Market Intelligence Questionnaire EIE483 EIE484.pdf
PDF 410 KB Posted
- Attached to
- Market Intelligence for EIE483 and EIE484
- Solicitation number
- W911KB27RWP11
About this file
This is a Market Intelligence Questionnaire (Sources Sought/RFI) issued by the U.S. Army Corps of Engineers Alaska District to gather industry feedback on optimal project delivery methods and contracting vehicles for two military construction projects at Eielson Air Force Base, Alaska.
Project Scope and Details:
The questionnaire addresses two MILCON-funded projects: EIE483 (Joint Mobility Center Expansion, $249.2M, FY27-FY31) and EIE484 (225-Bed Permanent Party Dormitory, $305M, FY27-FY31). EIE483 involves design and construction of a 53,809-square-foot Deployment Processing Facility, 38,782-square-foot Hazardous Materials Storage facility, and 25,349 square feet of exterior covered storage canopies. Design begins FY27 with construction starting FY29. EIE484 involves construction of a 127,546-square-foot, 3-story permanent party dormitory housing 225 unaccompanied enlisted airmen, with design starting FY27 and construction beginning FY28. Both projects require responses by October 27, 2026, at 14:00 Alaska Time to four specified points of contact.
Delivery Method Options and Key Challenges:
The Government seeks industry input on five acquisition strategies: Accelerated Design-Build to Budget (DBtB), Construction Manager at Risk (CM At Risk-OTA), Design-Build (DB-FAR), Design-Bid-Build (DBB-FAR), and Progressive Design-Build (PDB-OTA). The questionnaire addresses significant site and project-specific challenges including high groundwater tables, permafrost-affected soils, PFAS and asbestos contamination, limited Alaskan construction windows, proximity to active airfields, mobilization constraints, temporary space requirements, budget realism, cost drivers, supply chain risks, collaboration priorities, contract incentive preferences, and evaluation strategies. Respondents must provide detailed technical responses addressing risk mitigation strategies, construction duration estimates, coordination approaches, and bonding capacity to support Government decision-making on project delivery structure.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Market Intelligence Questionnaire | Project Delivery & Acquisition Strategy
Market Intelligence Questionnaire
Project Delivery & Acquisition Strategy
Originating Agency U.S. Army Corps of Engineers / Alaska District
Document Type Sources Sought / Request for Information (RFI) Template
Target Audience Project Delivery Teams (PDTs) & Industry Partners
Classification Unclassified / Pre-Solicitation
Table of Contents
1. Project Information Packet (PIP)
Project Overviews & Constraints
2. Industry Questionnaire
Part I: Company Information & Bidding Intent
Part II: Project-Specific Challenges
1. Site and Environmental Constraints ………………
2. Schedule Risks & Limited Construction Window
3. Temporary Space Requirements ………………………………………..……………………………..................… 8
4. Construction Duration & Schedule Realism
5. Construction near Airfields (EIE483)
6. Mobilization & Start-Work Readiness (EIE483)
7. Mobilization & Start Work Readiness (EIE484) …………………
8. Unidentified Project Risks…………………………………………………………….……...............…………………10
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism
2. Primary Cost Drivers
3. Schedule/Supply Chain Risk
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities
2. Industry Engagement & Proprietary Meetings
3. Stipends (Honorariums) & Proposal Costs
4. Contract Incentives
5. Program Capability/Interest
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path
2. Basis of Recommendation & Contracting Vehicle
3. Evaluation Strategy
4. Commercial Best Practices & Concerns
1. Project Information Packet (PIP)
Project Overviews & Constraints EIE483 – Joint Mobility Center Expansion
Project Name & Location Joint Mobility Center Expansion, Eielson AFB, Alaska
Mission Statement Design and construction of a new Deployment Processing Facility.
The new facility will be occupied by 354th Logistics Readiness
Squadron personnel. The facility will contain areas for the Personnel
Deployment Function, Cargo Deployment Function, and
Deployment Control Center, plus building support spaces. The
Personnel Deployment Function area will contain a non-sterile holding area for processing passengers, a manifesting office for weighing passengers with their gear, a sterile holding area for passengers who have been manifested and are awaiting mission briefing, and a second sterile holding area for mission briefings.
Facility Type & Scale Deployment Processing Facility (53,809 SF), Hazardous Materials
Storage (38,782 SF), Exterior Covered Storage Canopies (25,349 SF)
Primary Functional Spaces The new Deployment Processing Facility will be appropriately sited relative to the airfield and supporting facilities and will house all spaces necessary to support Deployment Processing operations.
These spaces include Deployment Control Center with three double-occupant offices and open office area with 8 workstations;
non-sterile holding area for 250 passengers and 20 personnel;
sterile holding area for 250 passengers and 10 personnel; second sterile holding/briefing area for 250 passengers and 10 personnel.
Funding Type MILCON
Target Budget (CCL) $249.2M
Period of Performance FY27 – FY31
Critical Milestones Design Starts FY27 and Construction Starts FY29
EIE484 -225-Bed Permanent Party Dormitory
Project Name & Location 225-Bed Permanent Party Dorm, Eielson AFB, Alaska
Mission Statement Eielson’s current unaccompanied housing is at 129% utilization rate
(795 airmen and 615 beds) with more personnel still arriving in support of the F-35 bed down and other missions. Eielson currently has six permanent-party dormitories providing 615 rooms. This project is required to provide enough housing for enlisted personnel at Eielson with the construction of a 225-Bed Permanent
Party Dorm.
Facility Type & Scale Airmen Dormitory Housing (127,546 SF)
Primary Functional Spaces Construct a 3-story permanent party dormitory to house 225 unaccompanied enlisted airmen. Construction will include slab-on-grade and steel frame with concrete masonry unit block veneer and insulated metal panel over metal studs at exterior walls. Supporting facilities include 200 parking spaces, extension of steam, water, and sewer utilities, power distribution, and land scaping to service the new facility. Main facility spaces include 225 dormitory units, activity space, communal kitchens, dorm management office, public restroom, laundry, theater/meeting space, elevator, and mechanical/utility space.
Funding Type MILCON
Target Budget (CCL) $305M
Period of Performance FY27 – FY31
Critical Milestones Design Starts FY27 and Construction Starts FY28
2. Industry Questionnaire
Purpose: The Government seeks your expert feedback to select the optimal project delivery method and contracting vehicle (FAR-based or OTA) for the above facilities. Please email your response to
Mark Corn (Mark.R.Corn@usace.army.mil), Kim Tripp (Kimberly.D.Tripp@usace.army.mil), Theresa Afrank (Theresa.M.Afrank@usace.army.mil), and Jennifer Gosh (Jennifer.Gosh@usace.army.mil) by 27 October 2026 at 14:00 Alaska Time.
Accelerated Design-Build to Budget (DBtB)
FAR-based delivery approach where the Government develops sufficient project definition to competitively establish a Firm-Fixed-Price before collaborative design development.
Construction Manager at Risk (CM At Risk) - OTA
Project delivery method where a construction manager acts as a consultant to the owner during the design phase and transitions to a general contractor role during construction.
Design-Build (DB) - FAR
Design-build is a project delivery method where a single entity provides both the architectural design and construction services under one unified contract.
Design-Bid-Build (DBB) – FAR
Design-bid-build is a traditional, sequential construction project delivery method where an owner hires a designer and a contractor under two separate, independent contracts.
Progressive Design-Build (PDB) – OTA
Single design-build agreement. Phase 1 collaboratively matures the design and negotiates a Guaranteed
Maximum Price cost before the Government decides whether to proceed with construction.
Part I: Company Information & Bidding Intent
Company Name & CAGE Code
Point of Contact
Socioeconomic Status
(Check all that apply) ☐ Large Business
☐ Small Business (SB)
☐ 8(a) Business Development Program
☐ HUBZone Small Business
☐ Service-Disabled Veteran-Owned (SDVOSB)
☐ Women-Owned Small Business (WOSB) mailto:Mark.R.Corn@usace.army.mil mailto:Kimberly.D.Tripp@usace.army.mil mailto:Theresa.M.Afrank@usace.army.mil mailto:Jennifer.Gosh@usace.army.mil
Bonding Capacity Single Project Limit: $[Insert Amount Here]_______________
Aggregate Limit: $[Insert Amount Here]_______________
Intent to Propose on EIE483 ☐ Yes as Prime
☐ Yes as Sub
☐ No
☐ Undecided
Anticipated Teaming for EIE483 ☐ Standalone Prime
☐ Joint Venture (JV)
☐ Mentor-Protégé
☐ Subcontractor/Designer Only
Intent to Propose on EIE484 ☐ Yes as Prime
☐ Yes as Sub
☐ No
☐ Undecided
Anticipated Teaming for EIE484 ☐ Standalone Prime
☐ Joint Venture (JV)
☐ Mentor-Protégé
☐ Subcontractor/Designer Only
Part II: Project-Specific Challenges
1. Site and Environmental Constraints
Site location contains a high-water table (3’ below ground level in several areas) and likely soil contamination to include PFAS. Projects requiring utilidor demolition and construction may encounter asbestos or PCB contamination. Some site locations for the projects are impacted by permafrost creating ground instability when thawed requiring specialized foundation designs and engineering strategies to maintain structural integrity of the projects. What risks do you anticipate associated with the high groundwater conditions, the potential for permafrost, and contaminated soils during construction? What methods would you use to help mitigate these risks? What information or project requirements would you recommend be established during preconstruction to reduce these risks?
2. Schedule Risk & Limited Construction Window
Given the timelines required to complete design and construction for these projects and the realities of the short Alaskan limited construction window, how would you mitigate weather delays? Please describe off-site prefabrication strategies, modular construction, winter-enclosure techniques, and/or other strategies that you would propose to maintain construction schedule. How could the
Government best structure initial design phase collaboration to evaluate the cost-versus-time tradeoffs of the described acquisition methods before finalizing a Guaranteed Maximum Price for
Construction phase services?
3. Temporary Space Requirements
For each project identified (EIE483 and EIE484), what is the estimated space requirement for temporary facilities including, but not limited to: material laydown, worksite offices, workforce parking, etc.? Furthermore, do you foresee any need for new or upgraded supporting infrastructure, such as access roads or port facilities, to support construction logistics for each of the identified projects?
4. Construction Duration & Schedule Realism
What do you believe is a reasonable timeframe (in calendar days or years) to complete each projects’ (EIE483 and EIE484) design and construction phase, assume the awarded agreement is in the fourth quarter of the identified fiscal year?
5. Construction near Airfields (EIE483)
For EIE483 Joint Mobility Expansion center project the site location is near an active airfield.
Describe coordination strategies for design and construction activities. Active planning and deconfliction will need to take place between the project, the installation, and airfield management.
Which OTA acquisition strategy do you believe would lend itself best for the required coordination strategy to accomplish the project?
6. Mobilization & Start-Work Readiness (EIE483)
Which OTA acquisition strategy for each separate project (EIE483), CM at Risk or PDB, would be best for the project and what would be the advantages/disadvantages? Assuming an award is made, for each separate project (EIE483), what is your firm's estimated lead time to mobilize
Phase 1 (Design and Preconstruction Services) and Phase 2 (Final Design & Construction
Services)? What is the optimal time of year for a contract award to align with your mobilization and maximize the active construction season?
7. Mobilization & Start-Work Readiness (EIE484)
EIE484 Permanent Party Dorm is currently at a 65% Design. Which OTA acquisition strategy, CM at
Risk or PDB, would be best for the project and what would be the advantages/disadvantages?
Assuming an award is made, what is your firm's estimated lead time to mobilize Phase 1
(Preconstruction Services) and Phase 2 (Construction Services)? What is the optimal time of year for a contract award to align with your mobilization and maximize the active construction season?
8. Unidentified Project Risks
Outside of the challenges already identified, what other significant risks do you foresee for projects by project (EIE483 and EIE484) of this scale, type and complexity at Eielson AFB? Which project delivery method best supports potential offeror’s ability to address unidentified project risks with minimal cost and/or delay of project delivery?
Part III: Budget, Cost Drivers & Schedule
1. Budget Realism
Based on current market data, do the target budgets appear realistic for these facility types and scale?
2. Primary Cost Drivers
What specific project needs or functional requirements do you anticipate driving the most cost?
3. Schedule/Supply Chain Risk
What systems or trades present the most significant schedule risk (e.g., long-lead MEP, local labor)?
Part IV: Defining Value, Collaboration & Financial Drivers
1. Collaboration Priorities
Please rank the areas that would benefit most from early builder involvement during the design phase of the above projects (1 = Greatest Benefit, 5 = Least Benefit).
Area of Collaboration EIE483 Rank (1–5) EIE484 Rank (1–5)
Cost Certainty & Real-
Time Estimating _______________ _______________
Schedule Certainty &
Phasing _______________ _______________
Constructability &
Quality Control _______________ _______________
2. Industry Engagement & Proprietary Meetings
If the Government utilizes a delivery method that allows for confidential, one-on-one proprietary meetings during the solicitation phase to collaboratively discuss innovative solutions, would your firm participate?
☐ Yes ☐ No
3. Stipends (Honorariums) & Proposal Costs
EIE483 – Joint Mobility Center Expansion
In procurement methods with significant proposal phase efforts, would the Government's offer of a stipend significantly influence your decision to compete?
☐Yes ☐ No
If Yes, what is a commercially reasonable stipend amount for a project of this scale? [Insert
Amount/Percentage Here] ______________________________
EIE484 -225-Bed Permanent Party Dormitory
In procurement methods with significant proposal phase efforts, would the Government's offer of a stipend significantly influence your decision to compete?
☐Yes ☐ No
If Yes, what is a commercially reasonable stipend amount for a project of this scale? [Insert
Amount/Percentage Here] ______________________________
4. Contract Incentives
EIE483 – Joint Mobility Center Expansion
What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?
☐ Shared Cost Savings (e.g., within a GMP Structure)
☐ Award Fee for Quality / Innovation
Innovation & Scope
Betterments (Getting more for the money) _______________ _______________
Overall Risk Reduction /
Site Mitigations _______________ _______________
☐ Other [Insert Recommendations Here] ______________________________
EIE484 -225-Bed Permanent Party Dormitory
What specific contract incentives would best drive innovation and maximize your firm's interest in these projects?
☐ Shared Cost Savings (e.g., within a GMP Structure)
☐ Award Fee for Quality / Innovation
☐ Other [Insert Recommendations Here] ______________________________
5. Program Capability/Interest
Considering the projects listed: EIE483 and EIE484
a) Which projects would your firm be interested in proposing as a prime contractor?
b) Does your firm have the necessary bonding capacity to cover the total estimated project(s) value?
☐Yes ☐ No
c) If yes, please state your firm’s current aggregate bonding capacity. [Insert Amount Here]
Part V: Overall Delivery Recommendation
1. Recommended Project Delivery Path
Considering all factors, which project delivery path is optimal for these specific projects?
(Provide a response for each project listed in Section 1 above)
EIE483 – Joint Mobility Center Expansion
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Bid-Build (DBB): Scope and design is fully defined; traditional FAR part 36 and FAR part 15 is sufficient.
☐ Design-Build: Scope is defined close to 35%; traditional FAR part 36 and FAR part 15 is sufficient.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive
(10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
EIE484 -225-Bed Permanent Party Dormitory
☐ CM@Risk: Government needs to control the design but needs early builder collaboration.
☐ Design-Bid-Build (DBB): Scope and design is fully defined; traditional FAR part 36 and FAR part 15 is sufficient.
☐ Design-Build: Scope is defined close to 35%; traditional FAR part 36 and FAR part 15 is sufficient.
☐ Design-Build to Budget (DBtB): Requirements are understood enough to drive a competitive
(10-15%), fixed-price solution, use of proprietary meetings to advance design solutions (highly collaborative).
☐ Progressive Design-Build (PDB): Scope is highly complex/undefined. Requires a single contract to collaboratively mature the design before locking in a GMP.
2. Basis of Recommendation & Contracting Vehicle
Please explain your selections above for each project. Additionally, please indicate if you recommend executing this via a standard FAR-based contract vs the provided OTA type options.
3. Evaluation Strategy
For each project, rank what evaluation criteria you believe the Government should weight most heavily to ensure the highest value project?
Evaluation Factors EIE483 Rank (1–4) EIE484 Rank (1–4)
Past Performance _______________ _______________
Technical Approach/Design _______________ _______________
Price/GMP _______________ _______________
Key Personnel & Team Integration _______________ _______________
Other [Insert Recommendations]
4. Commercial Best Practices & Concerns
Please provide any additional comments, overly prescriptive constraints to avoid, and/or commercial best practices the Government should consider.