McAAP Specifications_DRAFT.pdf

PDF 15 MB Posted

Attached to
Ammunition Demolition Shop, McAlester Army Ammunition Plant, Oklahoma
Solicitation number
Not on record
Issued by

About this file

The provided document is a draft specification for the Ammunition Demolition Shop project at the McAlester Army Ammunition Plant in Oklahoma. This is in response to a Special Notice Request from the Department of the Army Corps of Engineers Engineering District Tulsa, seeking industry input for preliminary planning purposes in the acquisition of the Ammunition Demolition Shop. This is not a solicitation for proposals, and no contract will be awarded from this request. The Special Notice Request document, a PLA Markey Survey, and industry Questions are attached. The key details provided include a description of the project, the government agency involved, and that no reimbursement will be made for costs associated with providing information in response to this request or any follow up requests. This document appears to be a draft specification for the potential future acquisition of the Ammunition Demolition Shop.

View the file

Other files

File Type Posted
Questions for Industry.pdf PDF
PLA Markey Survey.pdf PDF
Special Notice Request.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: W912BV23R0029 McAlester Army Ammunition Plant Project Number: 65443 Ammunition Demolition Shop

SECTION 01 11 00

SUMMARY OF WORK

08/ 15, CHG 2: 08/ 21

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The base scope of work includes the construction of Ammunition Demolition process facilities at McAlester Army Ammunition Plant (MCAAP). The Ammunition Demolition Shop includes demilitarization process facilities for machine out, melt out, wash out, control, boiler and unattended process control rooms, employee changing rooms, break room, and railroad spur access. Project also includes special foundations, heating plant, fire tank and pump, railroad spur, building information systems, fire protection and alarm systems, and Utility Monitoring Control Systems (UMCS) connection.

Options include the following as indicated on the drawings: an additional water storage tank; Lightning Protection System at Control and Boiler buildings; West Rail Spur; and Emergency access gravel road, fencing, and gates.

1.1.2 Location

The work is located at the McAlester Army Ammunition Plant in McAlester, Oklahoma, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.3 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

1.3.1 Notification Prior to Excavation

Notify the Contracting Officer at least 21 days prior to starting

SECTION 01 11 00 Page 1 Ready To Advertise July 17, 2023 excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

11/ 22, CHG 1: 02/ 23

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours are between 6:00 a.m. and 4:30 p.m., Monday through Thursday, excluding Federal holidays.

1.3 FEDERAL HOLIDAYS

The following Federal holidays are excluded from standard work days:

SECTION 01 14 00 Page 1 Ready To Advertise August 4, 2023

HOLIDAY DATE OBSERVED

New Year's Day 1 January

Martin Luther King's Birthday 3rd Monday in January

President's Day 3rd Monday in February

Founder's Day May 35, 2023

Memorial Day Last Monday in May

Junteenth Day 19 June

Independence Day Shut Down 3-4 July

Labor Day 1st Monday in September

Columbus Day 2nd Monday in October

Veteran's Day 11 November

Thanksgiving 4th Thursday in November

Christmas Holiday Shut Down 25-28 December

When one of the designated holidays falls on a Friday or Saturday, holiday will be observed on Thursday. If the holiday falls on a Sunday, holiday will be observed on the following Monday.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air and steam are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

SECTION 01 14 00 Page 2

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.3 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

1.3.1 ANTITERRORISM (AT)/OPERATIONS SECURITY (OPSEC) PROVISIONS

1.3.1.1 AT Level I Training

All Contractor employees, to include subcontractor employees, requiring access to Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

https://jko.jten.mil ; or it can be provided by the RA ATO in presentation form which will be documented via memorandum.

1.3.1.2 Access and General Protection/Security Policy and Procedures

All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

1.3.1.2.1 Contractors Who Do Not Require CAC, But Require Access To A DoD Facility Or Installation

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater

SECTION 01 14 00 Page 3 regulations.

1.3.1.3 Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something)

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

1.3.1.4 OPSEC Standing Operating Procedure/Plan

OPSEC Plan can be as simple as a document that spells out how the contractor will protect the sensitive information given to him to accomplish the contract or any sensitive information gathered in the course of accomplishing the contract. This should include how documents/data will be stored when not in use and who will control them.

We need some deliverable assurances that either what we give to the contractor or what they gather as work product that is of a sensitive nature is protected.

1.3.1.5 OPSEC Training

All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training.

OPSEC awareness training is available at the following websites:

https://www.iad.gov/ioss/ or https://www.cdse.edu/catalog/operations-security.html ; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 4

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/ 20, CHG 2: 05/ 22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

SD-07 Certificates

Superintendent Qualifications ; G

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for

SECTION 01 30 00 Page 1 unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent who must be a graduate engineer or architect with a minimum of 10 years professional experience. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.

The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent.

The Superintendent may serve no other roles.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION CONFERENCE

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value

SECTION 01 30 00 Page 2 engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out.

Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.8.1 Facilitated (Formal) Partnering

a. Within 90 calendar days after award and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .

c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.

Partnering session may take place concurrently with the Pre-Construction Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

SECTION 01 30 00 Page 3

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 00 Page 4

SECTION 01 30 01.00 47

ADDITIONAL ADMINISTRATIVE REQUIREMENTS

10/ 19, CHG 1: 02/ 23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule

1.2 ADDITIONAL ADMINISTRATIVE REQUIREMENTS

The conditions listed below are additional administrative requirements incorporated into this Section.

1.2.1 Contractor Supply and Use of Electronic Software for Processing Construction Wage Rate Requirements Statute Certified Labor Payrolls

a. The Contractor shall use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Construction Wage Rate Requirements statute.

b. The Contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with the Construction Wage Rate Requirements statute. When the Contractor uses an electronic payroll system, the electronic payroll service shall be used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. The Contractor shall obtain and provide electronic system access to the Government, as required to comply with the Construction Wage Rate Requirements over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the Contractor.

c. The Contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:

(1) Commercially available;

(2) Compliant with appropriate Construction Wage Rate Requirements statute payroll provisions in the Federal Acquisition Regulation

SECTION 01 30 01.00 47 Page 1

(FAR);

(3) Able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;

(4) No payroll data shall be entered in RMS 3.0 CM;

(5) Demonstrated security of data and data entry rights;

(6) Ability to produce Contractor-certified electronic versions of weekly payroll data;

(7) Ability to identify erroneous entries and track the date/time of all versions of the certified Construction Wage Rate Requirements statute payrolls submitted to the government over the life of the contract; and

(8) Capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.

d. All Contractor-incurred costs related to the Contractor's provision and use of an electronic payroll processing service shall be included in the Contractor's price for the overall work under the contract. The costs for compliance with the Construction Wage Rate Requirements statute by using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.

1.2.2 Equipment Ownership and Operating Expense Schedule

a. This requirement does not apply to terminations. See UAI 5152.249-9000, Basis for Settlement of Proposals, and FAR part 49.

b. Allowable costs for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the Contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the Contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8 Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

c. Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, SECTION 01 30 01.00 47 Page 2 except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

d. When actual equipment costs are proposed and the total amount of the pricing action exceeds the simplified acquisition threshold (SAT), the contracting officer shall request the Contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

1.2.3 Payment for Materials Delivered Off-Site

a. Pursuant to FAR 52.232-5, Payments Under Fixed Price Construction Contracts, materials delivered to the Contractor at locations other than the site of the work may be taken into consideration in making payments if included in payment estimates and if all the conditions of the General Provisions are fulfilled. Payment for items delivered to locations other than the work site shall be limited to:

(1) Materials required by the technical provisions; or

(2) Materials that have been fabricated to the point where they are identifiable to an item of work required under this contract; or

(3) Items specifically listed below.

b. Payment for materials delivered off-site shall be made only after receipt of paid invoices listing the value of material and labor incorporated in the items along with a canceled check showing the Prime Contractor's title to the items delivered off site. Payment for materials delivered off-site shall be limited to the following items:

(1) AS AUTHORIZED BY THE CONTRACTING OFFICER.

1.2.4 Required Insurance (FAR 28.307-2)

The Contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance:

a. Workmen's Compensation and Employer's Liability Insurance in compliance with applicable state statutes, with a minimum liability coverage of $100,000.

b. Comprehensive General Liability Insurance for bodily injury in the minimum limits of $500,000 per occurrence. No property damage liability insurance is required.

c. Comprehensive Automobile Liability Insurance covering the operation of all automobiles used in connection with the performance of the contract in the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $25,000 per occurrence for property damage.

The Contractor agrees to insert the substance of this clause, including this paragraph, in all subcontracts hereunder.

SECTION 01 30 01.00 47 Page 3

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 01.00 47 Page 4

SECTION 01 32 01.00 10

PROJECT SCHEDULE MILCON-SRM-O&M

03/ 22, CHG 2: 05/ 23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. DEPARTMENT OF DEFENSE (DOD)

DA PAM 415-28 (2006) Guide to Army Real Property Category Codes

UFC 1-300-08 (2009; with Change 2, 2011) Criteria for Transfer and Acceptance of DoD Real Property

AFCATCODE 2010 (2010) AIR FORCE CATEGORY CODES

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1110-345-723 (2017) TOTAL BUILDING COMMISSIONING

PROCEDURES

ER 1-1-11 (2017) Administration - Project Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING, when included in the project.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Preliminary Project Schedule ; G

Initial Project Schedule ; G

Recovery Schedule ; G

SECTION 01 32 01.00 10 Page 1

Construction Completion Schedule ; G

Periodic Schedule Monthly Update ; G

Preliminary Project Schedule Cost Loading ; G

Initial Project Schedule Cost Loading ; G

Recovery Project Schedule Cost Loading ; G

Construction Completion Schedule Cost Loading ; G

Weekly Progress Meeting Minutes : G

SD-07 Certificates

Designated Authorized Representative (DAR)- Project Scheduler Qualifications ; G

Documentation listing, not limited to:

a. Detailed documentation of experience in scheduling (school, training, software, years scheduling, etc.)

b. Minimum of 3 previously developed, created, and maintained projects similar in nature and complexity to the project, detailing name, contract amount, and location of projects.

c. Minimum of 2 years experiences scheduling construction projects similar in nature of this project.

d. Qualifications meet or exceed requirements under paragraph 1.3

"PROJECT SCHEDULER QUALIFICATIONS - DESIGNATED AUTHORIZED

REPRESENTATIVE

Submittals SD-01 and SD-07 shall be submitted as separate 4025's for approval.

1.3 DESIGNATED AUTHORIZED REPRESENTATIVE (DAR)- PROJECT SCHEDULER

QUALIFICATIONS

Designate an authorized representative(DAR)to be responsible for the preparation of the schedule and all required updating and production of reports. The DAR shall have no other responsibilities involving the project unless approved by the Contracting Officer. The DAR must have a minimum of 2-years' experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. DAR must have a comprehensive knowledge of CPM scheduling principles and application. DAR shall be same person or employee of a company approved under paragraph 1.2 "Submittals", SD-07 Certificates. A DAR change shall be submitted and approved,per paragraph 1.2 "Submittals", before new DAR takes over responsibilities from previous DAR. DAR to be responsible for the preparation of the schedule, all required updating, preparing of reports, and all requirements of this specification. DAR shall have experience in the use of the scheduling software that meets the requirements of this specification. USACE reserves the right to have DAR removed/replaced when schedule management, expertise, and performance are determined to be not

SECTION 01 32 01.00 10 Page 2 meeting the requirement set forth in this specification. If so requested by USACE, DAR shall come to site or USACE office for any meeting.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government will use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the scheduling software manufacturer.

2.1.3 Primavera

If Primavera P6 is selected for use, provide the ".xer" backup file in a version of P6 importable, uncorrupted, and loadable by the Government system. If xer file provided is incapable or does not meet this requirement and cannot load correctly (examples: CLINs not balancing when loaded on Government computer or contains POBS tables) USACE shall return for corrections and Contractor shall revise and resend for approval.

2.1.4 Other Than Primavera

If the Contractor chooses software other than Primavera P6, the software shall be compliant with this specification. The software routine used to create the required SDEF file must be created and supported by the software manufacturer. In addition, the Contractor shall provide for the Government's use two licenses, two computers, and software training for two Government employees by a certified training firm, which that cost will include any expenses required for travel, meals, transportation, and overnight accommodations. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned to the Contractor at project completion.

2.1.5 Conversion from One Scheduling Software to Another

The scheduling software utilized to create the schedule shall be the one used for the project. Creating the schedule in one scheduling software and conversing to another scheduling software is prohibited. Also, conversion utilizing spreadsheet or word documentation software is prohibited.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, "Schedule for Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated

SECTION 01 32 01.00 10 Page 3 for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development.

Subcontractors and suppliers Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each monthly update period and therefore the amount of each progress payment.

Lack of an approved monthly update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment.The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

Based on USACE requirements, Contractor can present a separate Pay Application for bonds before the Preliminary schedule is approved, however no additional Pay Applications shall be presented and/or processed until an acceptable and approved schedule submittal is in place. Before any Pay Application and/or schedule update files are transmitted through RMS, the SDEF that was created from the accepted and approved schedule submittal or updated monthly schedule shall be loaded into RMS and accepted.

A separate "bond" Pay Application can be presented by Contractor however USACE will require that a "bond" SDEF be created and approved before such Pay Application can be processed. Contractor shall get requirements from

USACE.

3.2.1 Activity Cost Loading

Contractor shall transmit via 4025 in RMS a cost loading submittal named Preliminary Project Schedule Cost Loading , Initial Project Schedule Cost Loading , Recovery Project Schedule Cost Loading , Construction Completion Schedule Cost Loading and receive approval of cost loading before submission of Preliminary, Initial, Recovery, or Construction Completion Schedule submittals, and executed modifications that involve cost loading of individual activities to evaluate the cost loading to determine if cost loading is reasonable and without front end loading. Non-compliance with this requirement will result in an automatic rejection of Preliminary, Initial, Recovery, or Construction Completion Schedule submittals and approval of executed modification activities to be inserted into the schedule that costs associated with them. Cost loading shall be done within the time frame required for submission of schedule submittals per paragraphs 3.4 "PROJECT SCHEDULE SUBMISSIONS", 3.4.1 " Preliminary Project Schedule Submission", 3.4.2 "Initial Project Schedule Submission", and 3.4.3 "Recovery Schedule or Construction Completion Schedule Submission".

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer. See additional cost loading requirements under paragraphs 3.3.20.1 "As-Built Drawings", 3.3.20.2 "O & M Manuals", and 3.3.20.3 "Correction of Punch List". Contractor to present cost loading to USACE by means of submittal in RMS, utilizing spreadsheet format or report created from scheduling software,acceptable to USACE.

SECTION 01 32 01.00 10 Page 4

Each activity shall be cost loaded and subtotaled by CLINs whether or not there is a cost associated with the activity.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the Preliminary, Initial, Recovery, Construction Completion and/or Periodic Schedule, executed modification activities to be added to schedule, and will result in rejection of payment requests until compliance is met.

Until the Preliminary, Initial, Recovery, Construction Completion Periodic Schedule Update Schedules or executed modification activities to be added to schedule are approved, no Pay Applications shall be processed or approved for payment. If Pay Application is presented before acceptance and approval of any schedule submittal, the Pay Application will be returned with no action taken. See 3.2 "BASIS FOR PAYMENT AND COST LOADING" for process given on bonds.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent project schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made or reject Pay Application with no further action until such corrections are made.

In the case where the Periodic Monthly Schedule Update, Recovery Schedule Monthly Update, or Construction Completion Monthly Update schedule is status and shows the project is 10 calendar days or more in total negative total float, the Contracting officer may withhold 10 percent in retainage.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. Contracting Officer will have the right to have Contractor provide additional detail to schedule as deemed warranted.

Contractor shall provide a submittal activity for administrative, design, construction, or close-out activity that requires a submittal (even if submittal is for information only) broken down into the following four (4)Descriptions: "Prep", "Submit", "Government Review", and "Approval", unless activity is for procurement, then follow directions in paragraph

3.3.4 "Procurement Activities". The activity called "Prep" shall represent time to prepare submittal or design before submitting. The original duration for Submit shall not include any days for Prep.

Submittal activities are not allowed to be cost loaded. Original duration for "Submit" and "Approval" activity shall be one (1) calendar day.

"Government Review" shall be based on contract requirements. If contract requirements does not give original duration for Government review in work or calendar days, then duration shall be 30 calendar days.

Using BOD, Beneficial Occupancy, Substantial Completion, Turn Over, or any other description related to Owner acceptance as an activity and/or

SECTION 01 32 01.00 10 Page 5 description is prohibited.

The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Non-procurement activities (tasks) shall have Original Durations (OD) no greater than 10 work days or 14 calendar days. This does not include activities that are "placeholders" for activities in the Preliminary Schedule that will be broken down further in the Initial Schedule. Once the schedule (Preliminary, Initial, Recovery, Construction Completion, or Periodic Update Schedule Updates) is approved, no changes to original activity durations shall be made without prior approval of the Government.

3.3.3 Design and Permit Activities

Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the Preliminary, Initial, Recovery, Construction Completion, or Periodic Update Schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period.

Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.Also include review and correction periods associated with each item.

3.3.4 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence shall include the string of activities: Prep, Submit, Government Review, Approve, Procure, Fabricate, Deliver and Payment, with Payment being the cost loaded activity.The Payment activity shall be clarified during cost loading submittal if that cost will represent stored materials or materials that will be installed immediately once on site, or stored on site. Contractor shall follow FAR requirements for any stored materials for payments.

3.3.5 Holiday Periods for Government Reviews and Actions

The Contractor shall not schedule meetings, Government reviews, or responses during the last two weeks of December or other official Federal Government holidays (including Friday after Thanksgiving) and shall exclude such dates and periods from any durations specified for Government actions.

3.3.6 Mandatory Tasks

Include the following activities/tasks in the Preliminary (as applicable), Initial, Recovery, Construction Completion Project Schedules and Periodic Monthly Schedule updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

SECTION 01 32 01.00 10 Page 6

b. Submission, review and acceptance/approval of features requiring design completion.

c. Submission, review, and acceptance/approval of design packages.

d. Submission, review, and acceptance/approval of mechanical/electrical/information systems layout drawings.

e. Long procurement activities

f. Submission, review, and acceptance/approval of O & M manuals.

g. Submission, review, and acceptance/approval of as-built drawings.

h. Submission, review, and acceptance/approval of DD1354 data and installed equipment lists.

i. Submission, review, and acceptance/approval of testing and air balance(TAB)report.

j. Submission, review, and acceptance/approval of TAB specialist design review report.

k. Submission, review, and acceptance/approval of fire protection specialist.

l. Submission, review, and acceptance/approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion. Provide activities and comply with paragraph 3.3.7.9 "Commissioning Coding (MCOM)".

m. Air and water balancing.

n. Building commissioning - Functional Performance Testing.

o. Submission, review, and acceptance/approval of Controls testing plan submission.

p. Submission, review, and acceptance/approval of Controls testing.

q. Performance Verification testing.

r. Submission, review, and acceptance/approval of other systems testing, if required.

s. Contractor's pre-final inspection.

t. Correction of punch list from Contractor's pre-final inspection.

u. Government's pre-final inspection.

v. Correction of punch list from Government's pre-final inspection.

w. Final inspection.

SECTION 01 32 01.00 10 Page 7

3.3.7 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements. No Government Activities shall be cost loaded.

3.3.8 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . Contractor shall create the schedule using the following codes for each individual project. Contractor shall define each activity code as a PROJECT activity code. This exact structure is mandatory. All Activity Codes shall be developed and assigned to activities as detailed herein.

The SDEF format is as follows:

Field Activity Code

Length Description

1 WRKP 3 Workers Per Day

2 RESP 4 Responsible Party

3 AREA 4 Area of Work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of Work

7 CATW 1 Category of Work

8 FOW 20 Feature of Work *

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements. Activity Code shown shall be exactly used in the software.

3.3.8.1 Workers Per Day Coding (WRKP)

Assign Workers Per Day code (WRKP) for all field construction or direct work activities, if directed by the Contracting Officer. Workers Per Day shall be the number of workers (crew size) expected each day to perform a task for the duration of that activity. This code shall be used when Contractor is required to provide a resource (manloaded) loaded schedule.

Activities may have more than one WRKP code so as to document different number of resources assigned to that activity. Using RESP or any other activity code and/or resource/expenses to provide number of resources assign to an activity is prohibited. WRKP codes shall be numeric-alpha.

Example would be Code Value 3M, 3=CREW SIZE, M=Mason. Workers Per Day codes shall be imported through the SDEF conversion of the schedule into

SECTION 01 32 01.00 10 Page 8

RMS. Manual inputting of Workers Per Day codes into RMS is prohibited.

This code shall not be used as a means of tracking modifications to the contract or any other use except for above.

3.3.8.2 Responsible Party Coding (RESP)

Assign responsibility code (RESP) for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government "GOVT" Responsible Party code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements. Government "GOVT" Responsible Party code shall not be used for any activity that has costs associated with

it. For activities that require Government approval and must have cost associated with them, the Contractor shall use "ABTG" for those activities.

b. Activities cannot have more than one Responsible Party code. Examples of acceptable Responsible Party code values for (RESP) are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE). Assign Responsible Party code for all activities. Unacceptable code values are abbreviations of the names of prime contractors or subcontractors.

RESP codes shall be alpha; numeric is not allowed for RESP codes.

Responsible Party codes shall be imported through the SDEF conversion of the schedule into RMS. Manual inputting of Responsible Party codes into RMS is prohibited.

3.3.8.3 Area of Work Coding (AREA)

Assign Area of Work code (AREA) to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on…