This is an Invitation to Bid issued by the City of Warsaw, Missouri for two combined capital improvement projects on Main Street. Project A, "Warsaw Main Street Improvements - Arcadia to Hackberry" (Federal Project TAP-9901(461) / ARPA #SLFRP4542), designed by Great River Engineering, encompasses approximately 1,360 feet of roadway improvements including grading, concrete and aggregate bicycle lanes, street lighting, sidewalks, asphaltic pavement widening and overlay, curb and gutter, storm sewers, driveways, pavement markings, and signage between Arcadia Street and Hackberry Street. Project B, "Main St. Non-Motorized Street Improvements II" (Federal Project TAP-9901(559)), designed by OWN Engineering, includes construction of a 5-foot concrete sidewalk and 4-foot concrete bike lane along approximately 1,710 feet of sidewalk and 2,140 feet of bike lane on the south side of Main Street between Hackberry Street and Dogwood Drive, with associated storm sewers, curb and gutter, street lighting, asphalt widening, milling and overlay, pavement markings, and signage. Sealed bids will be received until 2:00 P.M. on Tuesday, June 23rd, 2026 at the Warsaw Community Building, 181 W. Harrison Street, Warsaw, Missouri. A non-mandatory prebid meeting is scheduled for 2:00 P.M. on Tuesday, June 16th, 2026 at the same location. The project will be awarded to the lowest responsive and responsible bidder for the combined bid amount of both projects.

Plans and specifications are available from the City of Warsaw or directly from the engineering firms for a non-refundable deposit of $50.00 per set, with additional shipping costs borne by the bidder. Digital plans and contract documents are available from Great River Engineering (sshank@greatriv.com, 417-868-7171) and OWN, Inc. (cdake@weareown.com, 417-866-2741). All contractors must be on MoDOT's Qualified Contractor List and must submit a completed contractor questionnaire seven days prior to bid opening. A certified cashier's check or bid bond in the amount of 5% of the bid must accompany each proposal. The contract requires payment of prevailing wage rates as determined by both the Missouri Department of Labor and Industrial Relations and the United States Department of Labor, with contractors obligated to pay the higher applicable rate. Contractors and subcontractors must provide a 10-Hour OSHA construction safety program or approved equivalent to on-site employees within 60 days of project commencement. The DBE (Disadvantaged Business Enterprise) goal for the project is 0%, and no second-tier subcontracting is permitted. All bids must be submitted as hard copies.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO BID, CITY OF WARSAW, MO

MAIN STREET IMPROVEMENTS

ARCADIA STREET TO DOGWOOD DRIVE

Sealed bids for two (2) combined capital improvement projects labeled as “Warsaw Main Street Improvements – Arcadia to Hackberry, Federal Project TAP-9901(461) / ARPA #SLFRP4542” (Project A) and Main St. Non- Motorized Street Improvements II, Hackberry to Dogwood Drive, Federal Project TAP-9901(559)” (Project B), addressed to the City of Warsaw, Missouri, 201 W. Main Street, Warsaw, Missouri 65355, will be received by the City of Warsaw until 2:00 P.M., Prevailing Local Time, on Tuesday June 23rd, 2026 at the Warsaw Community Building, 181 W. Harrison Street, in Warsaw, Missouri, and at that time will be publicly opened and read aloud. A non-mandatory prebid meeting will be held at 2:00 P.M. on Tuesday June 16th, 2026 at the Warsaw Community Building, 181 W. Harrison Street in Warsaw, Missouri. All bids shall be submitted as a Hard Copy.

The proposed work for Project A, designed by Great River Engineering, generally includes the following:

Grading and Embankment, Concrete Bicycle Lanes, Aggregate Bicycle Lane, Street Lighting, Sidewalks, Asphaltic Pavement Widening and overlay, Aggregate Base, Curb and Gutter, Storm Sewers, Driveways, Pavement Markings, and Signage. The project is located along Main Street between Arcadia Street and Hackberry Street.

Arcadia Street to Illinois Street includes construction of an aggregate bicycle lane on the north side of the roadway.

Between Illinois Street to Hackberry Street, the project is along both sides of the roadway, and includes full-width asphalt overlay. The full project is approximately 1,360 feet in length. Questions regarding Project A should be directed to Great River Engineering at (417) 868-7171..

The proposed work for Project B, designed by OWN Engineering, generally includes the following: Construction of a 5’ concrete sidewalk and 4’ wide concrete bike lane, access connections, storm sewers, curb and gutter, street lighting, asphalt widening, milling and overlay, Pavement Markings, and Signage and any incidental work related thereto, including street improvements within the project area in accordance with the plans and specifications. The project is generally located along the south side of Main St. between Hackberry St. and Dogwood Dr. The total length of improvements is approximately 1,710 feet of sidewalk and 2,140 feet of bike lane. Questions regarding Project B should be directed to OWN Engineering at (417) 866-2741..

Plans and Specifications for both projects may be obtained from the City of Warsaw at 201 W. Main Street, Warsaw, Missouri 65355 (660-438-5522) or from either of the engineering firms. A nonrefundable deposit in the amount of $50.00 for each set of plans and specifications is required. Additional shipping and handling expenses are applicable and shall be the responsibility of the bidder.

Plans and specifications for Project A may be obtained at the offices of Great River Engineering, 2826 South Ingram Mill Road, Springfield, Missouri, upon payment of a submission of a non-refundable deposit of $50.00 for each set. Additional shipping and handling expenses are applicable and the responsibility of the bidder.

Checks for plans, specifications and shipping are to be made payable to Great River Engineering. Digital plans and contract documents may be obtained from the Engineer by contacting sshank@greatriv.com or calling (417) 868-7171.

Plans and specifications for Project B may be obtained at the offices of OWN, Inc, formerly Anderson Engineering, 3213 South West Bypass, Springfield, Missouri, upon payment of a submission of a non-refundable deposit of $50.00 for each set. Additional shipping and handling expenses are applicable and the responsibility of the bidder.

Checks for plans, specifications and shipping are to be made payable to OWN, Inc. Digital plans and contract documents may be obtained from the Engineer by contacting cdake@weareown.com or calling (417) 866-2741.

This contract requires payment of the prevailing hourly rate of wages for each craft or type of work required to execute the contract as determined by the Missouri Department of Labor and Industrial Relations, and requires adherence to a schedule of minimum wages as determined by the United States Department of Labor. For work performed anywhere on this project, the contractor and the contractor’s subcontractors shall pay the higher of these two applicable wage rates. The applicable state rates for this contract are detailed in “Annual Wage Order 32”, that is attached to this bidding document. The applicable federal wage rates for this contract are the effective Davis-Bacon federal wage rates posted the tenth day before the bid opening date and can be found at:

https://sam.gov/content/wage-determinations. These supplemental bidding documents have important legal consequences. It shall be conclusively presumed that they are in the bidder’s possession, and they have been reviewed and used by the bidder in the preparation of any bid submitted on this project.

The City of Warsaw, Missouri hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, businesses owned and controlled by socially and economically disadvantaged individuals will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, religion, creed, sex, age, ancestry, or national origin in consideration for an award.

All bidders must be on MoDOT’s Qualified Contractor List per Section 102.2 of the current version of the Missouri Standard Specifications for Highway Construction. The contractor questionnaire must be on file 7 days prior to bid opening.

Contractors and sub-contractors who sign a contract to work on public works projects shall provide a 10-Hour OSHA construction safety program, or similar program approved by the Department of Labor and Industrial Relations, to be completed by their on-site employees within sixty (60) days of beginning work on the construction project.

A certified cashier’s check or a bid bond in the amount of 5% shall be submitted with each proposal.

The City of Warsaw, Missouri reserves the right to reject any or all bids.

The project will be awarded to the lowest, responsive, responsible bidder for the combined bid amount for both projects.

The DBE Goal for this project is 0%.

No 2nd tier subcontracting will be allowed on this project.