This document is a Special Provision for Maintenance and Protection of Traffic (Item 9000-0012) for the City of Pittsburgh's Department of Mobility and Infrastructure, specifically related to the Stanton Ave/McCandless Ave Stairs Construction project. The document outlines the contractor's responsibilities for traffic management, including developing a Traffic Control Plan that must be signed and sealed by a Transportation Professional and submitted to the City for approval. Key requirements include providing two weeks advance notice to multiple city departments and services, obtaining an obstruction permit, and maintaining traffic flow on Stanton Avenue and McCandless Avenue during construction, with specific lane and bike lane maintenance provisions.

The traffic management plan allows for potential lane restrictions during construction hours with representative approval, and includes a provision for a potential full closure of McCandless Avenue to accommodate crane operations for setting precast elements. The payment for these traffic control services will be handled as a Lump Sum (LS), covering all materials and labor required for installation, maintenance, and removal of traffic control devices. The contractor is responsible for coordinating with nearby construction activities, securing necessary permits, and ensuring minimal disruption to existing traffic patterns while facilitating the stair construction project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM 9000-0012 MAINTENANCE AND PROTECTION OF TRAFFIC

In accordance with Section 901 and as follows:

DESCRIPTION – Add the following:

This work is the furnishing, installing, maintaining and protection of traffic adjacent to and within the Work Zone including the Active Work Zone, and relocating of traffic control devices.

It is the Contractor’s responsibility to develop the Traffic Control Plan. The Traffic Control Plan shall be signed, sealed, and endorsed by a Transportation Professional and submitted to the City for approval.

The contractor is responsible for securing all permits and coordinating with nearby construction activity and events.

CONSTRUCTION – Add the following:

Provide two (2) weeks advance notice to affected municipality, emergency services, City of Pittsburgh Police (412-323-7800), City of Pittsburgh Department of Mobility and Infrastructure (412-255-2597), City of Pittsburgh Department of Public Works (412-255-8850), City of Pittsburgh Public Schools (Administration 412-529-4357), Allegheny County Port Authority, Chuck Rompala (412-566-5321).

Obtain an obstruction permit from the City of Pittsburgh Department of Mobility and Infrastructure, Permits Division as needed.

Outline the Active Work Zone with construction fencing and channelizing devices and obtain approval from the Representative on the layout prior to performing any work.

Maintain traffic on Stanton Avenue at all times. Two 11-ft minimum lanes and the existing bike lane including buffer must be maintained during non-construction hours. Traffic may be restricted to one lane during construction hours with the approval of the Representative and in accordance with the approved MPT plan. In this case, provide flagging or any other appropriate traffic control device.

McCandless Avenue may require full closure and a short-term detour to accommodate the crane that will set the precast elements. The crane will be located along McCandless Avenue. A detour plan will be submitted in accordance with MUTCD. Once precast elements are set into place, maintain traffic on McCandless Avenue. Traffic may be restricted to one lane during construction hours with the approval of the Representative and in accordance with the approved MPT plan. In this case, provide flagging or any other appropriate traffic control device.

MEASURMENT AND PAYMENT – Lump Sum (LS)

Includes all materials and labor required for the proper installation, maintenance, and removal of all traffic control devices.

END OF SPECIAL PROVISION