MCM18-R-0001_Amendment_(1).pdf

PDF 5 MB Posted

Attached to
Marine Corps Marathon Event series race t-shirts
Solicitation number
MCM18-R-0001
Issued by

About this file

Answers to received questions.

View the file

Other files

File Type Posted
TurkeyTrot_2018_Mechanical.ai AI file
1775K_2018_Mechanical.ai AI file
MCM18-R-0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Answers to Request for Information

Tyanna R. Villarreal Regional Procurement Director

The attached is in answer to questions received for the above mentioned procurement.

Marine Corps Community Services Regional Procurement Office National Capital Region 2015 Julian Dr.

Quantico, VA 22134

Tyanna Villarreal Regional Procurement Director National Capital Region

PH: 703-784-5636

E: tyanna.villarreal@usmc-mccs.org

N/A

MCM18-R-0001

08/20/2018

07/27/2018

VILLARREAL.TYANNA.R

OCHELLE.1279740714

Digitally signed by

VILLARREAL.TYANNA.ROCHELLE.1279740714

Date: 2018.08.20 12:37:50 -04'00'

8/20/2018

1 6

Amendment MCM18-R-0001 (01)

The following questions were received concerning the MCMO Race Series Shirts:

Q1:. On the price form there are multiple lines of “Option Custom Dye” and “Option off the shelf” followed by T-Shirt description. Please provide clarification.

A1: MCMO would like pricing for both in the event that they order one or the other.

Q2: Can a Canadian company participate in submitting proposals for this company and is it mandatory for products to be made in Canada or USA?

A2: See section K.6 on page 68 of the RFP for an explanation.

Q3: What is the due date for sample t-shirts and final product.

A3: Sample t-shirts are due as part of the solicitation package on 12 September 12:00 PM. See timeline for final products in section C.

Q4: The weight of the MCM Competitor ¼ zip is listed as 120-140 grams. This is a lightweight t-shirt weight. Is this the correct weight?

A4: Yes, 120-140 grams is the correct weight.

Q5: Fully seam to seam sublimation is a printing process that you are requesting on most of the shirts and is done on the cut flats of the shirts before they are sewn together so that the sublimation print covers the entire shirt. Otherwise it is difficult for the printing to cover the areas by all the seams and the shirt will not look good. So even the solid looking color of a fully sublimated shirt does not come from dying the shirt fabric but comes from the sublimation printing the same as all the colors in the graphic design. The fabric for dye sublimation starts out white or as greige goods which is the fabric before it is dyed. Therefore, the option for custom dye fabric for sublimation does not really make sense and is not a viable product. We plan to put N/A in that space – Confirm your understanding.

A5: Understand the dye sublimation process but we are asking for options if we can screen print and options for off the shelf process for future years of the contract. Depending on the selections of colors per year per event we are asking for options to custom dye. N/A may make your company unresponsive. If you feel that you cannot do this process or it is incorrect a suggestion should be made as to an alternate.

Q6: Since the fully sublimated shirts are done on cut flats at the factory before sewn there really is not an off the shelf option for these sublimated shirts. We intend to put N/A in that space. This is applicable for the shirts requesting screen printing and will fill in the price accordingly.

A6: We are asking for options if we change from dye sublimation to another style type of shirt. N/A may make your company unresponsive. If you feel that you cannot do this process or it is incorrect a suggestion should be made as to an alternate.

Q7: Pricing for XXL and XXXL? Will there be an addendum with pricing for different sizes?

A7: No, if you cannot provide all sizes of shirts at the same price add an additional page with this pricing information.

Q8: Your bid notes the fabric as “technical” and also notes some types of finishing on the technical fabrics as “smooth” or “Marquis” or eclipse”. But your bid does not note the substance of the fabric or what it is made of which is 100% polyester. Is 100% polyester technical fabric the category you want to stay in? Also, your bid states at least 120-140gsm in weight? We can literally make any gsm weight so again is this the weight range you want to stay in?

A8: Yes, 100% polyester; yes 120-140 gsm

Q9: Eclipse fabric shirt requested for the Quantico Triathlon and Quantico 12k events shirt does not take dye sublimation printing well as it has too much texture. Would you like us to substitute the marquis or smooth fabric for those event shirts that we can sublimate, or would you like us to quote the eclipse shirt that we can screen print?

A9: Yes would like the option to substitute fabric depending on the process and yes provide a quote to screen print on the eclipse shirt.

Q10: You requested a LS Mock Turtle Neck with neck embroidery specified in your request. In the MCM Marathon Competitor and MCM10k the neck embroidery was specified as an OPTION. But in paragraph L1 for the medical shirts the last sentence says – this is optional. Do you want the neck embroidery included in the base price for the medical shirts or priced as an optional add-on?

A10: Optional add on

Q11: Blend shirts are combinations of cotton and poly. We found that the best combination is a 60%cotton/40% poly mixture. We find this is softer than the 50-50 combinatino and makes for a better shirt. Can we bid our 60-40 shirt vs a 50-50? We also carry the 60-40 vs the 50-50 off the shelf if needed.

A11: when you fill out the pricing page please note the price for 50/50 and add on for 60/40

Q12: Can you send artwork that has been provided before? I would like the art that was sent and to see the files as to how it was sent for maybe the Half Marathon and the Turkey Trot.

A12: See attached PDF of artwork.

Q13: When is artwork due to the contractor? How many days in advance of the delivery date?

A13: Please review pages 14 and 15 (SOW). Contractor will provide timeline depending on shirt process.

Please review the delivery date and submit a production schedule according to page 15.

Q14: Do you need samples of all shirts? All three option on all the races?

A14: No- please review pg. 77 for requested samples.

Q15: What terms are acceptable for payment?

A15: Net 30 Days

Q16: Is the first deliverable on this new contract the 1775 Race or the Turkey Trot in 2018?

A16: First deliverable will be the Marine Corps 1775k.

Q17: Is there any advantage to providing a 100 percent sourced product form the USA or is it fine to just use the approved countries as a source.

A17: Please see section K.6 on page 68 for Buy American Act/Trade Agreements. Make sure that you fill out section K.6.c- certification and list end products that are not domestic. See section K.6.d in regard to how Buy American Act affects this procurement.

Q18: Can we receives samples of what was used in 2018?

A18: We do not have samples but have attached example art work.

Q19: Will payment for the first race be processed once the contract is awarded and subsequent payments prior to product delivery?

A19: Payment is made after receipt of goods on a NET 30. See section I.21 for Invoicing and Payment.

Contractor may offer a prompt payment discount to be paid sooner than the NET 30 and will be taken into consideration provided that we are able to meet the payment date.

Q20: Will payment be processed once the items have been delivered to the installation?

A20: See above answer.

Q21: Are there any art files/designs which you can share with us?

A22: See attached PDF example. MCMO has the capability to send JPEG, PDF, and Vector files for designs.

Q22: What is the actual event date you are requesting these items for? For instance sublimation for custom clothing requires 60-90 day turnaround time or possibly longer depending on the time of year.

We know the Marine Corps Marathon for this year is just around the corner, but want to be sure in your planning that you are aware if you were needing these items for this year.

A22: We are covered for the Marathon this year. This contract will commence with the 1775 that takes place in April of 2019.

Q23: Can you provide a bid tab or previous vendors who bid, unit amount and award amount?

A23: We do not provide this information.

Q24: Pages 29 thru 35 there is requests for detailed info that i have not seen on other awards. Please provide clarification.

A24: This is in reference to the Service Contract Act and is required on all government service contracts over $2,500. If you need additional information on this please contact the Department of Labor.

Section H is SPECIAL CONTRACT REQUIREMENTS; there is not a waiver for these requirements.

ADD to Statement of work:

All standard sizes shall be equal to a Gildan or better style shirt. Off the shelf and custom style shirts shall be approved by MCMO prior to productions. Below size chart shall be used for this contract:

UNISEX Chest Waist X-Small 32” - 34” 25” - 27” Small 35” - 36” 28” - 30” Medium 37” - 39” 31” - 33” Large 40” - 42” 34” - 36” X-Large 43” - 45” 37” - 39”

2 XL 46” - 48” 40” - 42”

3 XL 49” - 51” 43” - 45”

4 XL 52” - 54” 46” - 48”

All other terms and conditions shall remain in effect.

**SOW explanation, page 14, each event is specified with the type of shirt and process we want. We would like the opportunity to have options per event to make changes throughout the contract. I understand there is a difference in pricing, so we are requesting options with dye-sublimation, screen printing, and embroidery. So many steps are involved in producing a shirt but we want the best quality for our runners.