McCandless_Steps_-_Pre-Bid_CPM_Schedule_-_4-10-2024.pdf
PDF 231 KB Posted
- Attached to
- Stanton Ave/McCandless Ave Stairs Construction
- Solicitation number
- 2024-IFB-309
- Issued by
- Allegheny County, Pennsylvania
About this file
This document is a Critical Path Method (CPM) Schedule for the Stanton Ave/McCandless Ave Stairs Construction project, prepared for the City of Pittsburgh's Department of Mobility and Infrastructure (DOMI). The comprehensive project schedule spans from June 27, 2024, to May 12, 2025, detailing a multi-phase construction process involving pre-construction activities, site preparation, structural work, and project closeout. Key activities include developing quality control plans, obtaining necessary approvals, installing environmental and safety controls, drilling caissons, setting soldier piles, pouring concrete, installing precast panels and components, constructing landings, forming and pouring walls and foundations, and completing final site restoration tasks.
The schedule indicates a project duration of approximately 11 months, with specific milestones such as mobilization, pre-construction meetings, traffic control implementation, and phased construction activities across multiple landings. Critical path activities include caisson drilling, concrete pouring, curing periods, panel and component installation, and final site restoration. The project includes specific technical requirements like seeding and erosion control, with prescribed germination periods between March 15th and June 1st, and August 1st to October 15th. The final project deadline is set for August 25th, with the contractor required to complete all construction, restoration, and closeout activities by May 12, 2025.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors
2024 2025 2 3 4 1
July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5
34 35 36 37 38 39 40 41 42 43 44
010.10
010.20
010.40
030.05
030.10
030.20
030.30
030.40
040.05
040.10
040.40
040.50
040.60
040.70
060.05
060.10
060.15
060.20
060.25
070.01
070.10
070.15
070.20
070.25
Administrative Tasks
Anticipated Notice to Proceed (6/27/2024)
Mobilization
Project Completion
PRE-CONSTRUCTION ACTIVITIES
Concrete QC Plans and Mix Designs
Develop/Submit QC Plans and Mix Designs
DOMI Review
Revise and Resubmit QC Plans and Mix Designs
DOMI Review and Approval
Pre-Concrete Meeting
Advanced Notice/RNAs
Notify County Conservation District
Notice to Municipalities and Emergency Services
Erect Advanced Warning Signs
Initial Press Release Notification
PA One Call
On-Site Pre Construction Meeting
CPM Schedule
Develop CPM Schedule
DOMI Review
Revise/Resubmit CPM Schedule
DOMI Review and Acceptance
Monitor and Progress Schedule
Precast Components
Prepare and submit precast component shop drawings
DOMI review of precast component shop drawings
Revise and resubmit precast component shop drawings
DOMI Review and Acceptance of precast component shop drawings
Fabricate precast components
27 Jun 24
27 Jun 24 *
11 Jul 24
12 May 25
27 Jun 24
27 Jun 24
27 Jun 24
05 Jul 24
19 Jul 24
26 Jul 24
02 Aug 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
27 Jun 24
12 Jul 24
26 Jul 24
02 Aug 24
09 Aug 24
27 Jun 24
27 Jun 24
28 Jul 24
12 Aug 24
17 Aug 24
24 Aug 24
12 May 25
27 Jun 24
11 Jul 24
12 May 25
13 Mar 25
02 Aug 24
03 Jul 24
18 Jul 24
25 Jul 24
01 Aug 24
02 Aug 24
10 Jul 24
10 Jul 24
10 Jul 24
06 Jul 24
06 Jul 24
29 Jun 24
27 Jun 24
13 Aug 24
11 Jul 24
25 Jul 24
01 Aug 24
08 Aug 24
13 Aug 24
24 Oct 24
27 Jul 24
10 Aug 24
16 Aug 24
23 Aug 24
24 Oct 24
218.0d
1.0d
250.0d
36.0d
5.0d
14.0d
5.0d
7.0d
1.0d
13.0d
14.0d
14.0d
10.0d
10.0d
3.0d
1.0d
33.0d
10.0d
14.0d
5.0d
7.0d
5.0d
83.0d
30.0d
14.0d
5.0d
7.0d
60.0d
0.0d
0.0d
112.0d
0.0d
42.0d
139.0d
98.0d
139.0d
97.0d
139.0d
97.0d
160.0d
165.0d
165.0d
169.0d
169.0d
176.0d
117.0d
85.0d
85.0d
121.0d
85.0d
121.0d
126.0d
79.0d
112.0d
112.0d
79.0d
113.0d
113.0d
5-DAY
5-DAY
5-DAY
5-DAY
7-DAY
7-DAY
5-DAY
7-DAY
5-DAY
7-DAY
5-DAY
7-DAY
Calendar Day
Calendar Day
Calendar Day
Calendar Day
Calendar Day
5-DAY
5-DAY
5-DAY
7-DAY
5-DAY
7-DAY
Calendar Day
5-DAY
7-DAY
7-DAY
5-DAY
7-DAY
7-DAY
None
Start on
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
Anticipated Notice to Proceed (6/27/2024), PA One Call, Notify County Conservation District, Notice to Municipalities and Emergency Services, Erect Advanced Warning
Signs, Initial Press Release Notification
Project Complete
Anticipated Notice to Proceed (6/27/2024)
Develop/Submit QC Plans and Mix Designs
DOMI Review
Revise and Resubmit QC Plans and Mix Designs
DOMI Review and Approval
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Anticipated Notice to Proceed (6/27/2024)
Develop CPM Schedule
DOMI Review
Revise/Resubmit CPM Schedule
DOMI Review and Acceptance
Anticipated Notice to Proceed (6/27/2024)
Prepare and submit precast component shop drawings
DOMI review of precast component shop drawings
Revise and resubmit precast component shop drawings
DOMI Review and Acceptance of precast component shop drawings
Mobilization , Develop/Submit QC Plans and Mix Designs, Notify County Conservation District, Notice to Municipalities and Emergency Services, Erect
Advanced Warning Signs, Initial Press Release Notification, Develop CPM Schedule, Prepare and submit railing shop drawings, On-Site Pre Construction
Meeting, Prepare and submit precast component shop drawings, Prepare Precast Panel Shop Drawings, Structural Steel - Soldier Piles, PA One Call
Implement Traffic Control
DOMI Review
Revise and Resubmit QC Plans and Mix Designs
DOMI Review and Approval
Pre-Concrete Meeting
Drill caissons - set soldier piles for retaining wall - pour caisson concrete, Install precast panels, Drill caissons for landings 4, 3, 2, and 1, set cages, and pour, Form, tie, and pour columns at landings 4, 3, 2, and 1, Excavate, form, tie, and pour pad at landing 0, Form, tie, and pour walls at landing 0, Excavate, form, tie, and pour foundation at landing 5
Mobilization
Mobilization
Mobilization , Implement Traffic Control
Mobilization
Mobilization
Implement Traffic Control, Install E&S Controls
DOMI Review
Revise/Resubmit CPM Schedule
DOMI Review and Acceptance
Monitor and Progress Schedule
Project Complete, Install E&S Controls
DOMI review of precast component shop drawings
Revise and resubmit precast component shop drawings
DOMI Review and Acceptance of precast component shop drawings
Fabricate precast components
Set precast components
Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors
2 3 4 1
July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5
34 35 36 37 38 39 40 41 42 43 44
080.05
080.15
080.20
080.25
080.30
100.05
100.10
100.15
100.20
100.21
100.25
200.020
200.030
200.040
200.041
200.045
200.050
200.060
200.070
200.071
200.080
200.100
200.110
200.130
200.140
200.150
200.160
200.165
200.170
200.180
200.185
200.190
Railing
Prepare and submit railing shop drawings
DOMI review of railing shop drawings
Revise and resubmit railing shop drawings
DOMI review and acceptance railing shop drawings
Fabricate railings
Retaining Wall - Precast Lagging and Soldier Piles
Prepare Precast Panel Shop Drawings
DOMI Review of Precast Panel Shop Drawings
Revise and Resubmit Precast Panel Shop Drawings
DOMI Review and Acceptance of Precast Panel Shop Drawings
Fabricate precast lagging
Structural Steel - Soldier Piles
Construction Work
Install E&S Controls
Remove Existing Guiderail along McCandless Avenue
Clearing and Grubbing
Demolish Existing Stairs
Implement Traffic Control
Drill caissons - set soldier piles for retaining wall - pour caisson concrete
Cure caisson concrete
Install precast panels
Form, tie, and pour closure pours
Cure closure pours
Backfill soldier pile wall
Drill caissons for landings 4, 3, 2, and 1, set cages, and pour
Cure caisson concrete
Form, tie, and pour columns at landings 4, 3, 2, and 1
Cure column concrete at landings 4, 3, 2, and 1
Form, tie, pour caps at landings 4, 3, 2, and 1
Cure caps at landings 4, 3, 2, and 1
Excavate, form, tie, and pour foundation at landing 5
Cure foundation at landing 5
Backfill foundation at landing 5
Set precast components
27 Jun 24
27 Jun 24
09 Aug 24
23 Aug 24
30 Aug 24
07 Sep 24
27 Jun 24
27 Jun 24
12 Jul 24
26 Jul 24
02 Aug 24
09 Aug 24
27 Jun 24
14 Aug 24
14 Aug 24
15 Aug 24
16 Aug 24
17 Aug 24
26 Sep 24
27 Sep 24
01 Oct 24
09 Oct 24
10 Oct 24
12 Oct 24
19 Oct 24
19 Oct 24
23 Oct 24
30 Oct 24
01 Nov 24
08 Nov 24
15 Nov 24
15 Nov 24
19 Nov 24
26 Nov 24
27 Nov 24
13 Mar 25
08 Aug 24
22 Aug 24
29 Aug 24
06 Sep 24
13 Mar 25
08 Oct 24
11 Jul 24
25 Jul 24
01 Aug 24
08 Aug 24
08 Oct 24
26 Sep 24
17 Mar 25
14 Aug 24
15 Aug 24
16 Aug 24
19 Aug 24
26 Sep 24
30 Sep 24
07 Oct 24
09 Oct 24
11 Oct 24
18 Oct 24
19 Oct 24
22 Oct 24
29 Oct 24
31 Oct 24
07 Nov 24
14 Nov 24
21 Nov 24
18 Nov 24
25 Nov 24
26 Nov 24
30 Nov 24
176.0d
30.0d
14.0d
5.0d
7.0d
180.0d
72.0d
10.0d
14.0d
5.0d
7.0d
60.0d
90.0d
176.0d
1.0d
1.0d
1.0d
2.0d
1.0d
3.0d
7.0d
1.0d
2.0d
7.0d
1.0d
3.0d
7.0d
2.0d
7.0d
5.0d
7.0d
3.0d
7.0d
1.0d
2.0d
30.0d
30.0d
44.0d
30.0d
42.0d
42.0d
57.0d
60.0d
85.0d
59.0d
83.0d
83.0d
85.0d
36.0d
103.0d
103.0d
103.0d
103.0d
72.0d
72.0d
90.0d
70.0d
70.0d
89.0d
100.0d
71.0d
89.0d
70.0d
89.0d
70.0d
92.0d
70.0d
87.0d
69.0d
69.0d
5-DAY
5-DAY
7-DAY
5-DAY
7-DAY
7-DAY
5-DAY
5-DAY
7-DAY
5-DAY
7-DAY
7-DAY
7-DAY
6-DAY
6-DAY
6-DAY
6-DAY
6-DAY
6-DAY
6-DAY
CURE
6-DAY
6-DAY
CURE
6-DAY
6-DAY
CURE
6-DAY
CURE
6-DAY
CURE
6-DAY
CURE
6-DAY
6-DAY
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
None
Anticipated Notice to Proceed (6/27/2024)
Prepare and submit railing shop drawings
DOMI review of railing shop drawings
Revise and resubmit railing shop drawings
DOMI review and acceptance railing shop drawings
Anticipated Notice to Proceed (6/27/2024)
Prepare Precast Panel Shop Drawings
DOMI Review of Precast Panel Shop Drawings
Revise and Resubmit Precast Panel Shop Drawings
DOMI Review and Acceptance of Precast Panel Shop Drawings
Anticipated Notice to Proceed (6/27/2024)
Monitor and Progress Schedule, On-Site Pre Construction Meeting
Install E&S Controls
Remove Existing Guiderail along McCandless Avenue
Clearing and Grubbing
On-Site Pre Construction Meeting, Erect Advanced Warning Signs, Mobilization , Demolish Existing Stairs
Clearing and Grubbing, Pre-Concrete Meeting, Structural Steel - Soldier Piles, Implement Traffic Control
Drill caissons - set soldier piles for retaining wall - pour caisson concrete
Cure caisson concrete, Pre-Concrete Meeting, Fabricate precast lagging
Install precast panels
Form, tie, and pour closure pours
Cure closure pours
Pre-Concrete Meeting, Cure closure pours
Drill caissons for landings 4, 3, 2, and 1, set cages, and pour
Cure caisson concrete, Pre-Concrete Meeting
Form, tie, and pour columns at landings 4, 3, 2, and 1
Cure column concrete at landings 4, 3, 2, and 1
Form, tie, pour caps at landings 4, 3, 2, and 1
Pre-Concrete Meeting, Form, tie, pour caps at landings 4, 3, 2, and 1
Excavate, form, tie, and pour foundation at landing 5
Cure foundation at landing 5
Backfill foundation at landing 5, Cure caps at landings 4, 3, 2, and 1, Fabricate precast components, Backfill soldier pile wall
DOMI review of railing shop drawings
Revise and resubmit railing shop drawings
DOMI review and acceptance railing shop drawings
Fabricate railings
Install railing
DOMI Review of Precast Panel Shop Drawings
Revise and Resubmit Precast Panel Shop Drawings
DOMI Review and Acceptance of Precast Panel Shop Drawings
Fabricate precast lagging
Install precast panels
Drill caissons - set soldier piles for retaining wall - pour caisson concrete
Remove Existing Guiderail along McCandless Avenue
Clearing and Grubbing
Drill caissons - set soldier piles for retaining wall - pour caisson concrete, Demolish Existing Stairs
Implement Traffic Control
Drill caissons - set soldier piles for retaining wall - pour caisson concrete
Cure caisson concrete
Install precast panels
Form, tie, and pour closure pours
Cure closure pours
Backfill soldier pile wall, Drill caissons for landings 4, 3, 2, and 1, set cages, and pour
Set precast components
Cure caisson concrete
Form, tie, and pour columns at landings 4, 3, 2, and 1
Cure column concrete at landings 4, 3, 2, and 1
Form, tie, pour caps at landings 4, 3, 2, and 1
Cure caps at landings 4, 3, 2, and 1, Excavate, form, tie, and pour foundation at landing 5
Set precast components
Cure foundation at landing 5
Backfill foundation at landing 5
Set precast components
Excavate, form, tie, and pour pad at landing 0
Line Activity ID Activity Desc. Start Finish Duration Total float Calendar Constraint Predecessors Successors
2 3 4 1
July August September October November December January February March April May 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5
34 35 36 37 38 39 40 41 42 43 44
200.200
200.201
200.202
200.210
200.220
200.230
200.240
200.245
200.250
300.010
300.020
800.010
800.020
800.030
800.40
Excavate, form, tie, and pour pad at landing 0
Cure pad at landing 0
Form, tie, and pour walls at landing 0
Cure walls at landing 0
Backfill walls at landing 0
Install railing
Restore pavement along Stanton and McCandless Aves
Reinstall guideraill along McCandless Ave
Remove Traffic Control
Seeding / E&S Controls
Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th)
Remove E&S controls
Project Closeout
Final Inspection
Project Punchlist Items
Project Complete
Project Deadline (Finish on or before August 25th)
02 Dec 24
05 Dec 24
09 Dec 24
11 Dec 24
18 Dec 24
14 Mar 25
19 Dec 24
21 Dec 24
17 Mar 25
15 Mar 25
15 Mar 25 *
26 Apr 25
28 Apr 25
28 Apr 25
29 Apr 25
12 May 25
12 May 25
04 Dec 24
07 Dec 24
10 Dec 24
17 Dec 24
18 Dec 24
15 Mar 25
20 Dec 24
21 Dec 24
17 Mar 25
26 Apr 25
25 Apr 25
26 Apr 25
12 May 25
28 Apr 25
12 May 25
12 May 25
12 May 25
3.0d
3.0d
2.0d
7.0d
1.0d
2.0d
2.0d
1.0d
1.0d
43.0d
42.0d
1.0d
11.0d
1.0d
10.0d
69.0d
85.0d
68.0d
84.0d
68.0d
36.0d
68.0d
104.0d
36.0d
0.0d
0.0d
0.0d
0.0d
0.0d
0.0d
0.0d
0.0d
6-DAY
CURE
6-DAY
CURE
6-DAY
6-DAY
6-DAY
6-DAY
6-DAY
7-DAY
7-DAY
6-DAY
5-DAY
5-DAY
5-DAY
5-DAY
5-DAY
None
None
None
None
None
None
None
None
None
None
Start on or after
None
None
None
None
None
None
Set precast components, Pre-Concrete Meeting
Excavate, form, tie, and pour pad at landing 0
Cure pad at landing 0, Pre-Concrete Meeting
Form, tie, and pour walls at landing 0
Cure walls at landing 0
Backfill walls at landing 0, Fabricate railings
Backfill walls at landing 0
Restore pavement along Stanton and McCandless Aves
Restore pavement along Stanton and McCandless Aves, Install railing, Reinstall guideraill along McCandless Ave
Restore pavement along Stanton and McCandless Aves
Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th)
Remove E&S controls
Final Inspection, Remove E&S controls, Remove Traffic Control
Monitor and Progress Schedule, Project Punchlist Items
Project Complete
Cure pad at landing 0
Form, tie, and pour walls at landing 0
Cure walls at landing 0
Backfill walls at landing 0
Install railing, Restore pavement along Stanton and McCandless Aves
Remove Traffic Control
Remove Traffic Control, Complete Seeding / Germination (March 15th to June 1st, and August 1st to October 15th), Reinstall guideraill along McCandless Ave
Remove Traffic Control
Project Punchlist Items
Remove E&S controls
Project Punchlist Items, Final Inspection
Project Punchlist Items
Project Complete
Project Deadline (Finish on or before August 25th), Project Completion
Milestone Appearances
Diamond