Addendum 1 follow up Answer to Bidder Delivery Question.docx

DOCX document 14 KB Posted

Attached to
Transit- LYNN FERRY COMMERCIAL
Solicitation number
BD-20-1030-0T100-0T281-46069
Issued by
Suffolk County, Massachusetts

About this file

This document is an addendum to a Request for Response (RFR) issued by the Massachusetts Department of Transportation (MassDOT) for the Lynn Ferry Commercial Specifications, COMMBUYS Number BD-20-1030-OT100-OT281-46069. The RFR was released on November 19, 2019. The addendum addresses a question from bidders regarding the delivery schedule, stating that MassDOT will accept a 24-month delivery schedule from the Notice-to-Proceed, although only those bidders proposing an 18-month delivery schedule will receive points for delivery in the RFR evaluation.

The related state and local contract opportunity is for a transit project in Massachusetts, specifically in Suffolk County and the City of Boston. The contract will be awarded by MassDOT.

View the file

Other files

File Type Posted
Lynn Ferry_Commercial Specification 2020-01-27.docx DOCX document
Addendum 9 - 2020-11-04.docx DOCX document
Ferry QA - 2020-01-27.xlsx XLSX spreadsheet
Lynn Ferry Technical Specification 2019.pdf PDF
Lynn Ferry addendum 2.pdf PDF
Addendum 1 - 2020-01-27.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFR: LYNN FERRY COMMERCIAL SPECIFICATIONS

COMMBUYS NUMBER: BD-20-1030-0T100-0T281-46069

RFR RELEASE DATE: NOVEMBER 19, 2019

Question 1: Would a 24-month delivery be acceptable under RFR Section A1.17?

Answer 1: Yes, MassDOT will accept a 24-month delivery schedule from Notice-to-Proceed. The Bidder MUST respond with their proposed delivery schedule in response to Section 3 – Manufacturing Plan. While MassDOT will accept a 24-month delivery schedule presented by Bidders as part of their Manufacturing Plan only those Bidders proposing to deliver the ferry within the 18-month delivery schedule from Notice-to-Proceed requested in Section A1.17, Delivery Conditions will receive points for delivery in the RFR Evaluation.