Liquidated Damages Memo_Replace Steam lines.docx

DOCX document 20 KB Posted

Attached to
Z1DA--LEBANON - ALTOONA MATOC HOLDERS ONLY 595-21-103 Replace Steam, Condensate and Vaults Phase 1
Solicitation number
36C24426R0090
Issued by

About this file

This is a Liquidated Damages Formulation Memo for Solicitation Number 36C244, Project 595-21-103, Replace Steam, Condensate, and Vaults Phase 1, at the Lebanon-Altoona VAMC under VISN 4 of the Department of Veterans Affairs. The memo establishes a daily liquidated damages rate of $725.00 per calendar day for contractor delays beyond the scheduled completion date.

The liquidated damages calculation is derived from two cost categories: VISN 4 Contracting and Legal reviews ($384.30 per day) and Facility Engineering oversight including a Projects Supervisor, Project Engineer, and Construction Control Representative ($339.97 per day). Wage rates are based on 2022 General Schedule Locality Pay for Pittsburgh and 2025 rates for Harrisburg with Special Rate Table 773 adjustments. The memo specifies that liquidated damages are compensatory in nature and that the government retains the right to pursue actual damages separately from those assessed for missed completion dates, in accordance with FAR 36.206.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Liquidation Damages Formulation Memo

Solicitation Number: 36C244

Project: Replace Steam, Condensate, and Vaults Phase 1 Project Number: 595-21-103

1. Estimated liquidated damages for VISN 4 Contracting, and Legal reviews per day of inexcusable delay (wage rates based upon the General Schedule Locality Pay Table 2022-PIT):

CLASSIFICATION
GRADE
RATE
HOURS TOTAL
TOTAL RATE
Contracting Officer Supervisor
GS-13 / 5
$59.17
2 Hours
$118.34
Contracting Officer
GS-12 / 5
$49.76
4 Hours
$199.04
Legal Officer
GS-14 / 5
$69.92
1 Hour
$66.92

TOTAL PER DAY

$384.30

2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay (wage rates based upon the General Schedule Locality Pay Table 2025-HB and Special Rate Table 773):

CLASSIFICATION
GRADE
RATE
HOURS TOTAL
TOTAL RATE
Projects Supervisor
GS-13 / 5
$64.75
1 Hours
$64.75
Project Engineer
GS-12 / 5
$55.69
2 Hours
$111.38
Construction Control Rep
GS-11 / 5
$40.96
4 Hours
$163.84

TOTAL PER DAY

$339.97

Grand Total Per Day

$724.27 round up to $725.00

3. The Contractor shall pay liquidated damages to the Government in the amount of $725.00 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.

4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.