Lyons Creek Truck Parking Area Maintenance Specification.docx
DOCX document 53 KB Posted
- Solicitation number
- MDT-316612-KB
- Issued by
- Cascade County, Montana
About this file
This is a Scope of Work specification document from the Montana Department of Transportation for maintenance services at Lyons Creek Truck Parking Area, located in Lewis and Clark County on I-15 near Wolf Creek, Montana. The Department seeks bids from caretaker management firms or individuals to provide comprehensive maintenance of the facility, including labor, equipment, supplies, tools, and materials for vault toilets, grounds, parking lots, and associated facilities. The work excludes snow and ice removal from parking lots but includes snow and ice removal from pedestrian walkways. The contract operates on two seasonal schedules: May 1 through September 30 requiring daily service seven days per week (8:00 a.m. to 12:00 p.m.), and October 1 through April 30 requiring service three days per week (Monday, Wednesday, Friday). The initial contract term runs from execution date through July 31, 2027, with options to extend for up to six additional one-year increments, not to exceed seven years total. Sealed bids are due October 5, 2026 at 2:00 p.m. MDT and must be submitted through the eMACS system. The truck parking area contains four vault toilets, two storage sheds, and four outside garbage cans requiring maintenance and monitoring.
The Montana Department of Transportation furnishes paper products, garbage bags and containers, paint, cleaning chemicals, deicer materials for sidewalks, and graffiti removal chemicals, while the Contractor provides all other labor, equipment, tools, and supplies. Bidders must submit monthly cost quotes separately for the May-September period (5 months) and October-April period (7 months) and comply with prevailing wage rates for nonconstruction work as specified. Payment is made monthly upon satisfactory completion of services, with the Department retaining the right to withhold payment for substandard or defective work. The Contractor must maintain a daily checklist and log submitted to the Department at least twice monthly and must be on-call for emergencies with a contact phone number. A joint inspection will be conducted prior to commencement of work to document existing conditions, with the Department responsible for corrections of identified substandard items. The contract includes detailed compliance and performance requirements with termination provisions for failure to cure deficiencies within 24 hours of written notice. Contractors who are Montana State employees are ineligible, and any current employee who becomes ineligible during the contract term must immediately notify the Department or face immediate termination.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit I Location Maps.pdf | ||
| Prevailing Wage Rates - Nonconstruction 2026.pdf | ||
| 1443923-event.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LYONS CREEK TRUCK PARKING AREA MAINTENANCE SPECIFICATIONS
SCOPE OF WORK
1.1. DESCRIPTION OF WORK
The Montana Department of Transportation (Department) is seeking bids from caretaker management firms or individuals for the maintenance of the Lyons Creek Truck Parking Area located in Lewis and Clark County on I-15 milepost 221.1 Southbound and 222.0 Northbound. The work shall include, but not limited to, furnishing labor, equipment, supplies not provided by the Department, tools and materials required to effectively maintain and operate the truck parking area including the vault toilets, grounds, parking lots and all other facilities within the truck parking area proper.
The scope of the work does not include the maintenance, repair, or removal of snow from the parking lots including entrances and exits to the parking lots of the truck parking area.
In addition to the routine work outlined in this document, the resulting purchase order requires a Contractor or Contractor's representative capable and authorized to confer on a daily basis with the Department's representative concerning situations and problems that arise and to be on call for emergencies.
Prior to commencement of work, the Department will arrange a meeting with the Contractor to discuss the resulting purchase order terms and work performance requirements. At this time, an inspection of the truck parking area will be conducted jointly to document conditions that exist. The Department is responsible for corrections of any identified substandard items listed as a result of the inspection.
All mechanical, electrical, plumbing, etc. work must be within codes and performed by appropriate licensed tradesperson.
(Refer to Exhibit I, Location Maps) [These maps show specific work requirements. Copies of these maps will be distributed at the site inspection.]
1.2. WORK LOCATIONS AND SCHEDULES
The Truck Parking Area is located at Wolf Creek, MT. on I-15 milepost 220.0 northbound and 222.1 southbound.
The following schedules will apply:
Daily Schedule |_| YES |_| NO
May 1st through September 30th The Contractor shall provide appropriate personnel to service and clean the vault toilets, picnic tables and park benches a minimum of once a day, seven days per week.
This cleaning for each site shall be between 8:00 am and 12:00 pm.
The cleaning requirements are based on minimum service levels required to keep the site refreshed throughout the day. The Contractor shall provide additional cleanup and care during periods of high use and, if necessary, through temporary closures, holidays and weekends.
October 1st through April 30th The Contractor shall provide appropriate personnel to service and clean the vault toilets, picnic tables and park benches a minimum of once a day, on Monday, Wednesday, and Friday.
This cleaning for each site shall be between 8:00 am and 12:00 pm.
The cleaning requirements are based on minimum service levels required to keep the site refreshed throughout the day. The Contractor shall provide additional cleanup and care during periods of high use and, if necessary, through temporary closures, holidays and weekends.
Cleaning Schedule In addition to routine janitorial services the Contractor will be responsible for, but not limited to, the following typical maintenance duties:
Doors – Repair and/or Replace
| 1. | Touch up paint to maintain appearance. |
| 2. | Replace push plates, kick plates and door pulls. |
| 3. | Maintain hydraulic closures. |
Fixtures – Repair and/or Maintain
| 1. | Toilet paper dispensers. |
| 2. | Toilet seats. |
Painting – touch up to maintain appearance of:
1. Vault toilet walls.
2. Doors.
1.3. INVENTORY OF TRUCK PARKING AREA
| Outside garbage cans | |
| Four (4) |
| Vault Toilets | |
| Two (2) |
| Storage Shed | |
| One (1) |
1.4. GENERAL REQUIREMENTS
Under the terms of the resulting purchase order, the Contractor and employees are prohibited from operating or advertising any commercial enterprise or activity on any premises that are the subject of the proposed purchase order.
The Contractor shall provide all labor, equipment, tools, materials and supplies (except as specified below) necessary to provide minor maintenance services associated with the facilities and parking area, to effectively maintain and operate the truck parking area.
The Department agrees to furnish only the following:
| a) |
| Paper Products |
| e) |
| Cleaning chemicals |
| b) |
| Garbage Bags & Containers |
| f) |
| Deicer Materials for sidewalks |
| c) |
| Touch-up and other paint |
| g) |
| Graffiti Removal Chemicals |
| d) |
| Kavik cleaner |
The Contractor shall provide the appropriate personnel to maintain the truck parking area facilities in a safe, sanitary, clean and attractive manner in accordance with the terms and conditions of the resulting purchase order.
The Contractor agrees to have a phone during the duration of the resulting purchase order and shall provide the Department with the name(s) and telephone number(s) of all on-call personnel.
Contractor personnel may assist the Department's appointed representative in making random on-site facility inspections and in coordinating other operational requirements. All site inspection deficiencies and recommended corrective actions will be shared with the Contractor.
The Contractor shall promptly notify appropriate authorities of emergencies that occur in the truck parking area. In the event of illness or injury to visitors or others while in the truck parking area, the Contractor's personnel shall call for professional help as requested or deemed appropriate.
The Contractor shall immediately report to the Department any suspected hazardous material spills. The Contractor shall barricade the area. The Contractor shall not attempt cleanup and will keep people away until qualified authorities decide on proper action.
The Contractor shall report all incidents such as vandalism, excessive occupancy, camping, etc., to the Department daily. The Department shall receive notification of any incidents relative to public health or safety immediately and incidents of a lesser nature during the next normal workday.
The Contractor and their employees shall not accept tips or other gratuities for any service performed in the truck parking area.
The Contractor or its’ employees cannot have pets; or children requiring the supervision of the Contractor or its’ employee, on site while performing work on the rest area.
In the event questions concerning areas of responsibility and duties arise, the Department shall have final authority.
1.5. WORK DETAIL - CLEANING/SERVICING REQUIREMENTS
Vault Toilets Water is not available on site. Contractor must provide the necessary water to maintain the vaults.
Floors, doors and vault toilets shall be scrubbed thoroughly, with additional cleaning as necessary.
After being washed, shall be wiped dry with a clean rag and floors shall be dried by either forced air or dry mopping.
Paper goods dispensers shall be replenished as necessary. At least one-half roll of toilet paper should be in evidence in each stall.
Walls shall be scrubbed weekly with soap and water, or appropriate cleaner, and wiped dry to maintain a clean, smear-free appearance. Daily spot cleaning is to be done as needed.
The entire inside of the vault toilets shall be deep cleaned at least twice a month or more often if required to maintain in original condition. The Department will provide the necessary equipment and chemicals to accomplish the deep cleaning.
The Department shall provide paper goods, garbage bags, and cleaning supplies. Material Safety Data Sheets (MSDS) must be present for all appropriate products.
The Contractor shall immediately remove any graffiti or markings of any kind on any surface inside the vault toilets.
Plaza Areas (outside the vault toilets) Walkways and doors shall be thoroughly cleaned each day, with additional cleaning as necessary. Smooth walls and overhead surfaces shall be scrubbed monthly with soap and water and wiped dry to maintain a clean, smear-free appearance. Rough surfaces shall be brushed and/or swept clean as necessary and shall be pressure washed a minimum of once every three months on 90-day intervals except during winter weather conditions.
Grounds and Parking Lots All trash, paper, other litter and pet waste shall be removed from the grounds, (core area around vault toilets), ramps and parking areas once per shift, or more often if necessary. All types of litter shall be removed from the surrounding areas daily. All garbage containers shall be emptied, cleaned and lids washed if dirty, and fitted with new bags as often as necessary to avoid overflow.
The Contractor should use his judgment to determine whether an almost empty garbage bag actually needs to be replaced. The Contractor shall notify the Department when garbage containers need replaced due to damage, normal wear and tear, etc.
The Contractor will be responsible for collecting and transporting all litter, debris and garbage to a site designated by the Department.
· The designated site is located at Hardy Creek on I-15, exit 247. This site contains a dumpster and is a residential area by Tower Rock State Park just south of Cascade. The designated dumpsite at Hardy Creek is Cascade County’s dump site and has limited hours of operation. Dump fees will be the Contractor’s responsibility.
Garbage bags placed in garbage storage containers must be tightly secured in order to reduce the risk of creating unsanitary conditions.
Parking areas, sidewalks and walkways shall be inspected and debris removed at least once per workday or as needed.
The Contractor shall be responsible for removing snow and ice from the pedestrian walkways to provide bare walkways for safe access. The pedestrian walkway applies only to the walkways in front of the vault toilets from the parking lot to the vault toilets themselves. Pick-up trucks or heavy tractors with snowplows or blades are not allowed on the pedestrian walkways in the truck parking area.
The Department will be responsible for snow removal from the parking lots area.
The Contractor shall immediately remove any graffiti or markings of any kind on any surface in the truck parking area. If the graffiti problem persists, or is of a violent or obscene nature, the problem shall be reported to the Department immediately.
Sewage System The Contractor is responsible for informing the Department when vault toilets need to be pumped. The Department is responsible for the pumping of the vault toilets.
Miscellaneous The Contractor shall provide safe storage for found articles and shall deliver unclaimed articles weekly to the Department. All incidents of lost/found shall be recorded in the daily checklist and log. (See Exhibit II.)
1.6. WORK DETAIL - MAINTENANCE REQUIREMENTS
The Contractor shall:
Maintain in good working condition all fixtures in the vault toilets including toilet seats, toilet paper dispensers, doors, hinges, latches and supports.
Be responsible for pruning and trimming (dead branches and any limbs or branches obstructing the walk ways) trees and shrubs.
Be responsible for mowing lawns to maintain a height of not less than 4 inches nor more than 6 inches. The natural areas will be maintained by the Department.
Be responsible for edging and trimming along all curbs and sidewalks.
Be responsible for removing lawn clippings, needles and leaves from the maintained area.
1.7. WORK DETAIL - REPAIR AND REPLACEMENT REQUIREMENTS
The Contractor shall:
Be responsible for replacing unserviceable or broken fixtures including toilet seats, doors, toilet paper dispensers and other related fixtures with Department provided fixtures. The Department will make the final determination if a fixture needs replaced.
The Department will:
Be responsible for providing replacement fixtures for the vault toilets and truck parking area proper, including, but not limited to: toilets, toilet seats, doors, toilet paper dispensers, and garbage containers.
Reserve the right to make any repairs, remove or add fixtures, facilities, landscaping or any other improvements or maintenance activity it deems necessary.
1.8. SAFETY REQUIREMENTS
The Department will furnish signs and barricades for emergency closure of the truck parking area. The Contractor shall furnish pedestrian signs deemed necessary to adequately warn or protect the public from possible hazardous conditions. Special precautions must be used when power equipment is operated.
The public shall be permitted use of vault toilets during cleaning if they so request.
The Contractor shall comply with applicable laws and regulations governing safety, health and sanitation.
The Department will provide a first aid kit. The Contractor shall keep the first aid supplies stocked at all times. The resident caretaker may attend a first aid course (conducted by the Department) if he or she so desire.
The Contractor and/or employees are not security personnel. All security or safety issues are to be reported to appropriate law enforcement entity and the Department immediately.
The Department will maintain security cameras if equipped.
1.9. CONTRACTOR'S EMPLOYEES
Each employee shall wear a visible easily read identification badge that contains the Contractor's and the employee's names. Because work performed on the rest area reflects directly on the Department, especially in the eyes of the traveling public, Contractor’s employees must dress in a professional and appropriate manner (i.e., clothing that appears clean, no shabby or ragged clothing, no halter/tank tops, no very short cutoffs, etc.)
Employees are prohibited from having firearms in their possession while on site. They also may not be in possession of any non-prescription or illegal drugs, or prescription drugs that are not currently prescribed to them. They may not be under the influence of any alcohol or drugs, prescription or otherwise, while on-site or performing work under the purchase order.
Employees shall treat the public in a friendly, courteous manner.
Contractor employees should be well informed on local road conditions, detours, and tourist attractions.
The Department reserves the right to require the Contractor to remove employees performing any duties associated with the resulting purchase order who endanger persons or property. Who are in violation of any of these requirements, or whose continued employment does not serve the best interest of the Department.
1.10. RECORDS
The Contractor shall keep a daily checklist and log which will be kept on site and available to the Department at any time. The checklist and log shall contain time and details of unusual activity (accidents, vandalism, etc.), lost and found articles, traffic counter reading, etc. A sample Daily Checklist and Log is attached as Exhibit II. The checklist and log shall be kept in the storage or mechanical room and be available for inspection by Department personnel.
Copies of the Daily Logs will be mailed or delivered to the Department no less than twice a month to the location listed below:
| Montana Department of Transportation |
| PO Box 1359 |
Great Falls, MT 59403-1359
1.11. DEPARTMENT'S RESPONSIBILITIES
Grounds, Parking Lot and Roadway The Department will be responsible for all repairs to pavement, walks and curbs. If the Department determines that any damage is the result of a negligent act by the Contractor, the cost of repairs shall be the responsibility of the Contractor.
Signs and Symbols The Department will provide all necessary permanent signs and pavement markings.
No additional signs shall be installed or erected by the Contractor except those required on a temporary basis to designate vault toilet cleaning. The Contractor shall do emergency closure of the truck parking area by use of the signs, barricades, and deployment plan provided by the Department. The Department must approve closures. The Contractor shall remove closure signs and barricades when the emergency is over and the truck parking area is to be reopened. The Department shall be notified immediately of any emergency.
Complaints All letters of complaint directed to the Contractor from the public shall be forwarded to the Department for reply. Copies of any complaints received, or responses issued by the Department will be provided to the Contractor.
Acts of Nature The Department will be responsible for all damage and other problems caused by acts of nature.
Inspection The Department will perform inspection(s) to ascertain the Contractor's compliance with requirements. The Contractor's designated supervisor may accompany the Department representative when inspections are made, but no advance notice of inspection time will be given. Refer to Exhibit III for the Department checklist and scoring criteria for each item.
The Department will allow adjustment only for the following reasons:
· Acts beyond the control of the Contractor
· Inspections performed during a large influx of visitors, such as a bus tour
· The Contractor demonstrates that broken or malfunctioning items noted were repaired within 5 working days of the inspection
1.12. TRUCK PARKING AREA CLOSURE
In the event that the truck parking area or one of the truck parking areas specified in this IFB is to be closed for a period of more than two weeks for any reason (such as fire, vandalism, sewage or highway construction, truck parking area renovation, reduction of funding, etc.) it is agreed by the parties that, upon written notification by registered mail from the DEPARTMENT to the CONTRACTOR, payments provided for in the resulting purchase order, will be discontinued starting two weeks after the date of postmark.
If the notification of closure falls between monthly payment periods the amount due will be prorated based upon the monthly rate and the number of days worked prior to the date payment will be discontinued.
When the truck parking area becomes operational, payment will commence from the first day the services are rendered. If services are provided for less than one full month, payment will be for the number of days worked based on the monthly rate.
If this IFB is for maintenance services on a dual truck parking area and only one facility is taken out of service, payments will be reduced by 1/3, based upon the monthly rate The DEPARTMENT may terminate the resulting purchase order for any of the closure causes listed above.
1.13. PURCHASE ORDER EXTENSION
The resulting purchase order may, upon mutual agreement, be extended in one (1) year increments for a period not to exceed a total of seven (7) years, [six (6) additional years]. This extension is contingent upon legislative appropriations and in no case may the resulting purchase order run longer than seven (7) years. Extension of the resulting purchase order will be possible only by way of duplication of the terms, conditions and prices of the original existing purchase order.
Any intention to extend the purchase order must be initiated in writing prior to the termination date of the existing purchase order or termination date of a purchase order, which has been previously extended.
The initial term of the purchase order resulting from this Invitation for Bid shall be the date upon contract execution through July 31, 2027.
1.14. PAYMENT REOUIREMENTS
The making and acceptance of payment for work, or material replacement, performed by the Contractor shall constitute a waiver of all claims by the Contractor, other than those arising from faulty work and of all or any claims by the Contractor previously made and unsettled.
Payments shall be made as provided:
· Upon satisfactory completion of services specified herein, the Contractor shall be paid monthly as soon as possible after receipt of invoices.
· Upon satisfactory completion of repairs, the Contractor will be paid the invoice price for materials not purchased by the Department. Each submitted invoice shall be itemized to show each item of the materials used. If outside expertise is required to make the repairs, the Department will pay the invoice. The Department must approve all repairs and materials in advance.
· Payments otherwise due may be withheld for substandard or defective work not remedied. The Department will provide written explanation to the Contractor of why payment is withheld.
1.15. COMPLIANCE
If the Department registers a formal and written complaint with the Contractor in respect to undesirable or unsanitary conditions in this truck parking area, the Contractor will have 24 hours in which to respond in person to the complaint, at the Great Falls Maintenance Division office to remedy the problems. Failure to respond in the prescribed time to the complaint or to remedy the problem may result in termination of the resulting purchase order as provided in Section 1.16 TERMINATION.
If the Department is not satisfied with the results and remediation of the complaint, the Department may require periodic and joint inspections of the truck parking area with the Contractor to discuss and point out Contractor violations. Failure of the Contractor to attend these inspections may result in termination of the resulting purchase order.
1.16. TERMINATION
The resulting Purchase Order may be terminated for failure to provide the services or accomplish work enumerated herein. Upon receiving written notice from the DEPARTMENT, the CONTRACTOR has 24 hours to cure the failure; the CONTRACTOR'S failure to cure the failure within the time allowed will be grounds for the immediate termination of the resulting Purchase Order.
The resulting purchase order may be terminated by the DEPARTMENT without cause; the DEPARTMENT seeking to terminate the resulting purchase order must give written notice of intention to do so to the CONTRACTOR at least thirty (30) days prior to effective day of termination, unless immediate termination is necessary.
If the Contractor fails to provide services required by the resulting purchase order or such services within the time specified herein or any extension thereof, the Department may, by written notice of default to the Contractor, cancel the whole or any part of the resulting purchase order upon written notice.
The Department may, upon finding that the Contractor is not in compliance with any law or regulation, or applicable licensure and certification requirement, cancel the resulting purchase order upon written notice to the Contractor.
The above remedies are in addition to any other remedies provided by law or the terms on the resulting purchase order.
Due to requirements of Federal labor laws, individuals who are presently a Montana State employee will not be considered for potential award of the resulting purchase order. A successful bidder who, during the post-bid period or during the term of the resulting purchase order, becomes a Montana State employee, must immediately notify in writing the DEPARTMENT'S Purchasing Services Section. CONTRACTOR agrees that, if it becomes a Montana State employee during those periods, or if it hires anyone to perform more than 50% of the work under the resulting purchase order who is a Montana State employee, the resulting purchase order is subject to immediate termination.
Should the Contractor neglect to prosecute the work properly, or fail to perform any provision of the resulting purchase order, the Department, after seven days' written notice to the Contractor, may, without prejudice to any other remedy they may have, make good the deficiencies and may deduct the cost thereof from the payment then or thereafter due to the Contractor or, at its option, may terminate the resulting purchase order and take possession of all materials, tools, fixtures, and finish the work by such means as the Department sees fit, and if the unpaid balance of the resulting purchase order price exceeds the expense of finishing the work, such excess shall be paid to the Contractor, but if such expense exceeds such unpaid balance, the Contractor or their surety shall pay the difference to the Department.
QUOTE SECTION
Provide all labor, materials, equipment and incidentals necessary to perform Truck Parking Area Maintenance as stated under “Scope of Work”. The resulting purchase order term is the date upon contract execution through July 31, 2027.
May 1st – September 30th Cost per Month: $__________ Extension for Five (5) Months: $__________
| October 1st – April 30th | ||
| Cost per Month: | $__________ | |
| Extension for Seven (7) Months: $__________ |
TRUCK PARKING AREA MAINTENANCE EXHIBIT II
DAILY SAFETY CHECK LIST
Truck Parking Area Name and Location: LYONS CREEK I-15 MILEPOST 222.0 NORTHBOUND & 222.1 SOUTHBOUND
| Activity Check List – Check Items Completed |
| Time Completed |
| 1 |
| Unisex Vault Toilets |
am pm
Clean Toilet and Wash Walls
Clean and Mop Floors
Clean Window
Remove or Cover Graffiti
| 2 |
| Sidewalks and Parking Lot |
am pm
Clean Sidewalks and Plaza Area
Empty Garbage Containers
Pick Up Litter and Trash Outside
| 6 |
| Mow Lawn – Remove Clippings |
am pm
Comments: (Lost and Found, Repairs, Vandalism, etc.) ____________
Date Time (am pm) (Signed) Contractor's Representative
Records must be maintained on site and turned into the appointed contract compliance officer two times a month. (White copy to Department, Yellow retained by Contractor)
CONTRACT COMPLIANCE REVIEW EXHIBIT III
| Ratings: | ||
| Date | Time ______________am/pm | (0) Unacceptable |
| Facility Name/Dist. | (1) Needs Improvement | |
| Contractor Name/Rep. | (2) Contract Minimums | |
| Department Rep. | (3) Exceeds Minimums | |
| Inspection by. | (NA) Not Applicable |
| No. |
| DESCRIPTION |
| RATING |
| COMMENTS |
| 1 |
| Driveways and parking lots clean of debris and litter. |
| 2 |
| Sidewalks Clean of all spills, dust, dirt, sand and of all snow or ice. |
| 3 |
| Garbage Containers clean and not overflowing. |
| 4 |
| All lawns between 4 and 6 inches and all lawns, trees and shrubs are neat and not obstructing walkways. |
| 5 |
| Natural Areas preserved and litter and trash free. |
| 6 |
| Building exterior clean and neat free of cobwebs, dirt and grime. No graffiti. |
| 7 |
| Vault toilet floors are clean. Walls are clean and free of graffiti and all fixtures operate properly. |
| 8 |
| Toilet Stool surfaces are free of dust, grim, stains and fingerprints. Toilet paper minimum half roll evident. All are operating properly. |
| 9 |
| Is deep cleaning necessary to remove buildup of dirt and grime on the floors, floorboards, corners, and walls? |
| No rating |
| Yes No |
If yes schedule additional deep cleaning.
Yes No If yes schedule additional cleaning.
| 10 |
| Storage Shed free of clutter, dirt and cobwebs. Fire extinguisher and first aid kits are full and ready in case of an emergency. |
| ITEM |
| FACILITIES |
| RATING |
| COMMENTS |
| 12 |
| Custodian's Appearance neat and clean. Was employee wearing I.D. badge |
| 13 |
| Record Keeping/Daily Log. Daily records being maintained and available. |
Sum of Ratings ==>
Sum of Ratings _____ ___ Number of Items Evaluated = ___ Final Rating Score
Additional Comments:
We agree that the rest area inspection was performed with both parties present and that the ratings as listed above are accurate and were discussed during the inspection.
(Signed by Contract Reviewer)
(Signed by Contractor)
Approved for payment to be made to the caretaker for the previous period:
| ______________________________ | ______________________________ | |
| Maintenance Chief Signature | Date |
TRUCK PARKING AREA MAINTENANCE CHECK LIST _____________ EXHIBIT IV
Frequency Key:
| D = daily | W = weekly | M = monthly | Y = yearly |
| A = as needed | W2 = 2 x week | M2 = 2 x month | Y2 = 2 x year |
NA = not applicable
| Task – Facilities |
| Minimum Results Expected |
| Frequency |
1. Driveways - Parking Lots Pickup and dispose of all litter. Sweep and clean curbs and gutters.
| Parking lots and driveways shall be clean of all debris and litter. Curbs and gutters must be clean. |
| D/A |
2. Side Walks Sweep and clean sidewalks. Wash off spilled food, drinks, dirt, sand. Remove snow and ice.
| Sidewalks shall be clean of all spills, dust, dirt, sand and of all snow or ice. |
| D/A |
3. Garbage Containers Check and replace garbage bags to prevent overflow or unsanitary conditions. Check and clean garbage container and lids.
| All garbage containers shall be maintained clean and free of dirt and grime. All garbage bags shall be replaced as often as necessary to prevent overflow. |
| D/A |
4. Lawn –Trees - Shrubs Mow and edge the grassy area. Maintain lawn between 4 and 6 inches in height. Prune trees and shrubs as required. Edge lawns, curbs and sidewalks as required.
| All lawns, trees/shrubs shall have a neat well-maintained appearance. All debris, trash and litter in these areas will be picked up at all times and disposed of. |
| A |
5. Natural Areas Clean up and remove all litter and trash and dispose.
| Native characteristics shall be preserved and enhanced. Area must be litter and trash free. Wild flower beds and area shall be preserved and maintained to enhance the rest area. |
| A |
6. Building Exterior Clean walls, doors and entryway. Sweep down cobwebs. Remove graffiti. Keep gutters free of debris, leaves and needles.
| Clean and neat appearing building exterior free of cobwebs, dirt and grime. |
| D/A |
7. Vault Toilet Floors and Walls Mop floor with a high strength detergent. Clean all walls with a disinfectant cleaner and wipe dry. Remove and/or paint over all graffiti. Make sure doors operate and lock properly.
| Vault toilet floors are clean and sanitized. Clean and well-maintained walls that are free of dirt, grime and graffiti with doors and all fixtures operating properly. |
| D/A |
8. Toilet Stools Clean and thoroughly scrub with high-strength detergent containing a deodorant and anti-bacterial agent. Rinse with clean water and wipe dry. Check to make sure adequate supplies of toilet paper are present in the dispensers. At least one-half roll of toilet paper shall be in evidence in each stall.
| All surfaces and toilet stools are free of dust, grime, stains and fingerprints. Toilet paper shall be available at all times and should never run out. |
| D/A |
9. Vault Toilet Deep Cleaning Clean and thoroughly scrub with high-pressure washer or appropriate cleaning system to deep clean and disinfect vault toilet interior. A high strength cleaning detergent contain a deodorant and anti-bacterial agent will be used. Rinse and dry.
| Deep cleaning is necessary to sanitize, disinfect and thoroughly clean the vault toilet to prevent buildup of dirt and grime on the floors, floorboards, corners and walls. This cleaning shall be done at low-use periods as scheduled. |
| W |
10. Storage Shed Keep storage shed clean, organized and free of litter. Keep up-to-date MSDS sheets on all cleaning products in a visible place and easily accessible in case of emergency. Check fire extinguishers. Check first aid kit.
| Storage shed shall be free of clutter, dirt and cobwebs. Fire extinguisher and first aid kits shall be full and ready in case of emergency. |
| W |
11. Caretaker Appearance The caretaker shall wear an I.D. badge, which contains Contractor and employee's name. The caretaker and employees’ appearance shall be neat and clean at all times.
| Employees shall be friendly and courteous to rest area users. Employees shall wear I.D. badges at all times while working within rest area complex. |
| D |
12. Record Keeping/Daily Log Keep a daily log listing activities completed. Enter unusual or required information (i.e. traffic counts, lost and found articles, accidents, vandalism). Keep the daily log in the storage shed.
| Daily logs and records shall be maintained every time cleaning activities occur. Logs will be maintained on site and be available for Department inspection. Daily sheet, logs and records shall be delivered twice a month to the Department. |
| D |
- 2 -
- 1 –
REVISED: 12/08/08
File details come from the government source that posted it. Updated .