LR1 P1 TO CDRL_ Draft_8.3.2026.pdf
PDF 88 KB Posted
- Solicitation number
- 80GRC026SPARC
About this file
This is a Draft Contract Data Requirements List (CDRL) for the Lunar Reactor 1 Phase 1 Task Order dated August 8, 2026. The CDRL outlines 26 data requirements organized across multiple technical and programmatic disciplines that the contractor must deliver throughout the Phase 1 effort, which encompasses design and Engineering Test Unit (ETU) activities.
The deliverables span six primary functional areas: cybersecurity (1 requirement), regulatory and compliance planning (1), project management (3), systems engineering (8), safety and mission assurance (4), software development (6), and supply chain management (1). Deliverables are classified into three types based on criticality: Type 1 requirements are critical and include Security Requirements for Unclassified IT Resources and Flight System Requirements; Type 2 requirements include the Project Management Plan, Test Plans, and various software specifications; Type 3 requirements include detailed design documentation, CAD models, test reports, and procedural documents. Submission timing varies by requirement, with some deliverables due at proposal (Executive summaries), at kickoff or within 30 days of Award to Proceed (ATP), at Preliminary or Critical Design Reviews, and at phase completion. Several deliverables require ongoing updates on monthly or quarterly schedules, while others are submitted as-needed or upon revision. The CDRL indicates that preliminary versions of select documents are required at proposal, with baseline and final versions due at subsequent program milestones.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPARC Listing of Respondents_8-25-26.pdf | ||
| LR1 P1 TO SOW_Draft Rev 5_8.3.2026.pdf | ||
| SPARC SOW_Draft Rev 1_8.3.2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lunar Reactor 1 Phase 1 Task Order August 8, 2026 DRAFT Contract Data Requirements List (CDRL)
The following DRAFT CDRL summarizes Data Requirements currently anticipated as applicable for the Lunar Reactor 1 Phase 1 Task Order:
DRD Number DRD Title Type At Proposal During Phase 1 (Design + ETU) Frequency
LR1-CD-001
Security Requirements for Unclassified IT Resources 1
Executive summary B- At ATP
Update Upon Revision
LR1-NLAM-001
Plan & Deliverables for Regulatory Engagement and NSPM-20 Compliance 3 Preliminary
P-at kickoff B- 30 days after ATP
LR1-PM-001 Project Management Plan 2 Executive summary
Exec summary at proposal B-Kickoff
Update Upon Revision
LR1-PM-002 Integrated Master Schedule (IMS) 3 Executive summary
B-30 Days After ATP (at kickoff) Update Monthly
LR1-PM-003 Project Management Review Packages 3 - Each month, meet in person quarterly Monthly
LR1-SE-001 Flight System Requirements 1 Preliminary B-at SRR Updated at Major Milestones
LR1-SE-002 Test Plans for ETU 2 - P - ATP +6mo
B - TRR
LR1-SE-003 Test Reports 3 - F - End of Phase within 30 Days of Test Completion
F-Within 30 Days of Test
Completion
LR1-SE-004
30% Flight Design CAD, Models, and Associated Lists 3 - End of Phase
LR1-SE-005 ETU Design Description Document 3 - End of Phase
LR1-SE-006
ETU CAD and Drawings, software (source code) 3 - End of Phase
LR1-SE-007 ETU User Manual 3 - End of Phase Updated at Major Milestones
LR1-SE-008 Final Report 2 - End of Phase LR1-SMA-001 Request for Deviation or Waiver 1 - as needed
LR1-SMA-002 Safety and Mission Assurance Plan 3 Executive summary B- Kickoff
LR1-SMA-003
Failure Modes and Effects and Critical Items List (FMEA/CIL) 2 - P-End of Phase U
LR1-SMA-004
Preliminary Hazards List and Analysis (PHL/PHA) 2 - P-End of Phase U
LR1-SW-001 Software Requirements Specification 1 -
P-SRR
B-End of Phase LR1-SW-002 Master Data Dictionary 2 - P-End of Phase
LR1-SW-003 Software Management and Development Plan 2 - P-60 Days After ATP
LR1-SW-004 Software Verification and Validation Plan 2 - P-60 Days After ATP LR1-SW-005 Software Release 3 - P-End of Phase LR1-SW-006 Software Verification Procedure 3 - B-end f phase
LR1-SC-001 Supply Chain Assessment Report 3 Preliminary B-w/final report Updates included in PMR charts