About this file
This document is a Liquidated Damages Calculator for the Pinellas County FY 2026 Pavement Preservation Package 3 project (PID No. 25-0072-REQ), which involves a roadway improvement initiative targeting five neighborhood locations. The project has a planned construction duration of 210 calendar days, with an engineer's estimated probable construction cost of $5,021,370.74. The liquidated damages calculation provides a framework for assessing financial penalties in the event of project delays.
The liquidated damages are calculated at $1,434.66 per day, which includes $1,356.00 for construction administration/inspection and $78.66 for project management hourly rates. The document breaks down various potential cost elements such as construction administration, project overhead, and staff-related expenses, though most line items are marked as zero or not applicable. The calculator serves as a financial risk mitigation tool to ensure project timelines are met and to compensate the county for potential indirect costs resulting from project delays.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Enter Design Consultant's total post design fee -$ Enter Construction Administrator's total Fee N/A Duration of Construction (calendar days) 210 Enter Total Project Enclosed Square Footage (if applicable) N/A Enter Total Daily Department PM/APM Full time Equivalents N/A Engineer's Estimate of probable construction cost 5,021,370.74$
Elements for Liquidated Damages Determination:
Design Consultant Fees 0 Total post design fee divided by construction duration *3%
Construction Administration/Inspection 1,356.00$ Daily combined burdened rate for CA staff + Consultant CEI
Project Manager/Assistant Project Manager 78.66$ (1 hour/day burdened rate) Department Project Overhead LD Schedule Agency Administrative Costs -$ Temporary Heat/Cooling/Electric -$ Temporary Storage of Owner Provided FFE -$ Rental/Lease of Facilites for Staff, and/or Clients -$ Lost revenues -$ Lost grant revenues -$ Interest -$ Rental / moving expenses -$ Cost for Insurance Other Total Liquidated Damages Amount per day 1,434.66$
Prepared by:
Edit Highlighted Areas
LIQUIDATED DAMAGES CALCULATOR
Project Name: FY 2026 Pavement Preservation Package 3
PID No.: 25-0072-REQ