This is Addendum 1 to the Invitation to Bid for the Mid-Atlantic Advanced Manufacturing Center (MAMaC) Elevated Water Storage Tank project in Virginia, issued on September 17, 2026. The addendum reorganizes and expands the Project Manual by removing section C-415 (Measurement and Payment) from the Table of Contents and adding thirteen new sections to Division 01 (General Requirements), including Measurement and Payment (01 20 00), Substitutions (01 25 00), Coordination (01 31 00), Project Meetings (01 31 19), Submittals (01 33 00), Testing and Inspection (01 40 00), Definitions (01 42 16), Manufacturer's Services (01 43 33), Temporary Facilities and Environmental Protection (01 50 00), Materials and Equipment (01 60 00), Closeout Procedures (01 70 00), Operating and Maintenance Data (01 78 23), and Warranties and Guarantees (01 78 36). The project scope includes construction of a 1-million-gallon composite elevated water storage tank with a water booster pumping station, approximately 835 linear feet of 16-inch waterline (including two jack and bore installations totaling 300 linear feet), a 125-linear-foot northern connection of 12-inch waterline, and a 175-linear-foot eastern connection of 12-inch waterline. Response to this addendum must be acknowledged on the bid form, and all other terms and conditions remain unchanged.
The addendum establishes comprehensive contractual procedures governing measurement and payment methodologies, material substitution processes, project coordination requirements, testing and inspection protocols, manufacturer's field services, environmental protection measures, and closeout procedures. Measurement and payment shall be based on completion of work in accordance with contract documents, with the contractor responsible for incidental items including dust control, clearing and grubbing, construction entrances, dewatering, site restoration, stakeout and surveying, traffic control, and record drawings. The contractor must submit a schedule of values for lump sum bid items within fourteen days of the effective agreement date and may submit modification requests for construction methods or materials that result in net cost savings to the owner within ten calendar days after notice to proceed. The contract retains five percent of each partial progress payment, with provisions allowing contractors to utilize escrow account procedures for retained funds on contracts of $200,000 or more. Contractor-furnished quality control testing and owner-furnished inspection services are required, including special inspections for structural steel, earthwork, and concrete, with testing charges borne by the owner when compliance is demonstrated and by the contractor when non-compliance is found. The contractor shall provide manufacturer's representatives for installation, startup, and operator training, and must maintain record drawings throughout construction showing all changes, underground utilities, and concealed work prior to final payment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM TO INVITATION TO BID
PROJECT: MID-ATLANTIC ADVANCED MANUFACTURING CENTER –
ELEVATED WATER STORAGE TANK
DATE: SEPTEMBER 17, 2026
ADDENDUM: 1
The following items represent changes, modifications, and/or clarifications to the Contract Documents for this project.
REVISIONS:
1. The Project Manual is reissued in its entirety to incorporate the following revisions, completely superseding the original version. These additional sections are formally issued via Addendum 1.
a. The following section was removed from the Table of Contents:
i. C-415 Measurement and Payment
b. The following section was added to the Table of Contents:
i. 01 20 00 Measurement and Payment
c. The following sections were added to the Project Manual:
i. 01 20 00 Measurement and Payment
ii. 01 25 00 Substitutions
iii. 01 31 00 Coordination
iv. 01 31 19 Project Meetings
v. 01 33 00 Submittals
vi. 01 40 00 Testing and Inspection
vii. 01 42 16 Definitions
viii. 01 43 33 Manufacturer's Services
ix. 01 50 00 Temporary Facilities and Environmental Protection
x. 01 60 00 Materials and Equipment
xi. 01 70 00 Closeout Procedures
xii. 01 78 23 Operating and Maintenance Data
xiii. 01 78 36 Warranties and Guarantees
RESPONSE MUST ACKNOWLEDGE RECEIPT OF THIS ADDENDUM ON THE BID
FORM
All other terms and conditions remain unchanged.
TABLE OF CONTENTS
SECTION TITLE
BID AND CONTRACT DOCUMENTS
BID DOCUMENTS
C-020 Invitation for Bids
C-200 Instructions to Bidders C-410 Bid Form
C-430 Bid Bond
CONTRACT DOCUMENTS
C-520 Form of Agreement Between Owner and Contractor for Construction Contract
C-550 Notice to Proceed
C-610 Performance Bond C-615 Payment Bond
C-620 Contractor’s Application for Payment
C-625 Certificate of Substantial Completion C-700 Standard General Conditions
C-800 Supplementary Conditions of the Construction Contract
C-940 Work Change Directive
C-941 Change Order C-942 Field Order
TECHNICAL SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 20 00 Measreument and Payment
01 25 00 Substitutions
01 31 00 Coordination
01 31 19 Project Meetings 01 33 00 Submittals
01 40 00 Testing and Inspection
01 42 16 Definitions 01 43 33 Manufacturer’s Services
01 50 00 Temporary Facilities and Environmental Protection
01 60 00 Materials and Equipment
01 70 00 Closeout Procedures 01 78 23 Operating and Maintenance Data
01 78 36 Startup Warranties and Guarantees
DIVISION 02 – EXISTING CONDITIONS
02 00 00 Site Condition
DIVISION 03 – CONCRETE
03 15 00 Concrete Anchors
03 30 00 Cast-In Place Concrete
03 60 00 Grout
ISSUED PER ADDENDUM 1
DIVISION 22 – PLUMBING
22 00 10 General Provisions for Plumbing 22 05 00 Common Work Results for Plumbing
22 05 19 Meters and Gauges for Plumbing
22 05 23 General Duty Valves for Plumbing 22 05 29 Hangers And Supports for Plumbing
22 05 53 Identification for Plumbing Piping and Equipment
22 07 00 Plumbing Insulation
22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties
22 13 16 Sanitary Waste and Vent Piping
22 13 19 Sanitary Waste and Vent Specialties
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
23 00 10 Heating, Ventilation and Air Conditioning General Provisions 23 05 00 Common Work Results for HVAC
23 05 13 Common Motor Requirements for HVAC Equipment
23 05 29 Hangers And Supports for HVAC Piping and Equipment
23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC
23 07 00 HVAC Insulation
23 09 00 Instrumentation and Control for HVAC 23 09 50 Instrumentation and Control Sequences for HVAC
23 81 26 Split-System Air-Conditioners
DIVISION 25 – INTEGRATED AUTOMATION
25 05 03 Basic Instrumentation System Requirements
25 05 03.13 Controls and Instrumentation Installation Drawings
25 08 00 Controls and Instrumentation Installation Startup 25 56 00 Input/Output List
25 90 00 Sequence of Operation
DIVISION 26 – ELECTRICAL
26 05 00 General Electrical Provisions
26 05 26 Grounding and Bonding for Electrical Systems
26 05 43 Underground Ducts and Raceways for Electrical Systems 26 05 53 Identification for Electrical Systems
26 24 14 Power Distribution System Study
26 24 16 Panelboards 26 27 26 Basic Materials and Methods
26 32 13 Standby Power System
26 32 14 Lighting Protection System for Buildings
DIVISION 33 – EXTERIOR IMPROVEMENTS
33 05 07 Jack and Bore
33 05 26 Pipe Identification Markers 33 10 00 Water Distribution System
33 14 43 Packaged Pumping Systems for Water Utility Service
33 16 11 Elevated Composite Water Storage Tanks
DIVISION 40 – PROCESS PIPE AND SPECIALTIES
40 05 07 Process Pipe Supports and Stands 40 71 13.13 Inline Magnetic Flow Meters
40 73 13 Pressure Gauges and Transmitters
DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.13 Bridge Cranes
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
46 41 21 Jet Mixing Equipment
46 41 23 Submersible Mixers
ATTACHMENT A – GEOTECHNICAL REPORT
SECTION 01 20 00
MEASUREMENT AND PAYMENT
01 43 33 / 1 of 9
1. GENERAL
1.1 GENERAL
A. Measurement will be made on the basis of completion of the Work in accordance with the
Contract Documents and the appropriate specification section.
B. Measurement of quantities will be made by the Contractor in the presence of the Owner.
The methods of measurement and computations used in determination of quantities of materials furnished and installed shall be those generally recognized as conforming to good engineering practice.
C. The term "Complete in Place" will mean that the item of Work shall be furnished and installed in accordance with the Contract Documents complete with all appurtenances necessary for the item to be used for its intended function. Testing and acceptable results shall be included.
D. Linear foot and vertical foot measurements shall be measured along the horizontal plane of the ground or paved surface.
E. Area computations shall be made on the surface. Pay measurements for area computations will not exceed plan dimensions as shown on the Drawings, unless otherwise approved by the Owner in writing.
F. No payment will be made for length, width, or depth, in excess of that shown on the Drawings or specified in the Specifications for any construction, unless otherwise approved by the Owner in writing.
G. The term "Each" when used as an item of payment will mean complete payment for the
Work described in the Contract Documents.
H. The word "Lump Sum" when used as an item of payment will mean complete payment for Work described in the item, including all materials, labor, and equipment necessary to complete the Work in accordance with the Contract Documents.
I. Quantities will be measured and paid for in accordance with one of the following methods, and as specified on the Bid form.
1.2 Incidental Items
A. There are numerous incidental items of Work that are required to complete the Project.
While these items may not be specifically mentioned or illustrated by the Contract
Documents and there may be no specific pay items listed for them, the Contractor will be required to perform those incidental tasks that can be anticipated through inspection of the Contract Documents, inspection of the construction area, and experience in this class of construction.
01 43 33 / 2 of 9
B. Items considered incidental Work shall not be measured for payment or paid for as such unless specified as unit price by items on the Bid form. These items and their costs shall be included in the unit prices or lump sum Bid for the pay items unless Bid separately.
Incidental items include but are not limited to the following:
1. Allaying dust and mud
2. Clearing and grubbing
3. Construction entrances
4. Contaminated groundwater management
5. Daily cleanup
6. Drainage feature restoration including culvert end-walls, swales, and paved swales
7. Excavation and dewatering
8. Final surface restoration
9. Fittings and Restrained Joints
10. Furnishing, hauling, placing, manipulating, and compacting material
11. Location of existing utilities
12. Material royalties
13. Minor relocation of buried cables, water lines, sewer lines, or similar utility lines 2 inches and smaller in diameter
14. Offsite disposal of excess excavated, surplus and remnant excavated materials
15. On-site manufacturer or representative services
16. Pavement marking
17. Permits, unless provided by the Owner
18. Protection of existing utilities and other facilities
19. Removal and replacement of existing signs, fences, mail boxes, and similar existing improvements
20. Shoulder tie-in to restored pavement
21. Site restoration and cleanup
22. Site security
23. Stakeout and surveying
24. Traffic control
25. Top soil and seeding
26. Record Drawings
1.3 Schedule of Values for Lump Sum Bid Items
A. Within fourteen (14) Days after the Effective Date of the Agreement, the Contractor shall submit a schedule of values for all of the Work which shall include quantities and prices of items aggregating the Contract Price and shall subdivide the Work into component parts in sufficient detail to serve as the basis for progress payments during construction. Such prices shall include an appropriate amount of overhead and profit applicable to each item of Work.
B. The Owner shall review the schedule and shall respond in writing to the Contractor within ten (10) Days either approving or disapproving the schedule. If the schedule of values is disapproved, the Contractor shall resubmit the schedule with revised value or additional substantiating data and the Owner shall either approve or disapprove the revised schedule
01 43 33 / 3 of 9 within ten (10) Days. No payments shall be processed or approved until the schedule of values is approved by the Owner.
C. The Contractor shall include Erosion and Sedimentation Maintenance Line Item in the
Schedule of Values.
1.4 Application for Progress Payment by Contractor
A. Unless otherwise provided in this Section, the Owner shall make monthly progress payments to the Contractor on the basis of a duly certified and approved Application for
Payment for Work performed during the preceding calendar month as approved by the
Owner.
B. At least ten (10) Days before each partial progress payment (but not more often than once a month), the Contractor shall submit to the Owner an Application for Payment filled out and signed by the Contractor for the Work completed during the period covered by the partial progress payment estimate and supported by such data as is required by the Contract
Documents.
C. The schedule of values for lump sum items established as provided in Section 1.02 shall serve as the basis for progress payments and shall be incorporated into a form of
Application for Payment acceptable to the Owner.
1.5 Payment for Material on Hand
A. If payment is requested on the basis of materials and equipment not incorporated in the
Work, but delivered and suitably stored at the site or at another location agreed to in writing, the Application for Payment shall be accompanied by a bill of sale, invoice or other instrument documenting that the materials and equipment are free and clear of all
Liens and evidence that the materials and equipment are covered by appropriate property insurance, all of which will be satisfactory to the Owner. The Owner, at its sole discretion, may not pay for stored materials without prejudice and without cause.
1.6 Review of Applications for Progress Payments
A. The Owner shall, within ten (10) Days after receipt of each Application for Payment, make such investigations as deemed necessary to verify the accuracy of the Application for
Payment and either accept the application as accurate and suitable for payment or return the Application to the Contractor indicating in writing the Owner’s reasons for refusing payment. If payment is refused, the Contractor shall make the necessary corrections and resubmit the Application and the Owner shall have an additional ten (10) Days after receipt of the corrected Application for Payment from the Contractor to determine whether this
Application is accurate and suitable for payment.
B. The Owner shall, within 30 Days after acceptance of the Application for Payment, make payment to the Contractor. The Owner may refuse to make payment of the full amount because claims have been made against the Owner on account of the Contractor’s performance or furnishing of the Work, or because Liens have been filed in connection with the Work, or because there are other claims entitling the Owner to a set-off against the payment. The Owner shall give the Contractor immediate written Notice stating the reasons for its failure to make payment.
01 43 33 / 4 of 9
C. The Owner may also refuse to make payment of the full amount because there are other items entitling the Owner to retain set-offs from the amount recommended, including but not limited to:
1. Owner compensation to the Engineer for actual costs for extra personnel hours for labor plus expenses because of the following Contractor caused events:
a) Witnessing re-testing of corrected or replaced defective Work.
b) Return visits to manufacturing facilities to witness factory testing or re-testing.
c) Evaluation of proposed substitutes and in making changes to Contract Documents occasioned thereby.
d) Overtime worked by the Contractor necessitating the Engineer, Resident Project
Representative (and support staff, if any), to work overtime.
2. Liability for liquidated damages incurred by the Contractor as set forth in the Agreement.
3. Loss to Owner caused by Contractor acts or omissions including, but not limited to:
a) Defective Work not remedied;
b) Claims filed or reasonable evidence indicating probable filing of claims against the
Contractor;
c) Failure of the Contractor to make payments properly to subcontractors or for materials or labor;
d) A reasonable doubt that the Project can be completed for the balance then unpaid;
e) Failure to maintain (each month) the record set of Drawings and Specifications.
Failure to provide the Owner with record Drawings and Specifications within thirty
(30) calendar Days from the date of the Substantial Completion;
f) Failure to periodically remove and dispose of accumulated debris, rubbish, and discarded/damaged materials;
g) Persistent failure to carry out the Work in accordance with the Contract
Documents;
h) A reasonable doubt that the Work will be completed within the Contract Time.
4. Failure of the Contractor to submit an updated progress schedule or other required supporting documentation (if requested by the Owner) to the Owner with the monthly application for progress payment.
1.07 Retained Funds
A. The Owner shall retain 5 percent (%) of the total amount of each partial progress payment to assure faithful performance of the Agreement by the Contractor. The Owner will release all retainage upon Final Payment.
01 43 33 / 5 of 9
B. Pursuant to and in accordance with Section 2.2-4334 of the Code of Virginia, the Contractor may exercise the option to use the escrow account utilization procedure with respect to retained funds. The Contractor may do so by indicating its preference for this procedure in the appropriate space provided on the Bid form.
1. Should this option be selected, the Contractor shall execute the Escrow Agreement and shall submit same to the Owner in the manner prescribed by law. If the Escrow
Agreement form is not submitted as noted, the Contractor shall forfeit such rights to the use of the escrow account utilization procedure.
2. In order to have retained funds paid to an escrow account, the Escrow Agreement shall be executed by the Contractor, the escrow agent, and the surety, and shall be submitted by the Contractor to the Owner for approval by the Owner’s attorney. The Contractor’s escrow agent shall be a trust company, bank or savings institution with its principal office located in the Commonwealth of Virginia. The Escrow Agreement shall contain the complete address of the escrow agent and surety, and the executed Escrow Agreement will be authority for the Owner to make payment of retained funds to the
Escrow Agent. After approving the Escrow Agreement, the Owner shall pay to the escrow agent the funds retained as provided herein except that funds retained for lack of progress or other deficiencies on the part of the Contractor shall not be paid to the
Escrow Agent. The Escrow Agent may, in accordance with the terms of the Escrow
Agreement, invest the funds paid into the escrow account and pay earnings on such investments to the Contractor or release the funds to the Contractor provided that such funds are fully secured by approved securities.
3. Retained funds invested and securities held as collateral for retainage may be released only as and when directed by the Owner. When the Final Payment is paid, the Owner shall direct to the Contractor monies due as determined by the Owner. The Owner reserves the right to recall retained funds and to release retained funds to the surety upon receipt of written request from the Contractor or in the event of default.
4. The escrow account procedure shall apply to any contract for the sum of Two Hundred
Thousand Dollars ($200,000), or more, for construction of highways, roads, streets, bridges, parking lots, demolition, clearing, grading, excavating, paving, pile driving, miscellaneous drainage structures, and the installation of water, gas, sewer lines, and pumping stations.
1.08 Conditions of Payment to Contractor
A. All material and Work covered by partial progress payments shall thereupon become the sole property of the Owner, but this provision shall not be construed as relieving the Contractor from the sole responsibility for the safety and protection of all materials and
Work upon which payments have been made or the restoration or replacement of any damaged or stolen Work or property or as a waiver of the right of the Owner to require the fulfillment of all the terms of the Agreement
B. Prior to Substantial Completion, the Owner, with the concurrence of the Contractor, may use any completed or substantially completed portions of the Work. Such use shall not constitute an acceptance of such portions of the Work.
C. The Owner shall have the right to enter the premises for the purpose of doing work not covered by the Contract Documents. This provision shall not be construed as relieving the
01 43 33 / 6 of 9
Contractor of the sole responsibility for the care and protection of the Work, or the restoration of any damaged Work except such as may be caused by agents or employees of the Owner.
D. The Contractor shall indemnify and save the Owner or the Owner's agents harmless from all claims growing out of the lawful demands of Subcontractors, laborers, workmen, mechanics, material men, and furnishers of machinery and parts thereof, equipment, tools and all supplies, incurred in the furtherance of the performance of the Work. The Contractor shall, at the Owner's request, furnish satisfactory evidence that all obligations of the nature designated above have been paid, discharged, or waived. If the Contractor fails to do so the Owner may, after having notified the Contractor, either pay unpaid bills or withhold from the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to pay any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully discharged whereupon payment to the
Contractor shall be resumed, in accordance with the terms of the Contract Documents but in no event shall the provisions of this Section be construed to impose any obligations upon the Owner to either Contractor, the Surety, or any third party. In paying any unpaid bills of the Contractor, any payment so made by the Owner shall be considered as a payment made under the Contract Documents by the Owner to the Contractor and the Owner shall not be liable to the Contractor for any such payments made in good faith.
E. The Contractor shall take one of the two following actions within seven (7) Days after receipt of amounts paid to the Contractor by the Owner for Work performed by the
Subcontractor under the Agreement:
1. Pay to the Subcontractor the proportionate share of the total payment received attributable to the Work performed by the Subcontractor under the Agreement; or
2. Notify the Owner and Subcontractor, in writing, or his intention to withhold all or a part of the Subcontractor’s payment with the reason for nonpayment.
F. All contracts awarded by the Contractor to a Subcontractor for any portion of the Work shall include:
1. An interest clause that obligates the Contractor to pay interest to the Subcontractor on all amounts owed by the Contractor that remain unpaid after seven (7) Days following receipt by the Contractor of payment from the Owner for Work performed by the
Subcontractor under that contract, except for amounts withheld as allowed.
2. An interest rate clause stating, “Unless otherwise provided under the terms of this contract, interest shall accrue at the rate of one percent per month.”
3. A payment clause that requires (i) individual contractors to provide their social security numbers and (ii) proprietorships, partnerships, limited liability companies and corporations to provide their federal employer identification numbers.
G. The Contractor shall include in each of its subcontracts a provision requiring each
Subcontractor to include or otherwise be subject to the same payment and interest requirements as specified in Section 1.07 above, with respect to each lower-tier
Subcontractor.
01 43 33 / 7 of 9
H. A Contractor’s obligation to pay an interest charge to a Subcontractor pursuant to the payment clause in this section may not be construed to be an obligation of the Owner. A contract modification may not be made for the purpose of providing reimbursement for such interest charge. A cost reimbursement claim may not include any amount for reimbursement for such interest charge.
1.09 Final Payment
A. After the Contractor has completed all corrective Work as determined by a final inspection to the satisfaction of the Owner and has delivered all maintenance and operations manuals, schedules, guarantees, bonds, certificates of inspection, and other documents as required by the Contract Documents, the Contractor may make application for final payment following the procedure for partial progress payments. Within thirty (30) Days after approval, the Owner shall pay to the Contractor the amount stated, less all prior payments and advances to or for the account of the Contractor. All prior estimates and payments including those relating to extra Work shall be subject to correction by this payment, which is called the Final Payment. The Contractor's obligation to perform the Work and complete the Project in accordance with the Contract Documents shall be absolute. Neither approval of any progress or Final Payment by the Owner nor the issuance of a Certificate of Substantial Completion, nor any payment by Owner to Contractor under the Contract
Documents, nor any use or occupancy of the Project or any part thereof by Owner, nor any act of acceptance by Owner nor any failure to do so, nor any correction of defective Work by Owner shall constitute an acceptance of Work not in accordance with the Contract
Documents.
1.10 Acceptance of Final Payment Constitutes Release
A. The acceptance by the Contractor of the Final Payment shall be and operate as a release to the Owner of all claims and of all liability to the Contractor for all things done or furnished in connection with this Work excepting the Contractor's claims for interest upon Final Payment, should this payment be improperly delayed. No payment, final or otherwise, or partial or entire use or occupancy of the Work by the Owner, shall constitute an acceptance of any Work or materials not in accordance with the Contract Documents, nor shall the same relieve the Contractor of responsibility for faulty materials or workmanship or operate to release the Contractor or his Surety from any obligation under the Contract, the
Performance Bond and Payment Bond.
1.11 Assignments
A. Neither party to the Agreement shall sell, transfer, assign or otherwise dispose of the whole or any parts of the Agreement or of the right, title or interest therein without the prior written consent of the other, nor shall the Contractor assign any monies due or to become due hereunder, without the previous written consent of the Owner.
1.12 Payment Affidavit
A. The Owner, before making any payment, including the final payment, if it is deemed that such procedure necessary to protect his interests, may require the Contractor to furnish an affidavit from all subcontractors and material suppliers used in conjunction with this Contract that each has been paid in full, or in the alternative, an affidavit that so far as he has knowledge or information, all payments have been made and that there is no basis under which a claim against the payment bond could be filed. However, the Owner may
01 43 33 / 8 of 9 make payments in part or in full to the Contractor without requiring the affidavits, and the payments so made shall not impair the obligations of any Surety or Sureties on any bond or bonds furnished under this Contract.
1.13 CHANGE ORDERS AND FIELD ORDERS
A. The Owner may at any time, as the need arises, order changes within the scope of the Work without invalidating the Agreement. If such changes increase or decrease the amount due under the Contract Documents, or in the time required for performance of the Work, an equitable adjustment shall be authorized by Change Order.
B. The Contract Price and Contract Time may be changed only by a Change Order, approved by the Owner prior to the performance of the Work by the Contractor or granted by the Owner upon written Notice by Contractor. The value of any Work covered by a Change
Order or of any claim for increase or decrease in the Contract Price or Contract Time shall be established in accordance with the following methods in the order of precedence listed below:
1. Established contract unit prices;
2. An agreed lump sum or unit price established by direct negotiation between the
Contractor and the Owner; or,
3. In the event that any changes in the Work are not settled under 1. and 2. above, the
Contract Price shall be adjusted in accordance with the following:
a) In any case such change involves extra Work which is performed by the
Contractor, the Contract Price shall be increased by (a) the direct cost of such Work, as mutually agreed upon or otherwise as determined in accordance with the
Contract Documents, and (b) ten percent (10%) of the amount of (a) to cover
Contractor’s additional job (field and home office) overhead, and (c) five percent
(5%) of the sum of (a) and (b) to cover Contractor’s additional job profit.
b) In any case such change involves extra Work which is performed by a
Subcontractor, the Contract Price shall be increased by (a) the amount paid by the Contractor to the Subcontractor for such extra Work, and (b) seven and one-half percent (7-1/2%) of the amount paid to the Subcontractor to cover the Contractor’s additional job (field and home office) overhead and (c) five percent (5%) of the sum of (a) and (b) to cover Contractor’s additional job profit. On Work performed by the Subcontractor, the Subcontractor shall be allowed overhead and profit in accordance with paragraph 3 (A) above.
c) In the case of either subparagraph (a) or (b) above, the Contract Price shall also be increased by the corresponding increase in the cost of the Contractor’s performance bond.
C. It is the Contractor's responsibility to notify his Surety of any change affecting the general scope of the Work or change in the Contract Price and/or Contract Time so that the amount of the applicable Bonds shall be adjusted accordingly. The Contractor shall furnish proof of such adjustment to the Owner.
D. Whenever changes, alterations, additions, omissions, or revisions are called for by the
01 43 33 / 9 of 9
Owner for which the necessary Drawings and details have been completed and submitted to the Contractor, or when changes, alterations, additions or omissions are clearly given in writing to the Contractor, the Contractor is to submit an itemized statement of quantities and prices incidental to such revisions, changes, additions and omissions.
E. The Owner may at any time order minor changes within the scope of Work by issuing a
Field Order. The Contractor shall proceed with the performance of any changes in the
Work so ordered by the Owner unless the Contractor believes that such Field Order entitles the Contractor to a change in Contract Price or Time or both, in which event the Contractor shall give the Owner written Notice thereof within seven (7) Days after the receipt of the ordered change. The Contractor shall not execute such changes pending the receipt of an executed Change Order or further instruction from the Owner. The Owner shall respond to such written Notice from Contractor within twenty-one (21) days after receipt of all supporting data from Contractor.
F. If any item in the Agreement is determined to be unnecessary for the proper completion of the Work contracted, the Owner may, upon written Notice to the Contractor, eliminate such item from the Agreement. Payment will not be made for such item except that the
Contractor shall be compensated for the actual cost of any Work performed for the installation of such item and the net cost of materials purchased, including freight and tax costs, as evidenced by invoice. No additional compensation will be made for overhead or anticipated profit.
G. The Contractor shall not be entitled to any adjustment in the Contract Price or Contract
Time due to any condition or alleged condition if:
a) The Contractor knew of the existence of such conditions at the time the Contractor made a final commitment to the Owner in respect of Contract Price and Contract
Time by the submission of a Bid; or
b) The existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test or study of the site and contiguous areas required by the Contract Documents to be conducted by or for the Contractor prior to the Contractor making such final commitment; or
c) The Contractor failed to give the written Notice to the Owner within 20 Days after occurrence of the event giving rise to such claim, or within 20 Days after the claimant recognizes the condition, whichever is later.
END OF SECTION
SECTION 01 25 00
SUBSTITUTIONS
1. GENERAL
1.1 General
A. All materials furnished under this contract shall be as specified or required, or in the absence of particular specification shall be the best of their respective kinds, or new stock, unused and not deteriorated and all the work contemplated and described shall be done in a good, substantial and workmanlike manner.
B. Wherever in these Specifications or on the plans, the terms ASTM, AWWA, or other such reference Specifications are used, it shall be considered to mean the latest pertinent
Specifications and any subsequent amendments thereto.
1.2 Product Substitutions
A. Equivalents and Substitutes:
1. Whenever materials or equipment are described in the Contract Documents by using a certain brand, make, supplier, Manufacturer or by specification, such naming or specification shall be regarded to convey function, design features, general style, type, materials of construction, character and quality of material or equipment serviceability and such other desired essential characteristics. It is not intended to restrict competition among bidders.
2. Unless words are used indicating that no "or equivalent" or "substitution" is allowed, an
"equivalent" or "substitute" item may be accepted by the Engineer if, in the Engineer’s judgment, the item meets the criteria set forth in the specification and as further described in the following paragraphs and its use will not increase the Contract Price nor Contract Duration.
3. The Contractor’s written application for the "or equivalent" or substitute item shall provide sufficient information to allow the Engineer to determine whether the proposed material or equipment:
a) Will equally perform the functions and achieve the results called for by the general design concept,
b) Is at least of equal materials of construction, quality and necessary essential design features,
c) Is suited to the same use as that named or specified,
d) Conforms substantially to the desired detailed requirements, e.g. durability, strength, appearance, aesthetics (if aesthetics are significant), safety, useful life, reliability, economy of operation and ease of maintenance, evidences a proven record of performance and the availability of local and responsive service,
e) Will not increase Contract Price,
f) Will not increase Contract Duration.
4. The Engineer shall not be required to supplement the information supplied by the
Contractor.
5. Each written application shall certify whether or not acceptance of the proposed "or equivalent" or substitute item will require a change in any of the work or any other means and methods indicated in or required by the Contract Documents, or in work performed by the Owner or others, and whether or not incorporation or use of the proposed item is subject to payment of any license fee or royalty. All variations of the proposed item from the item named or specified shall be identified (operation, materials or construction finish, thickness or gauge of material, dimensions, loads, 01 25 00 / 2 of 3 tolerances, deleted or added features, etc.) and information regarding available maintenance, repair, and replacement services shall be indicated.
6. The application shall contain an itemized estimate of all direct, indirect, and consequential costs that will result from the evaluation and acceptance of the proposed "or equivalent" or substitute item, including but not limited to cost and delays of redesign, or claims of other Contractor’s (Subcontractor’s) affected by the proposed item and changes in operating, maintenance, repair, replacement or spare parts costs. The Owner may require the Contractor to furnish a list of locations of similar installations that have been in service for at least three (3) years before the date of the application, and any other relevant information/data.
7. The Contractor shall be responsible for verifying the "or equivalent" or substitute items conform to the Contract Documents, and that all dimensions, arrangement, design and construction details and other features are suited to the specified purpose. If an "or equivalent" “or substitute” item differs materially from the item named or specified, and that difference was not expressly identified in the Contractor's written application, or results in changes in the work or in the general design concept, the Engineer has authority to require removal and replacement of that "or equivalent" “or substitute” item. The Contractor shall be responsible for any delay and all costs resulting from:
a) Any such removal and replacements of an "or equivalent" “or substitute” item,
b) Making any "or equivalent" or “substitute materials” or equipment conform with the Contract Documents, and
c) Implementing any changes in the work and/or in any other work to accommodate the "or equivalent" “or substitute” item.
8. In the event that an "or equivalent" “or substitution” is approved, the Contractor shall waive all claims for additional costs and delays related to the "or equivalent" “or substitution” which consequently became apparent.
B. Construction Methods or Procedures Substitution
1. The Contractor may, at his sole cost and expense, submit to the Engineer for his consideration a Modification Request to the Contract Documents for a change in equipment, materials, or methods of work that would result in net cost savings to the
Owner. A Modification Request will only be considered that will not compromise the useful life, operational costs, safety, code compliance, project schedule, or design integrity of the system.
2. The Contractor shall submit all Modification Requests to the Engineer within ten (10) calendar days after Notice to Proceed with the Contactor’s proposed net deduct price.
3. Submit number of copies of request for substitution as specified for submittal of Shop
Drawings. Submit a separate request for each substitution. In addition to requirements in the General Conditions, include in the request the following:
a) Detailed description of proposed substitutions.
b) Itemized comparison of the proposed substitution with specified item.
c) Drawings illustrating proposed substitutions.
d) Other data required by the Engineer to establish that the proposed substitution is equivalent to specified items.
4. The Engineer/Owner will evaluate the proposal and advise contractor within ten (10) working days after receipt of proposal if the proposal is acceptable.
01 25 00 / 3 of 3
2. PRODUCTS – NOT USED
3. EXECUTION – NOT USED
SECTION 01 31 00
COORDINATION
01 31 00 / 1 of 2
1.1 SUBMITTALS
A. Informational
1. Statement of Qualifications (SOQ) for Land Surveyor or Civil Engineer.
1.2 UTILITY NOTIFICATION AND COORDINATION
A. The Contractor will coordinate the Work with various utilities within the Project limits.
The Contractor will notify applicable utilities prior to commencing work and if damage occurs, or if conflicts, or emergencies arise during execution of the Work.
1.3 FACILITY OPERATIONS
A. Continuous operation of the Owner’s facilities is of critical importance. The Contractor shall schedule and conduct activities to enable existing facilities to operate continuously, unless otherwise specified.
B. The Contractor shall perform the Work continuously during critical connections and changeovers, and as required to prevent interruption of the Owner’s operations.
C. When necessary the Contractor shall plan, design, and provide various temporary services, utilities, connections, temporary piping, access, and similar items to maintain continuous operation of the Owner’s facility.
D. The Contractor shall not close lines, open or close valves, or take other actions which would affect the operations of the existing systems, except as specifically required by the
Contract Documents and after authorization by the Owner and Engineer. Such authorization will be considered within 48 hours after receipt of the Contractor’s written request.
E. Contractor shall not proceed with work affecting the facility’s operation without obtaining Owner’s and Engineer’s advanced approval.
1.4 REFERENCE POINTS AND SURVEYS
A. Contractor’s Responsibilities:
1. Check and establish exact location of existing facilities prior to construction of new facilities and any connections thereto.
2. In the event of a discrepancy in data the Contractor shall request clarification before proceeding with the Work.
3. The Contractor shall retain the services of a Professional Land surveyor or Civil
Engineer registered in the State of Virginia, who shall perform or supervise the engineering and surveying necessary for the construction staking and layout.
4. The Contractor shall maintain a complete and accurate log of the survey Work as it progresses as a Record Document.
5. On request of the Engineer, the Contractor shall submit documentation.
6. The Contractor shall provide competent employee(s), tools, stakes, and other equipment and materials as Engineer may require to:
a) Establish control points, lines, and easement boundaries.
b) Check layout, survey and measurement Work performed by others.
c) Measure quantities for payment purposes.
01 31 00 / 2 of 2
3. EXECUTION
3.1 CUTTING FITTING AND PATCHING
A. Cut, fit, adjust, or patch Work and work by others, including excavation and backfill as required, to make the Work complete.
B. Obtain prior written authorization from the Engineer before commencing the Work to cut or otherwise alter:
1. Structural reinforcing steel, structural column or beam, elevated slab, trusses, or other structural member.
2. Weather – or moisture-resistant elements.
3. Efficiency, maintenance, or safety element.
C. Work of others.
1. Refinish surfaces to provide an even finish.
2. Refinish continuous surfaces to nearest intersection.
3. Refinish entire assemblies.
4. Finish restored surfaces to such planes, shapes, and textures that no transition between existing work and Work is evident in finished surfaces.
5. Restore existing work, underground facilities, and surfaces that are to remain in completed Work including concrete-embedded piping, conduit, and other utilities as specified and as shown.
6. Make restorations with new materials and appropriate methods as specified for new
Work of similar nature; if not specified, use recommended practice of manufacturer or appropriate trade association.
7. Fit Work airtight pipes, sleeves, ducts, conduit and other penetrations through surfaces and fill voids.
8. Remove specimens of installed Work for testing when requested by the Engineer.
SECTION 01 31 19
PROJECT MEETINGS
01 31 19 / Page 1 of 1
1. GENERAL
1.1 REQUIREMENTS INCLUDED
A. Contractor participation in preconstruction conferences.
B. Contractor participation of progress meetings and pre-installation conferences.
1.2 PRECONSTRUCTION CONFERENCES
A. Engineer will administer preconstruction conference for execution of Owner-Contractor
Agreement and exchange of preliminary submittals.
B. Attendance: Owner, Engineer, Contractor, major Subcontractors, representatives of Quality
Control firm(s).
1.3 PROGRESS MEETINGS
A. Engineer shall schedule and administer project meetings throughout progress of the work at maximum monthly intervals, as well as administer called meetings, and pre-installation conferences.
B. Engineer shall make physical arrangements for meetings, prepare agenda with copies for participants, preside at meetings, record minutes, and distribute copies within seven (7) days to Contractor, participants, and those affected by decisions made at meetings.
C. Attendance: Contractor’s Superintendent, Contractor's Project Manager, major
Subcontractors and Suppliers; Owner and Engineer as appropriate to agenda topics for each meeting.
D. Suggested Agenda: Review of Work progress, status of progress schedule and adjustments thereto, delivery schedules, submittals, maintenance of quality standards, pending changes and substitutions, and other items affecting progress of Work.
1.4 PRE-INSTALLATION CONFERENCES
A. When required in individual specification Section, Contractor shall convene a pre-installation conference prior to commencing work of that Section.
B. Require attendance of entities directly affecting, or affected by, work of the Section.
C. Review conditions of installation, preparation and installation procedures, and coordination with related work.
SECTION 01 33 00
SUBMITTALS
01 33 00 / Page 1 of 5
1. GENERAL
1.1 REQUIREMENTS INCLUDED
A. Procedures
B. Schedule of Submittals
C. Construction Progress Schedules
D. Shop Drawings
E. Product Data
F. Manufacturer's Instructions
G. Operation & Maintenance Manuals
1.2 PROCEDURES
A. Contractor is required to provide submittals for all materials and equipment furnished and installed under this contract.
B. Contractor shall deliver submittals to Engineer.
C. Transmit each item with Submittal cover attached.
1. Number submittals by specification section and revision number (e.g. 013000-1 for initial submission of schedule of submittals.)
2. Submit only one item per cover. Highlight all deviations from the Contract Documents and provide explanation/justification for deviation.
3. Complete all portions of the form above the Contractor's signature line. Incomplete submittals or submittals with unhighlighted deviations will be returned unreviewed.
D. Submit initial progress schedules and schedule of submittals in duplicate within 15 days after date of Owner-Contractor Agreement. After review by Engineer revise and resubmit as required. Submit revised schedules with each Application for Payment, reflecting changes since previous submittal.
E. Comply with progress schedule for shop drawings, product data, and manufacturer's instructions related to Work progress, and coordinate submittal of related items.
F. Allow a minimum of two weeks' review time.
G. Distribute copies of reviewed submittals to appropriate parties. Instruct recipients to promptly report any inability to comply with provisions.
1.3 SCHEDULE OF SUBMITTALS
A. Contractor to provide to Engineer a Schedule of Submittals for all products used during construction 2 weeks prior to the start of work.
B. Submit the number of copies required by the Contractor, plus three for the Engineer to retain.
1.4 CONSTRUCTION PROGRESS SCHEDULES
01 33 00 / Page 2 of 5
A. Submit horizontal bar chart with separate bar for each major trade or operation, identifying first work day of each week. Show relationships between critical path items and indicate lead times for equipment and materials delivery, etc.
B. Show complete sequence of construction by activity, identifying work of separate stages and other logically grouped activities. Show projected percentage of completion for each item of Work as of time of each Application for Progress Payment.
C. Construction schedule shall consider the following typical number of weather days, (i.e. > 0.10" of precipitation) as well as days following during which site conditions may impede progress of the work. The Contractor will not be allowed a time extension due to inclement weather conditions if the total number of inclement weather days for the duration of the project is less than the total inclement weather days indicated below.
J F M A M J J A S O N D
6 6 7 6 6 6 8 6 5 5 5 6
D. Submit the number of copies required by the Contractor, plus three for the Engineer to retain.
E. Determination of actual rain days will be based on data published by NOAA for the gauging station nearest the project site, which will be identified at the pre-construction meeting.
F. At each monthly progress meeting, prepare a Monthly Project Summary Report (form included with this section) and attach to the revised project schedule.
1.5 SHOP DRAWINGS
A. Submit the number of copies required by the Contractor, plus three for the Engineer to retain.
1.6 PRODUCT DATA
A. Mark each copy to identify applicable products, models, options, and other data;
supplement manufacturer's standard data to provide information unique to the Work.
B. Submit the number of copies required by the Contractor, plus three for the Engineer to retain.
1.7 MANUFACTURER'S INSTRUCTIONS
A. Submit manufacturer's printed instructions for delivery, storage, assembly, installation adjusting, and finishing.
B. Submit the number of copies required by the Contractor, plus three for the Engineer to retain.
01 33 00 / Page 3 of 5
3. EXECUTION
3.1 SHOPDRAWINGS AND SUBMITTALS
A. Contractor shall keep a copy of all shop drawings and submittals on the project site for the duration of the contract.
(See Monthly Project Summary Report which follows)
(See Submittal Cover which follows)
01 33 00 / Page 4 of 5
MONTHLY PROJECT SUMMARY REPORT
MEETING DATE: ________________
Is the project on Schedule? ________ Yes _______ No
Number of weeks AHEAD of Schedule ______
Number of weeks BEHIND Schedule ________
List items from Schedule which are AHEAD OF SCHEDULE:
List items from Schedule which are RIGHT ON SCHEDULE:
List items from Schedule which are BEHIND SCHEDULE:
If behind, what is the Contractor doing to get back on schedule?
When does the Contractor anticipate the Project to be back on Schedule? Date: _____________
Are there any outstanding change order items? ________ Yes ________No
If so, list them:
Adverse Weather Summary
J F M A M J J A S O N D
Scheduled
Actual
Balance
SUBMITTED:___________________________ DATE: _________________________
SIGNED: ______________________________ TITLE: _________________________
01 33 00 / Page 5 of 5
Submittal Cover
No. - .
Project: Project #:
To: Timmons Group From:
Attn:
7053 Celebration Park Ave., Suite 300 Richmond, Virginia 23225
Date Submitted: Review Requested Not Later Than:
Submittal Information and Contractor’s Representation
Subject:
Pursuant to Specification Section(s): Drawing No(s).
Submitted as: Specified Item “Equal” Item Substitution
Items Submitted:
The Contractor’s submittal of items for the Engineer’s review and approval constitutes a representation that the items proposed have been reviewed thoroughly by the Contractor and found to be in conformance with the requirements of the Contract Drawings and Specifications. All deviations have been clearly listed in the submittal package and an explanation provided for the deviation.
Contractor’s Reviewer (sign): Date:
Review Information Timmons Group:
Received on: Forwarded for review to:
Reviewer:
Received On: Reviewed by:
Review is for general compliance with the Contract Documents. Nothing in this review shall be taken as permitting variation from the Contract Documents, unless specifically stated by the reviewer in writing. Sole responsibility for correctness of dimensions, options, details, quantities, and safety during fabrication and erection shall remain with the Contractor. EVALUATION OF
INSTALLATION FOR FINAL ACCEPTANCE WILL BE BASED ON THE CONTRACT DOCUMENTS,
NOT THE SUBMITTALS, EXCEPT AS SPECIFICALLY APPROVED OTHERWISE IN WRITING.
No Exceptions Taken Rejected Resubmission Not Required
Revise and Resubmit Submit Specified Item
Comments:
Returned to Timmons Group: Returned to Contractor:
SECTION 01 40 00
TESTING AND INSPECTION
01 40 00 / 1 of 4
1.1 REQUIREMENTS INCLUDED
A. Testing and Inspection
1. Concrete
2. Reinforcing Steel
3. Structural Steel
4. Coatings
5. Piping Systems
6. Equipment and Controls
1.2 OWNER FURNISHED INSPECTION SERVICES
A. The Owner shall retain the services and be responsible for payment for an independent inspection firm or firms (Inspection Firm) to provide on-site inspection of certain aspects of the elevated tank including:
1. Special Inspections Required by the Building Official
a) Structural Steel
b) Earthwork
c) Concrete
2. Coatings
a) Weld grinding
b) Blasting
c) Holiday testing
d) Paint film thickness testing
1.3 CONTRACTOR FURNISHED TESTING SERVICES
A. At the time of the Preconstruction Conference, the Contractor shall provide to the Engineer and Owner the identity of the quality control firm and laboratory (QC Firm) proposed to perform the field quality control…