence of any exceptions by the bidder, it will be presumed and required that the goods and services as described in the bid specification be provided or performed. It is the responsibility of the bidder to document and/or demonstrate the equivalency of the goods and services offered. The County reserves the right to evaluate the equivalency of the goods and services.
In submitting its bid, the bidder certifies that the goods and services to be furnished will not infringe upon any valid patent or trademark and that the contractor shall, at its own expense, defend any and all actions or suits charging such infringement, and will save the County harmless from any damages resulting from such infringement.
Only manufactured and farm products of the United States, wherever available, shall be used pursuant to N.J.S.A. 40A:11-18. The contractor shall guarantee any or all goods and services supplied under these specifications. Defective or inferior goods shall be replaced at the expense of the contractor. The contractor will be responsible for return freight or restocking charges.
PRICING INFORMATION FOR PREPARATION OF BIDS
The County is exempt from any local, state or federal sales, use or excise tax.
Contractor shall be responsible for obtaining any applicable permits or licenses from any government entity that has jurisdiction to require the same. All bids submitted shall have included this cost.
METHOD OF CONTRACT AWARD
The length of the contract shall be stated in the technical specifications. Pursuant to requirements of N.J.A.C. 5:30-5.1 et seq., any contract resulting from this bid shall be subject to the availability and appropriation of sufficient funds annually. Please see Section entitled Termination of Contract.
If the award is to be made on the basis of a base bid only, it shall be made to that responsible and responsive bidder submitting the lowest base bid.
The form of contract shall be submitted by the County to the contractor . Terms of the specifications/bid package prevail.
TERMINATION OF CONTRACT
A. If, through any cause, the contractor shall fail to fulfill in a timely and proper manner obligations under the contract or if the contractor shall violate any of the requirements of the contract, then the County shall have the right to terminate the contract by giving written notice to the contractor of such termination and specifying the effective date of termination. Such termination shall relieve the County of any obligation for balances to the contractor of any sum or sums set forth in the contract. County will pay only for goods and services accepted prior to termination.
B. Notwithstanding the above, the contractor shall not be relieved of liability to the County for damages sustained by the County by virtue of any breach of the contract by the contractor and the County may withhold any payments to the contractor for the purpose of compensation until such time as the exact amount of the damage due the County from the contractor is determined.
C. The contractor agrees to indemnify and hold the County harmless from any liability to subcontractors or suppliers concerning payment for work performed or goods supplied arising out of the lawful termination of the contract by the County under this provision.
D. In case of default by the contractor, the County may procure the goods or services from other sources and hold the contractor responsible for any excess cost.
E. Continuation of the terms of the contract beyond the fiscal year is contingent on availability of funds in the following year's budget. In the event of unavailability of such funds, the County reserves the right to cancel the contract.
F. ACQUISITION, MERGER, SALE AND/OR TRANSFER OF BUSINESS, ETC.
It is understood by all parties that if, during the life of the contract, the contractor disposes any of their business concern by acquisition, merger, sale and or/transfer or by any means convey their interest(s) to another party, all obligations are transferred to that new party. In this event, the new party(s) will be required to submit all documentation/legal instruments that were required in the original bid/contract. Any change is subject to County approval.
G. The contractor will not assign any interest in the contract and shall not transfer any interest in the same without the prior written consent of the County.
H. The County of Mercer reserves the right, at its option, to terminate this contract upon giving thirty (30) days written notice to the contractor. Such termination shall relieve the County of any obligation for balances to the contractor of any sum or sums set forth in the contract.
County will pay only for goods and services accepted prior to termination.
PAYMENT
No payment will be made unless duly authorized by the County of Mercer’s authorized representative and accompanied by proper documentation. Payment will be made in accordance with the County of Mercer’s policy and procedures and in accordance with the Prompt Payment Act, N.J.S.A. 2A:30A-1 et seq.
TRANSITIONAL PERIOD
In the event services are terminated by contract expiration or by voluntary termination by either the Contractor or The County of Mercer, the Contractor shall continue all terms and conditions of said contract for a period not to exceed thirty (30) days at the County’s request.
NEW JERSEY SALES TAX
In submitting a bid, the Contractor certifies that the total base bid set forth does not include any New Jersey Sales Tax, and he further certifies that in the event of a successful bid, bidder will only apply for an exemption for materials or supplies to be used in connection with County property.
Contractor’s Exemption Purchase Certificate, Form ST-13, issued by the State of New Jersey Division of Taxation, Sales Tax Bureau, shall be completed and presented to their suppliers for material used to make any permanent change to a County Building on this contract.
http://www.state.nj.us/treasury/taxation/pdf/other_forms/sales/st13.pdf
LATE FEE POLICY
The County of Mercer pays vouchers bi-weekly, thus vendors, in most cases are paid in less than 30 calendar days, if the vendor has complied by responding promptly with delivery, a signed voucher and an original invoice. The County of Mercer can pay only for goods and services rendered and in accordance with N.J.S.A. 2A:30A-2 (c) . All credit applications or similar forms are carefully read in Finance and terms the County does not agree to, are stricken.
BUDGET SEQUESTRATION
All contracts shall include the following language with regard to automatic spending cuts to State of New Jersey and/or United States federal government funding:
“THE CONTRACT AWARD IS CONTINGENT UPON RECEIVING REQUISITE STATE and/or FEDERAL
FUNDING NECESSARY TO COMPLETE THE TERMS OF THE CONTRACT.”
MANDATORY AFFIRMATIVE ACTION CERTIFICATION
All successful bidders (goods and services vendors, professional service vendors and construction contractors) are required to submit evidence of appropriate affirmative action compliance to the Division of Public Contracts Equal Employment Opportunity Compliance and the County. During a review, Division representatives will review the County files to determine whether the affirmative action evidence has been submitted by the vendor/contractor. Specifically, each vendor/contractor shall submit to the County, prior to execution of the County contract, the following documents:
• The construction contractors shall complete and submit an Initial Project Workforce Report, Form AA-201 upon notification of award but prior to signing contract . Proper completion and submission of this report shall constitute evidence of the contractor’s compliance with the regulations. Failure to submit this form may result in the contract being terminated.
• The contractor also agrees to submit a copy of the Monthly Project Workforce Report, Form AA-202 once a month thereafter for the duration of the contract to the Division and to the County Compliance Officer. After notification of award, but prior to signing a construction contract the EEO/AA evidence must be submitted. The County shall retain the Affirmative Action evidence in our bid file for review by the Division.
BID WITHDRAWAL FOR PUBLIC WORKS PROJECTS, N.J.S.A. 40A:11-23.3
PERMISSION FOR BIDDER TO WITHDRAW A BID DUE TO A MISTAKE IN CERTAIN CIRCUMSTANCES N.J.S.A. 40A:11-23.3 authorizes a bidder to request withdrawal of a public works bid due to a mistake on the part of the bidder. A mistake is defined by N.J.S.A. 40A:11-2(42) as a clerical error that is an unintentional and substantial computational error or an unintentional omission of a substantial quantity of labor, material, or both, from the final bid computation. A bidder claiming a mistake under N.J.S.A. 40A:11-23.3 must submit a request for withdrawal, in writing, by certified or registered mail to:
Department of Purchasing 640 S. Broad Street Third Floor PO Box 8068 Trenton, NJ 08650-0068
The bidder must request withdrawal of a bid due to a mistake, as defined by the law, within five business days after the opening of the bids. Since the bid withdrawal request shall be effective as of the postmark of the certified or registered mailing.
A bidder’s request to withdraw the bid shall contain evidence, including any pertinent documents, demonstrating that a mistake was made. Such documents and relevant written information shall be reviewed and evaluated in accordance with N.J.S.A. 40A:11-23.3.
The County will not consider any written request for a bid withdrawal for a mistake, as defined by N.J.S.A. 40A:11-2(42), by a bidder in the preparation of a bid proposal unless the postmark of the certified or registered mailing is within the five business days following the opening of bids.
NEW JERSEY WORKER AND COMMUNITY RIGHT TO KNOW ACT
The manufacturer or supplier of chemical substances or mixtures shall label them in accordance with the N.J. Worker and Community Right to Know Law (N.J.S.A. 34:5A-1 et seq., and N.J.A.C 7:1G-1.1 et seq.,). Containers that the law and rules require to be labeled shall show the Chemical Abstracts Service number of all the components and the chemical name. Further, all applicable Material Safety Data Sheets (MSDS) and hazardous substance fact sheets must be furnished. All direct use containers shall bear a label indicating the chemical name(s) and Chemical Abstracts Service number(s) of all hazardous substances in the container, and all other substances which are among the five most predominant substances in the container, or their trade secret registry number(s). (N.J.A.C. 8:59-5) or adhere to the requirements of The Globally Harmonized System of Classification and Labeling of Chemicals (GHS) and the U.S. Occupational Safety and Health Administration (OSHA) Hazard Communication Standard (HCS) as outlined in the Federal Register / Vol. 77, No. 58 / Monday, March 26, 2012 / Rules and Regulations as adopted in final rule by DEPARTMENT OF LABOR, Occupational Safety and Health Administration, 29 CFR Parts 1910, 1915, and 1926, [Docket No. OSHA–H022K–2006– 0062, (formerly Docket No. H022K)], RIN 1218–AC20, Hazard Communication.
PREVAILING WAGE ACT
Pursuant to N.J.S.A. 34:11-56.25 et seq., contractors on projects for public work shall adhere to all requirements of the New Jersey Prevailing Wage Act. The contractor shall be required to submit a certified payroll record to the owner within ten (10) days of the payment of the wages. The County of Mercer may terminate work if workers are paid less than prevailing wage. The contractor is also responsible for obtaining and submitting all subcontractors' certified payroll records within the aforementioned time period. In the event it is found that any worker, employed by the contractor or any subcontractor has been paid a rate of wages less than the prevailing wage required to be paid, the owner may terminate the contractor's or subcontractor's right to proceed with the work, or such part of the work as to which there has been a failure to pay required wages and the contractor and subcontractor then be required to continue the work to completion or otherwise. The contractor is also responsible for obtaining and submitting all subcontractors' certified payroll records within the aforementioned time period. The contractor shall submit said certified payrolls in the form set forth in N.J.A.C. 12:60-6.1(c). It is the contractor's responsibility to obtain any additional copies of the certified payroll form to be submitted by contacting the New Jersey Department of Labor and Workforce Development, Division of Workplace Standards.
Public Contracts Section Office of Wage and Hour Compliance CN 389 Trenton, New Jersey 08625-0389 Telephone number: (609) 292-2259
This law, N.J.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .