LR1 P1 TO CDRL_ Draft_8.3.2026.pdf

PDF 88 KB Posted

Attached to
Space Power and Reactor Capabilities (SPARC) - Sources Sought Notice
Solicitation number
80GRC026SPARC
Issued by

About this file

This is a Draft Contract Data Requirements List (CDRL) for the Lunar Reactor 1 Phase 1 Task Order dated August 8, 2026. The CDRL outlines 26 data requirements organized across multiple technical and programmatic disciplines that the contractor must deliver throughout the Phase 1 effort, which encompasses design and Engineering Test Unit (ETU) activities.

The deliverables span six primary functional areas: cybersecurity (1 requirement), regulatory and compliance planning (1), project management (3), systems engineering (8), safety and mission assurance (4), software development (6), and supply chain management (1). Deliverables are classified into three types based on criticality: Type 1 requirements are critical and include Security Requirements for Unclassified IT Resources and Flight System Requirements; Type 2 requirements include the Project Management Plan, Test Plans, and various software specifications; Type 3 requirements include detailed design documentation, CAD models, test reports, and procedural documents. Submission timing varies by requirement, with some deliverables due at proposal (Executive summaries), at kickoff or within 30 days of Award to Proceed (ATP), at Preliminary or Critical Design Reviews, and at phase completion. Several deliverables require ongoing updates on monthly or quarterly schedules, while others are submitted as-needed or upon revision. The CDRL indicates that preliminary versions of select documents are required at proposal, with baseline and final versions due at subsequent program milestones.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lunar Reactor 1 Phase 1 Task Order August 8, 2026 DRAFT Contract Data Requirements List (CDRL)

The following DRAFT CDRL summarizes Data Requirements currently anticipated as applicable for the Lunar Reactor 1 Phase 1 Task Order:

DRD Number DRD Title Type At Proposal During Phase 1 (Design + ETU) Frequency

LR1-CD-001

Security Requirements for Unclassified IT Resources 1

Executive summary B- At ATP

Update Upon Revision

LR1-NLAM-001

Plan & Deliverables for Regulatory Engagement and NSPM-20 Compliance 3 Preliminary

P-at kickoff B- 30 days after ATP

LR1-PM-001 Project Management Plan 2 Executive summary

Exec summary at proposal B-Kickoff

Update Upon Revision

LR1-PM-002 Integrated Master Schedule (IMS) 3 Executive summary

B-30 Days After ATP (at kickoff) Update Monthly

LR1-PM-003 Project Management Review Packages 3 - Each month, meet in person quarterly Monthly

LR1-SE-001 Flight System Requirements 1 Preliminary B-at SRR Updated at Major Milestones

LR1-SE-002 Test Plans for ETU 2 - P - ATP +6mo

B - TRR

LR1-SE-003 Test Reports 3 - F - End of Phase within 30 Days of Test Completion

F-Within 30 Days of Test

Completion

LR1-SE-004

30% Flight Design CAD, Models, and Associated Lists 3 - End of Phase

LR1-SE-005 ETU Design Description Document 3 - End of Phase

LR1-SE-006

ETU CAD and Drawings, software (source code) 3 - End of Phase

LR1-SE-007 ETU User Manual 3 - End of Phase Updated at Major Milestones

LR1-SE-008 Final Report 2 - End of Phase LR1-SMA-001 Request for Deviation or Waiver 1 - as needed

LR1-SMA-002 Safety and Mission Assurance Plan 3 Executive summary B- Kickoff

LR1-SMA-003

Failure Modes and Effects and Critical Items List (FMEA/CIL) 2 - P-End of Phase U

LR1-SMA-004

Preliminary Hazards List and Analysis (PHL/PHA) 2 - P-End of Phase U

LR1-SW-001 Software Requirements Specification 1 -

P-SRR

B-End of Phase LR1-SW-002 Master Data Dictionary 2 - P-End of Phase

LR1-SW-003 Software Management and Development Plan 2 - P-60 Days After ATP

LR1-SW-004 Software Verification and Validation Plan 2 - P-60 Days After ATP LR1-SW-005 Software Release 3 - P-End of Phase LR1-SW-006 Software Verification Procedure 3 - B-end f phase

LR1-SC-001 Supply Chain Assessment Report 3 Preliminary B-w/final report Updates included in PMR charts