This document is a comprehensive set of technical specifications for the Ralph Brennan Water Treatment Plant (WTP) Lime Sludge Handling Improvements Project, issued by the City of Daytona Beach, Florida. The project involves constructing four lime sludge drying beds, installing pressure piping from the drying beds to the thickener sludge pump station, building a pole barn for storage of dewatered lime sludge, constructing lights around the pole barn, and installing a gravity drain line from sumps to the pump station. The project will be competitively bid through an online procurement platform, with a non-mandatory pre-bid conference and an online bid opening. Bidders must submit questions through the platform by the specified deadline, and all bid responses must be submitted electronically through the City's procurement portal.
The technical specifications provide detailed requirements for concrete work, electrical systems, metal fabrication, and other critical project components. The project is funded by the City of Daytona Beach and will be completed at the Ralph Brennan Water Treatment Plant located at 3651 LPGA Blvd in Daytona Beach. Bidders are required to comply with local, state, and federal regulations, including building codes, electrical standards, and environmental requirements. The specifications outline precise technical requirements for materials, installation methods, testing protocols, and quality assurance measures. Bid responses will be held for evaluation for up to 60 days, and the project aims to improve the facility's sludge handling and storage capabilities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Documents
City of Daytona Beach
Ralph Brennan WTP
Lime Sludge Handling Improvements Project
100% Submittal
April 2025
City of Daytona Beach
Technical Specifications
44263-006 TOC-1 CODB RALPH BRENNAN WTP
LIME SLUDGE HANDLING IMPROVEMENTS
CITY OF DAYTONA BEACH
100% SUBMITTAL
RALPH BRENNAN WATER TREATMENT PLAN
LIME SLUDGE HANDLING IMPROVEMENTS
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 14 00 Coordination with Owner’s Operations
01 20 00 Measurement and Payment
01 25 00 Substitution Procedures
01 26 00 Contract Modification Procedures
01 29 76 Progress Payment Procedures
01 31 19 Project Meetings
01 32 00 Construction Progress Schedule
01 33 00 Submittal Procedures
01 42 00 References
01 52 00 Construction Facilities
01 55 00 Contractor Access and Parking
01 57 00 Temporary Controls
01 61 00 Product Requirements and Options
01 65 00 Product Delivery Requirements
01 66 00 Product Storage and Protection Requirements
01 71 33 Protection of Work and Property
01 73 00 Demolition and Execution of Work
01 74 00 Cleaning and Waste Management
01 75 00 Checkout and Startup Procedures
01 77 19 Closeout Requirements
01 78 23 Operation and Maintenance Data
01 78 39 Project Record Documents
01 78 43 Spare Parts and Extra Material
DIVISION 02 – EXISTING CONDITIONS
02 32 00 Subsurface Exploration
44263-006 TOC-2 CODB RALPH BRENNAN WTP
DIVISION 03 – CONCRETE
03 11 00 Concrete Formwork
03 15 16 Concrete Joints and Joint Accessories
03 21 00 Concrete Reinforcement
03 30 00 Cast-in-Place Concrete
03 35 00 Concrete Finishes
03 60 00 Grout
03 74 00 Modifications and Repair to Concrete
DIVISION 05 – METALS
05 50 00 Miscellaneous Metal
DIVISION 09 – FINISHES
09 90 00 Painting
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 19 Pre-Engineered Metal Building
DIVISION 26 – ELECTRICAL
26 05 00 Basic Electrical Requirements
26 05 19 Low-Voltage Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33.13 Conduit for Electrical Systems
26 05 33.16 Boxes for Electrical Systems
26 27 26 Wiring Devices
26 41 00 Facility Lightning Protection
26 50 00 Lighting
DIVISION 31 – EARTHWORK
31 00 01 Earthwork
31 05 16 Aggregate Materials
31 11 00 Clearing and Grubbing
31 12 00 Site Preparation
31 23 00 Excavation and Backfill for Utilities
31 23 19 Dewatering
31 25 00 Erosion and Sedimentation Control – Stormwater Pollution Prevention
31 31 00 Soil Preparation
44263-006 TOC-3 CODB RALPH BRENNAN WTP
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 00 Surface Restoration
32 90 00 Final Grading and Landscaping
32 92 01 Sodding
DIVISION 40 – PROCESS INTERCONNECTIONS
40 05 00 Basic Mechanical Requirements
40 05 19 Ductile Iron Pipe
40 05 31 Polyvinyl Chloride (PVC) Pressure Pipe Fittings
40 05 51 Valves, General
40 05 61 Gate Valves (Including Knife Gate Valves)
40 05 62 Plug Valves
40 06 20 Process Pipe, Valve, and Gate Schedules
END OF SECTION
44263-006 TOC-4 CODB RALPH BRENNAN WTP
THIS PAGE IS INTENTIONALLY LEFT BLANK
DIVISION 1
General Requirements
44263-006 01 11 00-1 CODB RALPH BRENNAN WTP
SECTION 01 11 00
SUMMARY OF WORK
PART 1 – GENERAL
1.01 SUMMARY
A. Section includes:
1. Summary
2. Location and Description of Work
3. Construction Contracts, This Project
4. Construction Contracts, Other Projects
5. Work by Others
6. Work by Owner
7. Owner Furnished Equipment and Materials
8. Owner Assigned Procurement Contracts
9. Owner Pre-selected Equipment and Materials
10. Sequence and Progress of Work
11. Contractor’s Use of Site
12. Easements and Rights-of-Way
13. Notices to Owners and Authorities of Properties Adjacent to the Work
14. Salvage of Equipment and Materials
15. Partial Utilization by Owner
1.02 LOCATION AND DESCRIPTION OF WORK
A. The Work is located at the following Site:
1. Ralph Brennan Water Treatment Plant, 3651 LPGA Blvd., Daytona Beach, FL, 32124
44263-006 01 11 00-2 CODB RALPH BRENNAN WTP
B. The Work to be performed under this Contract includes, but is not limited to, constructing the Work described below and all appurtenances related to the Work. The Work shall be as follows:
1. Construction of four lime sludge drying beds
2. Construction of pressure piping from the drying beds to tie-in at the 4-inch MJ plug at the thickener sludge pump station
3. Construction of a pole barn for storage of dewatered lime sludge
4. Construction of lights around the pole barn
5. Gravity drain line from sumps to pump station
1.03 CONSTRUCTION CONTRACTS, THIS PROJECT
A. The Contracts under which the Project will be constructed are:
1. Work specified in Divisions 01 through 40 (inclusive) of the Specifications.
2. Work shown on sheets 1 through 28 (inclusive) of the Drawings.
1.04 CONSTRUCTION CONTRACTS, OTHER PROJECTS
A. Construction at the Westside Regional WRF headworks
1.05 WORK BY OTHERS (NOT USED)
1.06 WORK BY OWNER (NOT USED)
1.07 OWNER-FURNISHED EQUIPMENT AND MATERIALS (NOT USED)
1.08 OWNER ASSIGNED PROCUREMENT DOCUMENTS (NOT USED)
1.09 OWNER PRE-SELECTED EQUIPMENT AND MATERIALS (NOT USED)
1.10 SEQUENCE AND PROGRESS OF WORK
A. Requirements for sequencing and coordinating with Owner’s operations, including maintenance of plant operations during construction, and requirements for tie-ins and shutdowns, are in Section 01 14 00 − Coordination with Owner’s Operations.
1.11 CONTRACTOR’S USE OF SITE
A. Contractors’ use of the Site shall be confined to the areas shown. Contractors shall share use of the Site with other contractors and others specified in this Section.
44263-006 01 11 00-3 CODB RALPH BRENNAN WTP
B. Contractor shall move stored products that interfere with operations of Owner, other contractors, or others performing work for Owner.
1.12 EASEMENTS AND RIGHTS-OF-WAY
A. Easements and rights-of-way will be provided by Owner in accordance with the General
Conditions. Confine construction operations to within Owner’s property, public rights-of-way, easements obtained by Owner, and the limits shown. Use care in placing construction tools, equipment, excavated materials, and products to be incorporated into the Work to avoid damaging property and interfering with traffic. Do not enter private property outside the construction limits without permission from the owner of the property.
1.13 NOTICES TO OWNERS AND AUTHORITIES OF PROPERTIES ADJACENT TO THE
WORK
A. Notify owners of adjacent property and utilities when execution of the Work may affect their property, facilities, or use of property.
B. When it is necessary to temporarily obstruct access to property, or when utility service connection will be interrupted, provide notices sufficiently in advance to enable affected persons to provide for their needs. Conform notices to Laws and Regulations and, whether delivered orally or in writing, include appropriate information concerning the interruption and instructions on how to limit inconvenience caused.
C. Notify utility owners and other concerned entities at least 48 hours prior to cutting or closing streets or other traffic areas or excavating near Underground Facilities or exposed utilities.
1.14 SALVAGE OF EQUIPMENT AND MATERIALS (NOT USED)
1.15 PARTIAL UTILIZATION BY OWNER
A. Owner reserves the right to enter and use portions of the Work prior to Certificate of
Substantial Completion is issued by Engineer.
B. Owner shall be responsible to prevent premature connections by private and public parties, persons or groups of persons, before Engineer issues Certificate of Substantial
Completion for the portion of Work being partially utilized by Owner.
C. Contractor shall cooperate with Owner, Owner’s agents, and Engineer to accelerate completion of Work designed for partial utilization by Owner in accordance with
Contractor’s progress schedule.
44263-006 01 11 00-4 CODB RALPH BRENNAN WTP
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
44263-006 01 14 00-1 CODB RALPH BRENNAN WTP
SECTION 01 14 00
COORDINATION WITH OWNER’S OPERATIONS
PART 1 – GENERAL
1.01 SUMMARY
A. Section includes:
1. Requirements for coordinating with Owner’s operations during the Work and included requirements for tie-ins and shutdowns necessary to complete the Work without impact on Owner’s operations except as allowed in this Section.
2. Contractor shall provide labor, materials, tools, equipment and incidentals shown, specified and required to coordinate with Owner’s operations during the Work.
B. General Requirements:
1. Except for shutdowns specified in this Section, perform the Work such that Owner’s facility remains in continuous satisfactory operation during the Project. Schedule and conduct the Work such that the Work does not: impede Owner’s production or processes, create potential hazards to operating equipment and personnel, reduce the quality of the facility’s products or effluent, or cause odors or other nuisances.
2. Work not specifically covered in this Section or in referenced Sections may, in general, be completed at any time during regular working hours in accordance with the General Conditions and Supplementary Conditions, subject to the requirements in this Section.
3. Contractor has the option of providing additional temporary facilities that can eliminate or mitigate a constraint without additional cost to Owner, provided such additional temporary facilities: do not present hazards to the public, personnel, structures, and equipment; that such additional temporary facilities do not adversely affect Owner’s ability to comply with Laws and Regulations, permits, and operating requirements; that such temporary facilities do not generate or foster the generation of odors and other nuisances; and that requirements of the Contract Documents are fulfilled.
4. Coordinate shutdowns with Owner and Engineer. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on Owner’s operations and processes.
5. Do not shut off or disconnect existing operating systems, unless accepted by
Engineer in writing. Operation of existing equipment will be by Owner unless otherwise specified or indicated. Where necessary for the Work, Contractor shall seal or bulkhead Owner-operated gates and valves to prevent leakage that may
44263-006 01 14 00-2 CODB RALPH BRENNAN WTP
affect the Work, Owner’s operations, or both. Provide temporary watertight plugs, bulkheads, and line stops as required. After completing the Work, remove seals, plugs, bulkhead, and line stops to satisfaction of Engineer.
C. Continuous Treatment Provision:
1. Federal regulations prohibit bypassing of untreated or partially treated wastewater or sewage during construction Work.
2. Contractor shall provide labor, equipment, materials, and incidentals to provide continuous treatment to the level prior to construction Work.
3. Contractor shall be responsible for providing temporary pumping facilities, systems, piping, valve, appurtenances, equipment, materials, and temporary utilities necessary to complete the Work without treatment bypassing.
D. Related Sections:
1. Section 01 11 00 − Summary of Work
2. Section 01 25 00 − Substitution Procedures
3. Section 01 73 00 − Demolition and Execution of Work
1.02 REFERENCES
A. Definitions: A “shutdown” is when a portion of the normal operation of Owner’s facility, whether equipment, systems, piping, or conduit, has to be temporarily suspended or taken out of service to perform the Work.
1.03 ADMINISTRATIVE REQUIREMENTS
A. Coordination:
1. Review installation procedures under other Specification sections and coordinate
Work that must be performed with or before the Work specified in this Section.
2. Notify other contractors in advance of Work requiring coordination with Owner’s operations, to provide other contractors sufficient time for work included in their contracts that must be installed with or before Work specified in this Section.
3. When possible, combine multiple tie-ins into a single shutdown to minimize impacts on Owner’s operations and processes.
B. Pre-Shutdown Meetings: Contractor shall schedule and conduct meeting with Owner and
Engineer prior to scheduling shutdown
44263-006 01 14 00-3 CODB RALPH BRENNAN WTP
C. Sequencing:
1. Perform the Work in the specified sequence. Certain phases or stages of the Work may require working 24-hour days or work during hours outside of regular working hours. Work may be accelerated from a later stage to an earlier stage if Owner’s operations are not adversely affected by proposed sequence change, with
Engineer’s acceptance. Stages specified in this Section are sequential in performance of the Work.
D. Scheduling:
1. Work that may interrupt normal operations shall be accomplished at times convenient to Owner.
2. Furnish at the Site, in close proximity to the shutdown and tie-in work areas, tools, equipment, spare parts and materials, both temporary and permanent, necessary to successfully complete the shutdown. Complete to the extent possible, prefabrication of piping and other assemblies prior to the associated shutdown Demonstrate to
Engineer’s satisfaction that Contractor has complied with these requirements before commencing the shutdown.
3. If Contractor’s operations cause an unscheduled interruption of Owner’s operations, immediately re-establish satisfactory operation for Owner.
4. Unscheduled shutdowns or interruptions of continued safe and satisfactory operation of Owner’s facilities that result in fines or penalties by authorities having jurisdiction shall be paid solely by Contractor if, in Engineer’s opinion, Contractor did not conform to the requirements of the Contract Documents, or was negligent in the
Work, or did not exercise proper precautions in conducting the Work.
5. Work requiring service interruptions for tie-ins shall be performed during scheduled shutdowns.
6. Temporary, short-term shutdowns of smaller piping, conduits, equipment, and systems may be required. Coordinate requirements for such shutdowns with
Engineer and Owner.
1.04 SUBMITTALS
A. Action/Informational Submittals:
1. Substitute Sequence Submittal: When deviation from specified sequence is proposed, provide submittal explaining in detail the proposed sequence change and its effects, including evidence that Owner’s operations will not be adversely affected by proposed change. List benefits of proposed sequence change, including benefits to Progress Schedule. Submit in accordance with Section 01 25 00 − Substitution
Procedures.
44263-006 01 14 00-4 CODB RALPH BRENNAN WTP
2. Shutdown Planning Submittal:
a. For each shutdown, submit an inventory of labor and materials required to perform the shutdown and tie-in tasks, an estimate of time required to accomplish the complete shutdown including time for Owner to take down and start up existing equipment, systems, or conduits, and written description of steps required to complete the Work associated with the shutdown.
b. Furnish submittal to Engineer at least thirty (30) days prior to proposed shutdown start date. Do not start shutdown until obtaining Engineer’s acceptance of shutdown planning submittal.
3. Shutdown Notification: After acceptance of shutdown planning submittal and prior to starting the shutdown, provide written notification to Owner and Engineer of date and time each shutdown is to start. Provide notification at least 72 hours in advance of each shutdown.
1.05 SITE CONDITIONS
A. General Constraints: Specified in the Contract Documents are the sequence and shutdown durations, where applicable, for Owner’s equipment, systems, and conduits that are to be taken out of service temporarily for the Work. New equipment, materials, and systems may be used by Owner after the specified field quality controls and testing are successfully completed and the materials or equipment are Substantially Complete.
B. The following constraints apply to coordination with Owner’s operations:
1. Operational Access: Owner’s personnel shall have access to equipment and areas that remain in operation.
2. Schedule and perform equipment and system start-ups for Monday through
Thursday. Equipment and systems shall not be placed into operation on Friday, Saturday, and Sunday without prior approval of Owner.
3. Dead End Valves or Pipe: Provide blind flanges, watertight bulkheads, or valves at temporary and permanent terminuses of pipes and conduits. Blind flanges and bulkheads shall be suitable for the service and braced and blocked, as required, or otherwise restrained as directed by Engineer. Temporary valves shall be suitable for their associated service. Where valve is provided at permanent terminus of pipe or conduit, also provide on downstream side of valve a blind flange with drain/flushing connection.
4. Owner will assist Contractor in dewatering process tanks, basins, conduits, and other work areas to be dewatered for shutdowns. Maintain clean and dry work area by pumping and properly disposing of fluid that accumulates in work areas.
44263-006 01 14 00-5 CODB RALPH BRENNAN WTP
5. Draining and Cleaning of Conduits, Tanks, and Basins: Unless otherwise specified, Owner will dewater process tanks and basins at beginning of each shutdown. Owner will flush and wash down tanks and basins with plant non-potable water. Draining and cleaning conducted by Contractor shall be as specified below:
a. Contractor shall remove liquids and solids and dispose of them at appropriate location at the Site as directed by Engineer. Contents of pipes, tanks, basins, and conduits undergoing modifications shall be transferred to existing process tanks or conduits at the Site with capacity sufficient to accept such discharges, using hoses, piping, pumps, or other means provided by Contractor.
Discharge of fluids across floors is not allowed.
b. If drainage point is not available on the piping or conduit to be drained, provide a wet tap using tapping saddle and valve or other method approved by
Engineer. Uncontrolled spillage of pipe’s or conduit’s contents is not allowed.
c. Spillage shall be brought to Engineer’s attention immediately, both verbally and in writing, and reported in accordance with Laws and Regulations.
Contractor shall wash down spillage to floor drains or sumps and flush the system to prevent clogging and odors. If spillage is not suitable for discharge to the drainage system, such as chemical spills, as determined by Engineer, Contractor shall remove spillage by other method, such as vactor truck, acceptable to Engineer.
6. Electrical, Control, Communication, and Monitoring Systems:
a. Owner’s existing SCADA system and fiber optic network shall remain functional, subject to the constraints herein.
b. Unless Contractor elects to use existing fiber and/or temporary fiber, at his/her discretion, at least one communication path through the new dual redundant fiber optic ring to all communication points shall be in place at all times until substantial completion.
c. Each process area shall be permitted to have a single, non-concurrent, scheduled outage for the purpose of making PLC panel hardware modifications, loading the associated PLC logic, and its field testing/demonstration. Field testing and demonstration shall immediately follow modifications in an effort to keep scheduled shutdowns as short as possible. A 14-day day period of no SCADA outage shall proceed each scheduled shutdown.
1.06 SUGGESTED SEQUENCE OF WORK
A. Perform the Work in the specified sequence or as otherwise approved by Engineer.
Certain phases or stages of the Work may require working 24-hour days or work during hours outside of regular working hours. Work may be accelerated from a later stage to an
44263-006 01 14 00-6 CODB RALPH BRENNAN WTP
earlier stage if Owner’s operations are not adversely affected by proposed sequence change, and with Engineer’s acceptance. Stages specified in this Section are sequence-dependent.
1. Stage 1: Demolition of existing drying beds, clean up, and demolition of the metal building.
2. Stage 2: Construction of drain piping from the Dewatered Sludge Storage Building and the Drying Beds back to the Thickening Sludge Pump Station wet well.
3. Stage 3: Construction of pipeline from 4” sludge thickener discharge piping to the proposed drying beds. Construction of electrical conduits to the Dewatered Sludge
Storage Building.
4. Stage 4: Construction of drying beds. Construction of the Dewatered Sludge Storage
Building.
5. Stage 5: Tie in to the 4” sludge thickener. Tie in at the Thickening Sludge Pump
Station.
6. Stage 6: Construction of stormwater improvements and site restoration.
1.07 TIE-INS
A. Table 01 14 00-A in this Section lists connections by Contractor to existing facilities. Table
01 14 00-A may not include all tie-ins required for the Work; Contractor shall perform tie-ins required to complete the Work. For tie-ins not included in Table 01 14 00-A, obtain requirements for tie-ins from Engineer.
1.08 SHUTDOWNS
A. Pump stations will need to be shut down during tie-ins.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.01 GENERAL
A. In addition to requirements of this Section, conform to requirements of Section 01 73 00 −
Demolition and Execution of Work.
B. Refer to Table 01 14 00-B in this Section for schedule of process equipment and service lines out-of-service during shutdown.
44263-006 01 14 00-7 CODB RALPH BRENNAN WTP
C. Refer to Table 01 14 00-B in this Section for schedule of process equipment in operation during shutdown.
D. Refer to Table 01 14 00-B in this Section for tie-ins required during each shutdown. Refer to Table 01 14 00-A in this Section for detailed tie-in schedule.
E. Refer to Table 01 14 00-B in this Section for duration of each shutdown.
3.02 DETAILED SHUTDOWN REQUIREMENTS:
A. Prior to Typical Shutdown:
1. Obtain Engineer’s acceptance of proposed shutdown planning submittal and shutdown notification submittal.
2. Submittal and approval of all shop drawings required.
3. Coordinate with plant operations on timing of shutdown and provide required notice to Owner.
4. Bring necessary piping, couplings, valves, equipment, and appurtenances to the work areas.
5. Assist Owner in preparing to take equipment, tanks, basins, and conduits temporarily out of service.
6. Coordinate other tie-ins to be performed simultaneously.
7. Install and ensure functionality of temporary systems as applicable.
B. During Typical Shutdown:
1. Owner will dewater tanks and basins.
2. Remove existing equipment, piping, and accessories as required.
3. Verify operation of new equipment, materials, and systems.
4. Following approval from Engineer, return equipment and system to operation with
Owner.
C. Following Typical Shutdown:
1. Verify functionality of equipment and system.
2. Verify operation of new equipment and systems, and verify that joints in piping are watertight or gastight as applicable.
3. Repair joints that are not watertight or gastight as applicable.
44263-006 01 14 00-8 CODB RALPH BRENNAN WTP
4. Remove temporary systems as applicable.
3.03 PROPOSED SHUTDOWN SEQUENCE
A. Shutdown No. 1 Description: Thickener Sludge Pump Station
1. General:
a. Impact on Other Equipment and Processes: All equipment upstream of the
Thickener Pump Station will need to be paused while final tie-in to the wet well is being performed. Contractor shall coordinate timing with Owner to minimize impacts to plant operations.
b. Location: Thickener Sludge Pump Station
2. Prior to Shutdown:
a. Obtain Engineer’s acceptance of proposed shutdown planning submittal and shutdown notification submittal.
b. Assist Owner in preparing to take equipment, tanks, basins, and conduits temporarily out of service.
c. Specific requirements: _______________________.
3. During Shutdown:
a. Installation of remaining Work required.
b. Perform tie-ins shown on Table 01 14 00-B.
c. Verify functionality of equipment and system.
B. Shutdown No. 1 Description: Central Pump Station
1. General:
a. Impact on Other Equipment and Processes: All equipment upstream of the
Thickener Pump Station
b. Location: Thickener Sludge Pump Station
2. Prior to Shutdown:
a. Obtain Engineer’s acceptance of proposed shutdown planning submittal and shutdown notification submittal.
b. Assist Owner in preparing to take equipment, tanks, basins, and conduits temporarily out of service.
44263-006 01 14 00-9 CODB RALPH BRENNAN WTP
c. Specific requirements: _______________________.
3. During Shutdown:
a. Installation of remaining Work required.
b. Perform tie-ins shown on Table 01 14 00-B.
c. Verify functionality of equipment and system.
44263-006 01 14 00-10 CODB RALPH BRENNAN WTP
Table 01 14 00-A
Schedule of Tie-Ins
Tie-In No.
New Line
Size and Service Existing (Connecting) Line Size & Service Tie-In Building/Location
1. 4” Lime Sludge Line 4” MJ Wye Plug Sludge Pump Station
2. 4” Drain Line Thickening Sludge Pump Station Wet Well
3. 2” Potable Water Service 2” Type 316 Stainless Steel Tapping Saddle with
Transition Fittings Sludge Thickeners Area
44263-006 01 14 00-11 CODB RALPH BRENNAN WTP
Table 01 14 00-B
Schedule of Shutdowns
Shutdown
No.
Process Equipment and Service Lines
Out-of-Service During Shutdown
Process Equipment
In Operation During Shutdown Tie-In Nos.
Maximum
Duration
44263-006 01 14 00-12 CODB RALPH BRENNAN WTP
44263-006 01 20 00-1 CODB RALPH BRENNAN WTP
SECTION 01 20 00
MEASUREMENT AND PAYMENT
PART 1 – GENERAL
1.01 DESCRIPTION
A. This Section defines the method, which will be used to determine the quantities of work performed, or materials supplied and establishes the basis upon which payment will be made.
1.02 ENGINEER’S ESTIMATE OF QUANTITIES
A. Where quantities are shown they are approximate and are given only as a basis of calculation upon which the award of the Contract is to be made. The CITY does not assume any responsibility for the final quantities, nor shall Contractor claim misunderstanding because of such estimate of quantities. Final payment will be made only for the satisfactorily completed quantity of each item.
1.03 MEASUREMENT STANDARDS
A. All work completed under the Contract shall be measured according to United States
Standard Methods.
1.04 METHOD MEASUREMENT
A. Measurement of Length: Unless otherwise specified for the particular items involved, all measurements of distance for items to be paid for on the basis of length shall be taken horizontally or vertically.
B. Measurement of Area: In the measurement of items paid for on the basis of area of finished work, the lengths and/or widths to be used in the calculations shall be the actual dimensions measured along the surface of the completed work within the neat lines shown or designated. At intersections, the measurement used for length of side area will be measured from the outside edge of the width allowed along the main trench.
C. Measurement of Weight of Asphaltic Concrete Materials: Measurements of the weight of
Asphaltic Concrete Materials shall be made as provided in the latest edition of the Florida
Department of Transportation, Standard Specifications for Road and Bridge construction, except that the Contractor shall be responsible for writing and certifying the accuracy of truck tally tickets.
44263-006 01 20 00-2 CODB RALPH BRENNAN WTP
1.05 PAYMENT
A. Lump Sum Items: Where payment for items is shown to be paid for on a lump sum basis, no separate payment will be made for any item of work described herein and listed on the
Bid Form required to complete the lump sum item.
B. Unit Price Items: Where payment for items is shown to be paid for on a unit price basis, separate payment will be made for the items of work described herein and listed on the
Bid Form. Any related work not specifically listed, but required for satisfactory completion of the work, shall be considered to be included in the scope of the appropriate listed work items.
1.06 COSTS INCLUDED PAYENT ITEMS
A. No separate payment will be made for the following items and the cost of such work shall be included in the applicable pay items of work:
1. Construction surveying
2. Clearing and grubbing
3. Trench and roadway excavation including necessary pavement removal, rock and cemented coquina excavation and disposal and excavation and removal of unsuitable soils and unsuitable materials of any nature except as otherwise specified
4. Structural fill, backfill and grading
5. Cleanup
6. Testing and placing system in operation
7. Any material and equipment required to be installed and utilized for tests
8. Concrete encasement
9. Maintaining the existing quality of service during construction
10. Appurtenant work as required for a complete and operable system
B. Cleanup: Contractor’s attention is called to the fact the cleanup is considered a part of the work of construction. Final payment will not be made until cleanup is essentially complete.
C. Work Outside Authorized Limits: No payment will be made for work constructed outside the authorized limits of work.
44263-006 01 20 00-3 CODB RALPH BRENNAN WTP
1.07 APPLICATIONS FOR PAYMENT 4
A. Applications for payment shall be prepared by the Contractor and submitted to the CITY in accordance with the schedule established by the Conditions of the Contract Documents.
B. Applications for payment shall be submitted in the number and format established by the
CITY at the Pre-Construction Conference. The form shall be completely filled out and executed by an authorized representative of the Contractor. Supporting data such as schedules of stored materials shall be attached to each copy of the application.
1.08 CHANGE ORDER PROCEDURE
A. As defined in the General Conditions, a Change Order is a written order to the Contractor signed by the CITY authorizing an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Time, which is issued after the execution of the Contract. The following procedure shall be used in processing Change Orders:
1. For Additions to the Work: The CITY shall issue a written order to the Contractor directing him to accomplish the additional work. The Contractor shall review the order and, if he feels the additional work entitles him to additional payment or additional time, he may submit a Change Order.
2. For Deletions from the Work: The CITY shall issue a written order to the Contractor directing him to make the change. If the CITY feels the Contract price should be reduced as a result of the change, the CITY shall make a claim for the reduction.
3. Cost of the changes in the work shall be determined in accordance with the requirements of the Contract Documents.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.01 BID ITEMS
A. Bid Item No. 1 – Mobilization/Demobilization (Max. 5% of Bid)
Mobilization shall be the preparatory work and operations in mobilizing for beginning work on the project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for the establishment of temporary offices, storage buildings, safety equipment and first aid supplies, sanitary and other facilities, as required by the Contract Documents and applicable laws and regulations. The costs of bonds, required insurance, permits and any other preconstruction expenses necessary for the start of the work, excluding the cost of construction materials, shall also be included in this item. Mobilization/Demobilization shall be limited to a maximum of five percent (5%) of the Bid Price.
44263-006 01 20 00-4 CODB RALPH BRENNAN WTP
Partial payments for this item will be made in accordance with the following schedule:
Percent of Original Contract
Amount Earned
Allowable Percent of the
Lump Sum Price for the Item
After Contract Execution 10
5 25
10 50
25 75
50 95
100 100
These payments will be subject to the standard retainage provided in the Agreement.
Payment of the retainage will be made after completion of the work and demobilization.
B. Bid Item No. 2 – Construction Survey, Layout and As-Builts
Payment of the applicable lump sum price shall be full compensation for furnishing all plant, labor, materials and equipment necessary to provide survey, layout and “As-Built”
Drawings, certified by a registered land surveyor or professional engineer. The
Contractor’s attention is directed to Section 01 78 39, which addresses the requirements and for maintaining up to date “As-Built” Drawings. Final payment will be withheld until an acceptable set of “As-Built” Drawings are delivered to the City.
C. Bid Item No. 3 – Erosion Control
Payment of the applicable lump sum price shall be full compensation for all work that includes preparation and implementation of stormwater pollution prevention control plan, including monitoring, inspecting, and reporting, providing erosion and sediment control measures, preparing and filing EPA NPDES NOI and NOT forms, and providing required contractor certifications. Also includes hay bales, filter bags, and filter fabric as needed for supplemental inlet protection and to supplement silt fence, including replacement and maintenance needed during construction. In the event temporary staging and storage areas are used, any required erosion and sediment control measures are to be included in this item.
D. Bid Item No. 4 – Demolition of Existing Sludge Drying Beds
Payment shall be made in lump sum (LS) for the applicable work that includes removing and demolition of the existing sludge drying beds in a safe manner. All material removed by the Demolition of the Existing Sludge Drying Beds shall be disposed of offsite in an approved location.
44263-006 01 20 00-5 CODB RALPH BRENNAN WTP
E. Bid Item No. 5 – Excavating and Grading
Payment shall be made as unit price per Cubic Yards (CY) for the quantity of the applicable work which includes all plant, labor, materials, and equipment necessary to excavate and grade the areas shown on the drawings. All material removed by the excavating and grading operation shall be disposed of offsite at an approved location.
F. Bid Item No. 6 – 12-inch thick Concrete Drying Bed Slabs
Payment shall be made as unit price per Square Feet (SF) for the applicable work that includes forming, furnishing and installing, curing, reinforcement, joints, and testing of concrete as shown in the bid set of plans provided for the construction of the new slabs for the new Drying Beds. Work shall also include furnishing and installing the trench drains in the slab as shown on the plans. Note that the thickness of the slab varies at the trench drains and as needed to accommodate the slope shown on the plans.
G. Bid Item No. 7 – 12-inch thick Concrete Walls for Drying Beds (approximately 1.5’ to 5’ tall
– see plans for details)
Payment shall be made as unit price per Square Feet (SF) for the quantity of the applicable work that includes forming, furnishing and installing, curing, reinforcement, joints, and testing as shown in the bid set of plans provided for the construction of the new 12-inch dividing walls for the Drying Beds. Note that the height of the wall varies along the length of sludge drying beds.
H. Bid Item No. 8 – 5-foot thick Concrete Walkways for Drying Beds (approximately 5’ tall)
Payment shall be made as unit price per Square Feet (SF) for the quantity of the applicable work that includes forming, furnishing and installing, curing, reinforcement, joints, and testing as shown in the bid set of plans provided for the construction of the new 5-foot-thick walkways for the Drying Beds. Work shall also include furnishing and installing the new handrail for the walkways as shown on the plans.
I. Bid Item No. 9 – 8-inch thick Concrete Slab for Dewatered Sludge Area
Payment shall be made as unit price per Square Feet (SF) for the quantity of the applicable work that includes forming, furnishing and installing, curing, reinforcement, joints, and testing as shown in the bid set of plans provided for the construction of the new 8-inch-thick concrete slab for the Dewatered Sludge Area. Note that the thickness of the slab varies at the thickened footers and the area of the sump. Work shall also include the grating for the sump.
J. Bid Item No. 10 – 3-foot tall Concrete Walls for the Dewatered Sludge Area
Payment shall be made as unit price per Square Feet (SF) for the quantity of the applicable work that includes forming, furnishing and installing, curing, reinforcement, joints, and
44263-006 01 20 00-6 CODB RALPH BRENNAN WTP
testing as shown in the bid set of plans provided for the construction of the new 3-foot-tall
Walls for the Dewatered Sludge Area.
K. Bid Item No. 11 – Pre-Finished Metal Building
Payment shall be made on a lump sum (LS) basis for the applicable work that includes furnishing and installing, coatings, bracing, roofing, anchor bolts, and testing as shown in the bid set of plans for the construction of the new pre-finished metal building for the
Dewatered Sludge Area.
L. Bid Item No. 12 – 4-inch DIP RMJ Pipe
Payment shall be made as unit price per linear foot (LF) of 4-inch DIP RMJ shall be full compensation for furnishing all plant, labor, materials, and equipment necessary to install the complete 4-inch DIP RMJ piping per the bid set plans. This shall include excavation, backfilling, bedding, compaction, sloping, sheeting or shoring, dewatering, surface restoration where not included under other pay items and pressure testing the piping as specified. No separate payment shall be made for locator tape or locator wire required to be installed with buried pipe.
M. Bid Item No. 13 – 4-inch DIP Flanged Pipe
Payment shall be made as unit price per linear foot (LF) of 4-inch DIP flanged piping shall be full compensation for furnishing all plant, labor, materials, and equipment necessary to install the complete 4-inch DIP flanged piping per the bid set plans. This shall include all gaskets, temporary and permanent pipe supports, cleaning, pressure testing, and coatings for the piping as specified.
N. Bid Item No. 14 – 4-inch Gate Valves
Payment shall be made on a unit price per each for the 4-inch gate valves shall be full compensation for furnishing all plant, labor, materials, and equipment necessary to install the complete 4-inch gate valves per the bid set plans. This shall include all gaskets, temporary and permanent pipe supports, cleaning, pressure testing, actuators, and coatings for the gate valves as specified.
O. Bid Item No. 15 – Core Drill Thickening Sludge Pump Station and Connection
Payment shall be made as unit price for the core drilling the existing Thickening Sludge
Pump Station wet well and installing a compressible type link seal and grout as required per the bid set plans. This shall include all coordination for shutdown with plant staff, protections of existing plant functions, materials, labor, equipment, cleaning of the area, sheeting, shoring, and restoration of existing wet well coatings as specified.
P. Bid Item No. 16 – Miscellaneous Pipe Fittings and Appurtenances
Payment shall be made in lump sum (LS) for the applicable work that includes the miscellaneous pipe fitting and appurtenances that will be required for this specific project.
44263-006 01 20 00-7 CODB RALPH BRENNAN WTP
This includes any fittings such as bends, wyes, harnessed couplings, wall collar spools, etc. that may be required to complete the project per the bid set of plans. This shall include excavation, backfilling, bedding, compaction, sloping, sheeting or shoring, dewatering, surface restoration where not included under other pay items and pressure testing the piping as specified.
Q. Bid Item No. 17 – Roadway
Payment shall be at the unit price per square yard of the work which consists of asphalt removal and replacement (roadways and parking areas), including temporary restoration in accordance with the City’s policies. The work includes all backfill, compaction at specified lifts and required densities, materials, preparation of the surface, install stabilization and base and subbase materials, mixing, placing, rolling, testing, and the disposal of existing concrete and waste, thermoplastic striping, material testing, and work incidental thereto. The Contractor shall construct in accordance with the Florida
Department of Transportation, FY 2025-26 Standard Plans for Road and Bridge
Construction and the Florida Department of Transportation, Standard Specifications for
Road and Bridge Construction, or details in the Contract Documents.
44263-006 01 20 00-8 CODB RALPH BRENNAN WTP
44263-006 01 25 00-1 CODB RALPH BRENNAN WTP
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 – GENERAL
1.01 SUMMARY
A. Section includes:
1. Procedural requirements for product substitutions.
2. Procedural requirements for substitute construction methods or procedures, when construction methods or procedures are specified.
B. Requests for substitutions of equipment and material shall conform to the requirements of the General Conditions and Supplemental Conditions.
C. Procedure for substitution requests and review including evaluation, reimbursement, acceptance, and determination shall be in accordance with General Conditions and
Supplemental Conditions.
1.02 REFERENCES
A. Definitions: The following words or terms are not defined but, when used in this Section, have the following meaning:
1. “Acceptable Manufacturers” considered for substitution include Suppliers of equipment and material of proven reliability, and as manufactured by reputable manufacturers having experience in the production of specified equipment and material. Equipment furnished shall be designed, constructed, and installed in accordance with the industry accepted practices and shall operate satisfactorily when installed in accordance with the Contract Documents.
2. “Products” includes materials, equipment, machinery, components, fixtures, systems, and other goods incorporated in the Work. Products do not include machinery and equipment used for preparing, fabricating, conveying, erecting, or installing the Work. Products include Owner-furnished goods incorporated in the
Work where use of such goods is specifically required in the Contract Documents.
1.03 ADMINISTRATIVE REQUIREMENTS
A. Contractor’s Responsibilities: In submitting request for substitution, Contractor represents that:
1. Contractor has investigated proposed substitution and determined that it is equivalent to item, product, method, or procedure specified, as applicable.
44263-006 01 25 00-2 CODB RALPH BRENNAN WTP
2. Contractor will provide the same or better guarantees or warranties for proposed substitution as for the specified product, manufacturer, method, or procedure, as applicable.
3. Contractor waives all Claims for additional costs or extension of time related to proposed substitution that subsequently may become apparent.
4. Contractor shall submit a minimum of five (5) successful installations of the manufacturer’s equipment of the same model, size, and type as specified in the
Contract Documents.
5. All costs associated with incorporation of a substitution shall be borne by the
Contractor, including but not limited to, the cost of redesign and construction provisions.
B. Engineer’s Review: A proposed substitution will not be accepted for review if:
1. Approval would require changes in design concept or a substantial revision of the
Contract Documents.
2. Approval would delay completion of the Work or the work of other contractors.
3. Substitution request is indicated or implied on a Shop Drawing or other submittal, or on a request for interpretation or clarification, and is not accompanied by
Contractor’s formal request for substitution.
4. If the substitution is not clearly substantiated by performance criteria as providing an equivalent or superior performing installation.
5. All costs associated with Engineer’s review of a substitution shall be recorded by
Engineer, submitted to Owner, and charged to Contractor.
C. If Engineer does not approve the proposed substitute, Contractor shall provide the specified product, manufacturer, method, or procedure, as applicable.
D. Approval of a substitution request will not relieve Contractor from requirement for submitting Shop Drawings as set forth in the Contract Documents.
E. Product Substitutions Procedure:
1. Requests for approval of substitute products or items will be considered for a period of 30 days after the Effective Date of the Agreement. After end of specified period, requests will be considered only in case of unavailability of a specified product or other conditions beyond Contractor’s control.
2. Submit copies of request for substitution.
3. Submit separate request for each substitution.
44263-006 01 25 00-3 CODB RALPH BRENNAN WTP
4. In addition to requirements of the General Conditions and information required on substitution request forms, include with request the following:
a. Product identification, including manufacturer’s name and address.
b. Manufacturer’s literature with product description, performance and test data, and reference standards with which product complies.
c. Samples, if appropriate.
d. Name and address of similar projects on which product was used, and date of installation.
e. Certified tests, where applicable, by an independent laboratory attesting the proposed substitution is equal.
f. Cost information for the proposed substitution and the specified products.
g. Lead time information for the proposed substitution and specified products.
h. All other submittal requirements indicated in the individual Specification
Sections associated with the specified equipment and material.
F. Construction Methods Substitutions Procedures:
1. Where construction methods or procedures are specified, for a period of 30 days after the Effective Date of the Agreement, Engineer will consider Contractor’s written requests for substitute construction methods or procedures specified.
2. Submit copies of request for substitution.
3. Submit separate request for each substitution.
4. In addition to requirements of the General Conditions and information required on substitution request forms, include with request the following:
a. Detailed description of proposed method or procedure.
b. Itemized comparison of the proposed substitution with the specified method or procedure.
c. Drawings illustrating method or procedure.
d. Other data required by Engineer to establish that proposed substitution is equivalent to specified method or procedure.
44263-006 01 25 00-4 CODB RALPH BRENNAN WTP
PART 2 – PRODUCTS (NOT USED)
44263-006 01 26 00-1 CODB RALPH BRENNAN WTP
SECTION 01 26 00
CONTRACT MODIFICATION PROCEDURES
PART 1 – GENERAL
1.01 THE REQUIREMENT
A. Section includes:
1. General Conditions and Supplementary Conditions provision expansion, including the following:
a. Requests for interpretation.
b. Clarification notices
c. Field Orders
d. Work Change Directives
e. Proposal requests
f. Change Proposals
g. Change Orders
1.02 ADMINISTRATIVE REQUIREMENTS
A. Submit Contract modification documents to Engineer’s contact person and address in the
Contract Documents.
B. Retain at Contractor’s office and at the Site complete copy of each Contract modification document and related documents, and Engineer’s response.
1.03 REQUEST FOR INTERPRETATION
A. General:
1. Submit written or electronic requests for interpretation to Engineer. Contractor and
Owner may submit requests for interpretation.
2. Submit request for interpretation to obtain clarification or interpretation of the
Contract Documents. Report conflicts, errors, ambiguities, and discrepancies in the
Contract Documents using requests for interpretation.
3. Do not submit request for interpretation when other form of communication is appropriate, such as submittals, requests for substitutions or “or equals”, notices, 44263-006 01 26 00-2 CODB RALPH BRENNAN WTP ordinary correspondence, or other form of communication. Improperly prepared or inappropriate requests for interpretation will be returned without response or action.
B. Procedure:
1. Submit one original (hard copy or electronic) of each request for interpretation.
Submit each request for interpretation with separate letter of transmittal if hard copies are submitted.
2. Engineer will provide timely review of requests for interpretation. Allow sufficient time for review and response.
3. Engineer will maintain log of requests for interpretation. Copy of log will be provided upon request.
4. Engineer will provide written response to each request for interpretation. One copy of Engineer’s response will be distributed to:
a. Contractor
b. Owner
c. Engineer
d. Owner’s Site Representative (OSR)
C. If Engineer requests additional information to make an interpretation, provide information requested within ten (10) days, unless Engineer allows additional time, via correspondence referring to request for interpretation number.
D. If Contractor or Owner believes that a change in the Contract Price or Contract Times or other change to the Contract is required, notify Engineer in writing before proceeding with the Work associated with the request for interpretation.
E. Submit each request for interpretation on a form acceptable to Engineer.
1. Number each request for interpretation as follows: Numbering system shall be the
Contract number and designation followed by a hyphen and three-digit sequential number.
2. In space provided on form, describe the interpretation requested. Provide additional sheets as necessary. Include text and sketches as required in sufficient detail for engineer’s response.
3. When applicable, request for interpretation shall include Contractor’s recommended resolution.
44263-006 01 26 00-3 CODB RALPH BRENNAN WTP
1.04 CLARIFICATION NOTICES
A. General:
1. Clarification notices, when required, will be initiated and issued by Engineer.
2. Clarification notices do not change the Contract Price or Contract Times, and do not alter the Contract Documents.
3. Clarification notices will be issued as correspondence or using clarification notice form, with additional information as required.
B. Procedure:
1. One hard copy of each clarification notice will be distributed to:
a. Contractor
b. Owner
c. Engineer
d. Owner’s Site Representative
2. Electronic copies of Clarification Notices will be maintained, stored, and distributed by electronic construction document management system.
3. If Contractor or Owner believes that a change in the Contract Price or the Contract
Times or other change to the Contract is required, notify Engineer in writing before proceeding with the Work associated with clarification notice.
4. If clarification notice is unclear, submit request for interpretation.
1.05 FIELD ORDERS
A. General:
1. Field Orders, when…
This is the start of the file's text. The full file is on GovTribe.