SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS/RESPONSES

Question: APU starting Functionality sec 3.4.10.2

To meet this requirement will 12VDC be available from the vehicle 24 VDC battery source for starter and other 12 VDC use?

Government Response:

In accordance with Requirement 3.4.10.2, "APU shall draw current from MTVR vehicle batteries for startup during mounted operation". The vehicle batteries are connected in series and the vehicle architecture is 28VDC and thus a 12VDC source is not available in the mounted configuration. So in the mounted configuration, the APU will need provisions to start using a 28VDC source. For dismounted operation, in accordance with Requirement 3.4.10.2, the APU shall be capable of starting using a Government-supplied 12VDC battery. In conclusion, the APU should have provisions to start using a 12VDC AND 28VDC source. The 28VDC is only used when APU is mounted on the vehicle, the 12VDC source is only used when APU is operating off the vehicle.

Question: Is it mandatory to request the 3D CAD model?

Government Response:

No, it is not mandatory. However, offerors are urged to utilize the Controlled Unclassified Information request form to request the 3D CAD model. As a reminder, the solicitation contains the following:

L.3.1.6. System Integration. The Offeror shall substantiate through models, drawings, pictures, graphics or schematics compliance to the following APU Performance Specification requirements:

- APU System Specification Requirement 3.4.3 - Maximum Envelope Dimensions

- APU System Specification Requirement 3.4.2.1.2 - APU Removal and:

M.1.5 Rating Methodology:

Subfactor 6: System Integration

Using the Offeror’s models, drawings, pictures, graphics or schematics, Government shall evaluate compliance to the following APU Performance Specification requirements:

- APU System Specification Requirement 3.4.3 - Maximum Envelope Dimensions

- APU System Specification Requirement 3.4.2.1.2 - APU Removal

(End of Summary of Changes)