About this file

This addendum clarifies specifications for electrical and HVAC penetration points for a project administered by the Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs at 183 Milk Street in Westborough. The project involves the installation of one ductless HVAC split system and one dedicated 20-amp, 120-volt electrical circuit to serve a server room located on the third floor of a Victorian-style house. The HVAC work includes furnishing and installing an indoor air handler, outdoor condensing unit, insulated refrigerant line set, condensate drain piping with secondary drain and overflow protection, electrical disconnect, control wiring, thermostat, and system commissioning with pressure testing, evacuation, and charging. The electrical work requires furnishing and installing a dedicated 20-amp branch circuit from the existing electrical panel to the attic space as surface-mounted wiring. Both the HVAC and electrical installations must utilize a single shared penetration point below the roof soffit on the right side of the second-story window, with a second penetration through a second-floor closet ceiling to access the third-floor space. All penetration points must be appropriately sealed, and all work must comply with the National Electrical Code and applicable building codes.

The addendum specifies that all materials, labor, and commissioning are the contractor's responsibility. The penetration points must not pass through load-bearing members, and all piping, wiring, and equipment must be secured and supported in accordance with applicable codes and industry standards. The project is issued under Massachusetts General Law chapters 7, 22, and 30, sections 51 and 52, as well as 801 CMR 21.00 for Goods and Services procurement. Inquiries regarding the solicitation should be directed to Louis Mattei, Facilities Project Manager, at Louis.Mattei@mass.gov or (617) 733-7451.

View the file

Other files

File Type Posted
RFPSOW MEP-001-27SEPT~3.docx DOCX document
Image.jpeg JPEG file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM

BD-27-1042-ENVOP-FAC01-133090

This addendum is issued to clarify and correct the Electrical/HVAC Penetration point (s) outlined in the RFQ.

The HVAC/Electrical team will need to make the appropriate penetration points to gain access to the third floor as roughly outlined below:

The penetration point will be to the right of the second story window and below the soffit (see Image A). This will then enter a second-floor closet (see Image B) with a second penetration through the ceiling (see Image C) to enter the third-floor space.

As a reminder: All penetration points need to be appropriately sealed including the exterior.

All other terms and conditions of the RFQ remain unchanged. Bidders are advised to review this addendum carefully.

Thank you, Louis Mattei

Louis Mattei

Facilities Project Manager

Executive Office of Energy and Environmental Affairs Commonwealth of Massachusetts

100 Cambridge St., 10th Floor

Boston, Massachusetts 02114

Louis.Mattei@mass.gov

(617)733-7451 mailto:Louis.Mattei@mass.gov

II. Applicable Procurement Law This Solicitation is issued, and any contract will be awarded, under MGL c. 7, § 22; c.

30, § 51, § 52; and 801 CMR 21.00 (Goods and Services).

III. Scope of Work for Installation of HVAC Split System and 20-Amp Quad Receptacle in

Attic Space

In accordance with the latest recognized National Electrical Code, (and all other applicable codes) the contractor shall be responsible for furnishing, installing, and commissioning all the equipment listed below:

HVAC Split System Installation

• Furnish and install one (1) ductless HVAC split system to address cooling and heating needs in a server room located on the third floor of a Victorian style house (see attachment B).

• Install indoor air handler in designated area (see attachment B) and outdoor condensing unit in designated area (see attachment C) in accordance with the manufacturer's installation requirements.

• Install insulated refrigerant line set between indoor and outdoor units.

• Install condensate drain piping with secondary drain and overflow protection, as required by applicable building codes.

• All lines and piping should be surface mounted up the front of the house and shared with the electrical install at a single point of penetration below the roof soffit. Penetration should not be through a load bearing member. To be sealed appropriately upon completion.

• Install electrical disconnect at the outdoor condensing unit.

• Install control wiring and thermostat.

• Pressure test, evacuate, and charge the refrigerant system as required.

• Start up the system, verify proper operation, and perform functional testing.

• Secure and support all piping, wiring, and equipment in accordance with applicable codes and industry standards.

Electrical Work

• Furnish and install one (1) dedicated 20-amp, 120-volt branch circuit from the existing electrical panel to the attic space.

• This should be a surface mounted circuit that extends up the front of the house and penetrates below the roof soffit on the third floor. Penetration should not be through a load bearing member. The penetration point should be shared with condensate and cooling lines from split system install. To be sealed appropriately upon completion of work.

• Furnish and install one (1) dedicated circuit from the existing electrical panel to the split system unit.

Image A

Image B

Image C

ATTACHMENT B – Server room location 183 Milk St. Westborough

ATTACHMENT C – Outdoor condensing unit install Area

Addendum Electrical
RFPSOW MEP-001-27SEPT 2
III. Scope of Work for Installation of HVAC Split System and 20-Amp Quad Receptacle in Attic Space
ATTACHMENT B – Server room location