MassDOT_2026_Standard_Specifications_for_Highways_and_Bridges,_Amendments_to_Previous_Versions.pdf
PDF 479 KB Posted
- Attached to
- FY27-06 Guard Rail Products Installed
- Solicitation number
- FY27-06
- Issued by
- Berkshire County, Massachusetts
About this file
Summary of Files
The first file is an amendment document issued by the Massachusetts Department of Transportation detailing revisions to the 2026 edition of Standard Specifications for Highways and Bridges. This document encompasses comprehensive modifications across multiple sections affecting proposal requirements, insurance provisions, labor standards, measurement and payment methodologies, and construction specifications for earthwork, drainage, water systems, pavements, traffic control devices, structures, and materials. The amendments address updates published as of September 30, 2025, and incorporate standard specifications adopted through the fourth quarter of 2025, with changes intended to improve document accessibility and navigability through enhanced subsection numbering schemas.
The amendments introduce significant modifications to procurement and operational requirements, including revised proposal rejection criteria related to bonding capacity and prequalification status, expanded insurance requirements naming MassDOT and applicable railroads as additional insureds, and changes to payment calculations for extra work utilizing estimated rather than actual costs for FICA and insurance expenses. Notable revisions include comprehensive updates to traffic control device specifications, particularly for traffic signals and highway lighting with emphasis on verification inspection protocols and material documentation requirements, enhanced structural steel fabrication requirements with new M8.06 sections addressing shop approval, drawings, quality control and non-conformances, and material specification refinements addressing reinforcing bars, anchor bolts, epoxy coatings, and bridge-related steel components. Additional changes include deletion of temporary barrier specifications from Section 850 with establishment of new Section 853 for temporary barrier items, modifications to bridge joint and railing specifications, and updates to paint and protective coating standards incorporating zinc content specifications and QCML product requirements.
The second file is a competitive bid solicitation issued by the Berkshire Regional Group Purchasing Program (BRGPP) on behalf of 32 participating Berkshire County municipalities in Massachusetts for guardrail installation services under Contract FY27-06 for the fiscal period July 1, 2026 through June 30, 2027. The procurement encompasses installation of standard guard straight sections with steel posts at 12'6" and 6'3" spacings, curved guardrail configurations, steel terminal ends, deep post curved models, and supplementary services including removal and reset of existing guardrail, disposal of wood-treated products, and replacement of wood posts with steel posts, with work geographically organized across Northern, Central, and Southern Berkshire County divisions. Bids must be submitted through BRGPP's OpenGov online procurement portal no later than Thursday, April 2, 2026 at 1:00 p.m., with contract award anticipated by April 20, 2026 to the lowest responsive and eligible bidder; questions must be submitted by March 27, 2026 at 4:00 p.m.
All bidders must be pre-qualified by MassDOT for guardrail and fencing installation work and must comply with Massachusetts General Laws Chapter 149, Sections 26-27F and Chapter 30, Section 39M prevailing wage requirements, with certified weekly payroll submissions mandated throughout the contract period. A 5% bid deposit in the form of a bid bond, certified check, or cash is required for bids exceeding $50,000, and successful bidders must maintain comprehensive insurance coverage including $1,000,000 employer's liability, $1,000,000 automobile liability, and $1,000,000 general liability, along with a labor and materials payment bond equal to 50% of the contract value. Upon contract award, the successful bidder must pay a quarterly administrative fee of 1.75% of total reported purchases and submit quarterly reports within 21 days of each fiscal quarter end, with all prices remaining firm throughout the one-year contract period and exempt from federal excise taxes and Massachusetts sales tax. The estimated contract value for FY27-06 Guard Rail Installed is $40,114.00, and BRGPP retains the right to award to multiple bidders.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF MASSACHUSETTS
DEPARTMENT OF TRANSPORTATION
Amendments to the 2025 Edition of the Standard
Specifications for Highways and Bridges
Massachusetts Department of Transportation – Highway Division Standard Specifications for Highways and Bridges i
AMENDMENTS TO THE 2025 EDITION
Notes
For reference only, the following changes have been approved by the Department and incorporated into the 2026 edition of the Standard Specifications for Highways and Bridges.
This document is inclusive of the updates that were published as the Supplemental Specifications, dated September 30, 2025, and other standard specifications adopted through the last quarter of 2025.
To improve document accessibility and navigability, some subsection titles have been provided with additional numbering schema that had not existed in editions prior to 2025. These changes have not been specifically identified in this document.
This document is a companion to the Standard Specifications for Highways and Bridges but is not a part of the Standard Specifications for Highways and Bridges and is not a contract document. Any omissions contained herein are unintentional. In any case(s) where there are differences between the Standard Specifications and the changes listed below, the Standard Specifications shall prevail.
A.1
SECTION 2.00: PROPOSAL REQUIREMENTS AND CONDITIONS
Subsection 2.09: Rejection of Proposals
The first item in the bulleted list has been deleted and replaced with the following:
• award of the contract would result in the Bidder exceeding the Aggregate Bonding Capacity or the Single Bonding Capacity established by its Surety Company, or the Bidder's Proposal exceeds its Single Contract Limit, or the Bidder was not prequalified in the specified class of work on or before the time of bid opening; or
SECTION 7.00: LEGAL RELATIONS AND RESPONSIBILITY TO
PUBLIC
Subsection 7.05: Insurance Requirements
7.05.C: General
The following item has been added to the numbered list:
7. The Massachusetts Department of Transportation and applicable railroads shall be named as additional insureds.
Subsection 7.22: Labor, Lodging, Board, Maximum Hours of Employment, Minimum Wage Rates, Payment of Wages, Keeping of Payroll Records
This subsection has been renamed and replaced in its entirety.
SECTION 9.00: MEASUREMENT AND PAYMENT
Subsection 9.03: Payment for Extra Work
9.03.B: Payment for work or materials for which no price is contained in the Contract
The language of item 2 from the numbered list has been changed from “Plus 13 percent of direct labor, for actual costs of Federal Insurance Contributions Act (FICA),” to “Plus 13 percent of direct labor, for estimated costs of Federal Insurance Contributions Act (FICA).”
The language of item 3 from the numbered list has been changed from “Plus the actual cost of Workmen’s Compensation and Liability Insurance,” to “Plus the estimated cost of Workmen’s Compensation and Liability Insurance.”
A.2
SECTION 100: EARTHWORK, GRADING, DEMOLITION, RODENT
CONTROL AND BORINGS
SUBSECTION 119: CONTROL OF RODENTS
COMPENSATION
119.80: Method of Measurement
This construction specification has been added.
SUBSECTION 140: EXCAVATION FOR STRUCTURES
COMPENSATION
140.80: Method of Measurement
The following paragraph has been deleted:
“The unit of measurement for drainage structure abandoned or removed will be each structure abandoned for each structure removed, complete.”
The following paragraph has been added:
“Drainage structure abandoned and drainage structure removed will be measured each by the respective structure abandoned or removed.”
SECTION 200: DRAINAGE
SUBSECTION 201: BASINS, MANHOLES AND INLETS
COMPENSATION
201.80: Method of Measurement
This construction specification has been replaced in its entirety.
SECTION 300: WATER SYSTEMS
SUBSECTION 301: WATER SYSTEMS
CONSTRUCTION METHODS
301.60: General
301.60.G: Laying Pipe
The following paragraph has been deleted:
“Cast iron pipe sections shall be laid with the bell on the upgrade end. Before laying the pipe, the outside of the spigot and the inside of the bell shall be wire brushed and wiped clean and dry. When
A.3 placing a length of pipe, the yarning material for the joint shall be held around the bottom of spigot so that it will enter the bell as the pipe is shoved into position.”
The following paragraph has been added:
“Pipe sections shall be laid with the bell on the upgrade end. Before laying the pipe, the outside of the spigot and the inside of the bell shall be wire brushed and wiped clean and dry.”
COMPENSATION
301.80: Method of Measurement
The term “cast iron” has been removed from the last sentence of the first paragraph.
The following paragraph has been deleted:
“Fittings, consisting of bends, tees, caps, wyes, sleeves, reducers, increasers, blow-off fittings and other specials, applies only when new materials are necessary and which are not specifically provided for under other items in the Proposal. Fittings other than new will not be paid separately but only under the applicable foot items. When new fittings are measured for payment under the pound price for Item 308, the length occupied by the fittings will not be measured for payment under the foot items.”
The following paragraph has been added:
“Fittings, consisting of bends, tees, caps, wyes, sleeves, reducers, increasers, blow-off fittings and other special fittings, apply only when new materials are necessary and which are not specifically provided for under other items in the Proposal. Fittings other than new will not be paid separately but only under the applicable pipe items. When new fittings are measured separately for payment, the length of pipe occupied by the fittings will not be measured for payment.”
SECTION 400: SUB-BASE, BASE COURSES, SHOULDERS,
PAVEMENTS AND BERMS
SUBSECTION 466: STRESS ABSORBING MEMBRANE & STRESS ABSORBING
MEMBRANE INTERLAYER
COMPENSATION
The numbering schema for these construction specifications has been changed from 466.90, 466.91, and 466.92 to 466.80, 466.81, and 466.82, respectively.
SUBSECTION 476: CEMENT CONCRETE PAVEMENT
COMPENSATION
The numbering schema for these construction specifications has been changed from 476.70, 476.71, and 476.72 to 476.80, 476.81, and 476.82, respectively.
A.4
SUBSECTION 486: ULTRATHIN BONDED OVERLAY
COMPENSATION
The numbering schema for these construction specifications has been changed from 486.90, 486.91, and 486.92 to 486.80, 486.81, and 486.82, respectively.
SECTION 600: HIGHWAY GUARD, FENCES AND WALLS
SUBSECTION 644: CHAIN LINK FENCES AND GATES
COMPENSATION
644.80: Method of Measurement
The following paragraph has been deleted:
“Gates with gate posts will be measured between centers of the gate posts.”
The following paragraphs have been added:
“Gates with gate posts will be measured by the foot between centers of the gate posts.
“End posts and corner or intermediate brace posts will be measured by the unit each.”
SUBSECTION 660: METAL PIPE RAIL
MATERIALS
660.40: General
The materials reference table has been replaced in its entirety.
The following paragraph has been added:
“All material shall be inspected at the time of delivery for damage. All material shall be delivered with the required material documentation including certificates of compliance and mill test reports.
Storage of material shall conform to 960.66: Receiving, Handling and Storage on Site.”
CONSTRUCTION METHODS
660.60: Fabrication and Erection
This construction specification has been replaced in its entirety.
SECTION 700: INCIDENTAL WORK
SUBSECTION 710: BOUNDS
COMPENSATION
710.80: Method of Measurement
This construction specification has been added.
A.5
710.81: Basis of Payment
This construction specification has been replaced in its entirety.
SUBSECTION 722: CONSTRUCTION SCHEDULING
This subsection has been added.
SUBSECTION 740: ENGINEER’S FIELD OFFICE
This subsection has been renamed.
COMPENSATION
740.80: Method of Measurement
This construction specification has been added.
SECTION 800: TRAFFIC CONTROL DEVICES
SUBSECTION 815: TRAFFIC CONTROL SIGNALS
DESCRIPTION
815.20: General
The following sentence has been added to the 14th paragraph:
“Shop drawings shall be in accordance with Subsection 5.02: Plans and Detail Drawings.”
MATERIALS
815.40: General
The following paragraph has been added:
“Fabricated material arriving on site shall have the Verification Inspectors stamp and the required documentation. No material shall be accepted on site without the Verification Inspector’s stamp on the material and the required documentation. Material shipped without such stamp shall be rejected. The Contractor shall confirm proper alignment and fitment of the material prior to installation. Any damage from shipping and handling shall be immediately brought to the Engineer’s attention and repair procedures shall be submitted by the fabricator through the Contractor. Storage of material shall conform to 960.66: Receiving, Handling, and Storage on Site.”
815.43: Mast Arms, Strain Poles, and Span Wire Assemblies
This construction specification has been replaced in its entirety.
CONSTRUCTION METHODS
815.61: Coatings
A.6
815.62: Signals
815.62.A: General
The following paragraphs have been added:
“Acceptance will be conducted by the Department. If manufacturing imperfections cause the misalignment of bolted spliced connections to exceed design tolerances of ± ³⁄₁₆ in., the Engineer shall be notified prior to acceptance. If accepted the field misalignment shall be noted on the record shop drawing for that structure with the date and initialed by the Design engineer.
“Contractors will be responsible for responding to deficiencies identified during initial construction inspections. Evidence of repairs specifically requested by the Department must be provided for final acceptance and payment.”
SUBSECTION 820: HIGHWAY LIGHTING
DESCRIPTION
820.20: General
The 9th and 10th paragraphs were replaced with:
“Within 30 days following execution of the Contract, the Contractor shall submit to the Engineer for approval, a list of equipment which they propose to install. The submission shall include all equipment identified on the plans or in the specifications by the name of the manufacturer, model or identifying number of each item. The list shall be supplemented by catalog cuts and such other data as may be required, including wiring diagrams of any special equipment and of any proposed minor deviation from the plans. All of the above data shall be submitted in accordance with Subsection 5.02: Plans and Detail Drawings. The Department shall not be liable for any material purchased, labor performed, or delay to the work prior to such review and approval.
“The warranties that the Contractor receives from each manufacturer of equipment and materials pertinent to the complete and satisfactory operation of highway lighting installation shall be turned over to the Department at the time of acceptance of the project, at no cost to the Department. Each warranty so furnished shall indicate its expiration date and be in effect for a minimum period of one year from the date the highway lighting was placed in continuous operation. To be accepted for continuous operations the structure must pass initial ancillary structure inspection in accordance with 820.61: Tests Required Before Acceptance.”
820.21: Definitions
820.21.A: Highway Lighting Poles
Aluminum has been deleted as an option.
820.21.B: High Mast Tower
“Galvanized steel” has replaced “steel.”
A.7
MATERIALS
820.40: General
The 4th paragraph was deleted and replaced with:
“Highway lighting structures shall conform to M8.18.2: Highway Lighting Poles and Arms.
Fabricated material shall be in accordance with M8.06: Fabrication. The Fabricator shall be listed on the MassDOT Approved fabricators list under the Signs, Luminaires and Signal Supports category. All requirements for design and materials shall be in conformance with M8.18.2: Highway Lighting Poles and Arms.
“Fabricated material arriving on site shall have the Verification Inspectors stamp of approval and the required documentation. No material shall be accepted on site without the Verification Inspector’s stamp on the material and the required documentation. Material shipped without such stamp shall be rejected. The contractor shall confirm proper alignment and fitment of the material prior to installation. Any damage from shipping and handling shall be immediately brought to the Engineer’s attention and repair procedure shall be submitted from the fabricator through the contractor. Storage of material shall conform to 960.66: Receiving, Handling and Storage on Site.”
820.41: Design and Equipment Requirements
This construction specification has been replaced in its entirety.
CONSTRUCTION METHODS
820.60: General
The fourth paragraph has been replaced by the following paragraphs:
“Anchor rods shall be lubricated, and nuts shall be tightened using the turn-of-the-nut-method in accordance with 840.64: Overhead Sign Support Structures.
“The length of exposed thread below the bottom of the leveling nuts shall not exceed one bolt diameter in height above the concrete foundation.”
The following definition of “plumb” has been added to the sixth paragraph:
“…defined as less than 1-¼ in. over 4 ft. after accounting for taper…”
820.61: Tests Required Before Acceptance
820.61.B: Structural Inspection
A.8
SUBSECTION 828: TRAFFIC SIGNS
DESCRIPTION
828.20: General
The third paragraph has been replaced with the following:
“Sign foundations and supports shall be fabricated and erected in conformity with Subsection 840:
Sign Supports.”
SUBSECTION 840: SIGN SUPPORTS
DESCRIPTION
840.20: General
This construction specification has been replaced in its entirety.
840.21: Contractor Responsibilities
This construction specification has been added.
840.22: Staking and Field Measurements
This construction specification has been added.
840.23: Ground Mounted Sign Design
This construction specification has been added.
840.24: Overhead Sign Support Structure Design
This construction specification has been added.
840.25: Overhead Sign Support Structure Configuration
This construction specification has been added.
MATERIALS
840.30: General
This construction specification has been replaced in its entirety.
FABRICATION
840.40: General
This construction specification has been deleted.
CONSTRUCTION METHODS
840.60: General
This construction specification has been replaced in its entirety.
A.9
840.61: Pre-Installation Inspection
This construction specification has been added.
840.62: Foundations
This construction specification has been added.
840.63: Ground Mounted Sign Support Structures
This construction specification has been added.
840.64: Overhead Sign Support Structures
This construction specification has been added.
840.65: Ground Mounted Signs Without Concrete Foundations
This construction specification has been added.
DEPARTMENT ACCEPTANCE
840.70: General
This construction specification has been replaced in its entirety.
SUBSECTION 850: TRAFFIC CONTROL DEVICES FOR CONSTRUCTION AND
MAINTENANCE OPERATIONS
DESCRIPTION
850.29: Temporary Barrier and Temporary Barrier Removed and Reset
This construction specification has been deleted.
MATERIALS
850.49: Temporary Barrier
This construction specification has been deleted.
CONSTRUCTION METHODS
850.69: Temporary Barrier and Temporary Barrier Removed and Reset
This construction specification has been deleted.
COMPENSATION
850.80: Method of Measurement
Paragraphs related to Temporary Barrier and Temporary Barrier Removed and Reset have been deleted.
A.10
850.81: Basis of Payment
Paragraphs related to Temporary Barrier and Temporary Barrier Removed and Reset have been deleted.
850.82: Payment Items
Items related to Temporary Barrier and Temporary Barrier Removed and Reset have been deleted.
SUBSECTION 853: TEMPORARY BARRIER
This subsection has been added.
SECTION 900: STRUCTURES
SUBSECTION 901: CEMENT CONCRETE
DEPARTMENT ACCEPTANCE
901.64: Acceptance Sampling, Testing, and Inspection
901.64.B: Acceptance Testing
The first paragraph has been replaced in its entirety.
SUBSECTION 902: ULTRA-HIGH PERFORMANCE CONCRETE
CONSTRUCTION METHODS
902.32: Mockup
The width requirements for Link Slabs and Joint Headers in Table 902.32-1 have been modified.
902.33: Surface Preparation
Specification number corrected (previously shown as 902.32).
902.34: Temperature Control
Specification number corrected (previously shown as 902.33).
902.35: Protection from Adverse Conditions
Specification number corrected (previously shown as 902.34).
902.36: Formwork
Specification number corrected (previously shown as 902.35).
902.37: Mixing, Delivery, Handling, and Placing of Ultra-High Performance Concrete
Specification number corrected (previously shown as 902.36).
A.11
902.38: Finishing
Specification number corrected (previously shown as 902.37).
902.39: Curing
Specification number corrected (previously shown as 902.38).
SUBSECTION 940: DRIVEN PILES
DESCRIPTION
940.20: General
In the first paragraph, the word “close” has been removed from “close conformity.”
The following paragraph has been added:
“Material arriving on site shall be inspected for damage. All material shall have the required material documentation including certificates of compliance and mill test reports at the time of delivery. No material shall be accepted without documentation.”
MATERIALS
940.40: General
940.40.A: Length of Steel Pipe and H Piles
The second bullet in the list has been modified and the third bullet has been deleted.
940.40.D: Pile Shoes and Tips
The third paragraph has been replaced with the following:
“Steel pile shoes shall conform to subsection M8.03.2 Steel Castings.”
PILE INSTALLATION
940.65: Procedure for Driving
940.65.A: General
The following paragraph has been added:
“Any holes cut into a pile that are to remain in place shall be ground smooth and free of nicks and gouges. Holes are only permitted in the web.”
940.66: Splices
940.66.C: Steel Pipe Piles and Steel H Piles
This construction specification has been replaced in its entirety.
A.12
COMPENSATION
940.81: Basis of Payment
In the 11th paragraph, “and testing” has been added to “All costs for splicing and testing piles shall be included…”
SUBSECTION 960: STRUCTURAL STEEL AND MISCELLANEOUS METAL
PRODUCTS
This subsection has been replaced in its entirety.
SUBSECTION 972: STRIP SEAL BRIDGE JOINT SYSTEM
MATERIALS
972.40: General
Steel Extrusions section reference has been corrected to M8.05.8 from M8.05.7.
Fabrication Requirements has been added to the table.
972.60: General
This construction specification has been replaced in its entirety.
972.61: Preparation of Surfaces, Handling, and Storage
The second paragraph has been replaced in its entirety.
972.62: Pre-Installation Inspection
The following sentences have been added to the first paragraph:
“Material arriving on site shall have the Verification Inspectors stamp and the required documentation. No material shall be accepted on site without the Verification Inspector’s stamp on the material and the required documentation. Material shipped without such stamp shall be rejected.”
972.64: Field Splicing of Steel Extrusions
This construction specification has been replaced in its entirety.
SUBSECTION 975: METAL BRIDGE RAILINGS, PROTECTIVE SCREENS AND
SNOW FENCES
MATERIALS
975.40: General
The material requirements table has been replaced in its entirety.
A.13
CONSTRUCTION METHODS
975.61: Fabrication
This construction specification has been replaced in its entirety.
975.62: Pre-Installation Inspection
This construction specification has been added.
975.63: Setting Railing and Protective Screens
Specification renumbered from 975.62.
975.64: Galvanizing
Specification renumbered from 975.63 and replaced in its entirety.
975.64: Painting
This construction specification has been deleted.
975.65: Touch-up and Repairs
This construction specification has been replaced in its entirety.
975.66: Inspection
This construction specification has been deleted.
COMPENSATION
975.82: Payment Items
Item 975.2 has been deleted.
SUBSECTION 983: REVETMENT
DESCRIPTION
983.21: Classification
983.21.D: Slope Paving Under Bridges
This construction specification has been renamed and replaced in its entirety.
MATERIALS
983.40: General
References to sections M2.06.1 and M4.05.4 have been deleted and M4.06.7 have been added to the material requirements table.
A.14
CONSTRUCTION METHODS
983.64: Slope Paving Under Bridges
This construction specification has been renamed and replaced in its entirety.
COMPENSATION
983.82: Payment Items
Item 987. has been renamed “Slope Paving Under Bridge.”
The following items have been deleted: 987.1, 987.12, 987.2, and 987.3.
SUBSECTION 995: BRIDGE STRUCTURE
COMPENSATION
995.80: Method of Measurement
This construction specification has been added.
995.81: Basis of Payment
This construction specification has been replaced in its entirety.
SECTION M2: AGGREGATES AND RELATED MATERIALS
M2.01.0: Crushed Stone
The fourth paragraph has been changed to the following:
“The crushed stone shall have a maximum 45% wear as determined by the Los Angeles Abrasion Test (AASHTO T 96).
The table showing allowable wear by material type has been deleted.
M2.06.1: Slope Paving Under Bridge
This materials specification has been renamed.
SECTION M3: ASPHALTIC MATERIALS
M3.06.1: General
The following paragraph has been added:
“Approval of HMA mix designs shall be defined as the Department’s prequalification and verification of the mix design to ensure conformance with the materials requirements, design targets, and testing limits specified herein. The Contractor shall be responsible for selecting and placing approved HMA mix designs that meet the desired HMA properties, per the contract’s specified application.”
A.15
M3.06.4: Hot Mix Asphalt Mixture Design
The Sieve Sizes in Table M3.96.4-8 have been modified.
SECTION M5: PIPE, CULVERT SECTIONS AND CONDUIT
M5.01.0: Joint Materials for Pipe
This materials specification has been replaced in its entirety.
SECTION M7: PAINTS, PROTECTIVE COATINGS AND PAVEMENT
MARKINGS
M7.01.04: Fast Drying White and Yellow Waterborne Traffic Paint
This materials specification has been replaced in its entirety.
M7.04: Miscellaneous Coatings
The following language has been added to the materials specification for M7.04.07:
“Material shall meet ASTM A780, Annex A2, containing a minimum of 92% zinc by weight in the dry film. Material conforming to this specification shall be compatible with additional coats of an approved coating system to match existing coating system.”
The following language has been added to the materials specification for M7.04.11:
“Material shall meet ASTM A780, Annex A2, containing a minimum of 92% zinc by weight in the dry film. Material conforming to this specification shall be acceptable as the final condition, without additional coatings.”
M7.10.0: Galvanized Coatings
This materials specification has been replaced in its entirety.
M7.15.0: Metallized Coatings
This materials specification has been replaced in its entirety.
SECTION M8: METALS AND RELATED MATERIALS
M8.00.0: General
The following paragraph has been added:
“At the discretion of the Engineer, MassDOT will assign a Verification Inspector either employed by MassDOT or a Consultant inspector to act on behalf of the Department.”
The last paragraph has been replaced with the following:
“Samples for testing shall be taken in accordance with the applicable ASTM and/or AASHTO specification for the material. Samples shall be taken in the presence of the Verification Inspector when required. Field samples shall be taken by the Resident Engineer. Testing will be done in accordance with latest standard procedures of ASTM and/or AASHTO.”
A.16
M8.01.0: Reinforcing Bars
The following sentence has been added to the first paragraph:
“Reinforcing bars shall be from an approved supplier and manufacturer listed on the QCML.”
The following paragraph has been added:
“Coated reinforcement steel shall be secured using epoxy or plastic-coated tie wire.”
M8.01.2: Welded Steel Wire Fabric
The following sentence has been added to the first paragraph:
“Welded Steel Wire Fabric shall be from an approved supplier and manufacturer listed on the
QCML.”
M8.01.5: Anchor Bolts, Nuts, and Washers
This materials specification has been replaced in its entirety.
M8.01.7: Epoxy Coated Reinforcing Bars
This materials specification has been replaced in its entirety.
M8.04.1: Stud Shear Connectors
This materials specification has been replaced in its entirety.
M8.04.3: High Strength Bolts
This materials specification has been replaced in its entirety.
M8.05.0: Bridge Related Structural Steel
This materials specification has been renamed and replaced in its entirety.
M8.05.1: Steel Piles
This materials specification has been replaced in its entirety.
M8.05.4: Steel Sheeting
This materials specification has been replaced in its entirety.
M8.05.5: Steel Pipe Piles
This materials specification has been replaced in its entirety.
M8.05.6: Steel Casing for Drilled Shaft Foundations
This materials specification has been renamed and replaced in its entirety.
M8.05.7: Micropiles
This materials specification has been added.
A.17
M8.05.8: Steel Extrusions
This materials specification has been renumbered from M8.05.7 and replaced in its entirety.
M8.05.9: Bridge Railing, Steel
This materials specification has been added.
M8.06.0: Fabrication Requirements
This materials specification has been added.
M8.06.1: Fabrication Shop Approval
This materials specification has been added.
M8.06.2: Fabrication Shop Documents
This materials specification has been added.
M8.06.3: Fabrication Shop Drawings
This materials specification has been added.
M8.06.4: Fabrication Shop Schedule
This materials specification has been added.
M8.06.5: Fabrication Verification Inspection
This materials specification has been added.
M8.06.6: Fabrication Quality Control Inspection
This materials specification has been added.
M8.06.7: Fabrication Required Material Documentation
This materials specification has been added.
M8.06.8: Fabrication Non-conformances
This materials specification has been added.
M8.06.9: Fabrication Process
This materials specification has been added.
M8.10.0: Steel Pipe Rail or Fence
This materials specification has been replaced in its entirety.
M8.13.0: Aluminum Handrail, Protective Screen, and Snow Fence
A.18
M8.13.3: Aluminum Handrail, Protective Screen Type I and Type II, and Snow Fence
This materials specification has been deleted.
M8.18.0: Traffic Signal, Highway Lighting, and Sign Supports
This materials specification has been replaced in its entirety.
M8.18.1: Traffic Signal Supports
Charpy V Notch impact requirements has been changed from 15 ft-lb to 20 ft-lb.
AASHTO M 270 Grade 36 has been removed from the sixth paragraph.
The following paragraph has been deleted:
“Anchor bolt covers shall meet the requirements of ASTM A181/A181M or ASTM A126, Class A or AASHTO M 103M/M 103, Grade 450-240 (Grade 65-35) or ASTM A36/A36M.”
M8.18.2: Highway Lighting Poles and Arms
M8.18.2.A: Aluminum
This materials specification has been deleted.
M8.18.2.A: Steel
This materials specification has been renumbered from M8.18.2.B and replaced in its entirety.
M8.18.2.B: Anchor Bolts
This materials specification has been renumbered from M8.18.2.C and replaced in its entirety.
M8.18.3: Sign Supports
Charpy V Notch impact requirements has been changed from 15 ft-lb to 20 ft-lb.
ASTM A500 Grade C steel has been added to the second paragraph.
The 5th paragraph has been replaced in its entirety.
The following paragraph has been added:
“No transverse welds will be permitted in the tubular members, except at the base plate and flange plate connections or where reinforcing sleeves are required. Base plate and flange plate connections shall be socket-type connections with two continuous welds, one on the inside of the plate at the end of the tubular member and the other on the outside surface of the plate.
Alternatively, base plate and flange plate connections may be full-penetration groove-welded tube-to-transverse plate connections with backing ring attached to the plate with a full penetration weld, or with a continuous fillet-weld around the interior face of backing ring, combined with the backing ring welded to the interior of the tube with a continuous fillet-weld at the top face of the backing ring. All welds shall develop the full strength of the section at the point of connection.”
A.19
M8.18.3.A: Sign Posts – P5
M8.18.3.A.1: Square Tube Posts
The second paragraph has been replaced in its entirety.
SECTION M9: MISCELLANEOUS MATERIALS
M9.09.1: Primer
The following sentence has been added:
“Only products listed on the QCML will be accepted for use.”
M9.09.2: Damp-Proofing
The following sentence has been added:
“Only products listed on the QCML will be accepted for use.”
M9.12.0: Reflectors for Barriers
This materials specification has been deleted.
M9.14.5: Elastomeric Bearing Pads
M9.14.5.G: Testing Requirements
M9.14.5.G.5: Testing of Laminated Bearings
M9.14.5.G.5.c: Testing Requirements
Table M9.17.0-1: Physical Properties of Asphaltic Binder for Asphaltic Bridge Joint Systems was corrected to Table M9.14.5-1: Test requirements for Elastomeric Bearings.
M9.17.0: Asphaltic Binder for Asphaltic Bridge Joint System
In Table M9.17.0-1, the column for “Test Method” has been replaced in its entirety.
SECTION M10: TRAFFIC CONTROL DEVICES
M10.16.0: Temporary Barrier
This materials specification has been added.
M10.16.1: Limited Deflection Temporary Barrier
This materials specification has been added.
M10.16.2: Delineators for Temporary Barrier
| Commonwealth of Massachusetts Department of Transportation |
| Amendments to the 2025 Edition |
| Notes |
| Section 2.00: PROPOSAL REQUIREMENTS AND CONDITIONS |
| Subsection 2.09: Rejection of Proposals |
| Section 7.00: LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC |
| Subsection 7.05: Insurance Requirements |
| 7.05.C: General |
Subsection 7.22: Labor, Lodging, Board, Maximum Hours of Employment, Minimum Wage Rates, Payment of Wages, Keeping of Payroll Records
| Section 9.00: Measurement AND Payment |
| Subsection 9.03: Payment for Extra Work |
| 9.03.B: Payment for work or materials for which no price is contained in the Contract |
| Section 100: Earthwork, Grading, Demolition, Rodent Control and Borings |
| Subsection 119: Control of Rodents |
| Compensation |
| 119.80: Method of Measurement |
| Subsection 140: Excavation for Structures |
| Compensation |
| 140.80: Method of Measurement |
| Section 200: Drainage |
| Subsection 201: Basins, Manholes and Inlets |
| Compensation |
| 201.80: Method of Measurement |
| Section 300: Water Systems |
| Subsection 301: Water Systems |
| Construction Methods |
| 301.60: General |
| 301.60.G: Laying Pipe |
| Compensation |
| 301.80: Method of Measurement |
| Section 400: Sub-Base, Base Courses, Shoulders, Pavements and Berms |
| Subsection 466: Stress Absorbing Membrane & Stress Absorbing Membrane Interlayer |
| Compensation |
| Subsection 476: Cement Concrete Pavement |
| Compensation |
| Subsection 486: Ultrathin Bonded Overlay |
| Compensation |
| Section 600: highway Guard, Fences and Walls |
| Subsection 644: Chain Link Fences and Gates |
| Compensation |
| 644.80: Method of Measurement |
| Subsection 660: Metal Pipe Rail |
| Materials |
| 660.40: General |
| Construction Methods |
| 660.60: Fabrication and Erection |
| Section 700: Incidental Work |
| Subsection 710: Bounds |
| Compensation |
| 710.80: Method of Measurement |
| 710.81: Basis of Payment |
| Subsection 722: Construction Scheduling |
| Subsection 740: Engineer’s Field Office |
| Compensation |
| Section 800: Traffic Control Devices |
| Subsection 815: Traffic Control Signals |
| Description |
| 815.20: General |
| Materials |
| 815.40: General |
| 815.43: Mast Arms, Strain Poles, and Span Wire Assemblies |
| Construction Methods |
| 815.61: Coatings |
| 815.62: Signals |
| 815.62.A: General |
| Subsection 820: Highway Lighting |
| Description |
| 820.20: General |
| 820.21: Definitions |
| 820.21.A: Highway Lighting Poles |
| 820.21.B: High Mast Tower |
| Materials |
| 820.40: General |
| 820.41: Design and Equipment Requirements |
| Construction Methods |
| 820.60: General |
| 820.61: Tests Required Before Acceptance |
| 820.61.B: Structural Inspection |
| Subsection 828: Traffic Signs |
| Description |
| 828.20: General |
| Subsection 840: Sign Supports |
| Description |
| 840.20: General |
| 840.21: Contractor Responsibilities |
| 840.22: Staking and Field Measurements |
| 840.23: Ground Mounted Sign Design |
| 840.24: Overhead Sign Support Structure Design |
| 840.25: Overhead Sign Support Structure Configuration |
| Materials |
| 840.30: General |
| Fabrication |
| 840.40: General |
| Construction Methods |
| 840.60: General |
| 840.61: Pre-Installation Inspection |
| 840.62: Foundations |
| 840.63: Ground Mounted Sign Support Structures |
| 840.64: Overhead Sign Support Structures |
| 840.65: Ground Mounted Signs Without Concrete Foundations |
| Department Acceptance |
| 840.70: General |
| Subsection 850: Traffic Control Devices for Construction and Maintenance Operations |
| Description |
| 850.29: Temporary Barrier and Temporary Barrier Removed and Reset |
| Materials |
| 850.49: Temporary Barrier |
| Construction Methods |
| 850.69: Temporary Barrier and Temporary Barrier Removed and Reset |
| Compensation |
| 850.80: Method of Measurement |
| 850.81: Basis of Payment |
| 850.82: Payment Items |
Subsection 853: Temporary Barrier
| Section 900: Structures |
| Subsection 901: Cement Concrete |
| Department Acceptance |
| 901.64: Acceptance Sampling, Testing, and Inspection |
| 901.64.B: Acceptance Testing |
| Subsection 902: Ultra-High Performance Concrete |
| Construction Methods |
| 902.32: Mockup |
| 902.33: Surface Preparation |
| 902.34: Temperature Control |
| 902.35: Protection from Adverse Conditions |
| 902.36: Formwork |
| 902.37: Mixing, Delivery, Handling, and Placing of Ultra-High Performance Concrete |
| 902.38: Finishing |
| 902.39: Curing |
| Subsection 940: Driven Piles |
| Description |
| 940.20: General |
| Materials |
| 940.40: General |
| 940.40.A: Length of Steel Pipe and H Piles |
| 940.40.D: Pile Shoes and Tips |
| Pile Installation |
| 940.65: Procedure for Driving |
| 940.65.A: General |
| 940.66: Splices |
| 940.66.C: Steel Pipe Piles and Steel H Piles |
| Compensation |
| 940.81: Basis of Payment |
| Subsection 960: Structural Steel and Miscellaneous Metal Products |
| Subsection 972: Strip Seal Bridge Joint System |
| Materials |
| 972.40: General |
| 972.60: General |
| 972.61: Preparation of Surfaces, Handling, and Storage |
| 972.62: Pre-Installation Inspection |
| 972.64: Field Splicing of Steel Extrusions |
| Subsection 975: Metal Bridge Railings, Protective Screens and Snow Fences |
| Materials |
| 975.40: General |
| Construction Methods |
| 975.61: Fabrication |
| 975.62: Pre-Installation Inspection |
| 975.63: Setting Railing and Protective Screens |
| 975.64: Galvanizing |
| 975.64: Painting |
| 975.65: Touch-up and Repairs |
| 975.66: Inspection |
| Compensation |
| 975.82: Payment Items |
| Subsection 983: Revetment |
| Description |
| 983.21: Classification |
| 983.21.D: Slope Paving Under Bridges |
| Materials |
| 983.40: General |
| Construction Methods |
| 983.64: Slope Paving Under Bridges |
| Compensation |
| 983.82: Payment Items |
| Subsection 995: Bridge Structure |
| Compensation |
| 995.80: Method of Measurement |
| 995.81: Basis of Payment |
| Section M2: Aggregates and Related Materials |
| M2.01.0: Crushed Stone |
| M2.06.1: Slope Paving Under Bridge |
| Section M3: Asphaltic Materials |
| M3.06.1: General |
| M3.06.4: Hot Mix Asphalt Mixture Design |
| Section M5: Pipe, Culvert Sections and Conduit |
| M5.01.0: Joint Materials for Pipe |
| Section M7: Paints, Protective Coatings and Pavement Markings |
| M7.01.04: Fast Drying White and Yellow Waterborne Traffic Paint |
| M7.04: Miscellaneous Coatings |
| M7.10.0: Galvanized Coatings |
| M7.15.0: Metallized Coatings |
| Section M8: Metals and Related Materials |
| M8.00.0: General |
| M8.01.0: Reinforcing Bars |
| M8.01.2: Welded Steel Wire Fabric |
| M8.01.5: Anchor Bolts, Nuts, and Washers |
| M8.01.7: Epoxy Coated Reinforcing Bars |
| M8.04.1: Stud Shear Connectors |
| M8.04.3: High Strength Bolts |
| M8.05.0: Bridge Related Structural Steel |
| M8.05.1: Steel Piles |
| M8.05.4: Steel Sheeting |
| M8.05.5: Steel Pipe Piles |
| M8.05.6: Steel Casing for Drilled Shaft Foundations |
| M8.05.7: Micropiles |
| M8.05.8: Steel Extrusions |
| M8.05.9: Bridge Railing, Steel |
| M8.06.0: Fabrication Requirements |
| M8.06.1: Fabrication Shop Approval |
| M8.06.2: Fabrication Shop Documents |
| M8.06.3: Fabrication Shop Drawings |
| M8.06.4: Fabrication Shop Schedule |
| M8.06.5: Fabrication Verification Inspection |
| M8.06.6: Fabrication Quality Control Inspection |
| M8.06.7: Fabrication Required Material Documentation |
| M8.06.8: Fabrication Non-conformances |
| M8.06.9: Fabrication Process |
| M8.10.0: Steel Pipe Rail or Fence |
| M8.13.0: Aluminum Handrail, Protective Screen, and Snow Fence |
| M8.13.3: Aluminum Handrail, Protective Screen Type I and Type II, and Snow Fence |
| M8.18.0: Traffic Signal, Highway Lighting, and Sign Supports |
| M8.18.1: Traffic Signal Supports |
| M8.18.2: Highway Lighting Poles and Arms |
| M8.18.2.A: Aluminum |
| M8.18.2.A: Steel |
| M8.18.2.B: Anchor Bolts |
| M8.18.3: Sign Supports |
| M8.18.3.A: Sign Posts – P5 |
| M8.18.3.A.1: Square Tube Posts |
| Section M9: Miscellaneous Materials |
| M9.09.1: Primer |
| M9.09.2: Damp-Proofing |
| M9.12.0: Reflectors for Barriers |
| M9.14.5: Elastomeric Bearing Pads |
| M9.14.5.G: Testing Requirements |
| M9.14.5.G.5: Testing of Laminated Bearings |
| M9.14.5.G.5.c: Testing Requirements |
M9.17.0: Asphaltic Binder for Asphaltic Bridge Joint System
| Section M10: Traffic Control Devices |
| M10.16.0: Temporary Barrier |
| M10.16.1: Limited Deflection Temporary Barrier |
| M10.16.2: Delineators for Temporary Barrier |
File details come from the government source that posted it. Updated .