Liquidated Damages Memo_Replace Steam lines.docx
DOCX document 20 KB Posted
- Attached to
- Z1DA--LEBANON - ALTOONA MATOC HOLDERS ONLY 595-21-103 Replace Steam, Condensate and Vaults Phase 1
- Solicitation number
- 36C24426R0090
About this file
This is a Liquidated Damages Formulation Memo for Solicitation Number 36C244, Project 595-21-103, Replace Steam, Condensate, and Vaults Phase 1, at the Lebanon-Altoona VAMC under VISN 4 of the Department of Veterans Affairs. The memo establishes a daily liquidated damages rate of $725.00 per calendar day for contractor delays beyond the scheduled completion date.
The liquidated damages calculation is derived from two cost categories: VISN 4 Contracting and Legal reviews ($384.30 per day) and Facility Engineering oversight including a Projects Supervisor, Project Engineer, and Construction Control Representative ($339.97 per day). Wage rates are based on 2022 General Schedule Locality Pay for Pittsburgh and 2025 rates for Harrisburg with Special Rate Table 773 adjustments. The memo specifies that liquidated damages are compensatory in nature and that the government retains the right to pursue actual damages separately from those assessed for missed completion dates, in accordance with FAR 36.206.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Liquidation Damages Formulation Memo
Solicitation Number: 36C244
Project: Replace Steam, Condensate, and Vaults Phase 1 Project Number: 595-21-103
1. Estimated liquidated damages for VISN 4 Contracting, and Legal reviews per day of inexcusable delay (wage rates based upon the General Schedule Locality Pay Table 2022-PIT):
| CLASSIFICATION |
| GRADE |
| RATE |
| HOURS TOTAL |
| TOTAL RATE |
| Contracting Officer Supervisor |
| GS-13 / 5 |
| $59.17 |
| 2 Hours |
| $118.34 |
| Contracting Officer |
| GS-12 / 5 |
| $49.76 |
| 4 Hours |
| $199.04 |
| Legal Officer |
| GS-14 / 5 |
| $69.92 |
| 1 Hour |
| $66.92 |
TOTAL PER DAY
$384.30
2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay (wage rates based upon the General Schedule Locality Pay Table 2025-HB and Special Rate Table 773):
| CLASSIFICATION |
| GRADE |
| RATE |
| HOURS TOTAL |
| TOTAL RATE |
| Projects Supervisor |
| GS-13 / 5 |
| $64.75 |
| 1 Hours |
| $64.75 |
| Project Engineer |
| GS-12 / 5 |
| $55.69 |
| 2 Hours |
| $111.38 |
| Construction Control Rep |
| GS-11 / 5 |
| $40.96 |
| 4 Hours |
| $163.84 |
TOTAL PER DAY
$339.97
Grand Total Per Day
$724.27 round up to $725.00
3. The Contractor shall pay liquidated damages to the Government in the amount of $725.00 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.
4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.