M00146-15-T-9016_Q A_Attachment_1.docx
DOCX document 17 KB Posted
- Attached to
- Oil Quench Furnace and Gas Generator
- Solicitation number
- M00146-15-T-9016
- Issued by
-
United States Marine Corps
About this file
See attachment for government's response to questions received.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| M00146-15-T-9016_Amendment_2.doc | DOC document | |
| M00146-15-T-9016_Amendment_1.doc | DOC document | |
| PE-21522F_Attachment_1.pdf | ||
| M00146-15-T-9016_RFQ.doc | DOC document | |
| Brand_Name_Allen_Bradley_Attachment_3.pdf | ||
| Brand_Name_Honeywell_Attachment_2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEGRAL QUENCH FURNACE & ENDOTHERMIC GAS GENERATOR SOLICITATION M00146-15-T-9016
Questions Received Relating to this Solicitation and the Government’s Response
1. What is the height of the entrance doors to the building?
Response: One door measures 15'10"H x 9'7"W and the other door measures 7'10"H x 9'6"W.
2. Are photographs available of the general area of the furnace and generator?
Response: Pictures are available upon request from the Contracting Office via e-mail to larry.davis1@usmc.mil.
3. Re: Specification paragraph 3.3.1.1 Is the basket load station to be automated (i.e. a mechanism pushes the basket from the load station into the furnace vestibule at the beginning of the cycle and pull the tray from the vestibule onto the load station at the end of the cycle)? Or is the tray transferred manually by the operator?
Response: The basket load station shall be automated and if possible have a manual override.
4. Re: Specification paragraph 3.3.2.6 a. Referring to gas flow status – does this mean “on or off” or flow measurement in cubic feet per hour (CFH)?
Response: Gas flow status means flow measurement in CFH.
5. Re: Specification paragraph 3.6.2 d. states that the contractor is responsible for providing fluids and filling all reservoirs. Does this include quench oil? If yes, is there a particular brand that you are using?
Response: Yes. Contractor shall supply initial fill of quench oil. Currently we are using Chevron Quench Oil 70.
Attachment 1