McCandless_Steps_-_Pre-Bid_CPM_Schedule_-_4-10-2024.pdf

PDF 231 KB Posted

Attached to
Stanton Ave/McCandless Ave Stairs Construction
Solicitation number
2024-IFB-309
Issued by
Allegheny County, Pennsylvania

About this file

This document is a Critical Path Method (CPM) Schedule for the Stanton Ave/McCandless Ave Stairs Construction project, prepared for the City of Pittsburgh's Department of Mobility and Infrastructure (DOMI). The comprehensive project schedule spans from June 27, 2024, to May 12, 2025, detailing a multi-phase construction process involving pre-construction activities, site preparation, structural work, and project closeout. Key activities include developing quality control plans, obtaining necessary approvals, installing environmental and safety controls, drilling caissons, setting soldier piles, pouring concrete, installing precast panels and components, constructing landings, forming and pouring walls and foundations, and completing final site restoration tasks.

The schedule indicates a project duration of approximately 11 months, with specific milestones such as mobilization, pre-construction meetings, traffic control implementation, and phased construction activities across multiple landings. Critical path activities include caisson drilling, concrete pouring, curing periods, panel and component installation, and final site restoration. The project includes specific technical requirements like seeding and erosion control, with prescribed germination periods between March 15th and June 1st, and August 1st to October 15th. The final project deadline is set for August 25th, with the contractor required to complete all construction, restoration, and closeout activities by May 12, 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors

2024 2025 2 3 4 1

July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5

34 35 36 37 38 39 40 41 42 43 44

010.10

010.20

010.40

030.05

030.10

030.20

030.30

030.40

040.05

040.10

040.40

040.50

040.60

040.70

060.05

060.10

060.15

060.20

060.25

070.01

070.10

070.15

070.20

070.25

Administrative Tasks

Anticipated Notice to Proceed (6/27/2024)

Mobilization

Project Completion

PRE-CONSTRUCTION ACTIVITIES

Concrete QC Plans and Mix Designs

Develop/Submit QC Plans and Mix Designs

DOMI Review

Revise and Resubmit QC Plans and Mix Designs

DOMI Review and Approval

Pre-Concrete Meeting

Advanced Notice/RNAs

Notify County Conservation District

Notice to Municipalities and Emergency Services

Erect Advanced Warning Signs

Initial Press Release Notification

PA One Call

On-Site Pre Construction Meeting

CPM Schedule

Develop CPM Schedule

DOMI Review

Revise/Resubmit CPM Schedule

DOMI Review and Acceptance

Monitor and Progress Schedule

Precast Components

Prepare and submit precast component shop drawings

DOMI review of precast component shop drawings

Revise and resubmit precast component shop drawings

DOMI Review and Acceptance of precast component shop drawings

Fabricate precast components

27 Jun 24

27 Jun 24 *

11 Jul 24

12 May 25

27 Jun 24

27 Jun 24

27 Jun 24

05 Jul 24

19 Jul 24

26 Jul 24

02 Aug 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

27 Jun 24

12 Jul 24

26 Jul 24

02 Aug 24

09 Aug 24

27 Jun 24

27 Jun 24

28 Jul 24

12 Aug 24

17 Aug 24

24 Aug 24

12 May 25

27 Jun 24

11 Jul 24

12 May 25

13 Mar 25

02 Aug 24

03 Jul 24

18 Jul 24

25 Jul 24

01 Aug 24

02 Aug 24

10 Jul 24

10 Jul 24

10 Jul 24

06 Jul 24

06 Jul 24

29 Jun 24

27 Jun 24

13 Aug 24

11 Jul 24

25 Jul 24

01 Aug 24

08 Aug 24

13 Aug 24

24 Oct 24

27 Jul 24

10 Aug 24

16 Aug 24

23 Aug 24

24 Oct 24

218.0d

1.0d

250.0d

36.0d

5.0d

14.0d

5.0d

7.0d

1.0d

13.0d

14.0d

14.0d

10.0d

10.0d

3.0d

1.0d

33.0d

10.0d

14.0d

5.0d

7.0d

5.0d

83.0d

30.0d

14.0d

5.0d

7.0d

60.0d

0.0d

0.0d

112.0d

0.0d

42.0d

139.0d

98.0d

139.0d

97.0d

139.0d

97.0d

160.0d

165.0d

165.0d

169.0d

169.0d

176.0d

117.0d

85.0d

85.0d

121.0d

85.0d

121.0d

126.0d

79.0d

112.0d

112.0d

79.0d

113.0d

113.0d

5-DAY

5-DAY

5-DAY

5-DAY

7-DAY

7-DAY

5-DAY

7-DAY

5-DAY

7-DAY

5-DAY

7-DAY

Calendar Day

Calendar Day

Calendar Day

Calendar Day

Calendar Day

5-DAY

5-DAY

5-DAY

7-DAY

5-DAY

7-DAY

Calendar Day

5-DAY

7-DAY

7-DAY

5-DAY

7-DAY

7-DAY

None

Start on

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

Anticipated Notice to Proceed (6/27/2024), PA One Call, Notify County Conservation District, Notice to Municipalities and Emergency Services, Erect Advanced Warning

Signs, Initial Press Release Notification

Project Complete

Anticipated Notice to Proceed (6/27/2024)

Develop/Submit QC Plans and Mix Designs

DOMI Review

Revise and Resubmit QC Plans and Mix Designs

DOMI Review and Approval

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Anticipated Notice to Proceed (6/27/2024)

Develop CPM Schedule

DOMI Review

Revise/Resubmit CPM Schedule

DOMI Review and Acceptance

Anticipated Notice to Proceed (6/27/2024)

Prepare and submit precast component shop drawings

DOMI review of precast component shop drawings

Revise and resubmit precast component shop drawings

DOMI Review and Acceptance of precast component shop drawings

Mobilization , Develop/Submit QC Plans and Mix Designs, Notify County Conservation District, Notice to Municipalities and Emergency Services, Erect

Advanced Warning Signs, Initial Press Release Notification, Develop CPM Schedule, Prepare and submit railing shop drawings, On-Site Pre Construction

Meeting, Prepare and submit precast component shop drawings, Prepare Precast Panel Shop Drawings, Structural Steel - Soldier Piles, PA One Call

Implement Traffic Control

DOMI Review

Revise and Resubmit QC Plans and Mix Designs

DOMI Review and Approval

Pre-Concrete Meeting

Drill caissons - set soldier piles for retaining wall - pour caisson concrete, Install precast panels, Drill caissons for landings 4, 3, 2, and 1, set cages, and pour, Form, tie, and pour columns at landings 4, 3, 2, and 1, Excavate, form, tie, and pour pad at landing 0, Form, tie, and pour walls at landing 0, Excavate, form, tie, and pour foundation at landing 5

Mobilization

Mobilization

Mobilization , Implement Traffic Control

Mobilization

Mobilization

Implement Traffic Control, Install E&S Controls

DOMI Review

Revise/Resubmit CPM Schedule

DOMI Review and Acceptance

Monitor and Progress Schedule

Project Complete, Install E&S Controls

DOMI review of precast component shop drawings

Revise and resubmit precast component shop drawings

DOMI Review and Acceptance of precast component shop drawings

Fabricate precast components

Set precast components

Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors

2 3 4 1

July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5

34 35 36 37 38 39 40 41 42 43 44

080.05

080.15

080.20

080.25

080.30

100.05

100.10

100.15

100.20

100.21

100.25

200.020

200.030

200.040

200.041

200.045

200.050

200.060

200.070

200.071

200.080

200.100

200.110

200.130

200.140

200.150

200.160

200.165

200.170

200.180

200.185

200.190

Railing

Prepare and submit railing shop drawings

DOMI review of railing shop drawings

Revise and resubmit railing shop drawings

DOMI review and acceptance railing shop drawings

Fabricate railings

Retaining Wall - Precast Lagging and Soldier Piles

Prepare Precast Panel Shop Drawings

DOMI Review of Precast Panel Shop Drawings

Revise and Resubmit Precast Panel Shop Drawings

DOMI Review and Acceptance of Precast Panel Shop Drawings

Fabricate precast lagging

Structural Steel - Soldier Piles

Construction Work

Install E&S Controls

Remove Existing Guiderail along McCandless Avenue

Clearing and Grubbing

Demolish Existing Stairs

Implement Traffic Control

Drill caissons - set soldier piles for retaining wall - pour caisson concrete

Cure caisson concrete

Install precast panels

Form, tie, and pour closure pours

Cure closure pours

Backfill soldier pile wall

Drill caissons for landings 4, 3, 2, and 1, set cages, and pour

Cure caisson concrete

Form, tie, and pour columns at landings 4, 3, 2, and 1

Cure column concrete at landings 4, 3, 2, and 1

Form, tie, pour caps at landings 4, 3, 2, and 1

Cure caps at landings 4, 3, 2, and 1

Excavate, form, tie, and pour foundation at landing 5

Cure foundation at landing 5

Backfill foundation at landing 5

Set precast components

27 Jun 24

27 Jun 24

09 Aug 24

23 Aug 24

30 Aug 24

07 Sep 24

27 Jun 24

27 Jun 24

12 Jul 24

26 Jul 24

02 Aug 24

09 Aug 24

27 Jun 24

14 Aug 24

14 Aug 24

15 Aug 24

16 Aug 24

17 Aug 24

26 Sep 24

27 Sep 24

01 Oct 24

09 Oct 24

10 Oct 24

12 Oct 24

19 Oct 24

19 Oct 24

23 Oct 24

30 Oct 24

01 Nov 24

08 Nov 24

15 Nov 24

15 Nov 24

19 Nov 24

26 Nov 24

27 Nov 24

13 Mar 25

08 Aug 24

22 Aug 24

29 Aug 24

06 Sep 24

13 Mar 25

08 Oct 24

11 Jul 24

25 Jul 24

01 Aug 24

08 Aug 24

08 Oct 24

26 Sep 24

17 Mar 25

14 Aug 24

15 Aug 24

16 Aug 24

19 Aug 24

26 Sep 24

30 Sep 24

07 Oct 24

09 Oct 24

11 Oct 24

18 Oct 24

19 Oct 24

22 Oct 24

29 Oct 24

31 Oct 24

07 Nov 24

14 Nov 24

21 Nov 24

18 Nov 24

25 Nov 24

26 Nov 24

30 Nov 24

176.0d

30.0d

14.0d

5.0d

7.0d

180.0d

72.0d

10.0d

14.0d

5.0d

7.0d

60.0d

90.0d

176.0d

1.0d

1.0d

1.0d

2.0d

1.0d

3.0d

7.0d

1.0d

2.0d

7.0d

1.0d

3.0d

7.0d

2.0d

7.0d

5.0d

7.0d

3.0d

7.0d

1.0d

2.0d

30.0d

30.0d

44.0d

30.0d

42.0d

42.0d

57.0d

60.0d

85.0d

59.0d

83.0d

83.0d

85.0d

36.0d

103.0d

103.0d

103.0d

103.0d

72.0d

72.0d

90.0d

70.0d

70.0d

89.0d

100.0d

71.0d

89.0d

70.0d

89.0d

70.0d

92.0d

70.0d

87.0d

69.0d

69.0d

5-DAY

5-DAY

7-DAY

5-DAY

7-DAY

7-DAY

5-DAY

5-DAY

7-DAY

5-DAY

7-DAY

7-DAY

7-DAY

6-DAY

6-DAY

6-DAY

6-DAY

6-DAY

6-DAY

6-DAY

CURE

6-DAY

6-DAY

CURE

6-DAY

6-DAY

CURE

6-DAY

CURE

6-DAY

CURE

6-DAY

CURE

6-DAY

6-DAY

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

None

Anticipated Notice to Proceed (6/27/2024)

Prepare and submit railing shop drawings

DOMI review of railing shop drawings

Revise and resubmit railing shop drawings

DOMI review and acceptance railing shop drawings

Anticipated Notice to Proceed (6/27/2024)

Prepare Precast Panel Shop Drawings

DOMI Review of Precast Panel Shop Drawings

Revise and Resubmit Precast Panel Shop Drawings

DOMI Review and Acceptance of Precast Panel Shop Drawings

Anticipated Notice to Proceed (6/27/2024)

Monitor and Progress Schedule, On-Site Pre Construction Meeting

Install E&S Controls

Remove Existing Guiderail along McCandless Avenue

Clearing and Grubbing

On-Site Pre Construction Meeting, Erect Advanced Warning Signs, Mobilization , Demolish Existing Stairs

Clearing and Grubbing, Pre-Concrete Meeting, Structural Steel - Soldier Piles, Implement Traffic Control

Drill caissons - set soldier piles for retaining wall - pour caisson concrete

Cure caisson concrete, Pre-Concrete Meeting, Fabricate precast lagging

Install precast panels

Form, tie, and pour closure pours

Cure closure pours

Pre-Concrete Meeting, Cure closure pours

Drill caissons for landings 4, 3, 2, and 1, set cages, and pour

Cure caisson concrete, Pre-Concrete Meeting

Form, tie, and pour columns at landings 4, 3, 2, and 1

Cure column concrete at landings 4, 3, 2, and 1

Form, tie, pour caps at landings 4, 3, 2, and 1

Pre-Concrete Meeting, Form, tie, pour caps at landings 4, 3, 2, and 1

Excavate, form, tie, and pour foundation at landing 5

Cure foundation at landing 5

Backfill foundation at landing 5, Cure caps at landings 4, 3, 2, and 1, Fabricate precast components, Backfill soldier pile wall

DOMI review of railing shop drawings

Revise and resubmit railing shop drawings

DOMI review and acceptance railing shop drawings

Fabricate railings

Install railing

DOMI Review of Precast Panel Shop Drawings

Revise and Resubmit Precast Panel Shop Drawings

DOMI Review and Acceptance of Precast Panel Shop Drawings

Fabricate precast lagging

Install precast panels

Drill caissons - set soldier piles for retaining wall - pour caisson concrete

Remove Existing Guiderail along McCandless Avenue

Clearing and Grubbing

Drill caissons - set soldier piles for retaining wall - pour caisson concrete, Demolish Existing Stairs

Implement Traffic Control

Drill caissons - set soldier piles for retaining wall - pour caisson concrete

Cure caisson concrete

Install precast panels

Form, tie, and pour closure pours

Cure closure pours

Backfill soldier pile wall, Drill caissons for landings 4, 3, 2, and 1, set cages, and pour

Set precast components

Cure caisson concrete

Form, tie, and pour columns at landings 4, 3, 2, and 1

Cure column concrete at landings 4, 3, 2, and 1

Form, tie, pour caps at landings 4, 3, 2, and 1

Cure caps at landings 4, 3, 2, and 1, Excavate, form, tie, and pour foundation at landing 5

Set precast components

Cure foundation at landing 5

Backfill foundation at landing 5

Set precast components

Excavate, form, tie, and pour pad at landing 0

Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors

2 3 4 1

July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5

34 35 36 37 38 39 40 41 42 43 44

200.200

200.201

200.202

200.210

200.220

200.230

200.240

200.245

200.250

300.010

300.020

800.010

800.020

800.030

800.40

Excavate, form, tie, and pour pad at landing 0

Cure pad at landing 0

Form, tie, and pour walls at landing 0

Cure walls at landing 0

Backfill walls at landing 0

Install railing

Restore pavement along Stanton and McCandless Aves

Reinstall guideraill along McCandless Ave

Remove Traffic Control

Seeding / E&S Controls

Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th)

Remove E&S controls

Project Closeout

Final Inspection

Project Punchlist Items

Project Complete

Project Deadline (Finish on or before August 25th)

02 Dec 24

05 Dec 24

09 Dec 24

11 Dec 24

18 Dec 24

14 Mar 25

19 Dec 24

21 Dec 24

17 Mar 25

15 Mar 25

15 Mar 25 *

26 Apr 25

28 Apr 25

28 Apr 25

29 Apr 25

12 May 25

12 May 25

04 Dec 24

07 Dec 24

10 Dec 24

17 Dec 24

18 Dec 24

15 Mar 25

20 Dec 24

21 Dec 24

17 Mar 25

26 Apr 25

25 Apr 25

26 Apr 25

12 May 25

28 Apr 25

12 May 25

12 May 25

12 May 25

3.0d

3.0d

2.0d

7.0d

1.0d

2.0d

2.0d

1.0d

1.0d

43.0d

42.0d

1.0d

11.0d

1.0d

10.0d

69.0d

85.0d

68.0d

84.0d

68.0d

36.0d

68.0d

104.0d

36.0d

0.0d

0.0d

0.0d

0.0d

0.0d

0.0d

0.0d

0.0d

6-DAY

CURE

6-DAY

CURE

6-DAY

6-DAY

6-DAY

6-DAY

6-DAY

7-DAY

7-DAY

6-DAY

5-DAY

5-DAY

5-DAY

5-DAY

5-DAY

None

None

None

None

None

None

None

None

None

None

Start on or after

None

None

None

None

None

None

Set precast components, Pre-Concrete Meeting

Excavate, form, tie, and pour pad at landing 0

Cure pad at landing 0, Pre-Concrete Meeting

Form, tie, and pour walls at landing 0

Cure walls at landing 0

Backfill walls at landing 0, Fabricate railings

Backfill walls at landing 0

Restore pavement along Stanton and McCandless Aves

Restore pavement along Stanton and McCandless Aves, Install railing, Reinstall guideraill along McCandless Ave

Restore pavement along Stanton and McCandless Aves

Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th)

Remove E&S controls

Final Inspection, Remove E&S controls, Remove Traffic Control

Monitor and Progress Schedule, Project Punchlist Items

Project Complete

Cure pad at landing 0

Form, tie, and pour walls at landing 0

Cure walls at landing 0

Backfill walls at landing 0

Install railing, Restore pavement along Stanton and McCandless Aves

Remove Traffic Control

Remove Traffic Control, Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th), Reinstall guideraill along McCandless Ave

Remove Traffic Control

Project Punchlist Items

Remove E&S controls

Project Punchlist Items, Final Inspection

Project Punchlist Items

Project Complete

Project Deadline (Finish on or before August 25th), Project Completion

Milestone Appearances

Diamond

File details come from the government source that posted it. Updated .