This document is a technical specification for the design/build and delivery of a high-speed catamaran ferry to be used in commuter service between the City of Lynn and Boston, Massachusetts. The vessel shall be designed and constructed to meet the requirements of a 46 CFR Subchapter "T" passenger vessel with a Gross Regulatory Tonnage not to exceed 100 GT. It shall be certified for "Limited Coastwise" and "Cold Water" service and comply with the Federal Transit Administration's minimum 25-year service life requirement. The vessel shall have four diesel engines, four waterjet propulsion systems, and two auxiliary generators, and will be required to meet all applicable Environmental Protection Agency emission standards. The technical specification provides detailed requirements for the vessel's design, construction, documentation, testing, inspection, and delivery.
The technical specification does not provide pricing terms or funding information. However, it does note that the vessel's construction and service life must comply with Federal Transit Administration funding requirements, including the Buy America clause. The City of Lynn is the owner of the vessel, and the Massachusetts Department of Transportation is also involved in this procurement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Lynn Ferry_Commercial Specification 2020-01-27.docx | DOCX document | |
| Addendum 9 - 2020-11-04.docx | DOCX document | |
| Addendum 1 follow up Answer to Bidder Delivery Question.docx | DOCX document | |
| Ferry QA - 2020-01-27.xlsx | XLSX spreadsheet | |
| Lynn Ferry addendum 2.pdf | ||
| Addendum 1 - 2020-01-27.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lynn – Boston Passenger Ferry Specification 2019
PASSENGER-ONLY,
SUBCHAPTER “T” FERRY
TO SERVE LYNN, MA AND BOSTON, MA
TECHNICAL PROVISIONS NO. MDOTFEDFERRY
Technical Provisions No. MDOTFEDFERRY i
TABLE OF CONTENTS
000: GENERAL PROVISIONS
001 INTRODUCTION AND GENERAL SCOPE
002 GLOSSARY
002.1 ABBREVIATIONS
002.2 EXPANDED DEFINITIONS
003 REGULATIONS, DOCUMENTATION, CERTIFICATION
003.1 COMPLIANCE
003.2 DOCUMENTATION
003.3 CERTIFICATION
004 GENERAL SPECIFICATION REQUIREMENTS
004.1 GENERAL
004.2 GENERAL VESSEL DESCRIPTION
004.3 GENERAL CHARACTERISTICS
004.4 PVAG REQUIREMENTS
004.5 CONTRACTOR'S OBLIGATION
004.6 MANUFACTURERS' REPRESENTATIVES
005 CORRESPONDENCE & COMMUNICATIONS
006 DOCUMENTATION
006.1 PROPOSAL DRAWINGS
006.2 CONTRACT DRAWINGS
006.3 REQUIRED DRAWINGS AND DOCUMENTS
006.4 INTERFERENCE & ACCESS
006.5 ENGINEERING
006.6 AS-BUILT DRAWINGS
006.7 MANUALS AND MAINTENANCE INSTRUCTIONS
006.8 VESSEL HISTORY BOOKS
006.9 PHOTOGRAPHS
007 DRAWING REVIEW PROCESS
007.1 OVERVIEW
007.2 DESIGN PACKAGES
007.3 DESIGN REVIEW PROCESS
007.3 USCG COORDINATION
008 WEIGHT AND CENTER OF GRAVITY
008.1 WEIGHT ESTIMATE
008.2 WEIGHT SURVEY
009 STABILITY AND SUBDIVISION
009.1 SUBDIVISION
009.2 ACCESS AND LOGISTICAL REQUIREMENTS – STABILITY AND SUBDIVISION TESTS
010 ADMEASUREMENT TONNAGE
010.1 GENERAL
011 ACCESS & MAINTENANCE REQUIREMENTS
011.1 GENERAL
011.2 PIPES, VALVES, ETC
011.3 REMOVAL OF EQUIPMENT/MACHINERY
011.4 DRAINAGE
011.5 LIGHTENING HOLES, MANWAYS, LIMBER HOLES
011.6 MAINTAINABILITY DEMONSTRATION
012 ACCESS TO YARD/VESSEL/DOCUMENTS
012.1 ACCESS TO YARD/VESSEL
012.2 ACCESS TO DOCUMENTS
013 OFFICE
013.1 OFFICE
ii
013.2 CONFERENCE AREA
013.3 PARKING
015 PROGRESS REVIEW MEETINGS
017 MATERIALS & WORKMANSHIP
017.1 MATERIAL - GENERAL
017.2 WORKMANSHIP - GENERAL
017.3 STORAGE/PROTECTION
017.4 WELDING
018 QUALITY ASSURANCE
018.1 CONTRACTOR QUALITY MANAGEMENT SYSTEM
018.2 QUALITY DOCUMENT SUBMITTALS
018.3 CONTRACTOR QUALITY ASSURANCE DOCUMENTATION
018.4 CONTRACTOR QUALITY ASSURANCE AND QUALITY CONTROL PROCEDURES
018.5 CONTRACTOR INSPECTION PLAN
018.6 OWNER’S PARTICIPATION
019 HULL & STRUCTURE PROTECTION
019.1 WELDING
019.2 UNDERWATER HULL INSPECTION (AS APPLICABLE)
020 TRAINING
020.1 OPERATOR TRAINING
020.2 MAINTENANCE TRAINING
020.3 OPERATOR’S MANUAL
021 SPECIAL EQUIPMENT
021.1 PORTABLE TEST UNITS (PTUS)
021.2 SPECIAL TOOLS AND FIXTURES
022 SPARES
100. STRUCTURAL
100 GENERAL
100.1 HULLS, EQUIPMENT, ACCESS
100.2 SUPERSTRUCTURES, ACCOMMODATIONS
100.3 CLASSIFICATION
100.4 RIDE CONTROL
110 HULLS
110.1 MATERIALS AND DESIGN
110.2 SHEAR GUARDS
123 TANKS
123.1 POTABLE WATER TANK
123.2 FUEL OIL TANKS
123.3 COLLECTION AND HOLDING TANKS (CHT)
130 DECKS, FRAMING, & BRIDGE PLATE
130.1 DESIGN AND CONSTRUCTION
130.2 MAIN DECK
130.3 UPPER DECK
130.4 BRIDGE PLATES (TRANSITION PLATES) AND HOLDERS
150 SUPERSTRUCTURE
150.1 MAIN DECK TO UPPER DECK
150.2 UPPER DECK
151 ENGINE FOUNDATIONS
155 WATER JET INTAKE TUNNELS
167 WATERTIGHT HATCHES & SCUTTLES
167.1 GENERAL
167.2 HATCHES (SCUTTLES)
167.3 ENGINE ROOM ACCESS HATCHES
167.4 ENGINE REMOVAL ACCESS
168 WEATHERTIGHT DOORS
iii
171 MASTS
200. MECHANICAL
233 PROPULSION – DIESEL ENGINES
233.1 GENERAL
233.2 MAIN PROPULSION ENGINES
233.3 OPTION: ENGINE MONITORING SYSTEM
241 REVERSE/ REDUCTION GEARS
242 COUPLINGS, SHAFTING, SEALS
246 JET TUNNELS, WATER JETS
252 PROPULSION CONTROL SYSTEM
259 EXHAUST SYSTEMS
261 FUEL OIL SYSTEM
261.1 SYSTEM
261.2 FILTERS
261.3 FUEL SOUNDING
261.4 SHUT DOWNS
261.5 PUMPS
261.6 VENTS
262 LUBE OIL SYSTEM
300. ELECTRICAL
300 GENERAL
311 SHIP SERVICE DIESEL GENERATORS
313 BATTERIES & CHARGERS
313.1 EMERGENCY SERVICE 24V DC
313.2 ANTICIPATED 24V DC EMERGENCY LOADS
313.3 ALTERNATORS
313.4 MAIN ENGINE STARTING BATTERIES
313.5 GENERATOR STARTING BATTERIES
321 POWER DISTRIBUTION
321.1 SHORE POWER
321.2 POWER SOURCE TRANSFER
321.3 SHORE POWER RECEPTACLE & CABLES
324 SWITCHBOARD & POWER PANELS
324.1 MAIN SWITCHBOARD
324.2 POWER PANELS
324.3 CIRCUIT BREAKERS
324.4 COMMISSARY
331 LIGHTING FIXTURES & ILLUMINATION
331.1 GENERAL
331.2 INTERIOR LIGHTING
331.3 EXTERIOR LIGHTING
331.4 NAVIGATION LIGHTS & PANEL
331.5 FLOODLIGHTS
331.6 DECK LIGHTS
331.7 SEARCHLIGHT
331.8 STEP LIGHTS
400. NAVIGATION, COMMUNICATION AND SAFETY EQUIPMENT
421 NAVIGATION SYSTEMS
421.1 FLAGS & SHAPES
421.2 EMERGENCY SIGNALS
421.3 EPIRB
421.4 ANCHOR SIGNAL BELL
421.5 MAGNETIC COMPASS
421.6 SHIP’S HORN
421.7 THERMAL IMAGING CAMERA
iv
422 NAVIGATION LIGHTS & PANEL
423 NAVIGATION & EXTERIOR COMMUNICATION SYSTEMS (ELECTRONIC)
432 TELEPHONE/INTERCOM SYSTEM
433 PUBLIC ADDRESS & ALARM SYSTEMS
433.1 PUBLIC ADDRESS & ALARM SYSTEM
433.2 LOUD HAILER
434 AUDIO/VISUAL, WI-FI, & PASSENGER INFORMATION SYSTEM
434.1 AUDIO/VISUAL PASSENGER ENTERTAINMENT SYSTEM
434.2 WI-FI
434.3 PASSENGER INFORMATION SYSTEM
434.4 INDUCTION LOOP SYSTEM
436 SAFETY DEVICES
436.1 PERSONAL FLOATATION DEVICE (PFD) STORAGE
436.2 INFLATABLE BUOYANT APPARATUS (IBA)
439 CLOSED CIRCUIT TV (CCTV)
439.1 CCTV GENERAL REQUIREMENTS
439.2 OPTION: CCTV PASSENGER AREAS
439.3 OPTION: CCTV LIVE LOOK-IN FEATURE
441VHF RADIO
446 AUTOMATIC IDENTIFICATION SYSTEM (AIS)
500. PIPING, INSULATION, HVAC, FIRE SAFETY, ANCHORING & MOORING
501 PIPING SYSTEMS
508 INSULATION
508.1 THERMAL
508.2 ENGINE ROOM COMPARTMENT INSULATION
508.3 EXHAUST LAGGING & INSULATION
511 HEATING, VENTILATION AND AIR CONDITIONING (HVAC)
511.1 GENERAL
511.2 MAIN CABIN
511.3 PILOT HOUSE
511.4 HEADS
511.6 OTHER SPACES
511.7 MACHINERY SPACE VENTILATION
520 SEA CHESTS & VALVES
521 FIRE MAIN & BILGE PUMP SYSTEM
521.1 FIRE MAIN SYSTEM
521.2 BILGE SYSTEM
526 SCUPPERS AND DECK DRAINS
526.1 GENERAL
526.2 LOADING AREA DRAIN PANS
526.3 INTERIOR DECK DRAINS
528 PLUMBING DRAINS & SEWAGE SYSTEM
528.1 GENERAL
533 POTABLE WATER SYSTEM
555 FIRE EXTINGUISHING
555.1 FIXED SYSTEM
555.2 PORTABLE EQUIPMENT
568 MANEUVERING & CONTROL SYSTEM
568.1 GENERAL
568.2 SYSTEM DESCRIPTION
581 ANCHOR HANDLING AND STOWAGE
582 MOORING SYSTEM
600. OUTFITTING & MARKINGS
602 SIGNAGE & MARKINGS
602.1 GENERAL
v
602.2 REGULATORY HULL MARKINGS
602.3 COMPANY NAME & LOGOS
602.4 BUILDER’S PLAQUE
602.5 OWNER’S STANDARD SIGNAGE
611.1 HULL FITTINGS
611.1 DOORS, EXTERIOR WEATHER-TIGHT
611.2 DOORS, INTERIOR JOINER
611.3 TONNAGE OPENINGS
611.4 BITTS, CHOCKS, & FAIRLEADS
612 RAILS & STANCHIONS
621 NON-STRUCTURAL BULKHEADS
622 FLOOR PLATES, GUARDS, & LIFTING GEAR
622.1 FLOOR PLATES
622.2 GUARDS
622.3 LIFTING GEAR
623 LADDERS, STAIRS, & GATES
623.1 VERTICAL LADDERS
623.2 INCLINED STAIRS
623.3 GATES
623.4 PIER TO VESSEL INTERFACE
625 WINDOWS
625.1 PILOTHOUSE WINDOWS
625.2 MAIN DECK WINDOWS
625.3 HEAD WINDOWS
631 PAINTING
631.1 GENERAL
631.2 EXTERIOR
631.3 INTERIOR
631.4 PAINTING AND STYLING SCHEMES
633 CATHODIC PROTECTION
634 INTERIOR DECK COVERINGS
634.1 MAIN DECK
634.2 ENTRANCE MATTING
634.3 PILOTHOUSE INTERIOR
634.4 SAFETY MATTING
644 SANITARY SYSTEM, SPACES AND FIXTURES
644.1 PASSENGER HEADS
645 PASSENGER SPACES
645.1 GENERAL
645.2 MAIN DECK PASSENGER SPACE
645.3 UPPER DECK
646 PILOTHOUSE SPACE
646.1 PILOTHOUSE CONSOLE MOCK UP [CDRL 645-2]
651 COMMISSARY SPACE
654 UTILITY SPACES
671 LUGGAGE STOWAGE
672 TICKET COUNTER
673 BICYCLE RACKS
900. TESTS, INSPECTIONS, TRIALS & SERVICES
901 IN-PROCESS INSPECTIONS
901.1 GENERAL
901.2 SCHEDULING & ATTENDANCE
901.3 PREPARATIONS
901.4 REQUIRED INSPECTION POINTS
901.5 RE-INSPECTIONS
vi
902 FIRST ARTICLE INSPECTIONS
981 SURVEY & MEASUREMENT
982 TRIALS - GENERAL
982.1 GENERAL
982.2 TEST & INSPECTION PLAN
982.3 TEST PROCEDURES
982.4 TEST AND INSPECTION REPORTS
983 FUNCTIONAL TESTS (SUPPORTED AND APPROVED BY VENDOR REPRESENTATIVES)
984 DOCK TRIALS
984.1 GENERAL
984.2 REQUIRED DOCK TRIALS
985 Sea Trials
985.1 GENERAL
985.2 SCHEDULING & ATTENDANCE
985.3 ATTENDEES
985.4 SEA TRIAL LOCATION
985.5 SEA TRIAL DEADWEIGHT
985.6 SEA TRIAL VESSEL & AMBIENT CONDITIONS
985.7. REQUIRED SEA TRIALS
986 POST-DELIVERY TRIALS IN OWNER’S VENUE
986.1 BOARDING & DEBARKING/DOCK INTERFACE
986.2 NEW TO ZONE USCG SECTOR INSPECTION
987 DELIVERY
988 CERTIFICATIONS, REGISTRATIONS, AND OTHER REQUIRED DOCUMENTATION OR APPROVALS
994 CLEANING
997 DRYDOCKING
- SECTION NUMBERING CONFORMS TO THE STANDARD SHIP WORK BREAKDOWN STRUCTURE “SWBS” SYSTEM -
000: GENERAL PROVISIONS
001 INTRODUCTION AND GENERAL SCOPE
These SPECIFICATIONS are performance based and provide details of an RFP for the
Design/Build of one, 28-knot (at full load capacity and 85% power), catamaran ferry for use in commuter service between the City of Lynn and Boston for the City of Lynn, hereinafter referenced in these specifications as the OWNER. The vessel shall be designed and constructed to be fully capable in all respects of providing reliable, year-round service on the Lynn, MA to downtown Boston, MA route, and to be fully capable of providing seasonal service out to 20 miles from a safe harbor of refuge (Limited Coastwise).
The vessel shall have four (4) resiliently mounted diesel engines that meet all applicable
Environmental Protection Agency (EPA) Emission Standards for newly manufactured marine engines of their class at such time that the construction of the vessel commences (in conformance with EPA Emissions Standards “keel laying” requirements); four (4) waterjets; and two auxiliary generators. The vessel shall conform to all of the regulations that apply to a 46 CFR Subchapter
“T” Passenger Vessel with a Gross Regulatory Tonnage not to exceed 100GT (Gross Tons).
The vessel’s construction and service life shall comply with Federal Transit Administration (FTA) funding requirements. The Minimum Service Life of this vessel shall be (25) twenty-five years, as detailed in the latest version of FTA circulars 4220.1 and 5010.1. The CONTRACTOR is to comply with the provisions of the FTA Buy America requirements, where applicable, and as detailed in the Terms and Conditions.
References to particular manufacturers, vendors, or products are NOT to be interpreted as an endorsement by the OWNER. Such references are provided for information and guidance as to products which will be suitable, and to assist the CONTRACTOR in assessing and meeting the material and operational requirements of the proposed vessel. The CONTRACTOR shall make all reasonable efforts to select products and components for use in the vessel that would be expected to be supported by their manufacturers for ten (10) years after the date of vessel acceptance. Should this not be possible, as in the case of software, or should a part for which there is no competitive equivalent available in the market place become unavailable through the
CONTRACTOR during that time period, the CONTRACTOR agrees to assist the OWNER with drawings and specifications to facilitate component procurement by the OWNER when necessary.
The CONTRACTOR shall deliver the vessel to the OWNER at a facility designated, which will be located in the greater Boston, MA harbor or Lynn, MA. Upon delivery, all vessel systems shall be in operation, and ready for service. The CONTRACTOR shall assist the OWNER in obtaining a valid USCG Certificate of Inspection.
002 GLOSSARY
002.1 ABBREVIATIONS
As used throughout these Specifications, the following partial list of terms and abbreviations shall have the meanings stated:
ABS American Bureau of Shipping (classification society)
ADA Americans with Disabilities Act
AIS Automatic Identification System
ANSI American National Standards Institute
ASME American Society of Mechanical Engineers
ASTM American Society of Testing and Materials
CCTV Closed Circuit TV
CDRL Contract Deliverable Requirements List
CFR Code of Federal Regulations
CHT Sewage Tank “Collection & Holding Tank”
CMR Code of Massachusetts Regulations
. COI Certificate of Inspection
COLREGS Navigation Rules of the Road
CONTRACTOR (same as YARD or SHIPYARD)
CONTRACT Construction Contract between OWNER and the CONTRACTOR.
The Contract shall include these Specifications and Addendums
CuNi Copper Nickel Alloy
CRES Stainless Steel (SST)
DFT Dry Film Thickness
DGPS Differential Global Positioning System
DNV Det Norske Veritas (classification society)
DOJ U.S. Dept. of Justice
DOT U.S. Dept. of Transportation
DVTP Design Verification Test Procedure
DWG Contract Drawing
ECM Engine Control Module
EDM Electronic Display Module
E-LIGHT Light on Emergency Lighting Circuit
EPA Environmental Protection Agency
EPIRB Emergency Position Indicating Radio Beacon
ER Engine Room
FAI First Article Inspection
FCC Federal Communications Commission
FMEA Failure Mode Effects Analysis
FO Fuel Oil (in US gallons)
FRP Fiber Reinforced Plastic
FTA Federal Transit Administration
FW Freshwater (in US gallons)
GPM Gallons per Minute
HP Horsepower
HVAC Heating, Ventilation, and Air Conditioning
IBA Inflatable Buoyant Apparatus
IEEE Institute of Electrical & Electronics Engineers
IES Illumination Engineering Society
ITC International Tonnage Commission
JCM Jet Control Module
JR Jet Room
LCG Longitudinal Center of Gravity
LRU Lowest Replaceable Unit – a modular component that is designed to be replaced in the field by swapping out with another identical unit.
This is the lowest level of component that would be removed in regular maintenance, with any repair thereof performed elsewhere.
LT Long Ton - 2240 pounds
OWNER Owner, Lynn/MassDOT
MAAB Massachusetts Architectural Access Board
MARPOL International Convention for Prevention of Pollution from Ships
MassDOT Massachusetts Department of Transportation
ME Main Engine
MIG Metal Inert Gas (Welding)
MSO Marine Safety Office, USCG
MSC Marine Safety Center, USCG (Washington, DC)
NEMA National Electrical Manufacturer’s Association
NIST National Institute of Standards & Technology
NTP Notice to Proceed
NUC Not Under Command
NVIC Navigation and Vessel Inspection Circular
OCMI Officer in Charge of Marine Inspection
OF or OFE “Owner Furnished” or “Owner Furnished Equipment”
OREP Owner’s Representative
OWNER City of Lynn, Massachusetts)
P Port
P&S Port and Starboard
PFD Personal Flotation Device
PLC Programmable Logic Controllers
POC Point of Contact
PSTP Periodic Safety Test Procedure
PTU Portable Test Unit
PVAG Passenger Vessel Accessibility Guidelines 2013
QA Quality Assurance
QAWT Quick Acting Watertight
QMS Quality Management System
RFP Request for Proposal
S Starboard
SEAL WELD Structure which is double continuously welded
SHIPYARD CONTRACTOR or YARD
SNAME Society of Naval Architects & Marine Engineers
SST Stainless Steel (CRES)
SW Saltwater
SWBS Ship Work Breakdown Structure (numbering system)
TIG Tungsten Inert Gas (Welding)
TLI Tank Level Indicator
TWIC Transportation Workers Identity Card
UL Underwriters Laboratories
USAB United States Access Board
USCG United States Coast Guard
USCG/MSC United States Coast Guard Marine Safety Center (Washington DC)
USG U.S. Gallons
USPHS United States Public Health Service
UV Ultra-violet
VCG Vertical center of gravity
VESSEL Ship under contract
VMS Variable Message Sign
WTD Watertight Door(s)
YARD Contracting Shipyard (same as CONTRACTOR)
002.2 EXPANDED DEFINITIONS
002.2.1 CONTRACTOR-FURNISHED EQUIPMENT
Unless otherwise stated, the terms “provide,” “supply,” “install,” and other similar terms, as related to the CONTRACTOR, shall be understood to mean that the
CONTRACTOR is responsible for purchasing, integrating, installing, and warranting the associated piece of equipment or system in working condition. This includes all associated wiring, piping, and other connections, as well as consumables such as fluids, necessary for the proper functioning of the equipment or system.
For example: floodlights or navigation lights that are to be “provided” and “installed” will be purchased by the CONTRACTOR, installed with foundations, wired, powered, switched, and tested complete. This includes any necessary integration with other systems and consideration of interference and other effects on the vessel. The lights, and all associated parts required for the proper installation and operation of the lights
(excluding consumables) will also be warranted per the requirements of these
SPECIFICATIONS. If cable is required to bring power to that light, the cable shall be provided, integrated, installed and warranted as part and parcel of the light installation. If a kick-pipe is required, that kick-pipe shall be part of the installation.
002.2.2 OWNER-FURNISHED EQUIPMENT
All equipment herein specified as OWNER-furnished (OFE) is to be installed by the
YARD in such condition that it is completely operational and serviceable under normal conditions of vessel operations. Such installations are to adhere to all applicable specifications of regulatory agencies, and are to be to the satisfaction of the OWNER.
This includes, but is not limited to, the following:
a. Time and materials for assembly
b. Time and materials for positioning and proper securing
c. Time and materials for connections of piping, wiring, etc.
d. Time and materials for operational testing
OFE equipment, when specified, shall be new equipment in current production. It shall be supplied to the CONTRACTOR with installation instructions, vendor references, and vendor POC. All equipment, which is NOT herein specified as OFE, shall be CONTRACTOR furnished.
With the exception of purchasing the equipment, all other CONTRACTOR responsibilities for CONTRACTOR furnished equipment apply for OFE equipment.
002.2.3 GOOD SHIPBUILDING PRACTICE
The term "good shipbuilding practice" means construction practices which are in accordance with soundly engineered and detailed drawings, approved by the OWNER and USCG. These drawings are to meet the requirements contained within these
SPECIFICATIONS. Construction and testing shall conform to regulatory agency and industry accepted standards, so as to ensure that each vessel will meet the general and particular design requirements.
002.2.4 MINIMUM SERVICE LIFE/USEFUL LIFE
As a Federally funded procurement, the vessel supplied under this contract must be designed and built to meet the FTA’s defined minimum service life of 25 years for passenger ferry vessels. Per FTA Circular 5010-1, the service life – also called useful life – is defined as, “The expected lifetime of project property, or other acceptable period of use in service.”
002.2.5 SOLE SOURCE/BID SUBSTITUTIONS
Trade names and/or manufacturers’ names and part numbers shown throughout this specification are not “sole source” items, unless expressly stated in these
SPECIFICATIONS. The items specified in the opinion of the OWNER will meet the operating requirements of reliability, maintainability, life expectancy and interchangeability.
The CONTRACTOR is responsible for selecting equipment to provide a fully functional, integrated vessel and equipment, meeting all regulatory requirements and the performance criteria in these SPECIFICATIONS. The CONTRACTOR is permitted to submit bids containing substitutions (“or equals”), as long as such substitutions are clearly stated and detailed. Any substitution must be equal to the specified model, must be sufficiently documented to prove quality, and must meet the performance requirements of each vessel.
The CONTRACTOR is responsible for all additional costs associated with proposed substitutions including, but not limited to, required engineering expenses, and modifications to foundations, connection sizes, electrical interfaces, etc. which will render the substitution fully compatible with other installed equipment. In this regard, the SPECIFICATIONS herein are guidelines for minimum performance requirements.
If those SPECIFICATIONS are not offered by a particular manufacturer, product, or model, the CONTRACTOR will be expected to include a separate list of all discrepancies. Substituted manufacturers, products, or models will not be considered unless they have been demonstrated to be equal to or exceeding the quality, durability and design and the minimum performance functions of the specified equipment. Any proposed substitution must conform substantially to the specified requirements for the machinery and/or equipment, including manufacturer’s product support for (10) ten years.
Where the CONTRACTOR desires to provide substitute equipment or components for those specified in these SPECIFICATIONS, the DRAWINGS, or the
CONTRACTOR’s Proposal, the CONTRACTOR shall present, for the OWNER's review and approval, written documentation that the equipment and/or components proposed qualify as equal to those specified, and that spare parts and service for them are readily available.
Proposed substitutions shall not adversely affect any other component or system in the vessel; adversely affect the vessel's total performance; or relieve the CONTRACTOR from any obligation related to performance, warranty, etc. Any proposed substitution shall function as effectively as the equipment specified, with no increase in required maintenance or need for premature replacement.
002.2.6IN-PROGRESS SUBSTITUTIONS
It is the intent of these SPECIFICATIONS that all equipment shall be provided as specified herein. Substitutions shall be considered on a "case by case" basis upon timely written notice from the CONTRACTOR to the OWNER; or, in the case of the
OWNER’s generated substitution, upon timely written notice from the OWNER to the
CONTRACTOR. Such written notice shall include written documentation that the equipment and/or components proposed qualify as equal to those specified and that spare parts and service for them are readily available. The OWNER or
CONTRACTOR is under no obligation to accept substitutions by either party of any materials or equipment unless this written process is adhered to and both have signed off in agreement. The OWNER has the final decision concerning the acceptance of substitutions.
002.2.7 SUBSTITUTION CHECK LIST
The following items should be considered, and documented as part of the written substitution request, when bidding substitutions or proposing in-progress substitutions. Particular attention shall be paid to quality, reliability, performance, maintenance requirements, technical support and safety.
1. Functionality:
Functional characteristics
Electrical characteristics
Capacities (GPM, pressure, volume, wattage, HP, etc.)
2. Performance:
Industry performance
Rate service duty life
Reliability in similar applications
3. Quality:
Quality of fabrication, welding, and construction details
Materials of Construction (high quality marine grade)
4. Maintenance
Maintenance life cycle
Ease of maintenance
Manufacturer’s ability to support
5. Standards & Regulations:
Regulatory Body approval
Constructed to recognized standards (UL, IEEE, ANSI, ASTM, etc.)
Effect on vessel’s compliance with FTA Buy America
6. Safety Features
7. Form:
Conformance to salient features
Dimensional characteristics
Weight
003 REGULATIONS, DOCUMENTATION, CERTIFICATION
003.1 COMPLIANCE
The vessel, as delivered, shall comply with the requirements of applicable Local, State and
Federal Regulatory Agencies. These shall include, but shall not be limited to:
USCG: 46 CFR Subchapter “T” & “S” Passenger Vessel (Limited Coastwise)
Buy America clauses, as detailed in the Terms and Conditions
USPHS: Publication No.393, "Handbook on Sanitation of Vessel Construction"
USCG: International Rules of the Road (COLREGS)
Institute of Electrical & Electronics Engineers Standards #45 (IEEE)
Federal Communications Commission (FCC)
United States Access Board (USAB) (PVAG) Revised Draft Passenger Vessel
Accessibility Guidelines, as published in the Federal Register on June 25, 2013, USDOT
49 CFR Parts 39, Transportation for Individuals with Disabilities: Passenger Vessels. All interior passenger elements not specifically addressed by PVAG, shall conform with US
DOT 49 CFR Part 37 (and Subpart C) as well as 49 CFR Part 39.
If a conflict exists between State and Federal accessibility requirement/code the more stringent code must be followed. In addition, all design elements shall comply with the minimum
Federal requirements/code even if a State requirement/code is less stringent. The
CONTRACTOR is responsible for ensuring compliance with all applicable regulations. Any error or omission in these SPECIFICATIONS shall not relieve the CONTRACTOR from this obligation, and the obligation to immediately bring all discrepancies to the attention of the
OWNER.
003.2 DOCUMENTATION
All necessary certifications and/or documents covering the approval of, and indicating compliance with, applicable regulations shall be obtained by the CONTRACTOR and supplied to the OWNER. The OWNER shall provide the CONTRACTOR, in writing, the vessel names, Port of Documentation, and company name upon the CONTRACTOR’s request to complete the Application for Initial Documentation (CG-1258) and the application for an
Official Number. It is the OWNER's responsibility to provide the CONTRACTOR with a receipt for documents received and to retain these documents for presentation to Regulatory inspectors as and when required. When the OWNER receives the Bill of Sale and Builder’s
Certificate, the OWNER shall be responsible for obtaining the final Certificate of
Documentation.
003.3 CERTIFICATION
The vessel will be designed, constructed, and outfitted to meet the regulations of 46 CFR
Subchapter “T” Small Passenger Vessels (under 100 GT). It shall be certified for “Limited
Coastwise” and “Cold Water” service. The OWNER is responsible to notify the
CONTRACTOR of any special USCG requirements or mandates which shall be imposed by the USCG Local OCMI in the OWNER’s operating venue. A notification of any such requirement shall be made prior to Contract Award.
The CONTRACTOR is responsible for providing a vessel that will meet all requirements to receive the necessary certifications, including those obtained by the CONTRACTOR and by the OWNER. This includes, but is not limited to:
Stability Letter
Certificate of Inspection
FCC Documents
Fire Safety Instructions
Compass Deviation Card
MARPOL placard
Emergency Evacuation Plan
The latest amendments to all laws, regulations, rules and conventions, which are in force at the time of Contract Award, are to be considered as part of the Contract. Any amendment to such requirements or any new laws, regulations, rules or conventions that come into force after
Contract Award, shall be treated as a change to the CONTRACT, if not otherwise covered by these SPECIFICATIONS.
003.3.1 CERTIFICATION DISPLAY CASES
The CONTRACTOR shall provide and install on the vessel: two (2) OWNER-approved, aluminum, Plexi-glass front cases with hinged door(s) and lock provided.
One shall be installed in the pilothouse, and one in the passenger space, in OWNER-approved locations for display of the following documents:
Pilothouse:
Stability Letter
FCC Documents
Compass Deviation Card
MARPOL placard
Passenger Space:
Certificate of Inspection
Fire Safety Instructions
Emergency Evacuation Plan
Operator’s Licenses
003.3.2 CONTRACTOR-SUPPLIED CERTIFICATIONS
At delivery of the vessel, the CONTRACTOR shall provide the OWNER with the following documentation, posted in the certification display cases:
Stability Letter [CDRL 6-1]
FCC Documents [CDRL 6-2]
Fire Safety Instructions [CDRL6-3]
Compass Deviation Card [CDRL 6-4]
MARPOL placard [CDRL 6-5]
Emergency Evacuation Plan [CDRL 6-6]
004 GENERAL SPECIFICATION REQUIREMENTS
004.1 GENERAL
These TECHNICAL SPECIFICATIONS (“SPECIFICATIONS”) provide details of a Request for Proposal (RFP) for the design/build and delivery of a high-speed catamaran ferry. The vessel shall have resiliently mounted diesel engines that meet all applicable EPA Emission
Standards for newly manufactured Marine Engines of their class (in conformance with EPA
Emissions Standards “keel laying” requirements); waterjet propulsion systems;
reverse/reduction gears, and two auxiliary generators. The vessel shall conform to all of the regulations that apply to a 46 CFR Subchapter “T” Passenger Vessel with a Gross Regulatory
Tonnage not to exceed 100 GT. The vessels shall be designed and certified for “Limited
Coastwise” and “Cold Water” service. The vessel shall comply with the requirements of Buy
America, as detailed in the Terms and Conditions.
These SPECIFICATIONS are intended to give the CONTRACTOR all necessary information for the completion and submittal to the OWNER of a Design/Build Proposal. The submitted
Design/Build Proposal shall provide for delivery to the OWNER of one completely constructed, outfitted, integrated, seaworthy, and operational vessel that meets all applicable requirements of the applicable CFRs, pertinent regulatory bodies, and these
SPECIFICATIONS.
004.2 GENERAL VESSEL DESCRIPTION
The vessel described by these SPECIFICATIONS shall be a waterjet drive, diesel propelled, catamaran, Subchapter “T” passenger vessel with an arrangement of accommodations, stores, tanks, machinery, etc. suitable for a commuter service with the characteristics of the Lynn –
Boston service.
A “Z” bow configuration shall be considered to be advantageous; however, proposals are not limited to “Z” bow designs, and Contractor shall propose a bow configuration that is best suited to the Lynn service.
Passenger embarking and debarking shall be provided both over the bow and at side loading stations P&S aft giving access to the interior main deck passenger cabin. The U-shaped dock at the Lynn Terminal has a length of 60-70 feet along the sides, meaning that any side loading of the vessel would have to be positioned within the front 60-70 feet of the vessel. There are currently no provisions for bow loading at the Lynn Terminal.
Bow loading terminals are equipped with floating piers and are intended to be used with minimal height differential from dock surface to vessel deck. CONTRACTOR shall indicate in their proposal how their design will provide boarding and alighting over the bow without the use of stairs. Side loading terminals are equipped with floating piers that may require pier side modifications to meet ADA requirements. It is the responsibility of the CONTRACTOR to maintain open communication with the OWNER as to the details of bow and side loading requirements so that the vessels are outfitted to mate with pier structures and ramps in conformance with ADA regulations and the OWNER’s operational requirements.
004.3 GENERAL CHARACTERISTICS
CONTRACTOR shall be responsible for designing a vessel that is suitable for year round commuter service from Lynn to Boston. It must be suitable for use at major docks in the
Boston Harbor area, including Long Wharf, Rowes Wharf, Fan Pier, World Trade Center, and
Logan Airport as well as at Lynn’s Blossom Street Dock. While the final dimensions of the vessel shall be determined by the CONTRACTOR’s design, estimated approximate dimensions and characteristics are as follows:
Maximum Length Overall (approximate) 29 meters (95 feet)
Maximum Beam Overall (approximate) 10.4 meters (34 feet)
Maximum Draft (approximate) 1.5 meters (4.9 feet)
Top Speed: The vessel shall achieve a Trial Speed of
30 knots while carrying the Sea Trial
Deadweight detailed in Section 982.
Service Speed: 28 knots at 85% power while carrying the Sea Trial Deadweight detailed in
Section 982
Tank volumes for potable water, sewage and fuel oil shall be designed such that servicing is required no more frequently than once per day. This shall assume a maximum service day of
18 hours and 10 round trips between Lynn and Boston.
004.4 PVAG REQUIREMENTS
The vessel shall comply with all applicable accessibility laws and regulations applicable at the time of submission of proposal by the CONTRACTOR, including requirements documented in the United States Access Board (USAB) Draft Passenger Accessibility
Guidelines (PVAG) as published in the Federal Register on June 25, 2013, United States
Department of Justice (DOJ), United States Department of Transportation (DOT), Federal
Transit Administration (FTA), and Massachusetts Architectural Access Board (MAAB).
Within ninety (90) days of NTP, CONTRACTOR shall submit to OWNER for approval, arrangement drawings to demonstrate compliance with ADA requirements [CDRL 4-1].
PVAG Guideline references are provided in the following paragraphs for general guidance only. It shall be the CONTRACTOR’s responsibility to carefully review the applicability of all USAB PVAG 2013 Guidelines in respect to their proposed vessel design and to design in accordance with all applicable Sections.
ADA passenger access (PVAG Section V206) is mandatory from the main deck bow loading area and main deck side loading areas, port and starboard, to all areas of the main deck passenger spaces, including the commissary counter, ADA-accessible passenger head, aisles between seating and table sections, luggage stowage racks, etc. Accessible ADA seating, which is comparable to the exterior passenger seating available on the upper deck, shall be made available on the main deck. Aisle widths, wheelchair turning radii, table and seating configuration and construction, thresholds, door forces, etc. shall be carefully adhered to
(PVAG Sections V221 & V802).
The ADA passenger head shall be fully accessible in all respects, including, but not limited to door width and force, turning radii, toilet configuration, transfer bars, sink, mirror, towel and tissue dispensers, and baby changing table (PVAG Sections V213 & V603, V604, V606, V609).
The commissary counter shall be fully accessible (PVAG Sections V227, V308, V904).
OWNER-approved, raised text/Braille signage shall be provided for all passenger accessible spaces, do not enter rooms/areas, etc. (PVAG Sections V216, V703). All communication equipment shall be designed and operated to ensure customer service information is broadcast in dual-mode (audibly and visually) (PVAG Sections V219, V706).
All interior passenger elements not specifically addressed by PVAG, shall conform with US
DOT 49 CFR Part 37 (and Subpart C) as well as 49 CFR Part 39.
ADA Passenger Vessel Accessibility Guidelines can be viewed at:
http://www.federalregister.gov/articles/2013/06/25/2013-14367/passenger-vessels-accessibility-guidelines
The vessel design shall adequately address the requirements of PVAG Section V206 and all other applicable sections. The vessel design will provide for passenger boarding and http://www.federalregister.gov/articles/ debarking on the main deck only. It is anticipated that the design will not provide ADA access to the upper deck. The design, however, will provide for open deck passenger access on the upper deck. Therefore, a comparable open deck area must be provided for ADA access on the main deck. (Note PVAG Section V206.2.1 and applicable exceptions in sub-sections).
These SPECIFICATIONS interpret PVAG 2013 Section V206.1 as:
1. If a non-disabled passenger can access an open deck area, a disabled passenger must also be provided access to an open deck area that provides an equivalent experience.
2. If an open deck area is provided on the upper deck that is not accessible, an open deck area providing a reasonably similar experience shall be provided on the main deck.
3. If an open deck area is provided on the upper deck that provides wind screens and/or protection from the elements and/or vessel spray and is not accessible, an open deck area providing reasonably similar wind screens and/or protection from the elements and/or vessel spray shall be provided on the main deck.
4. CONTRACTOR’s design shall be subject to OWNER approval.
004.5 CONTRACTOR'S OBLIGATION
The CONTRACTOR is to provide all plant infrastructure, labor, and transportation for shipyard employees. The CONTRACTOR is responsible for vessel supplies as required during construction, tests and trials, and delivery, including, but not limited to: Fuel oil, lube oil, potable water, cooling system additives, filter cartridges, power, lighting, pressurized air, crane and forklift services, shipyard communications, line handling, wharfage, towing and shifting services. This obligation shall include equipment and power services to prevent cold weather freeze up, as well as adequate hot weather ventilation. This obligation encompasses all requirements of vessel deliveries as detailed in Section 983.
004.6 MANUFACTURERS' REPRESENTATIVES
Whether or not it is specifically stated in these SPECIFICATIONS, when it is required by the equipment manufacturer; by the specialized technical nature of the installation; for warranty purposes; or when work is outside the normal scope of the CONTRACTOR’s work force; the
CONTRACTOR is to provide the services of manufacturers' representatives. All
Manufacturer Rep services shall be at the CONTRACTOR’s cost. Assistance and expertise as is required for proper installation, on-line testing, calibration, adjustments, etc. shall receive certified Technical Support at the CONTRACTOR’s expense. At a minimum, manufacturers’ representatives shall be employed for supervision of the installation and testing of main engines, reduction gears, waterjets, generators, control systems, switchboards, and navigational electronics.
005 CORRESPONDENCE & COMMUNICATIONS
The CONTRACTOR shall provide the OWNER with a copy of all communications relating to vessel construction which the CONTRACTOR has with regulatory bodies, in particular, the USCG
Marine Safety Center (USCG/MSC) Washington, and the Local OCMI.
The CONTRACTOR shall invite the OWNER to be present during all discussions which relate to the vessel’s construction and operation which are held with the attending USCG Inspectors or other representatives of the Local OCMI.
These documents and discussions shall include, but are not limited to, the design, construction of modules, installation of equipment and machinery, testing, sea trials, delivery, and operation of the vessels.
Requirements for planning, scheduling, drawings, material specifications, instruction manuals, etc.
are detailed herein. The CONTRACTOR shall submit proposed Drawing, Correspondence, and
Communication Procedures to the OWNER for approval within 30 days after Contract Award
[CDRL 5-1].
006 DOCUMENTATION
The CONTRACTOR shall submit Proposal Drawings as an integral part of their response to the
RFP. As the design is developed, the CONTRACTOR shall submit Contract Drawings to the
OWNER for review, comments, and approval per the drawing review process described in Section
007. It is also the CONTRACTOR’s responsibility to submit drawings, as required, to the USCG
Marine Safety Center (USCG/MSC) Washington (and subsequently to the Local OCMI when directed by USCG/MSC) for review, comments, and/or approval.
006.1 PROPOSAL DRAWINGS
The CONTRACTOR’s response to the RFP shall include a Proposal Drawing Package as described in the Contract Terms & Conditions.
006.2 CONTRACT DRAWINGS
CONTRACTOR shall be responsible for preparation of standard drawing sheets with borders and title and application blocks. All drawings must be of a quality consistent with industry best practice.
All drawings shall be prepared on the OWNER's standard size sheets or as mutually agreed to by OWNER and CONTRACTOR.
All drawings shall include:
Title Blocks - All drawings shall utilize the CONTRACTOR’s standard title block in the lower right corner and the OWNER's standard application block in the upper right corner.
The OWNER has the option to add a logo beside the CONTRACTOR’s title block.
Unique Drawing Number - Drawing numbers shall include the CONTRACTOR’s assigned vessel job number, and an individual drawing designation.
Revision Level – Each drawing shall include a revision level. With each released revision of the drawing, its revision level shall increase.
Bill of Materials - All drawings shall include a Bill of Material with a numbering system for easy identification on the drawing. Bills of Material shall be carried on the drawings, or on attached sheets of the same size which shall bear the drawing number.
Piece part and assembly weights.
US equivalent materials.
Dimensions – shown in both English and metric units
English units shall be shown consistently on all drawings in either inches and fractions, or inches and decimals. Decimals shall be shown with maximum of three significant figures to the right of the decimal point as required. A one-inch mark (") shall be shown to the right of each English unit dimension.
Metric units shall be shown as millimeters and decimals. Millimeter units shall be accompanied by one blank space and the letters "mm" to the right of the figures.
Dimensions shall be shown in one of the following forms:
i. English dimensions followed by metric dimensions, enclosed in parentheses.
ii. Where longitudinal space is limited, English dimensions shall be shown as the numerators, and metric dimensions in parentheses shall be shown as the denominators, in fractional format.
iii. Where longitudinal and vertical space is limited, English dimensions only, or no dimensions, and a distinctive symbol shall be shown on the view or detail, and metric dimensions shall be shown by a key on the bottom edge of the drawing.
iv. CONTRACTOR’s standard format, if approved by the OWNER.
006.3 REQUIRED DRAWINGS AND DOCUMENTS
The detail and extent of the Contract Drawing package shall be determined by the
CONTRACTOR; however, the Contract Drawing package must include all drawings and calculation documents as required by USCG Marine Safety Center, and include at a minimum, drawings and calculations addressing the following titles. The OWNER’s primary purpose for this review of the design information, drawings, documents and data are to determine whether the requirements of this specification have been met, and the suitability of the design for its intended purpose.
The CONTRACTOR shall submit to the OWNER within 30 days of NTP, a master list of all contract drawings and documents indicating the title and revision of each, an updated version of this document shall be submitted to the OWNER monthly [CDRL6-1]:
1. General Arrangements
2. Emergency Evacuation Plan
3. Fire/Safety Plan
4. Outboard Profile
5. Tank Capacity Plan
6. Tonnage Plan & Calculations
7. Performance Calculations
8. Weight Estimate
9. Stability Calculations
10. Intact & Damaged Stability Analysis
11. Structural Drawings & Calculations
12. Machinery & Equipment Foundations
13. Hull Drawings
14. HVAC Systems & Calculations
15. Seachests
16. Ladders & Gratings
17. Rails & Bulwarks
18. Cathodic Protection
19. Doors, Hatches, Windows, Manholes
20. Superstructure
21. Mooring & Anchoring
22. Tankage Plan
23. Machinery Arrangements
24. Sea Water Systems
25. Fresh Water System
26. Sanitary System
27. Fuel Oil System
28. Lube Oil System
29. Deck Drains
30. Vents, Fills, Sounds
31. Waterjet Installations
32. Bilge System
33. Fire Main System
34. Lighting and Receptacle Plan
35. Electronic Controls
36. Main & Generator Starting Systems
37. Navigation & Communications Systems
38. Ventilation Systems
39. Shore Power
40. AC Electrical Load Analysis
41. DC Electrical Load Analysis
42. Commissary – Electrical
43. Machinery Miscellaneous
44. AC One-line Diagram
45. DC One-line Diagram
46. FMEA or USCG approved equal
47. DVTP or USCG approved equal
48. PSTP or USCG approved equal
49. Sanitary spaces
50. Accessible and Priority Seating Areas
51. Counters & Commissary
52. Boarding & debarking areas, bridging mechanisms
53. Coamings and drainage
54. Passenger Seating Arrangement
55. Switchboard Arrangement
56. Signage
006.4 INTERFERENCE & ACCESS
The elimination of all equipment interference; and the location of machinery, pumps, piping, wiring, ductwork and miscellaneous equipment; to allow proper access for operation and maintenance, is the CONTRACTOR’s responsibility. It is essential that the CONTRACTOR is aware of this obligation. The CONTRACTOR is responsible for ensuring that all installations are arranged and constructed using "good shipbuilding practice" and that they adhere to the requirements of the CFR. The CONTRACTOR and the OWNER are mutually responsible for the maintenance of ongoing communications, inspections, and approvals during construction.
A maintainability demonstration shall be required per Section 011.6 Maintainability
Demonstration.
006.5 ENGINEERING
The CONTRACTOR is responsible to provide competent and professional construction, engineering and design support to construct the vessel.
Notwithstanding any requirements of these SPECIFICATIONS, it shall be the
CONTRACTOR’s sole responsibility to determine and develop working drawings, which shall be necessary to complete the construction and delivery of the vessel. Working drawings shall be made available for timely inspection, comments, and approval by the OWNER.
Any construction details that are not shown on the Contract Plans (commonly referred to as
“Working Drawings” or “Yard Sketches”) that shall be required for fabrication and/or construction guidance shall be developed by the CONTRACTOR and shall be approved by the OWNER and, when required, by the USCG.
The CONTRACTOR shall provide sufficient and well-developed details to OWNER prior to the construction of the specific area in question. This requirement is particularly applicable to foundation sketches for all significant pieces of machinery.
When the OWNER grants approval to the CONTRACTOR for installation of a different (or equal) piece of equipment other than specified, per the terms and conditions of Section 0.2.2.5 or 0.2.2.6, the CONTRACTOR shall be responsible to revise any and all drawings, calculations, integration analyses and other documentation associated with the installation of the equipment.
006.5.1 CONTRACTOR’S REPRESENTATIVE (ENGINEERING & DESIGN)
The CONTRACTOR’s proposal, shall designate the individual who will serve as the
CONTRACTOR’s Representative for this Contract. Within ten (10) days of NTP, the
CONTRACTOR shall notify the OWNER of the CONTRACTOR Representative’s contact information [CDRL 6-2]. This individual shall serve as the contact person
(POC) between the OWNER and the CONTRACTOR in matters of engineering and design until another individual is so designated.
006.6 AS-BUILT DRAWINGS
Within 30-days following delivery of the vessel to OWNER, the CONTRACTOR shall provide the OWNER with a full set of “AS-BUILT” drawings, (10) copies in “D” size paper and (10) copies on PDF file CD for that vessel [CDRL6-3]. The OWNER will certify that these As-Built drawings will be used only for purposes of maintenance and repair on the
Contracted vessel as delivered and shall not be made available to other owners, shipyards, or contractors for the construction of subsequent vessels. The “As-Built” drawing package shall be received and approved by the OWNER prior to the release of final contract installment payment monies on the vessel delivered.
006.7 MANUALS AND MAINTENANCE INSTRUCTIONS
No later than 10 days prior to delivery of the vessel to the OWNER, the CONTRACTOR shall provide the OWNER with five (5) copies of all equipment cut sheets, engine and machinery manuals, parts manuals, and equipment information brochures [CDRL 6-4].
A complete set of maintenance instructions specifically prepared for this Contract that are to be incorporated into the Maintenance Instruction Book, including all cut sheets and diagrams, shall be submitted for review by the OWNER no later than thirty (30) days in advance of delivery of the vessel. [CDRL 6-6]
006.8 VESSEL HISTORY BOOKS
The CONTRACTOR shall furnish to the OWNER an 8.5 in. x 11 in. (216 mm x 279 mm) loose-leaf type Vessel History Book for the vessel, the pages of which shall be reproducible by black and white print process. CONTRACTOR shall confer with the OWNER to the format of this book, which shall include, but is not limited to:
1. Vessel Name, Official Number, Hull Number, and other identifying information
2. Equipment serial numbers
3. Tests & Trial reports
4. USCG Marine Safety Center communications
5. USCG Local OCMI communications
6. USCG Inspection reports
7. Regulatory Body reports and certifications
8. QA reports
9. Yard Progress Logs
10. Meeting Minutes
It shall be the responsibility of the CONTRACTOR to employ an acceptable system of configuration control in keeping individual Vessel History Books current throughout the construction and testing process.
The Vessel History Book shall be delivered incorporating serial record data as soon as practical [CDRL 6-7], but no later than prior to the start of the vessel delivery to the OWNER.
006.9 PHOTOGRAPHS
The CONTRACTOR shall provide the OWNER with a photographic record of the construction process for the vessel. General photos of progress shall be taken weekly. Photos of special events shall be taken at the time of the event. All photos shall be placed on CDs in
JPEG format, or another format approved by the OWNER, labeled, and provided to the
OWNER for inclusion in the vessel construction records [CDRL 6-8].
007 DRAWING REVIEW PROCESS
007.1 OVERVIEW
The design of the vessel shall be provided to the OWNER for review and comment through the submittal of design packages (see Section 007.2) in a formal review process.
CONTRACTOR shall develop a design package for each system on the vessel, including, but not limited to those listed in Section 007.2.2.
The review process includes three formal design review phases, listed below. The level of detail required for each design package increases as the design progresses from Conceptual
Design to Final Design.
Conceptual Design Review – provides general overview of the complete vessel and all major systems to form an agreement on the general functional, design and performance requirements within the scope of the contract.
Preliminary Design Review – one for each system or part of the vessel to review the detailed system design and allow for OWNER comment.
Final Design Review – one for each system or part of the vessel to review the detail design that addresses the OWNER’s comments from the Preliminary Design Review.
The OWNER may choose to review design submittals and respond via written correspondence.
However, for more complicated systems, it may be necessary for the CONTRACTOR to participate in design review meetings with the OWNER at which systems and concerns can be discussed in greater detail to resolve issues quickly
007.2 DESIGN PACKAGES
007.2.1 DESIGN PACKAGE CONTENTS
Design packages shall include, at a minimum:
System Functional Description which shall describe the system’s composition, functionality, design criteria, and any other information required to understand the system and its conformance to the OWNER’s specification, including any applicable regulations and standards.
Complete drawings package for the system, meeting the requirements of Section
006.2.
Electrical, pneumatic or other schematics, where applicable.
Calculations and Safety analyses, where applicable.
Any other information necessary to fully convey the concept and details of the design…