Question NumberSolicitation ReferenceQuestionAnswer
1SOW 3For clarification is the contractor responsible for all transportation from each site designated and also responsible for transportation of the modified EBFL to the designated locations in Attachment GYes, the contractor is responsible for all transportation. For those assets shipping to overseas locations the contractor will be responsible for delivery to a port designated by the government
2SOW 3Will those assets in Japan, Hawaii and Norway be the reasonability of contractor to provide transportation.No, the Government will coordinate the transportation of those EBFLS back to a designated CONUS location.
3SOW 3.1.1Are all EBFLs to receive a armored cab?Currently, only 100 amored cabs are being considered for procurement; however, that requirement is subject to change. For this reason, all EBFLs are required to be capable of integrating an armored cab.
4SOW 3Can serviceable parts from other EBFL deemed unrepairable be utilized to support the modernization of the 495 EBFLsYes.
5SOW 3.1.2.1.2Are Battery Disconnect Switches on all EBFLs? Are all required to have them?No. Only a few EBFLs procured in 2010 have the switches. Yes all EBFL are required to have the Battery Disconnect switches.
6SOW 3.1.2.1.3Can the batteries be replaced with an equivalent capacity battery other than hawker?No.
7SOW 3.1.2.1.3Can current installed hawker batteries be reused?Yes. As long as they are fully charged and meet the original performance standard.
8SOW 3.1.2.2Why are multiple service hours stated?Each service performed (250 hr, 500 hr, 1,000 hr, and 2,000 hr operator, field, and intermediate service intervals) entails different actions. The technical manual details the services and checks required for each service hour.
9SOW 3.1.4The para states the contractor shall provide the government with a Spare Parts Kits. Please quantify how many spares parts kits?The government intends to build 10 Spare Parts Kits with each of the components listed. Each kit will have one of each component listed. SOW 3.1.4 has been updated to clarify.
10SOW 3.1.4Are the spares to be new or can they be reconditioned?That is a business decision for each contractor. All spare must meet the EBFL requirements whether new or reconditioned.
11SOW 3.2.4Is the contractor picking up EBFLS at OCONUS location.No, the Government will coordinate the transportation of those EBFLS back to a designated CONUS location.
12SOW 3.9.7.2Subject paragraph states that “ECP shall be submitted by the contractor, and shall be limited to those, which are necessary or offer significant benefit to the Government. MIL-HDBK-61A provides guidance concerning the classification of ECP’s. Class I ECP’s shall be submitted when changes are required to: (a) Correct deficiencies; (b) Add or modify interface or interoperability requirements; (c) Make a significant and measurable effectiveness change in the operational capabilities or logistics supportability of the system; (d) Effect substantial life cycle costs/savings; and (e) Prevent slippage in an approved production schedule. Class II ECP’s shall be submitted by the contractor to the Acquisition Contracting Officer (ACO) for approval for those engineering changes, which impacts none of the factors listed above.” QUESTION: Will the contractor be allowed a day for day deliverable schedule adjustment for the elapsed time the government uses for approval of ECPs submitted after the Critical Design Review?As no two ECP's are alike in scope, critical path relationship, and circumstances, the Government cannot address this question. Each ECP-related schedule adjustment, if necessary, shall be considered separately based on its own unique merits.
13SOW 3.9.7.3Subject paragraph states that “ The contractor shall process Requests for Deviation (RFD) from current approved configuration documentation.” QUESTION: Will the contractor be allowed a day for day deliverable schedule adjustment for the elapsed time the government uses for approval of deviations submitted after the Critical Design Review?As no two RFD's are alike in scope, critical path relationship, and circumstances, the Government cannot address this question. Each RFD-related schedule adjustment, if necessary, shall be considered separately based on its own unique merits.
14RFPIs this project considered a new requirement?Yes.
16RFPAre you planning to award from the proposals received?While Government reserves the right to award without discussions, the Government also may engage with Offerors consistent with FAR 15.306 ("Exchanges with Offerors after receipt of proposals").
17PSAre coverage area and 3D models available?No.
18RFPWhen will the contract be awarded ?The Government intents to award a contract 90-120 days following the closing of the RFP.
19SOWWill the government allow the contractor to visit multiple bases to assess the EBFL conditions.Yes. Visit requests can be requested by emailing the contract specialist.
20SOW 7.2If no secret level work is performed at the Prime Contractors facility, is the Prime Contractor required to have a secret facility clearance level or can that be maintained exclusively at the armored cab supplier?Any facility safeguarding classified materials must have been cleared for that. If the Sub-contractor is the only cleared facility then that must be stated in the response, but the prime contractor is not required to have a secret facility clearance level if no classified work is being performed by the prime.
21PSWill test data or an test reports be available to Offerors upon request?Yes. This information can be obtained by emailing the contract specialist with a request.
22SOW 4.5.4Pertaining to SOW (page 51 of M67854-14-R-5011) paragraph 4.5.4, Provisioning Technical Documentation, will the USMC provide the existing SDFP and EDFP for the current EBFL to support the provisioning effort outside of the 5 modifications listed in paragraph 3.1.1, Modifications, of the SOW (page 39 of M67854-14-R-5011)?The offeror will provision for the entire Modernized EBFL. There is no existing PPL, LSA-036 or EDFP/SDFP. The all parts can be found in TMs. No EDFP or SDFP will be requried if an existing PN cross references to an active NSN. If the PN is no longer valid/discontinued or the NSN is not active any longer, a new part and all EDFP/SDFP will be requried.
23SOW 3.1.2.1.2Reference is made to TI 10794B-OR/2. Can we have access to this document?Yes. This information has been posted as Attachment H to this amendment.
24SOW 3.1.2.1.2Reference is made to JLG supplement 31200693. Can we have access to this document?Yes. This information has been posted as Attachment J to this amendment.
25SOW 3.1.1Are Base Year CLINs 11-34 to be priced ONLY for the items effected by the 5 modifications listed in paragraph 3.1.1, Modifications, of the SOW (page 39 of M67854-14-R-5011)?CLINs 11-34 are to be priced to include the cost to provide the item or service with profit included. Each offerors will have to determine its own pricing strategy. For example, the price for CLIN 0012 - Net for FUE should be the price it will cost to meet the requirements of SOW 6.1.2.2
26Attachment FAre Base Year CLINs 11-34 to be priced for the complete EBFL, whether it’s new (CLIN 0002) or modified (CLIN 0001)?CLINs 11-34 shall be based on a modernized EBFL. In contrast, CLIN 0002 is the offeror's proposed price for building an entirely new EBFL.
27Solicitation CLIN 0002The CLIN reads "this is the price for a new EBFL without an exchange credit" Is this intended to read this way or should the word "new" read "modernized"?Yes, the word new is correct and this is NOT intended to mean "modernized."
28Solicitation CLIN 0002Does the MCSC intend to purchase new EBFL units?No, MCSC does not intend to purchase new EBFL units. However, in accordance with DFARS 217.7004, the solicitation includes a request for offerors to state prices for new items being acquired without any exchange (CLIN 0002).
29Solicitation CLIN 0002Does the MCSC intend for all bidders to offer a price for a new EBFL unit?Yes, it is required per DFARS 217.7004.
30General IssueDoes the MCSC require all bidders to offer to provide every item or service related to each and every CLIN?Yes
31General IssueWill a bid be deemed unacceptable if a bidder decides to not offer a price for each and every CLIN?Yes, the Government understands pricing a new EBFL will be difficult, but as stated above a new CLIN is required per DFARS 217.7004
32General IssueThe RFP contains many requirements that can be collectively referred to as provisioning. Does the MCSC intend these sections to apply to the modernized EBFL system in its entirety or should these be read to refer to the modernization effort and subsystems impacted by that effort?The offeror will provision for the entire Modernized EBFL. There is no existing PPL, LSA-036 or EDFP/SDFP. The all parts can be found in TMs. No EDFP or SDFP will be requried if an existing PN cross references to an active NSN. If the PN is no longer valid/discontinued or the NSN is not active any longer, a new part and all EDFP/SDFP will be requried.
33Solicitation CLIN 0007Will NET CONUS - Operator training include training on the entire modernized EBFL system or just on those subsystems impacted by the modernization?Training is required only on the subsystems impacted by the modernization.
34Solicitation CLIN 0008Will NET OCONUS - Operator training include training on the entire modernized EBFL system or just on those subsystems impacted by the modernization?Training is required only on the subsystems impacted by the modernization.
35Solicitation CLIN 0009Will NET CONUS - Maintainer training include training on the entire modernized EBFL system or just on those subsystems impacted by the modernization?Training is required only on the subsystems impacted by the modernization.
36Solicitation CLIN 0010Will NET OCONUS - Maintainer training include training on the entire modernized EBFL system or just on those subsystems impacted by the modernization?Training is required only on the subsystems impacted by the modernization.
37Solicitation CLIN 0011-0019Various NET training materials. Does the MCSC intend and expect that these materials will cover the entire modernized EBFL system or cover subsystems impacted by the modernization?Training is required only on the subsystems impacted by the modernization.
38SOW 4.5.4Will the provisioning technical documentation cover the entire modernized EBFL system or cover only subsystems impacted by the modernization?The offeror will provision for the entire Modernized EBFL. There is no existing PPL, LSA-036 or EDFP/SDFP. The all parts can be found in TMs. No EDFP or SDFP will be requried if an existing PN cross references to an active NSN. If the PN is no longer valid/discontinued or the NSN is not active any longer, a new part and all EDFP/SDFP will be requried.
39SOW 5.3 and 5.15Does the MCSC intend and expect to receive a new and complete TM?Yes.
40SOW 5.3 and 5.15Does the MCSC intend and expect to receive a supplement to the current TM?No. The Government requires an entirely new TM. However, the current EBFL TM is available upon request from the contract specialist.
41SOW 5.3 and 5.15Will the new TM cover the entire modernized EBFL system or just those subsystems impacted by the modernization?The new TM should cover the entire EBFL system.
42General IssueWill pricing be fixed by the order year that the delivery order is issued or by the order year in which the equipment or service is delivered?Pricing will based on the price at the time of the order.
43SOW 3.2.4Will the MCSC consider contractor obligation to be delivery to a port of debarkation that is CONUS for those units being sent OCONUS as this will be a significant cost savings?Yes. See response 1.
44SOW 3.2.4Will the MCSC consider contractor obligation to be transportation from a port that is CONUS for those units being received from OCONUS as this will be a significant cost savings?Yes, see response 1.
45SOW 3.2.4Will the OCONUS transportation apply to MEF units or will the contractor exchange modernized units for existing units at a CONUS port?Yes, see response 1.
46SOW 3.4.4Will the required corrosion prevention and control plan be applicable to the entire modernized EBFL system or only to those subsystems impacted by the modernization?The plan should only include the subsystems impacted by the modernization.
47SOW 3.4.5.1Will the required reliability and maintainability program be applicable to the entire modernized EBFL system or only to those subsystems impacted by the modernization?Reliability and maintainability only applies to the subsystems impacted by the modernization
48SOW 3.9.3.2Will the MCSC accept modernized units that are comprised of serial numbered items from one or more core EBFL units?Yes.
49SOW 4.5.4.7Will the MCSC expect and intend the LSA-036 to include the entire modernized EBFL system or only subsystems impacted by the modernization?The LSA-036 should cover the entire EBFL system. The USMC will provide source data for the current EBFL system.
50General IssueWill the MCSC expect and intend provisioning to include the entire modernized EBFL system or only subsystems impacted by the modernization?See Response 32
51SOW 4.6.1Will the MCSC expect and intend the contractor to support DVD on the entire modernized EBFL system or only subsystems impacted by the modernization?The contractor is only required to support the subsystems impacted by the modernization.
52SOW 5.1Will the MCSC expect and intend the contractor to create new Operation and Maintenance Technical Manuals supporting the entire modernized EBFL system or only those subsystems impacted by the modernization?See Responses 40 and 41.
53SOW 7.2Is the Prime Contractor required to have a Secret Facility Clearance if the armor testing will be performed at a subcontractor's facility and that facility has a Secret Facility Clearance?No.
54SOW 7.2If the Prime Contractor is required to have a Secret Facility Clearance, is it required to obtain that clearance prior to starting work on the contract?All facility clearance must be in place prior to contract award. However, as stated in response 20 above, the prime is not required to have a facility clearance.
55SOW 7.2Must a Prime Contractor have a Secret Facility Clearance in place in order to submit a proposal for the EBFL modernization?No. However, if the subcontractor will be the one holding the facility clearance, then the subcontractor must have a FCL in place at the time of award.
56SOW 4.2Will the contractor be responsible for creating new IUID markings for the entire modernized EBFL or only to add additional markings to those items that require markings and are part of the modernization effort?New IUID labels will required for the entire EBFL system.
57General IssueWill the MCSC expect and intend that the Warranty coverage offered will apply to the entire modernized EBFL system or only to those subsystems impacted by the modernization which will be tracked by unique serial number?The contractor should provide its best warranty strategy. At a minimum, a warranty should provided for the subsystems impacted by the modernization.
58General IssueThe scope of the Warranty coverage is defined, does the MCSC desire the contractors to provide a price for an extended warranty period such as an additional 4 years?Each offeror should state the warranty it is proposing in its proposal submission. The Government will not pay for a separate warranty. The warranty will be evaluated in accordance with Section M of the RFP.
59General IssueIf extended Warranty coverage is desired will the MCSC create a CLIN for this purpose?No.
60General IssueWhat source document will be the baseline for EBFL performance against which the modernized EBFL will be measured?If a number is not specified in the PS, the Government will use the test data from the previous EBFL tests.
61PS 3.1Will the MCSC provide test report ATC-8697, NATC 20528 and WFE - E- 96?Yes. This information can be obtained by emailing the contract specialist with a request.
62PS 3.2.4.2Will the MCSC prescribe a maximum or desired time for removal of the cab and installation of the armored cab?Eight (8) hours total for installation and removal. PS 3.2.4.2 has been updated to clarify.
63PS 3.2.3.1Will the Modernized EBFL (MEBFL) be held to the same tested results as the original EBFL regardless of hours of previous usage and condition of the applied “core” driveline?Yes.
64PS 3.2.3.1Will all the baseline testing for the MEBFL be conducted with the same JP-8 specified fuel as the original PVT Testing?Yes.
65General IssueWill these baseline functional tests be completed at ATC on the same test course layout as the initial EBFL Program?These tests will completed at the course specified in the PS Section 4.
66PS 3.2.2.1When the hydraulic control valve for the carriage functions is relocated, will the time for completed function (sideshift or FP) need to remain the same as the PVT of the base contract?Yes.
67PS 3.3.2With the new lowered operator's cabin (lowered SIP test point) how will the degradation of fork tip and load placement visibility be treated?The design will have to meet the PS requirements of 3.3.2 Visibility.
68The requirement for the “internals” to be the same in the non-armored and armored version of the cabin would indicate that all 495 MEBFL trucks are fitted with a new cabin of similar size and interior regardless of C1 fitment or not?The EBFL needs to meet all of the PS requirements. All armored cabs must be the same, all unarmored cabs must be the same, but the armored and unarmored cabs are not required to be same but must have the same functionality.
69PS 3.1The requirement to replace all ZF equipped transfer case units with Carraro transfer cases would indicate that (a) the fleet core of “F” grade units has sufficient Carraro transfer cases to meet the need or (b) the contractor is required to arrange for the OE to produce the older style transfer case as a new replacement item for this demand. Which version will serve as the performance baseline for the MEBFL Fleet?The Carraro P/N 2915060 will serve as the baseline.
70General IssueWill the contractor be allowed to purchase any and all required new tires from DLA or will any new tires be a “street” purchase of the old style tire?A contractor can either purchase from DLA or in the open market. It is each contractor's prerogative to determine how it purchases the tires. The government will not facilitate any tire purchases; the vehicle for purchasing the tires, regardless of what it is, is completely the responsibility of the vendor.
71PS 1.2.1Will the MCSC require any MEBFL units to be shipped from the contractor's final test and sign-off location with an Armored Cab installed?No. Armored cabs do not need to be installed on the production units. All armored cabs will be shipped in separate containers.
72PS 3.2.4.1Is the STANAG Armor Requirement listed in the PS the correct one or is there a newer version that will apply for some or all C kits?Contractors need to request the classified addendum 1 as stated in SOW 7.3
73General IssueWill the modernized EBFL be held to current standards such as ANSI and others or the standards in effect when the EBFL units were produced?Contractors will be held to the current standards for the modernized subsystems only.
74SolicitationCLIN 0006 on page 4 of the solicitation states the quantity unit as "Each". On Attachment F, base year, CLIN 0006 states the quantity unit as "Lot." What unit of measure should be used?The correct unit of issue is Each. Attachment F has been updated.
75Solicitation/Attachment FCLIN 0001 & CLIN 0002 include additional rows that state "Quantities (Offeror - insert your step ladder quantities here)". Please provide a definition for the term "step ladder quantities"?Step-ladder pricing is is a structure that allows an offeror to propose different unit prices for various quantities of an item. For this solicitation, the Offeror is requsted to provide the steps at which the pricing will change, depending upon order quantities (for example, 1-5, 6-20, etc.). Step ladder pricing allows the government to order small quantities at one price while potentially securing more favorable pricing when purchasing larger quantities.
76SOW p 38, PS p 4In the SOW on page 38 under Applicable Documents it states "In the event of conflict between the applicable documents and this SOW, the SOW shall take precedence." The PS statement on page 4 section 2.4 states "Unless otherwise noted herein or in the contract, in the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence". Which document takes precedence?The term "applicable documents" in both the SOW and PS refer to the applicable documents listed in each document. Neither takes precedence over the other.
77SOW/PS/Attachment F PS 4.1.2, SOW 6.1.2.2Is there a Limited User Evaluation (LUE) per the PS section 4.1.2 paragraph ii, or a Field User Evaluation (FUE) per the SOW paragraph 6.1.2.2 and Attachment F, CLIN0012 or both?The correct term is FUE. The PS 4.1.2 has been updated to clarify.
78Solicitation Clause 52.209-4Reference Solicitation page 79, is the contractor expected to deliver base year PQT assets 120 day after date of contract award or 180 days after delivery order as stated in Attachment F?The test assets are due 180 ARO. FAR 52.209-4 has been updated.
79SOW 3.2.4Understand the contractor is responsible for pickup of OCONUS EBFLs. Is the contractor responsible for pickup from OCONUS destinations listed in Attachment D or at an East/West Coast Port of Embarkation?See Response 1
80SOW 3.2.4Understand the contractor is responsible for delivery of OCONUS EBFLs. Is the contractor responsible for delivery to OCONUS destinations listed in Attachment G or at an East/West Coast Port of Embarkation?See Response 1
81Attachment F, CLIN 0005States a quantity of 10 each for "Spare Parts Block" (SPK). The SOW reference page 41 section 3.1.4 states "Each SPK shall include the following items: Ten (10) Engines, Ten (10) Transmissions, One (1) set of Axles (one set includes one front axle and one rear axle), One (1) Boom assembly, Ten (10) Carraro Transfer Cases, Ten (10) 7k fork carriage assemblies and Ten (10) 11k fork carriage assemblies." Does the Government want pricing for the quantity of 10 SPKs? (i.e. Per Attachment F, 10 sets = 100 engines)Yes. The government wants pricing for 10 SPKs. SOW 3.1.4 has been updated to clarify.
82SOW 5.7The validated draft technical manual (DTM) delivery is scheduled for 160 DAC, but page 79 of the SOW identifies the timeframe for First Article approval as 180 DAC. It is our assumption and desire to validate the TMs against a Government approved design. Can the MCSC clarify what appears to be a schedule conflict?
This is not a schedule conflict. The 20 days is required to allow for Government review prior to test.
83SOW, Section BWhat is the definition/configuration of "New?" SOW paragraph 3. only defines "modernization."The term "new" refers a completely new EBFL that meets all of the requirements of the PS and SOW in exchange for old units. See responses 27-29.
84SOW 3.1.2.1Corrective Maintenance shall be conducted on all EBFLs provided by the Government.
Does Corrective Maintenance need to be performed on the entire fleet of EBFLs or just the quantity to be delivered? Please clarify.The Government only requires corrective maintenance on the 495 to be delivered.
85SOW 3Requirements - The contractor shall receive title to all exchanged EBFL systems in excess of the quantity to be delivered to the Government and shall be responsible for transportation and disposal of such systems to include all parts, components, and subsystems.
Will there be demilitarization requirements for any parts, components or subsystems? If so what level of demilitarization will be required by part, component or subsystem?The current EBFL armored cab will have to required demilitarization. The instructions for DEMIL have been added as a reference to the SOW under 2.4 and the DEMIL code for the cab has been added to paragraph 3 of the SOW.
86SOW 3.1.4Spare Parts Kit (SPK).
Can new parts be included within the SPK? If parts are reused, who makes the repair/replace/overhaul decision for the parts within the SPK?Yes, new parts can be included. It is a business decision that each contractor should determine. The only requirement is that the configuration remains the same. If the contractor chooses to refurbish a part, the contractors is responsible for that part and any associated failure.
87SOW 3.3.1, 3.3.2, 3.3.3, 3.4.2.1, 3.4.2.2, 3.4.2.3, 3.4.2.4, 3.4.2.5, 3.5.2Contractor Responsibilities - Reviews shall be conducted at either Government or contractor facilities.
Which reviews will be held at Government facilities? What are the locations of the Government facilities that will host the reviews?The locations of the reviews are TBD.
88SOW 3.4.3Requirements Traceability Matrix.
Please clarify the requirement of "…and preserved throughout the entire period of performance…"The period of performance on the contract is five years and thus this requirement is five years.
89SOW 3.9.4Configuration Management Meetings/Audits - The Government and the contractor shall conduct the PCA jointly, at a time and place designated by the Government. This paragraph and paragraph 3.4.2.5 (Physical Configuration Audit) is silent on location of the PCA.
Where is the meeting anticipated to be held?It is anticipated to be held at the contractor's facility.
90SOW 3.9.7.1Engineering Release System - The contractor shall submit an Engineering Release Record (ERR) to release new or revised configuration documentation to the Government for approval.
What CLIN/CDRL establishes the deliverable?CDRL A003 has been created to identify the deliverable and added as a reference in the SOW under 3.9.7.1, 3.9.7.2, 3.9.7.3 and 3.9.7.4.
91SOW 4.1.2Warranty Execution - The warranty shall begin on the date the asset is accepted at the Government's receiving unit.
What is the duration of the warranty?That is a business decision that each contractor should determine.
92PS 3.2.5.6The 7K carriage width shall be reduced to 60 inches.
Is the 60 inch dimension the maximum fork spread (outside edges of the forks when fully spread) or the overall outside dimension of the carriage width?This applies to the overall outside dimension of the carriage width.
93The third tab titled "Packaging and Markings" of Attachment CSection D Reference column of Attachment C items 3.1.1, 3.1.2, 3.2, 3.2.1, 4.3.2, 4.3.4, 4.3.5, 4.3.6, and 4.3.7 do not match up with the requirements title and/or the requirements do not appear in Section D of the Solicitation.

Please clarify the requirements.

Section D has been updated.
94Section L - 2.2 Part III Subcontracting/SB ParticipationThere is a discrepancy in numbers in this section for Small business percentage requirements. It is clear that small disadvantaged business has a goal of 5%, but small business is 30% in the 2nd sentence of this paragraph and in the 3rd sentence it is called out to be 25%.
Please clarify the small business goal requirement for this solicitation. Is it 25% or is it 30%?The small business goal is 30%. Section L has been updated.
95SOW 3.2.3Monthly production shall equal a minimum rate of twenty (20) Modernized EBFLs per month after successful PQT and a Full Rate Production (FRP) decision. The contractor shall notify the Government in writing within 10 days of any anticipated or projected work stoppages or delays that will impact schedules.

In Section L, paragraph 2.2, a "for planning purposes only" production schedule is provided for Modernized EBFLs as:

base ordering period = 6 ordering period 1 = 291 ordering period 2 = 69 ordering period 3 = 87 ordering period 4 = 42.

Producing 20 Modernized EBFLs per month during ordering period 1 is understood, but is this requirement also intended to apply to ordering periods 2, 3, and 4?SOW 3.2.3 has been updated to clarify.
96SOW 6.1.2.2 and 6.1.2.36.1.2.2 The contractor shall conduct EBFL FUE training for both operators and maintainers Military Occupational Specialty (MOS) 1345, Engineer Equipment Operator, and MOS 1341, Engineer Equipment Mechanic. Government-approved comments received from attendees and evaluators shall be incorporated into the course and training materials. The training materials developed for FUE training shall be improved upon for succeeding training events until the Government provides approval.

6.1.2.3 The contractor shall conduct EBFL I&KPT for both operators and maintainers Military Occupational Specialty (MOS) 1345, Engineer Equipment Operator, and MOS 1341, Engineer Equipment Mechanic. The contractor shall conduct I&KPT at a government specify location using training materials developed under this contract. The contractor shall provide the EBFL equipment, tools (common and special) and all replacement parts and consumables during the training. The I&KPT shall enable the instructors and key personnel to teach the operation and maintenance for the EBFL. Government-approved comments received from attendees and evaluators shall be incorporated into the course and training materials in preparation for NET.

Please identify the locations of these training events?Both events will be held at Ft. Leonardwood, MO.
97Solicitation, Section B - Supplies or Services and Prices, Page 18 of 107, Item No 1005Solicitation, Section B - Supplies or Services and Prices, Page 18 of 107, Item No 1005 appears to have an incorrect Ordering Period. It would appear this should be Ordering Period 1 rather than Ordering Period 2.
Please confirm this is pricing for Ordering Period 1 for this item.Yes, ordering period 1 is correct. Section B CLIN 1005 has been updated.
98Solicitation, Sec L, para. 2.2, Part IV, Operational Effectiveness, p. 102The RFP instructs "The offeror shall provide data to substantiate that their product meets or exceeds each requirement of the Performance Specification." The RFP is unclear as to where these data are to be provided, i.e., are they part of the 75 page-limited text-figure narrative or part of the unlimited page Attachment C?
Is it permissible to provide the substantiating data requested under RFP, Section L, para. 2.2, Part IV Technical Volume as an addendum to the Attachment C Matrix submittal?As stated in Section L, this information should be provided in Appendix A - Test Data to the technical volume. Appendix A has no page limit. All other substantiating data should be included within 75 pages of the technical volume.
99Solicitation, Section B: CLIN 0003. 1003, 2003, 3003, 4003Section B and F, CLINs 0003, 1003, 2003, 3003, and 4003 total 800 each. Attachment D identified 802 EBFLs with only known locations of 756.
Which quantity should the overall exchange credit represent? The qty of 756, 800, or 802?The exchange credit is the amount of credit each offeror is proposing to exchange the current EBFL for a modernized EBFL for a quantity of up to 800. As stated in the solicitation, the item number series ending in 03 is only for evaluation purposes and will be removed at award. Offeror should price the exchange credit based on the quantities listed in Section B and Attachment F.
100Solicitation Section B: Item number 0027Item number 0027, TM Outline, references SOW 5.3 and 5.15. SOW 5.3 is for Government furnished Information and SOW 5.15 is for TM Deliverables.
Should Item number 0027 reference SOW 5.5 titled "TM Outline"?Yes, Section B has been corrected.
101SOW 3.1.4 - Spare Parts KitsThe Spare Parts Kit paragraph does not reference whether SPK shall be delivered with or without EBFL. Section F - Deliveries or Performance reference Attachment G " Anticipated EBFL Delivery Locations and Quantities" gives destinations for 495 modernized EBFLs.
What are the destinations for the Spare Parts Kits? Will FOB point be changed to origin versus destination?Spare Parts Kits will be shipped to Albany, GA. It will remain FOB destination.
102Solicitation, Section B: Item number 0028Item number 0028, Preliminary Draft TM, references SOW 5.4 and 5.15. SOW 5.4 is for "Develop parts list TM figure and item data", and SOW 5.15 is for "TM Deliverables".
Should Item number 0028, reference SOW 5.6 titled "Preliminary Draft Technical Manual (PDTM)?Yes, Section B has been corrected.
103Solicitation, Section B - CLIN 0004 SeriesFor Armored Kit, CLIN 0004 series, FOB is destination. Section F references Attachment G "Anticipated EBFL Delivery Locations and Quantities," which gives destination for 456 EBFLs.
What are the destinations for CLIN 0004 series Armor Kits?The armor kits will be shipped to Albany, GA.
104Solicitation, Section B: Item number 0029Item number 0029, Draft TM, references SOW 5.5 and 5.15. SOW 5.5 is for "TM Outline" and SOW 5.15 is for "TM Deliverables".
Should Item number 0029 references SOW 5.7 titled "Draft Technical Manual (DTM)?Yes, Section B has been corrected.
105Solicitation, Section B: Item number 0030Item number 0030, Final Draft TM, references SOW 5.6 and 5.15. SOW 5.6 is for "Preliminary Draft Technical Manual (PDTM) and SOW 5.15 is for "TM Deliverables".
Should Item number 0030 reference SOW 5.8 titled "Final Draft Technical Manual (FDTM)"?Yes, Section B has been corrected.
106Solicitation, Section B: Item number 0031Item number 0031, Sign-off Copy of TM, references SOW 5.7 and 5.15. SOW 5.7 is for "Draft Technical Manual (DTM) and SOW 5.15 is for "TM Deliverables".
Should Item number 0031 reference SOW 5.9 titled "Sign-off Copy Technical Manual (SOCTM)"?Yes, Section B has been corrected.
107Solicitation, Section B: Item number 0032Item number 0032, Final Reproducible Copy of TM, references SOW 5.8 and 5.15. SOW 5.8 is for "Final Draft Technical Manual (FDTM)" and SOW 5.15 is for "TM Deliverables".
Should Item number 0032 reference SOW 5.10 titled "Final Reproducible Copy (FRC)"?Yes, Section B has been corrected.
108Solicitation, Section B: Item number 0003 seriesItem number 0003 series, Exchange Credit, references SOW 3. Section 3. of Section C, Descriptions and Specifications, of the SOW does not reference/discuss Exchange Credit.
Where does the solicitation define the contents of Exchange Credit?The exchange credit is the amount of credit each offeror is proposing to exchange the current EBFL for a modernized EBFL. As stated in the solicitation, the item number series ending in 03 is only for evaluation purposes and will be removed at award.
109Solicitation Section I FAR 52.209-4(a) and Attachment FFAR 52.209-4(a) First Article Approval - Government Testing - The Contractor shall deliver six (6) test unit(s) within 120 calendar days from the date of this contract to the Government at Transportation Officer U.S. Army Aberdeen Proving Ground, Bldg. 507… Attachment F states that CLIN 0001 for 6 each Modernized EBFLs are to be delivered 180 Days after receipt of order.
Are the six (6) test units within FAR 52.209-4(a) First Article Approval - Government Testing the quantities within CLIN 0001? If so, is CLIN 0001 due 120 or 180 days from receipt of order?The test assets are due 180 ARO. FAR 52.209-4 has been updated.
110Solicitation, Section B and CSection C - Descriptions and Specifications are outlined in paragraph form. Not all paragraphs have a corresponding CLIN. For example, 3.3.3 In-Process Reviews does not have an associated CLIN.
Where should the contractor propose costs that are not NSP and there is not a corresponding CLIN?Contractor should not propose prices for paragraphs that do not have a CLIN.
111Solicitation, Section B, L and Attachment FL 2.2 Content of Proposal (Business Volume: Part 1 Price {underlined}) Pricing shall be submitted on the provided spreadsheet, Attachment F. Further, "Not Separately Priced" (NSP) shall be indicated for the corresponding CLIN/SLIN. Part 1 shall include the model contract with all proposed pricing.

There are inconsistencies between Attachment F and Section B related to unit of measure, evaluated quantity vs. quantity, and SOW paragraph referenced.

Attachment F has pre-populated "NSP" within "Price" column.

Attachment F does not include CLINs 0101, 1101, 2101, 3101 and 4101.

Should Section B or Attachment F be used for unit of measure, quantity and SOW paragraph reference?

How should the contractor propose pricing within Attachment F for CLINs that are not "NSP" (e.g. CDR, TRR, etc. )?

Should the contractor include pricing within Attachment F for these CLINs?Those events should be NSP. Attachment F should take precedence. There is a flaw in the contract writing software does not show "NSP" until an actual award has been made. However, each of the CLINs that are NSP in Attachment F are NSP in Section B. Unfortunately, offerors cannot see that particular screen in the word document. Offeror should not propose pricing for CLINs that are NSP in Attachment F. The CDRLs CLINs have been added to attachment F; however, they are NSP as well.
112Solicitation, Attachment G; Section B CLINs 0001, 1001, 2001, 3001, 4001Attachment G - Anticipated_EBFL_Delivery_Locations_and_Quantities - outlines destinations for 495 Modernized EBFLs. Section B CLINs of the RFP breaks down the 495 Modernized EBFLs by order period.
What are the corresponding destinations for the quantities within each Order Period for Modernized EBFL CLIN (CLIN 0001, 1001, 2001, 3001 and 4001)? Furthermore, what is the order of pick-up by location, by year and by quantity that will support the scheduling of Modernized EBFLs?The delivery order has not been established. The delivery locations and quantities have been provided to assist with pricing.
113SOW 3.1.2.1.1Inspection-Based Maintenance - The contractor shall provide the Government an itemized estimate of the cost to repair any such systems which require complete overhaul.
The contractor is directed to ask for approval and provide cost estimates for system overhauls, yet there does not appear to be a separate call-up and funding mechanism for such overhauls. Is the intent for such overhauls to be authorized, priced and funded separately from the existing CLINs?Yes. This will negotiated on a case by case basis and funded separately should an overhaul be necessary.
114Solicitation, Section L Part II Past PerformanceCan offerors submit past performance information for its major subcontractors?Yes, Section L has been updated to clarify.
115Solicitation Section L 2.0"Offeror shall include one electronic “soft” copy (one copy of the business volume and one copy of the technical volume on separate discs) of the full proposal using the Microsoft Office for Windows suite of applications, submitted on CD-ROM, formatted for a personal computer. Schedules will be in MS Project or compatible format. "
In addition to Microsoft Office application formats, are PDF format files acceptable?PDF is permissible for Appendix A - Test Data only.
116General IssueShould contractors have a question regarding the classified Addendum, how should those questions be submitted?All questions regarding the classified addendum should be sent using classified procedures.
117SOW 3.Are contractors allowed to use rail for transportating the EBFL from Albany?Yes, contractors will be allowed to transport by truck or by rail or a combination of both.
118General IssueWhat source files, other than PDF, are available for existing TMs (TM 10794B-OR/A, TM 10794B-OI/A, & TM 11494A-OI/A), and is a sampling available?Only PDF are available.
119SOW 5.1Does the USMC desire engine maintenance and parts breakdown coverage in the new TMs?Yes
120SOW 4.5.3Does the USMC desire engine maintenance and parts breakdown coverage for provisioning?Yes, contractor will be requried to develop completely new tech data/provisioning data.
121SOW 4.5.3Is there an existing LSA-036 Report?No
122SOW 4.5.3, 4.5.4What changes are required to the legacy provisioning data?No changes are required to the legacy provisioning data unless the contractor's modifications impact the legacy system. However, all new modifications the contractor implements need to be included in the contractors provisioning data. See response 49.