This document is a Request for Quote (RFQ) for the procurement of appliances for buildings at Joint Base Lewis McChord (JBLM), Washington and Presidio of Monterey (POM), California. The RFQ includes a Standard Form 1449 (SF1449), an Excel version of Attachment #1, and a Word version of Attachment #8.
The key details are: Quotes are due by 12:00 Noon Central Standard Time (CST) on September 13, 2024, and must remain valid for 120 days. Vendors must submit quotes via email according to specific formatting and document requirements, including completing the SF1449, Attachment 1 Excel spreadsheet, and Attachment 8 Word document. Vendors are instructed to submit technical data sheets for each quoted item, organized sequentially. The RFQ is being issued by the U.S. Army Corps of Engineers, Huntsville Center, Furniture Team. Vendors are prohibited from contacting the onsite Technical Representative prior to contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT 1-RFQ-POM-646-Appliances.xlsx | XLSX spreadsheet | |
| SAM Gov RFQ W912DY24q0074 JBLM_POM Multi Bldgs.pdf | ||
| ATT 1-RFQ-JBLM-OPT 2020-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-JBLM-OPT 2021-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-JBLM-572-Appliances.xlsx | XLSX spreadsheet | |
| REV 6-6-24 ATT 1-RFQ-JBLM-9138-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-JBLM-OPT 12458-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-JBLM-12435-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-POM-648-Appliances.xlsx | XLSX spreadsheet | |
| REV 6-6-24 ATT 1-RFQ-JBLM-9137-Appliances.xlsx | XLSX spreadsheet | |
| ATT 1-RFQ-JBLM-574-Appliances.xlsx | XLSX spreadsheet | |
| MASTER NON-GSA ATT 8 - Vendor - JBLM Multi Bldgs - Appliances.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Review Round #1 Presidio of Monterey, CA - Building 646, 648 - Appliances
Vendor Instructions: The Technical Documents Checklist must be completed and returned in Word format by the contractor performing as the lead quoter. Each Vendor shall demonstrate in written form how they are meeting the FID (Att. 2) requirements. Manufacturer’s published catalogs and CAD drawings are acceptable forms of demonstrations. A blanket statement that Vendor is “meeting the FID requirement” or a quote submitted without the necessary documentation is considered non-conforming. Vendors must comment in the light blue fields only, in black text. HNC’s comments in the white fields in red text denotes the item is technically unacceptable or will be in black text when the item is technically acceptable. Vendor shall not modify prior rounds or HNC comments.
Technical Documents Checklist
Vendor or Lead Quoter:
Point of Contact for this RFQ:
Email Address:
Telephone Number:
For Admin Furnishings Tech Review answer questions 1-4. For Housing Furnishings Tech Review answer 2-4.
1. Do all quoted items meet all current environmental certificates?
Yes
No
If no, do not continue. To be considered for award all items shall meet current environmental certificates.
2. Are technical documents organized sequentially according to the Furniture Item Descriptions (FID)?
Yes
No
If no, do not continue; to be considered for award, technical documents shall be as stated above.
3. Do all quoted items meet all current required warranties?
Yes
No
If no, do not continue. To be considered for award, all items shall meet current warranties.
4. Are technical documents annotated to draw attention to the construction requirements and item descriptions required in the FID?
Yes
No
If no, do not continue. To be considered for award, technical documents shall be as stated above.
Vendors: Do not go beyond this point until requested as a response to clarifications / communications by HNC .
Vendor Technical Review of Quoted Items
HNC Clarification/Comment - white fields Vendor Reply- light blue fields
(INSERT EXCEL TABLE HERE)
To be completed by HNC only:
1st Round Technical Review
| Technically Acceptable: |
| Yes: |
No:
Date:
HNC Technical Evaluator:
Comments:
2nd Round Technical Review
| Technically Acceptable: |
| Yes: |
No:
Date:
HNC Technical Evaluator:
Comments:
3rd Round Technical Review
| Technically Acceptable: |
| Yes: |
No:
Date:
HNC Technical Evaluator:
Comments:
4th Round Technical Review
| Technically Acceptable: |
| Yes: |
No:
Date:
HNC Technical Evaluator:
Comments: