This document is Section C of a federal IDIQ (Indefinite Delivery/Indefinite Quantity) contract work statement for construction services supporting U.S. Immigration and Customs Enforcement (ICE) at a Service Processing Center (SPC).
The contract establishes a Multiple Award Construction Contract (MACC) with a five-year base period and optional extension periods. The contractor will provide design-build or performance-based construction delivery methods for projects including new construction, renovation, demolition, repair, building system installations, and infrastructure systems. Facilities may include dormitories, administrative buildings, medical clinics, classrooms, training centers, warehouses, roads, and firing ranges. Major work elements encompass architectural, civil, structural, mechanical, electrical, fire protection, and communication systems. Each task order will have its own specific period of performance and schedule determined by scope and complexity. Work must comply with numerous industry codes and standards including ACI, AISC, ASCE, ANSI, ASHRAE, ASTM, IBC, NFPA, and ICE-specific detention facility standards, along with all applicable federal, state, and county laws. The contractor must maintain capability to perform multiple concurrent task orders with overlapping schedules and demonstrate sufficient organizational, financial, and bonding capacity.
Key performance requirements include submission of a Management Plan within 15 days of award; attendance at post-award and pre-construction conferences; development of critical path method project schedules; independent utility locating using ground-penetrating radar; compliance with ICE security protocols including personnel background checks and badging; use of Kahua project management software; and submission of comprehensive deliverables including design documents at 35%, 65%, 95%, and 100% completion stages, as-built drawings, O&M manuals, warranty documentation, daily progress reports, quality control and safety plans, and NEPA documentation. The contractor must maintain a qualified Project Manager with a bachelor's degree and 10 years of experience, a Designer of Record with 5+ years of detention facility design experience, registered design professionals for each discipline, a superintendent with 5+ years of similar project experience on-site at all times, and a Quality Control Manager with appropriate engineering or construction management credentials and 5+ years of quality control experience. All contractor employees must be approved by ICE Security Division prior to site access, and the contractor is responsible for all damage to existing utilities caused by their activities.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATION/WORK STATEMENT
Disclaimer: This list is illustrative only and is provided for informational purposes to convey the general scope and nature of work that may be performed under this contract.
Inclusion of a project on this list does not obligate the Government to issue a task order for that project, nor does it guarantee that any task orders or awards will be made under this IDIQ contract. The Government reserves the right to issue task orders for other construction-related projects consistent with the overall scope of this contract.
C.1 General
This MACC will support primarily design-Build (DB) or performance-based construction delivery methods. Projects may include, but are not limited to new construction, renovation, demolition, repair, building system installations, and infrastructure systems. Major elements of the work may include architectural, civil, structural, mechanical, electrical, fire protection, and communication systems. Facilities may include, but are not limited to dorms, administrative buildings, medical clinics, classrooms, training centers, warehouses, roads, firing ranges.
Repairs may include, but are not limited to HVAC, electrical, fire suppression, site work, and security upgrades. Renovations may involve cosmetic upgrades up to major building renovations inclusive of change of occupancy use.
C.2 Period of Performance
The overall contract will include a base period of five (5) years from the date of award. The Government may include option periods as defined in the solicitation.
Each individual Task Order issued under this contract will include its own specific period of performance and schedule, which will be defined in the Task Order documentation. Task Order durations may vary depending on the scope and complexity of the work
C.3 Performance Requirements
The contractor shall perform all work in accordance with:
• Task Order-specific technical specifications, drawings, and schedules
• Applicable codes (Industry Criteria, latest edition upon task order solicitation) including, but not limited to:
American Correctional Association ACA Performance-Based Standards and Expected Practices for Adult Local Detention Facilities (Where the ICE Detention Standards are silent, the ACA Jail Standards must be followed)
American Concrete Institute
ACI Manual of Concrete Practice, ACI 315R-18, Guide to Presenting Reinforcing Steel Design Details ACI 318-19 Building Code Requirements for Reinforced Concrete o PCA Notes on ACI 318-19 ACI 301-16 Specifications for Structural Concrete for Buildings
American Institute of Steel Construction AISC Steel Construction Manual AISC Seismic Design Manual ANSI/AISC 360-22 Specification for Structural Steel Buildings ANSI/AISC 341-22 Seismic Provisions for Structural Steel Buildings
American Iron and Steel Institute AISI S100-16 North American Specification for the Design of Cold- Formed Steel Structural Members
American Society of Civil Engineers ASCE 7-22 Minimum Design Loads for Buildings
American National Standards Institute ANSI/TIA/EIA-568-B.2 Commercial Building Telecommunications Cabling Standard ANSI/IEEE C2-2002, National Safety Electric Code.
ANSI A117.1-2017 – Accessible and Usable Buildings and Facilities ANSI/NAAMM HMMA 863 - Guide Specifications for Detention Security Hollow Metal Doors and Frames ANSI/AWS D1.1 - Structural Welding Code-Steel ANSI/AWS D1.3 - Structural Welding Code - Sheet Steel
American Society of Heating, Refrigerating and Air Conditioning Engineers ASHRAE 55 Thermal Environmental Conditions for Human Occupancy ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality ASHRAE 90.1 Energy Standards for Buildings Except Low-Rise Residential Buildings
American Society for Testing and Materials ASTM A653/A653M - Specification for Steel Sheet, Zinc-Coated (Galvanized)or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process ASTM B117 - Standard Practice for Operating Salt Spray (Fog) Testing Apparatus ASTM D2794 - Test Method for Resistance of Organic Coatings to the Effects of Rapid Deformation (Impact) ASTM F33 Committee - Draft test method for steel Bunks, Seats, Tables used in detention facilities.
ASTM F2322-12- Test Methods for Physical Assaults on Fixed Barriers for Detention Facilities.
ASTM F2697-15; Physical Assault on Horizontal Fixed Barriers for Detention and Correctional Facilities.
ASTM F1450-12- Test Methods for Hollow Metal Swinging Door Assemblies for Detention Facilities
American Water Works Association Standards
AWWA C651-05
Illuminating Engineering Society The Lighting Handbook (illumination level requirements)
International Code Council IBC International Building Code IMC International Mechanical Code IPC International Plumbing Code IECC International Energy Conservation Code IFC International Fire Code IFGC International Fuel Gas Code
International Organization for Standardization (ISO)/International Electrotechnical Commission
(IEC)
ISO/IEC 27001:2013 Information Technology-Security Techniques- Information Security Management Systems Requirements
The Masonry Society TMS 402/602-22 Building Code Requirements and Specifications for Masonry Structures
National Design Specification NDS-18 National Design Specification for Wood Design w/ Supplement
National Fire Protection Association (If conflicts arise in code, NFPA 101 shall be the overarching document to be followed) NFPA 13, Installation of Sprinkler Systems NFPA 70, National Electric Code NFPA 70E - Electrical Workplace Safety NFPA 72, National Fire Alarm Code NFPA 90A Installation of Air Conditioning and Ventilating Systems NFPA 101 Life Safety Code
• Government Criteria:
All applicable Federal, State and County Laws and requirements (including applicable State Building Codes where design requirements more stringent than IBC)
Department of Homeland Security U.S. Immigration & Customs Enforcement Information and Communications Technology Systems Structured Cable Plant Standard, January 2025 Edition U.S. Immigration & Customs Enforcement Service Processing Center Detention Construction Standards U.S. Immigration & Customs Enforcement Facility Design Guide (Revised 2025) and references incorporated within the guide
U.S. Immigration & Customs Enforcement Health Services Design Standards (June 2023) U.S. Immigration & Customs Enforcement National Detention Standards (2025)
Department of Justice Prison Rape Elimination Act (PREA)
Federal Highway Administration Federal Highway Administration Publication No. FHWA-NHI-01¬021, Hydraulic Engineering Circular No. 22, Second Edition, URBAN DRAINAGE DESIGN MANUAL
U.S Weather Bureau U.S. Weather Bureau Technical Paper No. 40, dated May 1961, Rainfall Frequency Atlas of the United States for Durations from 30 minutes to 24 hours, and return periods from 1 to 100 years
United States Access Board Architectural Barriers Act (ABA) Standards
The contractor shall:
• Ensure all work is completed in a safe, timely, and professional manner.
• Maintain a clean and secure job site at all times.
• Coordinate with Government personnel to minimize disruption to ongoing operations.
• Submit and adhere to project designs schedules, construction schedules, safety plans, and quality control plans as required by each Task Order.
• Comply with all environmental protection requirements, including proper handling and disposal of hazardous materials.
• Provide as-built drawings, warranties, training, and operation and maintenance (O&M) manuals as required by each Task Order.
• The contractor shall maintain the capability to perform multiple, concurrent task orders under this contract. This includes, but is not limited to, the ability to manage overlapping schedules, allocate resources across projects, and coordinate subcontractors and suppliers, as needed.
• The Government may issue task orders with overlapping periods of performance at different locations.
• Contractors shall demonstrate sufficient organizational, financial, and bonding capacity to support concurrent execution of task orders. Bonding capacity may be used as an indicator of the contractor’s ability to manage multiple projects simultaneously.
C.4 Contractor Staff and Employees
1. Prior to the issuance of the first TO, the contractor shall provide the CO with the telephone number at which the contractor or his representative may be contacted at any time during the regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention. The above-mentioned representative, if provided, must have full power and authority to act upon the behalf of the contractor.
2. The contractor shall maintain a Project Manager and provide the CO a personnel list ten
(10) days prior to performance of the contract. The individual designated as the project manager shall have full authority to act for the contractor. The personnel shall meet or exceed the position requirements submitted in the SOW. The Government reserves the right to approve or disapprove personnel based on the position requirements. The contractor shall provide experienced and knowledgeable personnel in civil, structural, architectural, mechanical, and electrical disciplines.
Project Manager Qualifications: BS degree in an appropriate field in at least one of the following: (Building Engineering, Civil Engineering, Construction Management, Architecture, Construction Engineering). Shall have at least 10 years of experience managing project of similar size and value. The Project Manager must be capable of reading, writing, and conversing fluently in the English language.
3. For all Design Build contracts, the following key personnel, with applicable experience, shall be provided.
• Designer of Record
Designer-of-Record Qualifications: The design shall be accomplished by a professional Architecture Engineering firm (serving as the Designer of Record) with at least 5 years of experience in design related to projects of similar size, value, and scope. The Designer of Record shall be a registered professional engineer in the state of the project.
• Registered Design Professionals
Registered Design Professionals Qualifications: Registered Design Professionals, who will be responsible for each discipline of the design, shall be registered professionals (professional engineer, registered architect or certified by NCIDQ) in a state within the United States of America.
• Superintendent
Provide project superintendent with a minimum of 5 years as a superintendent on projects similar in size and complexity. The individual must be familiar with and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. Minimum Communication Requirements:
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the jobsite always during the performance of Contract work. The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted. A letter designating the superintendent shall be sent to the CO within ten (10) calendar days of receipt of the Notice to Proceed. This letter shall provide the superintendent’s complete name, address, daytime and after hours phone numbers. The superintendent must have the authority to act on behalf of the contractor (FAR 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)). A designation letter shall be submitted for each and every task order issued under this contract.
The superintendent shall have on site the drawings and specifications for this project
(FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB
1997)). Drawings shall be redlined (as necessary) and kept current for submission at the completion of the project. Drawings must always be available for CO’s Representative (COR) review throughout the project.
• Quality Control Manager
The Quality Control Manager must be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of five years construction quality control experience on construction similar to this Contract or a construction person with a minimum of ten years of construction experience, of which a minimum of five years’ experience must be in construction quality control on construction similar to this contract. The Quality Control Manager and all members of the quality control organization must be capable of reading, writing, and conversing fluently in the English language. The Quality Control Manager or qualified alternative must be on-site at all times during the performance of this contract work until the work is completed and accepted.
4. Supervision. The Government will not exercise any supervision or control over the contractor’s employees performing services under this contract. Such employees shall be accountable not to the Government, but solely to the contractor, who, in turn, is responsible to the Government. At all times during the performance of each TO under this contract, and until the work under that TO is completed and accepted, the contractor shall directly oversee the work under each TO, or assign, and have on the work site, a competent representative who is satisfactory to the CO and has authority to act for the contractor. This may include a working supervisor.
5. Contractor’s Employees: The contractor’s employees shall adhere to the rules and regulations of the SPC applicable to employees’ conduct/behavior. The CO may require, in writing, the contractor to remove from the job site any employee the CO deems incompetent, careless, or otherwise objectionable. The contractor shall select personnel who are well qualified to perform the required work, for supervising techniques used in their work, and for keeping them informed of all improvements, changes, and methods of operation. In addition, the contractor shall take appropriate personnel action, as required, in the event employee(s) become involved with law enforcement authorities as a result of misconduct.
C.5 Management Plan
Contractor shall submit a Management Plan within 15 days of contract award. The plan shall clearly explain how the contractor’s labor, resources, materials, and suppliers will be coordinated to include leveraging subcontractors to ensure successful project completion. An organizational structure depicted through a chart to articulate home office support, on site management and how the chain of command will be leveraged to address any potential issues. The organizational structure shall depict lines of authority and lines of communication. The plan should address how the offeror will address the labor challenges in this region to ensure available subcontractor skilled labor for successful project completion. The plan should address resource allocation, risk management, scheduling, and communication details.
C.6 Post-Award Conference
Before the issuance of the first task order under the contract, a post-award conference shall be conducted by the CO, with the COR in attendance, to acquaint the contractor with Government policies and procedures that shall be observed during the prosecution of the work, and to develop a mutual understanding relative to the administration of the contract. It is strongly suggested that the contractor's Project Manager, Quality Control Manager, Superintendent, and other appropriate employees attend this conference. Individual task order conference: At the discretion of the CO and/or the COR, a pre-construction conference may be conducted prior to the commencement of work on individual task orders.
C.7 Preconstruction Conference
Prior to start of construction for each individual task order, a pre-construction conference will be scheduled by the authorized representative of the Contracting Officer. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out and the processes for joint risk management between the Contractor and Government. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
C.8 Project Schedule
Develop a project schedule for each task order. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Use the Critical Path method (CPM) of network calculation to generate all project schedules. Include in the schedule activities associated with the critical submittals and their approvals, NEAPA review, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Include in the schedule activities for submission, review, and acceptance of design packages, submission and approval of O&M Manuals, submission and approval of As-Built drawings, pe-final inspections, punch list, and final inspection.
C.9 Existing Utilities
Utility locations when shown are approximate. Provide an independent, private utility locating company to positively identify underground utilities in the work area in addition to any station locating service and coordinated with the station utility department. The third party, independent, private locating company must locate utility depth by use of Ground Penetrating Radar (GPR), X-ray, bore scope, or ultrasound prior to the start of demolition and construction. The use of historical drawings does not alleviate the Contractor from meeting this requirement. Contractor responsible to fully repair all damage caused by their activities to existing utilities.
C.10 Security Requirements
The contractor shall comply with all ICE security protocols, including but not limited to:
• Personnel background checks and badging requirements
• Escort procedures for uncleared personnel
• Protection of Government property and controlled areas
• Immediate reporting of security incidents or breaches to the Contracting Officer and Security Office
Contractors shall ensure that all personnel are trained in site-specific security procedures and that access to restricted areas is controlled at all times.
C.11 Federal Construction Management Software Usage Requirements (MACC Contract)
ICE will be using Kahua as its project management software. All project documentation and submittals will be managed through Kahua.
C.12 Compliance and Security Standards
All personnel accessing the SPC must be prior approved by the ICE Security Division. Specific project security measures are provided elsewhere in these specifications.
The project is to be fully contained within a security fenced enclosure and access to the site is controlled via security protocols. The D-B Contractor must be responsible for constructing the perimeter security infrastructure needed to secure the site and its subsequent connection to the existing secure SPC campus and must tie into existing fiber optic perimeter fence detection system in all fencing being altered or added. Coordination with SPC personnel before removing or altering any fencing or security apparatus is required. All fencing removal and installation must be done with the plan to always provide containment at required levels.
C.13 Project Documentation and Collaboration
The Contractor shall perform all project activities including but not limited to:
• RFIs
• Submittals & Approvals
• Punch Lists
• Project Schedules
• Change Orders
• Design Reviews (for design-build)
• Progress Payments
• NEPA reviews and document preparation
C.14 Data Integrity and Audit Readiness
Contractors shall ensure:
• Complete audit trails of all transactions
• Document retention for 3 years after final payment in accordance with RFO 4.703
• Real-time budget tracking and reporting
• FOIA-compliant documentation for public transparency
C.15 Cleanup and Site Restoration
The contractor shall:
• Maintain a clean and orderly work site throughout the duration of the project
• Remove all construction debris, waste materials, and equipment upon completion of work
• Restore all disturbed areas to their original or specified condition, including landscaping, pavement, and utilities
• Dispose of all waste in accordance with federal, state, and local environmental regulations
• Conduct a final site walkthrough with the Government to verify cleanup and closeout compliance
If the Contractor fails to maintain a clean and safe work environment, the Government may decide to take corrective action or withhold payment until deficiencies are resolved.
C.16 Deliverables
The Government will define deliverables in each Task Order that may include, but are not limited to:
• Design Schedules
• Construction schedules
• Site Plan
• Design documents (35%, 65%, 95%, 100% as indicated)
• As-built drawings
• O&M Manuals
• Warranty Documentation
• Daily Progress reports
• Quality control plan and inspection reports
• Site Safety and Health plan and reports
• NEPA Categorical Exclusions, Environmental Assessments, and decisional documents (if applicable)
• LEED documentation (if applicable)
• BIM models (if applicable)
• Commissioning reports (if applicable)
• TAB reports
• Security plans (if applicable)
• Final inspection and acceptance documentation
C.17 Points of Contact
The contractor shall designate and provide the Government with primary and alternate points of contact (POCs) for task order issuance and coordination. These individuals shall be authorized by the Contractor to receive task order solicitations, respond to requests for proposals, and coordinate technical and contractual matters.
The contractor shall provide the following information for each POC:
• Full name
• Title/role
• Email address
• Direct phone number (mobile or office)
The contractor shall ensure that all POC information is kept current throughout the life of the contract. POC designations are valid until the Contracting Officer is notified of a change. Any changes to POC information shall be submitted to the Contracting Officer in writing within five
(5) business days of the change.
Each IDIQ task order will designate a Contracting Officer (CO) and a Contracting Officer’s Representative (COR). All contractual matters shall be directed to the CO at the Task Order
C.18 Information Technology
1. IT Purchase Authorization
The contractor shall ensure all IT products and services direct charged to the contract are approved through the OCIO’s Commercial IT Request (CITR) Application. This includes, but is not limited to, FITARA, Supply Chain Risk Management (SCRM), IPv6, and 508 compliance.
No purchases of commercial IT products or services should be made prior to coordination and approval by the OCIO. Contractor shall report purchases monthly. This contract shall only be used to purchase software, software maintenance, hardware, or hardware maintenance necessary for the performance of this contract. ICE shall own the license(s) or subscriptions for any software or applications purchased. All hardware shall be titled to ICE.
2. Section 508 Conformance
The contractor shall ensure that all products, platforms, services, and communications delivered as part of this work statement, that are Information and Communication Technology (ICT) or contain ICT, conform to the Revised Section 508 of the Rehabilitation Act Standards, 36 C.F.R.
§ 1194.1 & Apps. A, C & D. The Standards may be found at https://www.ecfr.gov/current/title- 36/section-1194.1
3. Records Management
• The Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law, including but not limited to, the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, as well as ICE records policies (NPD 1440.6, ICE Records Management Program, and NPR 1441.1, ICE Records Management Program Requirements).
• The Contractor shall ensure that ICE-owned/Contractor-held records are segregated from contractor-owned records and from non-record materials and report holdings of ICE records.
• The Contractor shall immediately notify the Contracting Officer and ICE Records Officer upon discovery of any inadvertent or unauthorized removal, defacing, alteration, or destruction of Federal records. Destruction of Federal Records is EXPRESSLY PROHIBITED unless in accordance with records retention schedules or as directed by the Contracting Officer.
• All Contractor employees assigned to this contract who create, work with, or otherwise handle Federal Records are required to complete mandatory ICE- provided records management training. The Contractor shall ensure that training has been completed according to agency policies, including initial training and any required annual or refresher training.
• The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.
4. Use of Artificial Intelligence (AI) During Contract Performance
• The contractor must disclose any potential or intended use of Artificial Intelligence (AI) technologies, tools, or systems in the performance of this contract. If it is unknown at the time of contract award whether AI will be used, the contractor must provide written notice to the Government prior to the deployment of any AI systems during contract performance. If AI technologies are introduced after the commencement of contract https://www.ecfr.gov/current/title-36/section-1194.1 https://www.ecfr.gov/current/title-36/section-1194.1 performance, the contractor must notify the contracting officer in writing prior to the release or deployment of any AI component, capability, or system in the ICE environment.
• The Government reserves the right to review, approve, or disapprove the proposed use of
AI technology in the performance of this contract. The contractor must obtain written approval from the contracting office before implementing AI systems.
• If any subcontractor intends to use AI technologies in the performance of work under this contract, the contractor must ensure that similar notification and disclosure requirements apply to all subcontractors. The contractor is responsible for collecting the notification and disclosure requirements from subcontractors and submitting them to the Government.
C.20 Data Requirement Deliverables (DRDs)
This section provides a description of the fields of the Data Requirement Documents (DRDs).
• DRD No.: Unique identifier for the DRD.
• DRD Title: Unique name for the DRD.
• Date: Date prepared.
• Purpose / Use: The purpose of and ICE’s intended use for the DRD.
• Remarks: This field provides additional submittal information, if necessary.
• Data Requirements: This field provides the detailed description of the required and/or expected content and scope of the deliverable(s).
DATA TRANSMITTAL AND FORMAT:
This section provides additional detail regarding the transmittal and format of the DRDs.
The Contractor shall transmit Data Transmittal DRDs to ICE electronically, by hardcopy, or by other mechanism agreed to by the Contracting Officer. The Contractor shall notify the Contracting Officer and the Contracting Officer Representative (COR) in writing of DRD delivery.
Data Transmittal Package:
• For each DRD, the Contractor shall ensure the transmittal package includes:
o Contractor transmittal memorandum that provides the following information:
a. Contract number.
b. Contractor name.
c. DRD number.
d. DRD data type (specified in “Type” column of the DRL).
e. Submission date or milestone being satisfied.
f. Document number and revision.
g. Document title.
h. File names of all files being delivered; multiple files per document must be clearly related to the document.
i. Distribution (Notification list as defined by the DRD distribution field and the
Contracting Officer’s letter).
j. Targeted release date.
o Electronic files submitted to the appropriate ICE or Contractor site.
---End of Section---
SECURITY REQUIREMENTS
GENERAL
The United States Immigration and Customs Enforcement (ICE) has determined that performance of the tasks as described in this contract requires that the Contractor, subcontractor(s), vendor(s), etc. (herein known as Contractor) have access to sensitive DHS information, and that the Contractor will adhere to the following.
POSITION DESIGNATION
IAW Title 5, CFR part 731, dated December 18, 2024, and 5 CFR 1400. Agencies are required to designate position risk and sensitivity level for all contractor employees to determine the commensurate level of background investigation. The public trust risk of a position is the assessment of the degree of potential damage to the efficiency or integrity of the service that could arise from misconduct by the incumbent in the position.
Therefore, once the contract is awarded and before the vendor starts submitting personnel for security vetting, the contractor will provide, through the Contracting Officer’s Representatives (CORs) a list of all positions, to include titles and specific description of the duties for each of positions assigned to support the contract.
PRELIMINARY FITNESS DETERMINATION
ICE will exercise full control over granting, denying, withholding or terminating unescorted government facility and/or sensitive Government information access for contractor applicants/employees, based upon the results of a Fitness screening process. ICE may, as it deems appropriate, authorize and make a favorable expedited preliminary Fitness determination based on preliminary security checks. The preliminary Fitness determination will allow the contractor employee to commence work temporarily prior to the completion of a Full Field Background Investigation. The granting of a favorable preliminary Fitness shall not be considered as assurance that a favorable final Fitness determination will follow as a result thereof. The granting of preliminary Fitness or final Fitness shall in no way prevent, preclude, or bar the withdrawal or termination of any such access by ICE, at any time during the term of the contract.
No employee of the contractor shall be allowed to enter on duty and/or access sensitive information or systems without a favorable preliminary Fitness determination by the Office of Professional Responsibility (OPR), ICE Personnel Security Division (PSD). No employee of the contractor shall be allowed unescorted access to a Government facility without a favorable preliminary Fitness determination by OPR PSD. Contract employees are processed under 5 CFR 731 dated December 18, 2024, and DHS
Instruction 121-01-007, Revision 2, dated August 10, 2024, or successors thereto; those having direct contact with Detainees will also have 6 CFR § 115.117 considerations made as part of the Fitness screening process. Sexual Abuse and Assault Prevention Standards implemented pursuant to Public Law 108-79 (Prison Rape Elimination Act (PREA) of 2003)).
BACKGROUND INVESTIGATIONS
Contractor employees (to include applicants, temporary, part-time and replacement employees) under the contract, needing access to sensitive information and/or ICE Detainees, shall undergo a position sensitivity analysis based on the duties each individual will perform on the contract. The results of the position sensitivity analysis shall identify the appropriate background investigation to be conducted.
Background investigations will be processed through OPR PSD. Contractor applicant/employees are nominated by a Contracting Officer Representative (COR) for consideration to support this contract via submission of the DHS Form 11000-25 and ICE Supplement to the DHS Form 11000-25 to OPR PSD.
This contract shall submit the following security vetting documentation to OPR PSD, through the COR, within 10 days of notification of initiation of an Electronic Application for Background Investigations (eAPP), or successor thereto, in the Office of Personnel Management (OPM) automated on-line system:
1. Standard Form 85P (Standard Form 85PS (with supplement to 85P required for those with direct contact with detainees or armed positions)), “Questionnaire for Public Trust Positions” form completed online and archived by the contractor applicant/employee in their NBIS eAPP account.
2. Signature Release Forms (Three total) generated by NBIS eAPP upon completion of Questionnaire (e-signature recommended/acceptable). Completed online and archived by the contractor applicant/employee in their NBIS eAPP account.
3. Electronic fingerprints taken at an approved facility OR two (2) SF 87 Fingerprint Cards (current revision) sent to OPR PSD. Additional information regarding fingerprints will be sent to the contractor applicant/employee from OPR PSD.
4. Optional Form 306 Declaration for Federal Employment. This document is sent as an attachment in an e-mail to the contractor applicant/employee from OPR PSD.
5. Social Security Administration 89 form (SSA-89): Authorization for the Social Security Administration (SSA) to Release Social Security Number (SSN) Verification. This document is sent as an attachment in an e-mail to the contractor applicant/employee from OPR PSD.
6. If occupying PREA designated position: Questionnaire regarding conduct defined under 6 CFR §
115.117 (Sexual Abuse and Assault Prevention Standards). This document is sent as an attachment in an e-mail to the contractor applicant/employee from OPR PSD.
7. One additional document may be applicable if the contractor applicant/employee was born abroad. If applicable, the document will be sent as an attachment in an e-mail to OPR PSD from the contractor applicant/employee.
Contractor employees who have an adequate, current investigation by another Federal Agency may not be required to submit complete security packages; the investigation may be accepted under transfer of trust.
The questionnaire related to 6 CFR § 115.117 listed above in item 5 will be required for positions designated under PREA. OPR PSD will determine if personnel meet transfer of trust requirements at the initial stage of processing and prior to requesting a new security questionnaire.
With respect to break-in-service requirements for transfer of trust, OPM removed the 24-month break-in-service provision. This requirement is replaced with a new process, established in the Federal Personnel Vetting Investigative Standards issued by the Suitability, Credentialing, and Security Executive Agents, which expands this window of time up to sixty months using a tiered, risk-based approach of graduated levels of investigation.
IAW 5 CFR 731 and E.O. 13764, the fixed five-year periodic reinvestigation for public trust positions and national security positions will soon be eliminated and only once personnel are enrolled in a continuous vetting program. Therefore, PSD will continue the reinvestigation process until this process is completed.
Required information for submission of security packet will be provided by OPR PSD at the time of award of the contract. Only complete packages will be accepted by OPR PSD as notified by the COR.
To ensure adequate background investigative coverage, contractor applicants/employees must currently reside in the United States or its Territories. Additionally, contractor applicants/employees are required to have resided within the United States or its Territories for three or more years out of the last five (ICE retains the right to deem a contractor applicant/employee ineligible due to insufficient background coverage). This timeline is assessed based on the signature date of the standard form questionnaire submitted for the applied position. Contractor employees falling under the following situations may be exempt from the residency requirement: 1) work or worked for the U.S. Government in foreign countries in federal civilian or military capacities; 2) were or are dependents accompanying a federal civilian or a military employee serving in foreign countries so long as they were or are authorized by the U.S.
Government to accompany their federal civilian or military sponsor in the foreign location; 3) worked as a contractor employee, volunteer, consultant or intern on behalf of the federal government overseas, where stateside coverage can be obtained to complete the background investigation; 4) studied abroad at a U.S.
affiliated college or university; or 5) have a current and adequate background investigation (commensurate with the position risk/sensitivity levels) completed for a federal or contractor employee position, barring any break in federal employment or federal sponsorship.
Only U.S. citizens and Legal Permanent Residents are eligible for employment on contracts requiring access to DHS sensitive information unless an exception is granted as outlined under DHS Instruction 121-01-007, Revision 2, dated August 10, 2024. Per DHS Sensitive Systems Policy Directive 4300A, only U.S. citizens are eligible for positions requiring access to DHS Information Technology (IT) systems or positions that are involved in the development, operation, management, or maintenance of DHS IT systems, unless an exception is granted as outlined under DHS Instruction 121-01-007, Revision 2, dated August 10, 2024.
CONTINUED ELIGIBILITY
ICE will exercise full control over granting, denying and/or restrict facility and information access of any contractor employee whose actions conflict with Fitness standards contained in 5 CFR 731 and DHS Instruction 121-01-007, Revision 2, dated August 10, 2024, or who violate standards of conduct under 6 CFR § 115.117. The Contracting Officer or their representative can determine if a risk of compromising sensitive Government information exists or if the efficiency of service is at risk and may direct immediate removal of a contractor employee from contract support.
The Federal Government is transitioning to Trusted Workforce (TW) 2.0. TW 2.0 is a whole-of-government background investigation reform effort overhauling the personnel vetting process by creating a government-wide system that allows transfer of trust across organizations. All contractor employees will be subjected to the transition and will be enrolled into a continuous vetting system. Enrollment will include multiple requirements from all personnel and potential changes to processes, procedures, and systems. This contract will comply with all requirements that facilitate the mandated transition to TW 2.0.
OPR PSD will evaluate concerns received via multiple sources under the continuous vetting process, to evaluate continued Fitness of contractor employees. If concerns cannot be mitigated, the contractor will be removed from the ICE contract upon notification from OPR PSD.
REQUIRED REPORTS
The contractor will notify OPR PSD, via the COR providing an ICE Form 50-005, Contractor Employee Separation Clearance Checklist, of all terminations/resignations of contractor employees under the contract within five days of occurrence to the ICEDepartureNotification@ice.dhs.gov group box. The contractor will return any expired ICE issued identification cards and building passes of terminated/resigned employees to the COR. If an identification card or building pass is not available to be returned, a report must be submitted to the COR referencing the pass or card number, name of individual to whom issued, the last known location and disposition of the pass or card. The COR will return the identification cards and building passes to the responsible ID Unit.
IAW DHS Instruction 121-01-007, Revision 2, dated August 10, 2024, the Contracting Officer’s Representatives (CORs) notify the servicing personnel and industrial security offices when a contractor employee is no longer working for DHS on any contract and report any derogatory information concerning the individual immediately, in accordance with the contract requirements. Report this information to PSD-CEP-REPORTING@ice.dhs.gov. The report shall include the contractor employees’ name and social security number, along with the adverse information being reported.
The contractor will provide, through the COR, a Quarterly Report (on a Microsoft Excel Spreadsheet) containing the names of contractor employees who are actively serving on their contract. The list shall include the Name, Position and SSN (Last Four) and should be derived from system(s) used for contractor payroll/voucher processing to ensure accuracy. This list is what ICE Industrial Security uses to reconcile the contract quarterly. CORs will submit reports to PSD-Industrial-Security@ice.dhs.gov no later than the 10th day of each January, April, July and October.
Contractors, who are involved with management and/or use of information/data deemed “sensitive” to include ‘law enforcement sensitive” are required to complete the DHS Form 11000-6-Sensitive but Unclassified Information Non-Disclosure Agreement (NDA) for contractor employee access to sensitive information. The NDA will be administered by the COR to all contract personnel within 10 calendar days of the entry on duty date. The completed form shall remain on file with the COR for purpose of administration and inspection.
Sensitive information as defined under the Computer Security Act of 1987, Public Law 100-235 is information not otherwise categorized by statute or regulation that if disclosed could have an adverse impact on the welfare or privacy of individuals or on the welfare or conduct of Federal programs or other programs or operations essential to the national interest. Examples of sensitive information include personal data such as Social Security numbers; trade secrets; system vulnerability information; pre-solicitation procurement documents, such as statements of work; and information pertaining to law enforcement investigative methods; similarly, detailed reports related to computer security deficiencies in internal controls are also sensitive information because of the potential damage that could be caused by the misuse of this information. All sensitive information must be protected from loss, misuse, modification, and unauthorized access in accordance with DHS Management Directive 11042.1, DHS Policy for Sensitive Information and ICE Policy 4003, Safeguarding Law Enforcement Sensitive Information.”
Any unauthorized disclosure of information should be reported to ICE.ADSEC@ice.dhs.gov.
mailto:ICEDepartureNotification@ice.dhs.gov mailto:PSD-CEP-REPORTING@ice.dhs.gov mailto:PSD-Industrial-Security@ice.dhs.gov mailto:ICE.ADSEC@ice.dhs.gov
SECURITY MANAGEMENT
The contractor shall appoint a senior official to act as the Corporate Security Officer. The individual will interface with OPR PSD through the COR on all security matters, to include physical, personnel, and protection of all Government information and data accessed by the contractor.
The COR and OPR shall have the right to inspect the procedures, methods, and facilities utilized by the contractor in complying with the security requirements under this contract. Should the COR determine that the contractor is not complying with the security requirements of this contract, the contractor will be informed in writing by the Contracting Officer of the proper action to be taken to effect compliance with such requirements.
INFORMATION TECHNOLOGY SECURITY
When sensitive government information is processed on Department telecommunications and automated information systems, the contract company agrees to provide for the administrative control of sensitive data being processed and to adhere to the procedures governing such data as outlined in DHS MD 4300.1, Information Technology Systems Security (or its replacement). Contractor employees must have favorably adjudicated background investigations commensurate with the defined sensitivity level.
Contractor employees who fail to comply with Department security policy are subject to having their access to Department IT systems and facilities terminated, regardless the failure results in criminal prosecution. Any person who improperly discloses sensitive information is subject to criminal and civil penalties and sanctions under a variety of laws (e.g., Privacy Act).
INFORMATION TECHNOLOGY SECURITY TRAINING AND OVERSIGHT
In accordance with Office of the Chief Information Officer (OCIO) requirements and provisions, all contractor employees accessing Department IT systems or processing DHS sensitive data via an IT system will require an ICE issued/provisioned Personal Identity Verification (PIV) card. Additionally, Cybersecurity Awareness Training (CSAT) will be required upon initial access and annually thereafter.
CSAT training will be provided by the appropriate component agency of DHS.
Contractor employees, who are involved with management, use, or operation of any IT systems that handle sensitive information within or under the supervision of the Department, shall receive periodic training at least annually in security awareness and accepted security practices, systems rules of behavior, to include Unauthorized Disclosure Training, available on the ICE Training System (ITS) or by contacting ICE.ADSEC@ice.dhs.gov. Contractor employees with significant security responsibilities shall receive specialized training specific to their security responsibilities annually. The level of training shall be commensurate with the individual’s duties and responsibilities and is intended to promote a consistent understanding of the principles and concepts of telecommunications and IT systems security.
All personnel who access Department information systems will be continually evaluated while performing these duties. System Administrators should be aware of any unusual or inappropriate behavior by personnel accessing systems. Any unauthorized access, sharing of passwords, or other questionable security procedures should be reported to the local Security Office or Inform
OCIO/ Data Management Unit (DMU) - Data Ownership Contract Requirements Language
1. Accessibility of Government-owned Data mailto:ICE.ADSEC@ice.dhs.gov
All stored program data associated with this acquisition shall be owned by the Government.
As such, it shall be made accessible to the Government in accordance with the Minimum Data Access Capability described below. This accessibility is required to allow full data transparency, flexibility in performing data analytics, and integration with data from other government programs.
In addition to the Minimum Data Access Capability, the Government prefers, but does not require, that program data be accessible via Enhanced Access Capabilities as described below.
Definition of “program data”: Program Data refers to any data resulting from ICE and DHS organizational activity. Examples of such data include but are not limited to administrative data resulting from human resource, management, and financial actions, as well as operational data resulting from performance of the ICE mission.
Definition of “associated with this acquisition”: Program Data is associated with an acquisition if it is created by DHS organizational activity that is facilitated by the contractor.
Examples of how a contractor might facilitate organizational activity follow:
o Program data is stored by contractor personnel o Program data is stored by software that is managed, developed, or used by the contractor o Program data is stored in a repository that is managed, developed, or used by the contractor
2. Minimum Data Access Capability
• The current version of all Program Data is accessible to the Government within 24 hours of request, as well as on any pre-defined schedule as required by the Government.
Data access can occur by various means, provided that Government security requirements are met, and data is accessible in a format that is acceptable to the Government. Examples include but are not limited to APIs that are consumable by the Government, files made available for Government download (e.g., Excel Spreadsheets), or direct database query by federal or contractor personnel.
• The contractor shall format program data accessed by the Government to anticipate the maximum file size of any data to be accessed. File size shall be small enough to assure rapid processing by government applications.
• The contractor shall provide the means for the Government to interpret accessible Program Data as follows:
o Data elements and groupings of data elements shall be clearly identifiable by labels embedded in the data itself, or by a separate schema or file layout which allows such elements and groupings to be identified.
In the case of a relational database schema defined through Data Definition Language (DDL), data elements would be represented as columns, and groupings of data would be represented as tables. In addition, relationships between tables would be described as foreign key relations.
o Labels or names used to identify data elements and groupings of data elements shall be approved by the Government. In addition, each label or name shall be associated with a government approved definition which describes the content of data held therein.
o Program data delivered to the Government shall conform to the…