This is a Questions and Answers (Q&A) document providing Government responses to clarifications requested by potential offerors regarding the Performance Work Statement (PWS) for support services to the Product Manager Fire Support Systems (PdM FSS) and Product Manager Organic Precision Fires (OPF) portfolios under solicitation M6785426I1018.
The Q&A addresses five substantive inquiries concerning staffing, facility requirements, and operational scope. Key clarifications include: (1) onsite support at Fort Sill, Oklahoma and Aberdeen Proving Ground requires one full-time equivalent (FTE) per location for acquisition and future requirements development, with duplicative language removed from PWS Section 4.6; (2) software development occurs at a contractor facility rather than a Government DevSecOps environment; (3) the Government will provide its own transportation for tactical vehicles, with contractor shipping costs treated as other direct costs if required; (4) detailed facility specifications should reference PWS Section 8.0 regarding contractor facilities; and (5) only COMSEC storage is required, not secret-level or higher security clearance for the secure laboratory. The document is dated April 8, 2026, and indicates this information is distributed to the Department of Work community only.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amnd_DRAFT_PWS_08April26.pdf | ||
| Amended_Sources Sought Notice_26I1018.pdf | ||
| DRAFT_PWS_M6785426I1018.pdf | ||
| Sources Sought Notice_26I1018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions
| Product Manager FSS and Product Manager OPF Support Services Q&A Responses | ||||||
| Identifier | Question | PWS Section | SSN | Government Response | ||
| 1 | PWS Paragraphs 4.1.2.3 and 4.6 both require onsite support at Fort Sill, OK and Aberdeen Proving Ground (APG) PEO Command, Control Communications and Network (PEO C3N) / Program Manager Mission Command. Will the Government clarify if this is two FTE, one on site in each location on a full time basis, or is the onsite requirement more of a Temporary Assigned Duty (TAD) support? | 4.1.2.3 | N/A | Paragraph 4.1.2.3 requires one FTE per location, the requirement is to support the acquisition & future requirements development. The amended PWS removes the duplicative language from Paragraph 4.6 . | ||
| 4.6 | N/A | |||||
| 2 | PWS Paragraph 4.2.3 describes SW Engineering, Integration, and Development efforts, but lacks sufficient detail for planning and proposal. Will the Government clarify if the software development is occurring in the Government's DevSecOps or is the contractor responsible for developing and maintaining the DevSecOps? | 4.2.3 | N/A | Software development occurs at a contractor facility. | ||
| 3 | PWS Paragraph 4.5.3.1 implies that the contractor will be required to not only drive, but also “transport Government owned tactical vehicles”. Will the Government clarify if the contractor is required to transport Government owned tactical vehicles or only arrange transport for those Government owned tactical vehicles (i.e., does the contractor need to own a fleet of flatbed tractor trailers?). | 4.5.3.1 | N/A | The Government plans to use government transportation. If the contractor is required to ship any systems this will be considered an other direct cost. | ||
| 4 | Describe the location and availability of facilities, including conference rooms, and | |||||
| a COMSEC storage facility, that will be used to support this PWS. Are there any specifics the Gov’ is looking for in size and proximity to MCSC? | 8 | 2 | Please refer to PWS Section 8.0 Contractor Facility. | |||
| 5 | Do you require a secret or greater for the secure lab and COMSEC storage facility? | N/A | 2 | The Government only requires COMSEC storage. See Attachment 2 – Notional Government Furnished Equipment. |