- Solicitation number
- 140A1126R0012
About this file
This is a Project Manual containing specifications for modifications to the Stop Log Lifting Beam End Guide at CRIP Headgate Rock Dam for the Bureau of Indian Affairs, Office of Trust Services – Division of Water and Power. The project is prepared by DOWL and identified as Project No. 4626.12494.01, with a date of March 6, 2026.
The contract includes two primary bid items: Item 101 (Lifting Beam End Guide Modifications and Transport) and Item 102 (Facilitate Final Test), both compensated on a lump sum basis. Item 101 requires the contractor to transport the Owner-furnished lifting beam to a fabrication shop, perform modifications according to design specifications and drawings, and deliver the modified beam back to the project site. This item encompasses all labor, equipment, materials, and required submittals. Item 102 requires the contractor to coordinate and facilitate a Final Test at the project site by providing a crane and operator, attending the test with a representative to demonstrate the adjustable end guide functionality, and making any required adjustments based on test results. Contractor may request payment on Item 101 following shop inspection and delivery; BIA will pay Item 102 upon completion of the work.
Submittal requirements are detailed in Section 01 33 00 and include shop drawings and product data for steel stoplogs (minimum 45 days before fabrication begins), shop testing and inspection plans (within 30 days of Notice to Award), and painting and coatings product data and testing plans (within 30 days of Notice to Award). All submittals must be approved by the contractor and submitted electronically in PDF format through a web-based portal, with a 28-day review period for each submittal. Section 05 05 13 specifies painting and coating requirements for ferrous metals using System S-1 (Series 94H2O Hydro-Zinc primer, Series 22 Epoxoline midcoat and topcoat) with a minimum total dry-film thickness of 18.0 mils. Section 40 05 59.16 addresses steel stoplogs and lifting beam fabrication, including material standards (ASTM A992 for wide flanges, ASTM A36 for shapes and plates, ASTM A500 for HSS), welding requirements per AWS D1.1, and neoprene or EPDM rubber seals with specified physical properties. The contractor has a maximum fabrication duration of 21 days from pickup to prepare the equipment for shop inspection, followed by 5 days post-inspection to make adjustments and deliver. The Final Test will occur at the Main Canal Headworks and must demonstrate that the modified lifting beam travels freely through stoplog slots without binding or excessive gaps; if nonconformities are identified, the contractor must promptly rectify them and reschedule the test.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A3_LiftingBeamMods_DemoDrawings_FINAL.pdf | ||
| SF-24_Bid_Bond_Form.pdf | ||
| SF-25A_Payment_Bond_Form.pdf | ||
| SF-25_Performance_Bond_Form.pdf | ||
| Sol_140A1126R0012.pdf | ||
| DOL_-_AZ20260052_5_18_26.pdf | ||
| B09__Questions_and_Answers_Log.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual for
CRIP Headgate Rock Dam Stop Log Lifting Beam End Guide Modifications
Bureau of Indian Affairs
Office of Trust Services – Division of Water and Power
Prepared By:
Project No. 4626.12494.01 \\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\00 00 00 - CoverPageSpecs.docx
March, 6, 2026
CRIP Headgate Rock Dam SECTION 00 01 10 Stop Log Lifting Beam End Guide Modifications TABLE OF CONTENTS
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\00 01 10 - TOC.docx 00 01 10 -1
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACT REQUIREMENTS
00 01 10 Table of Contents
DIVISION 01 – GENERAL CONDITIONS
01 29 00 Payment Procedures 01 33 00 Submittal Procedures
DIVISION 05 – METALS
05 05 13 Painting and Coatings
DIVISION 40 – EQUIPMENT
40 05 59.16 Stainless Steel Stop Logs
END OF SECTION
CRIP Headgate Rock Dam SECTION 01 29 00 Stop Log Lifting Beam End Guide Modifications PAYMENT PROCEDURES
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 29 00 - Payment Procedures.docx 01 29 00 - 1
GENERAL
SECTION INCLUDES
For each bid item, the work will be measured and paid for on either a unit price basis or on a lump sum basis. The quantities provided in the descriptions of the bid items are estimates of the actual quantities of work only and are included solely for guidance in determining the probable cost of work. The actual quantities of work may differ from the quantity estimates provided. The quantities for measurement and payment for unit price bid items shall be as calculated to the neatlines shown on the drawings. All labor, equipment, materials, and incidentals required to complete the work shall be considered subsidiary to that bid item and will not be paid for separately. The contractor agrees to make no claim for damages, loss of anticipated profits, or otherwise, due to differences between the actual work quantities and the quantity estimates provided.
Payment will be made only for each item included in the bid. No work will be paid for that is not completed in accordance with the drawings and specifications and accepted by the BIA Representative. No labor, equipment, materials, or incidentals required to complete the work will be furnished by the BIA Representative.
The basis of measurement and payment for each bid item is described below. A general listing of bid items, accompanied by a brief summary of the work, is also provided. The summaries are not intended to completely describe all work. Refer to the drawings and specifications for detailed information on each bid item.
ACRONYMS
Not applicable
MEASUREMENT AND PAYMENT PROCEDURES
Item 101: Lifting Beam End Guide Modifications and Transport
a. This item consists of transporting the Owner-furnished lifting beam to the fabrication shop, modifying the lifting beam, and delivering the modified lifting beam to the project site.
b. This bid item includes, but is not limited to:
i. Transporting the lifting beam from the project site to the fabrication shop and transporting the lifting beam back to the project site after the modifications are complete.
ii. Furnishing all labor, equipment, and materials to modify the lifting beam as described in the drawings and specifications.
iii. Developing, compiling, and submitting all information described under the in Section 01 33 00 – Submittal Procedures.
iv. Related submittal reviews, resubmittals, and coordination required to achieve final, approved/accepted submittals.
CRIP Headgate Rock Dam SECTION 01 29 00 Stop Log Lifting Beam End Guide Modifications PAYMENT PROCEDURES
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 29 00 - Payment Procedures.docx 01 29 00 - 2
c. Measurement and payment will be at the Contract lump sum price. Contractor may request payment on this item after the shop inspection and delivery to the project site.
Item 102: Facilitate Final Test
a. This item consists of the Contractor’s attendance and facilitation of the Final Test at the project site.
b. This bid item includes, but is not limited to:
i. Coordinating with BIA to select a date and time for the Final Test.
ii. Furnishing a crane and crane operator to support BIA’s field-directed testing.
iii. Attendance by Contractor’s representative at the Final Test and demonstration by this individual of the adjustable end guide functionality. End guide adjustments by the Contractor may be required based on the outcome of the trial stop log installation test.
c. Measurement and payment will be at the Contract lump sum price. BIA will pay the Contractor when the work associated with this item is complete.
PRODUCTS
Not Used
EXECUTION
Not Used
CRIP Headgate Rock Dam SECTION 01 33 00 Stop Log Lifting Beam End Guide Modifications SUBMITTAL PROCEDURES
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 33 00 - Submittal Procedures.docx 01 33 00 -1
GENERAL
SECTION INCLUDES
This section covers the requirements for submittals by the Contractor of descriptive information that will enable a determination of whether the Contractor’s proposed materials, equipment, and work methods are in general conformance to the design concept and in accordance with the specifications.
REQUIRED SUBMITTALS
Consists of:
Permits
Drawings
Product Data
Certifications
Manuals, Shop Drawings, and Specialized Tools
Samples
Test Reports
DEFINITIONS
Days: Calendar days.
Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
Submittal Types, as listed in Table 01 33 00A – List of Submittals:
A – Approval:
a. BIA Representative will accept or reject Approval submittals.
I – Informational:
a. The BIA Representative will acknowledge receipt and acceptance of these submittals.
b. The BIA Representative may request additional clarification, information, and/or documentation on the content of an informational submittal. If the BIA Representative arrives at different conclusions than described by the informational submittal, the BIA Representative may provide recommendations for Contractor’s consideration.
SUBMITTAL REQUIREMENTS
In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 33 00 - Submittal Procedures.docx 01 33 00 -2
Submittal Letter of Transmittal:
Contract number.
Project name.
RSN.
List of documents/content included with the submittal.
Relevant discussion and/or information that the BIA should be aware of to effectively review and fully understand the submittal content.
Statement that the submittal has been reviewed and approved by the Contractor’s authorized representative.
Signature of Contractor’s authorized representative.
SUBMITTAL CONTENT
Provide a complete submittal package: Include all documentation and information necessary to satisfy the submittal requirements. If an incomplete submittal package is submitted for review, identify what elements are missing and the reason those elements were omitted. The BIA Representative reserves the right to reject partial submittals.
Product Data Sheets: For manufacturer data with multiple items, the elements being submitted for review shall be clearly identified.
Certifications:
Certifications by a registered professional: Signed and sealed by registered professional.
Manufacturer’s certifications: Signed by authorized representative of manufacturer.
SUBMITTALS PROCEDURES
Contractor shall review and approve all submittals prior to submitting them. Submittals without evidence of Contractor’s approval will be returned for resubmission.
Submittals shall be submitted electronically in portable document file (pdf) format through a web-based portal. Submittals that cannot be submitted electronically, such as material/product samples, shall be submitted to the BIA Representative. Note that in the case of product samples, four samples shall be submitted.
Distribution and review status of individual submittals shall be administered through the web-based portal.
Reviewed submittals and submittal disposition shall be returned/sent to the Contractor electronically in pdf format.
REVIEW OF SUBMITTALS
Time Required:
Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 33 00 - Submittal Procedures.docx 01 33 00 -3
The review period for a submittal (or resubmittal) begins when a complete submittal package is received.
Return of Submittals:
Submittals will be returned either approved, approved as noted, not approved, or acknowledging receipt.
For submittals not approved:
a. Revise and resubmit for approval.
b. Show changes and revisions.
c. Resubmit returned submittals within 28 days after receiving the comments.
d. In the resubmittal transmittal letter, describe how the submittal was revised and the how comments on the initial (or previous) submission were addressed.
PRODUCTS
Not Used
EXECUTION
Not Used
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\01 33 00 - Submittal Procedures.docx 01 33 00 -4
Table 01 33 00A – List of Submittals
Submittal No. Section Title Submittals Required When to Submit Type
05 05 13-1 Painting and Coatings Product Data Within 30 days of Notice of Award A
05 05 13-2 Painting and Coatings Shop Testing and Inspection Plan Within 30 days of Notice of Award A
05 05 13-3 Painting and Coatings Shop Testing and Inspection Results
No more than 14 days after completing the test or inspection
I
40 05 59.16-1 Steel Stoplogs Shop Drawings and Product Data A minimum of 45 days before beginning fabrication.
A
40 05 59.16-2 Steel Stoplogs Shop Testing and Inspection Plan Within 30 days of Notice of Award A
40 05 59.16-3 Steel Stoplogs Shop Testing and Inspection Results
No more than 14 days after completing the test or inspection
I
CRIP Headgate Rock Dam SECTION 05 05 13 Stoplog Lifting Beam End Guide Modifications PAINTING AND COATINGS
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -1
GENERAL
DESCRIPTION
This specification section includes requirements for surface preparation, painting, and paint testing of all ferrous metals to be supplied per the contract documents.
BIA is adopting this section from the original fabrication specifications. Changes from the original specification are indicated herein by strikeout (for deletions) and italics (for additions).”
REFERENCE SPECIFICATIONS, CODES, AND STANDARDS
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. The most recent editions of the publications shall govern.
1. American Society for Testing and Materials
a. A380 Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems.
b. D2369 03 Test Method for Volatile Content of Coatings
c. D2697 Test Method for Volume Non-Volatile Matter in Clear or Pigmented Coatings.
d. D2832 92(R1999) Guide for Determining Volatile and Nonvolatile Content of Paint and Related Coatings
e. D3359 Standard Test Methods for Measuring Adhesion by Tape Test
f. D4541 Pull Off Adhesion
g. D4285 Standard Test Methods for Field Measurement of Surface Profile of Blast Cleaned Steel
h. D5163 Standard Practice for Discontinuity (Holiday) Testing of Non Conductive Protective Coating on Metal Substrates
2. National Association of Corrosion Engineers International (NACE) - RP 0188-99.
Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates.
3. The Society For Protective Coatings (SSPC-Formerly The Steel Structure Painting Council)
a. SP 1 Surface Preparation Specification No. 1, Solvent Cleaning
b. SP 2 Hand Tool Cleaning
c. SP 3 Power Tool Cleaning
d. SP 5 White Metal Blast Cleaning
e. SP 6 Commercial Blast Cleaning
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -2
f. SP 7 Brush-Off Blast Cleaning
g. SP 10 Near-White Blast Cleaning
h. SP 11 Power Tool Cleaning to Bare Metal
i. SP 12 High Pressure Water Jetting
j. Guide No.3 (PA 3) Guide to Safety in Paint Applications
k. Specification No.2 (PA2) Measurement of Dry Film Thickness with Magnetic Gauges
SUBMITTALS
Submit the following in accordance with the requirements of Section 01 33 00 – Submittals:
Product manufacturer's technical data sheets showing the following information:
1. Descriptive data.
2. Performance characteristics.
3. Product data sheets.
4. Surface preparation.
5. Application instructions.
6. Patching, repairs, and touch-up instructions.
7. Material safety data sheets.
8. Paint and color schedule.
9. Color swatches.
Inspection reports and data collection sheets for surface preparation and profile checks, coating thickness measurements for each coat, holiday tests, ambient conditions, and other pertinent records.
QA/QC Procedure Manual and Inspection and Testing Plan for review and acceptance.
Manufacturer’s product warranties.
Certificate of Conformance.
Three sets of manufacturer’s standard color guide for the specified coating system requiring a color selection.
PRODUCTS
GENERAL REQUIREMENTS
For each painting and coating system, the required surface preparation, prime coat, intermediate coat (if required), topcoat, and coating thicknesses are specified herein. Mil thicknesses shown or specified are minimum dry-film thicknesses.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -3
Provide materials for a specified painting system, including primer, intermediate, and finish coats by the same manufacturer. Thinners, cleaners, driers, and other additives shall be as recommended by the paint manufacturer for the particular coating system.
Deliver paints, whether for shop or field applications, in the original, unopened containers.
COATING SYSTEMS
The following schedule is a guide to the types of surfaces requiring painting and is not intended to be complete or exact. Generally, all metal surfaces are to be painted for protection unless otherwise specified differently herein.
System S-1: Ferrous metal subject to water immersion, excluding stainless steel and mating machined surfaces.
1. Epoxy (or Zinc) Primer Application
a. Once surface preparation has been completed and accepted, coating application can begin.
b. Prior to primer spray application, all welds, rivets, edges, and corners shall be stripe coated by brush or roller. Ensure the coating is well worked in to the substrate.
c. Once stripe coating has been completed the spray coat can be applied.
d. Minimum DFT shall be 6.0 mils.
e. Products: Series 94H2O Hydro-Zinc by Tnemec Inc.
2. Midcoat
a. Once the primer coat has properly dried/cured and has been accepted, the midcoat application can begin.
b. Prior to spray application, all welds, rivets, edges, and corners shall be stripe coated by brush.
c. Ensure that coating is well worked in to substrate.
d. Once stripe coating has been completed the spray coat can be applied.
e. Minimum DFT shall be 6.0 mils
f. Products: Series 22 Epoxoline by Tnemec Inc.
3. Topcoat
a. Once the midcoat has been completed and accepted, the topcoat shall be applied.
b. Minimum topcoat DFT shall be 6.0 mils.
c. The minimum total system DFT shall be 18.0 mils.
d. Products: Series 22 Epoxoline by Tnemec Inc.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -4
Other Acceptable Paint Products
System Manufacturer Prime Coat Intermediate Coat Finish Coat System S-1
Tnemec Series 94H2O Hydro- Zinc
Series 22 Epoxoline Series 22 Epoxoline
Carboline Reactactamine 760 Reactamine 760 Carbothane 133 HB Carboline Carboguard 635 Carboquick 200 Carboquick 200 PPG Industries Sigmashield 1200 Sigmashield 1200 Sigmashield 1200
COATING SCHEDULE
No.
Equipment, Material, Surface or Substrate
System No.
Color of Final Coat
1 Stoplogs & Lifting Beam S-1 Light Blue or Light Grey
General Field Touchup of Fabricator’s Shop-Applied Coatings
* Match Color
* Restore/touch-up shop-applied coatings in the field using touch-up paint furnished by the equipment fabricator.
EXECUTION
PROTECTION
Remove, mask, or otherwise protect hardware, concrete surfaces, machinery, and other surfaces not intended to be painted.
Provide drop cloths to prevent paint materials from falling on or marring adjacent surfaces.
Remove and clean up paint drips, spills, and splashes from areas not being painted.
SURFACE PREPARATION
Prepare all surfaces to be coated in accordance with the paint manufacturer’s written specifications and instructions.
Prepare steel surfaces for prime and finish coats in accordance with the Steel Structures Painting Council (SSPC) surface preparation specifications set forth below:
Specification Type Profile (Ave. Mils)
SP-1 Solvent Cleaning -- SP-2 Hand Cleaning -- SP-3 Power Tool Cleaning -- SP-5 White Metal Blast Cleaning 1.5 – 2.5 SP-6 Commercial Blast Cleaning 1.5 – 3.0 SP-10 Near White Metal Blast Cleaning 1.5 – 3.0
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -5
Do not sandblast or prepare more surface area in one day than can be coated in one day; prepare surfaces and apply coatings the same day. Remove all sharp edges, burrs, and weld spatter.
Remove oil and grease from metal surfaces in accordance with SSPC SP-1. Use clean cloths and cleaning solvents and wipe dry with clean cloths. Do not leave a film or greasy residue on the cleaned surfaces before sandblasting.
Remove weld spatter and weld slag from metal surfaces and grind smooth any rough welds, beads, peaked corners, sharp edges, erection lugs, etc. in accordance with SSPC SP-2 and
SSPC SP-3.
Neutralize welds with a chemical solvent that is compatible with the specified coating materials. Use clean cloths and chemical solvent. Wipe dry with clean cloths. Do not leave a residue on the cleaned surfaces.
ABRASIVE BLAST CLEANING
Abrasive blast cleaning is defined as cleaning the surface through the use of very fine abrasives, such as siliceous or mineral abrasives, 80 to 100 mesh. Apply a fine etch to the metal surface to clean the surface of any contamination or oxide.
Use dry abrasive blast cleaning for metal surfaces. Do not use abrasives that have become contaminated in automatic equipment. When shop or field blast cleaning with handheld nozzles, do not recycle or reuse blast particles.
After blast cleaning and prior to application of coating, dry clean surfaces to be coated by dusting, sweeping, and vacuuming to remove residue from blasting.
Keep the area of the work in a clean condition and do not permit blasting particles to accumulate and constitute a nuisance or hazard.
During sandblast cleaning, prevent damage to adjacent coatings. Schedule blast cleaning and coating such that dust, dirt, blast particles, old coatings, rust, mill scale, etc., will not damage or fall upon wet or newly coated surfaces.
Reclean prior to application of primer or touch-up coating any blast-cleaned surface not coated within said eight-hour period.
3.03 PAINT MIXING
Prepare multiple-component coatings using all of the contents of the container for each component as packaged by the paint manufacturer. Do not use partial batches. Do not use multiple-component coatings that have been mixed beyond their pot life. Provide small quantity kits for touch-up painting and for painting other small areas. Mix only the components specified and furnished by the paint manufacturer. Do not intermix additional components for reasons of color or otherwise, even within the same generic type of coating. When power mixing multiple components, do not introduce moisture or air into product.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -6
PRIME COATS
Apply prime coats in accordance with the coating manufacturer’s written specifications and instructions. Prime painting shall not be performed under adverse ambient conditions that may affect the life or appearance of the coating.
Prime prepared surfaces of steel and iron immediately after completion of surface preparation.
Do not apply prime coat over damp or moist surfaces.
Prime coats found to be incompatible with finish coats or applied to improperly prepared surfaces shall be removed and an appropriate prime coat applied at no additional cost to the Agency.
Apply primer immediately after blast cleaning and before any surface rusting occurs, or any dust, dirt, or any foreign matter has accumulated. Re-clean surfaces by blast cleaning that have surface colored or become moist prior to coating application.
Apply a brush coat of primer on welds, sharp edges, nuts, bolts, and irregular surfaces prior to the application of the primer and finish coat. The brush coat shall be done prior to and in conjunction with the spray coat application. Apply the spray coat over the brush coat.
Cure prime coats in accordance with the manufacturer’s written specifications and instructions.
INTERMEDIATE COATS
After proper application of the prime coat, apply by brush, one stripe coat of the intermediate coat epoxy, thinned 15%, to all welds, edges and corners, fasteners, and/or other difficult to reach areas.
FINISH COATS
Apply finish coats in accordance with the coating manufacturer’s written specifications and instructions. Follow the recommendations of the coating manufacturer including the selection of spray equipment, brushes, rollers, cleaners, thinners, mixing, drying time, temperature and humidity of application, and safety precautions. Painting shall not be performed under adverse ambient conditions that may affect the life or appearance of the coating.
Finish coats found to be incompatible with prime coats or applied to improperly prepared surfaces shall be removed and an appropriate finish coat applied at no additional cost to the Agency.
Do not apply coatings over damp or moist surfaces.
Prepare undercoats and intermediate coats to differ noticeably in coloration for each other on succeeding coating applications to ensure even coverage by shading or tinting, as appropriate, for the paint material and color. Shading or tinting shall be done by the paint manufacturer.
Conform to the requirements of SSPC PA-1, Shop, Field and Maintenance Painting.
Stir, strain, and keep coating materials at a uniform consistency during application. Apply each coating evenly, free of brush marks, sags, runs, and other evidence of poor workmanship.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -7
Do not use thinners unless recommended by the coating manufacturer. If thinning is allowed, do not exceed the maximum allowable amount of thinner per gallon of coating material. Stir coating materials at all times when adding thinner. Do not flood the coating material surface with thinner prior to mixing. Do not reduce coating materials more than is absolutely necessary to obtain the proper application characteristics and to obtain the specified dry-film thicknesses.
Remove dust, blast particles, and other debris from blast-cleaned surfaces by dusting, sweeping, and vacuuming. Allow ventilator fans to clean airborne dust to provide good visibility of working area prior to coating applications. Remove dust from coated surfaces by dusting, sweeping, and vacuuming prior to applying succeeding coats.
Apply coating systems to the specified minimum dry-film thicknesses as measured from above the peaks of the surface profile.
Finished surfaces shall be free from holidays, pinholes, bubbles, runs, drops, ridges, waves, laps, excessive or unsightly brush marks, and variations in color, texture, and gloss. Verify absence of holidays, pinholes, gaps, etc. by appropriate testing. Recoat and retest any areas failing these tests.
Cure coats in accordance with the manufacturer’s written specifications and instructions.
COATING INSPECTIONS
Measure coating thickness specified for metal surfaces with a calibrated magnetic-type dry-film thickness gauge. Provide dry-film thickness gauge as manufactured by Mikrotest or Elcometer. Check each coat for the correct dry-film thickness. Do not measure within eight hours after application of the coating.
A minimum of five spot measurements shall be taken in a given area to assure proper coat dry film thickness. The average of these measurements shall not be less than the specified thickness. No single spot measurement shall be less than 80 percent, or more than 120 percent, of the specified thickness.
Test the coating with a low-voltage (22.5 to 80 volts with approximately 80,000 ohm resistance) holiday detector, using a sponge saturated with a 0.5 percent sodium chloride solution. The coating shall be holiday-free.
Prepare and submit a report of prime, intermediate, and finish coatings inspections.
CONTACTING SURFACES
When ordinary bolted contact is to exist between surfaces of ferrous or other metal parts of substantially similar chemical composition, such surface will not be required to be painted, but any resulting crevices shall subsequently be filled or sealed with paint.
Contacting metal surfaces formed by high-strength bolts in friction-type connections shall not be painted.
Where a nonmetal surface is to be in bolted contact with a metal surface, the contacting surfaces of the metal shall be cleaned and given three coats of the specified primer.
\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\05 05 13 - Painting and Coatings.docx 05 05 13 -8
HANDLING AND TRANSPORTING SHOP-COATED ITEMS
When loading for shipment to the project site, use spacers and other protective devices to separate items to prevent damaging the shop-coated surfaces during transit and unloading. If wood spacers are used, remove wood splinters and particles from the shop-primed surfaces after separation. Use padded chains or ribbon binders to secure the loaded items and minimize damage to the shop-coated surfaces.
Handle shop-coated items with care during loading/unloading, installation, and erection operations to minimize damage. Do not place or store shop-coated items on the ground or on top of other work unless ground or work is covered with a protective covering or tarpaulin.
Place shop-coated items above the ground upon platforms, skids, or other supports.
Cover shop-coated items 100 percent with protective coverings or tarpaulins to prevent deposition of road salts, fuel residue, and other contaminants in transit.
FIELD PAINTING AND TOUCH-UP
Clean and recoat surfaces with the specified paint material to obtain the specified color and coverage, if the surfaces have an improper finish color or insufficient film thickness.
Sandblast or power-sand visible areas of chipped, peeled, or abraded paint, feathering of edges.
Prime and finish coat in accordance with the paint manufacturer’s written specifications and instructions. Work shall be free of runs, bridges, shiners, laps, or other imperfections.
UNCOATED SURFACES
Do not paint the following surfaces unless otherwise directed by the Contracting Officer’s Representative:
1. Stainless steel.
2. Plastic, Poly, and rubber.
3. Bronze, aluminum, and nonferrous materials.
CRIP Headgate Rock Dam SECTION 40 05 59.16 Stoplog Lifting Beam End Guide Modifications STEEL STOPLOGS
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -1
SUMMARY
This section applies to the steel stoplogs and lifting beam.
BIA is adopting this section from the original fabrication specifications. Changes from the original specification are indicated herein by strikeout (for deletions) and italics (for additions).”
REFERENCE SPECIFICATIONS, CODES, AND STANDARDS
American Institute of Steel Construction (AISC)
1. Code of Standard Practice for Steel Buildings and Bridges.
2. Specifications for the Design, Fabrication, and Erection of Structural Steel for Buildings.
ASTM International (ASTM)
1. AISC Manual of Steel Construction
2. AISI Design of Light Gauge, Cold-Formed Steel Structural Members
3. ASTM A36 Carbon Structural Steel
4. ASTM A48 Gray Iron Castings
5. ASTM A53 Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
6. ASTM A123 Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
7. ASTM A153 Zinc Coating (Hot-Dip) on Iron and Steel Hardware
8. ASTM A193 Alloy Steel and Stainless Steel Bolting Materials for High Temperature Service
9. ASTM A194 Carbon and Alloy Steel Nuts for Bolts for High Pressure and High Temperature Service
10. ASTM A307 Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength
11. ASTM F3125 Standard Specification for High Strength Bolts ASTM A325 Structural Bolts, Steel, Heat Treated, 120/105 ksi
12. ASTM A500 Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
13. ASTM A992 Steel for Structural Shapes for Use in Building Framing
14. ASTM B21 Standard Specification for Naval Brass Rod, Bar, and Shapes
15. ASTM D412 Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
16. ASTM D471 Standard Test Method for Rubber Property - Effect of Liquids
17. ASTM D572 Standard Test Method for Rubber - Deterioration by Heat and Oxygen
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -2
18. ASTM D2137 Standard Test Method for Rubber Property – Brittleness Point of Flexible Polymers and Coated Fabrics
19. ASTM D2240 Standard Test Metod for Rubber Property – Durometer Hardness
American Welding Society (AWS)
1. AWS D1.1 Structural Welding Code – Steel
2. AWS D1.6 Structural Welding Code – Stainless Steel
3. AWS QC1 Qualification and Certification of Welding Inspectors
The Society for Protective Coatings
1. SP-1 Solvent Cleaning
2. SP-7 Brush-Off Blast Cleaning
CONTRACTOR SUBMITTALS
Submit the following in accordance with the requirements of Section 01 33 00 – Submittals:
All submittals shall be provided in electronic format and include the following:
The contractor shall prepare and submit shop drawings for the steel stoplogs and the lifting beam. The dimensions and reference materials of construction by ASTM designation and grade shall be shown in the drawings. Also include complete fabrication and weld details, tolerances and finish requirements.
1. The weights of all major items shall be listed.
2. Fabrication schedule.
Shop inspection and test plan.
1. Weld procedure specifications, procedure qualification records including all destructive and nondestructive test results and welding bead profiles as required along with individual welder qualification certificates.
Certified copies of material test reports.
Manufacturer’s data sheet for each product proposed, including statements on the suitability of the material for the intended use.
Paint manufacturer’s color chart, instructions and recommendations on surface preparation and application.
Material Safety Data Sheet (MSDS) for each product proposed.
Quality control records of all material test reportsrecords, shop inspection and testing, dimensional checks and test data.
QUALITY ASSURANCE
Establish and maintain quality control for the Work specified to ensure compliance with the Contract Documents during fabrication.
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -3
Fabricate structural steel members in accordance with the AISC Code of Standard Practice and additional tolerances indicated on design drawings, if any.
Perform welding with electric arc process and in accordance with AWS D1.1, "Structural Welding Code".
In addition to complying with pertinent codes and regulations, comply with:
1. AISC “Code of Standard Practice for Steel Buildings and Bridges”.
2. AISC “Specifications for the Design, Fabrication, and Erection of Structural Steel Buildings” and including the “Commentary on the AISC Specification”.
QUALITY RECORDS
Inspection of all materials to be used for fabrication before starting fabrication.
Maintenance of all quality control records during fabrication.
Maintenance of all records of shop inspections, including dimensional tolerances, finishes, mating of interfacing parts, and non-destructive testing of welds.
MAXIMUM FABRICATION DURATION
The Contractor may determine and schedule the pickup date of the equipment at its discretion.
However, once the equipment is picked up, the Contractor shall comply with the following schedule requirements:
1. 21-Day Modification Period: Beginning on the date of pickup, Contractor has 21 days to modify the equipment and prepare it for the Owner’s shop inspection.
2. Scheduling the Shop Inspection: Contractor will comply with the advance notice requirement specified in this document. Unless authorized or directed by the Owner’s Representative, the Contractor shall schedule the shop inspection to occur not later than three (3) days after the end of the Contractor’s 21-day modification period.
3. Post Inspection Adjustments and Delivery: Following the shop inspection, the Contractor has five (5) days to make any required post-inspection adjustments and deliver the equipment to the Owner.
GENERAL
All materials incorporated in the modification work shall be new and both workmanship and materials shall be of first-class quality, free from defects and imperfections, and, where indicated on the Plans, of the classification and grades designated therein.
Material standards including grade, class, or type shall be shown on shop drawings prepared by Contractor. If equivalent material standards are to be used, complete details of the standards shall be submitted for review and approval by the BIA Contracting Officer’s Representative, including a list of the materials, their ASTM equivalents, and the identification of components of equipment for which they are to be used.
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -4
Defective material shall not be repaired and used in the construction of the equipment without prior approval. No peening, caulking, or filling shall be permitted in repairing cracks, pinholes, or blowholes. Defects in welds shall be repaired by chipping out to sound metal and re-welding.
Repair materials in accordance with ASTM or similar standards to the extent and in the manner permitted by the standards.
MATERIALS
Steel
Table 2.1 Wide Flange Shapes ASTM A992 Shapes, Plates, Bars ASTM A36 Pipe, Pipe Columns, Bollards ASTM A53, Type E or S, Grade B standard weight unless indicated otherwise HSS ASTM A500 Grade B
Rubber Seals
1. The rubber water seals shall be the product of a reputable seal supplier such as Seals Unlimited, 6410 NE Jacobson St., Hillsboro, OR 97124 (information available online at:
www.sealsunlimited.com) or approved equal.
2. The seals shown on the drawings shall be neoprene of EPDM compounded and cured to provide the physical properties listed in Table 2.2
Tests to determine physical properties of the seals material shall be conducted in accordance with applicable provisions of the test methods listed in Table 2.2. Specimens for seal tests shall be prepared from each batch of compound mixed for use in fabricating the seals to be furnished.
Table 2.2 – Physical Properties of Seals Physical Property ASTM Test Method Quantity
Minimum Ultimate Tensile Strength (lb/in2)
D 412, Method A 2,500
Minimum Elongation at Break (Percent) D 412 450 Shore A Durometer Hardness (Unitless) D 2240 60 to 70 Maximum Absorption of Water (70 hours @ 100º C; Percent Change in Volume)
D 471 10
Maximum Compression Set (Percent of Original Test Deflection)
D 395, Method B 30
Minimum Tensile Strength after Oxygen Bomb Aging (Percent of Ultimate Tensile Strength Before Aging)
D 572 80
Low Temperature Brittleness D 572
Non-brittle after 3 minutes @ -40º C
Maximum Change in Weight (46 Hours in Water at 70º C; Percent)
D 471 5
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -5
3. Seal strips shall be molded or extruded in convenient lengths and, if necessary, shall be butt spliced together by vulcanizing to obtain the minimum continuous lengths shown on the drawings. The number of splices in a required minimum continuous length of seal strip, not including splices with corner seals, shall not exceed one for each 9 feet of length and the minimum length of seal strip for splicing shall not be less than 2 feet.
4. All seal splices shall be vulcanized in molds using heat and pressure. Wrapped splices are not acceptable. Each splice shall have sufficient strength to allow 50 percent elongation over an element of seal strip which includes the splice. All splicing shall be performed by the seal manufacturer. To demonstrate the integrity of the splice process, the seal manufacturer shall perform at least two elongation tests of a sample seal splice in accordance with test method of ASTM designation: D 412. The sample splice joint shall be prepared with elements of seal strips made from the same batch compound mixed for use in fabricating the seals to be furnished. The results of these elongation tests shall be made available to the Government, upon request. Between initial fabrication of seal splices and final acceptance of installed seals by the Government, any splices that fail for show deficiencies (e.g., separation, holes, incomplete bonding, misalignment, etc.)
shall be re-spliced.
At vulcanized splices, the dimensions of the cross sections to be joined shall be matched to avoid any pronounced offsets that might result in leakage. For joints in music-note seals, the cylindrical sealing surface of the bulb and the face of the stem that is tangent to the bulb shall be flush. Offsets to these surfaces at all spliced joints shall be buffed flush with a transition slope not exceeding 1/16 inch in 24 inches of seal length.
The splices that are not designated to be vulcanized shall be cemented together at shop installation, by the stoplog fabricator. At final assembly, seal joint surfaces shall be buffed with 80-grit sandpaper and joined together with cement recommended by seal manufacturer.
5. Tolerances for the cross section dimensions of music-note seals are shown on drawings 40-D-6274 and 40-D-6275.
6. The contractor shall be responsible for all costs and time delays resulting from defective seals, including any additional testing required by the Government to ensure that sound and durable seals have been obtained.
7. Corner seals shown on drawing 1117-D-589 shall be molded in once piece or vulcanized as shown, with sufficient excess length to allow for cutting and fitting to the joint locations dimensioned on the drawings.
8. The seals shall be fabricated and cured in such a manner that any cross section will be dense, homogeneous, and free from porosity and other imperfections. Exterior surfaces of the seals shall be free from pits, blisters, and other imperfections that will impair sealing. Dimensions shall be uniform from one seal cross section to the next. Variations in dimensions between cross section of continuous seal strips shall not exceed a rate of change of 1/16 inch in 24 inches of seal length, except that measurements of cross sections should not be checked at intervals less than 6 inches apart.
9. Unless otherwise specified, all hardware for new rubber seals shall be of stainless steel ASTM A276, type 304/316 with stainless steel plain washer and neoprene seal washer.
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -6
The nuts used with stainless steel bolts shall be of bronze per ASTM B 21, Alloy No.
464 half hard (naval brass).
Stainless Steel
1. Unless otherwise indicated, stainless steel metalwork and bolts shall be fabricated from Type 304 stainless steel.
Ultra-High Molecular Weight Polyethylene (UHMW)
1. UHMW material shall be in accordance with ASTM D4020; virgin, extruded or molded, white
STRUCTURAL STEEL FABRICATION
Design and fabrication of structural parts shall conform to the applicable provisions of the AISC Specifications for the Design, Fabrication, and Erection of Structural Steel forBuildings, andof the AISC, Code of Standard Practice for Steel Buildings and Bridges.
Fabrication and assembly shall be performed in the shop.
All bolts, nuts, screws, rivets, threads, pipe, and measurements or dimensions shown on the Plans shall conform to English standards.
Manufacturing Process. The Contractor shall be responsible for the proper selection of manufacturing methods and assembly. The Contractor shall also be responsible for the correct fit of parts.
Workmanship. All work shall be performed and completed in a thorough workmanlike manner and shall follow the best modern practices in the design and manufacture of heavy welded structures. All work shall be done by personnel skilled in the related professions and operations. All parts shall be made accurately to standard gages so as to facilitate replacement and repairs. All special gages and templates necessary for field erection shall become the property of the Government. Like parts shall be interchangeable wherever possible. Machining fits on renewable parts shall be accurate and to specific dimensions so that replacements made to the size shown on the shop drawings may be readily installed.
Structural Steel Fabrication and Erection. Material must be straight before being laid off or worked. If straightening is necessary, it shall be done by methods that will not impair the metal.
Sharp kinks or bends shall be cause for rejection of the material. Material with welds will not be accepted except where welding is definitely specified, indicated or otherwise approved.
Bends shall be made by approved dies, press brakes or bending rolls. Where heating is required, precautions shall be taken to avoid overheating the metal and it shall be allowed to cool in a manner that will not impair the original properties of the metal. Proposed flame cutting of material other than structural steel shall be subject to approval of the BIA Contracting Officer’s Representative and shall be indicated on shop drawings. Shearing shall be accurate and all portions of the work shall be neatly finished. Corners shall be square and true unless otherwise shown on the Plans. Re-entrant cuts shall be filleted to a minimum radius of 3/4-inch unless otherwise approved by the BIA Contracting Officer’s Representative. Finished members shall be free of twists, bends and open joints. Steel may be cut by mechanically guided or hand guided torches, provided an accurate profile with a surface that is smooth and free from cracks and notches is obtained. Surfaces and edges to be welded shall be prepared in accordance with
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -7
AWS D1.1. Where structural steel is not to be welded, chipping or grinding will not be required except as necessary to remove slag and sharp edges of mechanically guided or hand guided cuts not exposed to view. Hand guided cuts which are to be exposed or visible shall be chipped, ground or machined to sound metal.
Dimensional Tolerances for Structural Work. Dimensions shall be measured using calibrated steel tapes and measuring devices of approximately the same temperature as the material being measured. The overall dimensions of an assembled structural unit shall be within the tolerances indicated on the drawings, as specified in the particular section of the contract documents for the item of work, or as required for the proper operation of the equipment. Where tolerances are not specified an allowable variation of 1/32-inch is permissible in the overall length of component members with both ends milled. Component members without milled ends shall not deviate from the dimensions shown by not more than 1/16 inch for members 30 feet or less in length and by more than 1/8-inch for members over 30 feet in length. Erection tolerances not specified shall be as noted in AISC S303, Code of Standard Practices for Steel Buildings and Bridges, Section 7.
SHOP WELDING
Codes. All welding shall be welded in accordance with AWS D.1 or D1.6, as applicable. The Contractor shall be responsible for developing the procedure and performing the welding in accordance with the approved procedure at no additional cost to the Government.
General. All welds shall be continuous and watertight. All welding shall be performed by the electric-arc method, by a process that excludes the atmosphere from the molten metal, and where practicable, by automatic machines. Machined surfaces of parts affected by welding shall be machined to final dimensions after welding. Machined surfaces of parts requiring stress relief shall be machined to final dimensions after the parts have been stress relieved.
Localized stress relieving shall not be permitted on shop welded parts. Welder qualification, weld procedure qualification, base metal preparation, preparation for welding, weld electrode selection, weld finish, inspection and acceptance criteria and methods used in correcting defective welds shall be per AWS D1.1. Certificates of welders' qualifications shall be submitted when requested. Weld procedures shall be submitted for approval by the Engineer.
Minimum Weld Requirements. Unless noted otherwise in the contract documents, the minimum size of fillet welds shall be 1/4-inch measured on the leg. Welds larger than 5/16-inch shall not be made in less than two passes. All groove welds including butt welds shall be full penetration, welded from both sides.
Filler Metal. The electrode and electrode-flux combination shall conform to the appropriate AWS specification for the base metal and welding process being used and shall not have a minimum tensile stress less than the strength of the base or parent metal. The AWS designation of the electrodes to be used shall be included in the schedule of welding procedures. Only low hydrogen electrodes shall be used for manual shielded metal-arc welding. A controlled temperature storage oven shall be used at the job site as to maintain low moisture of low hydrogen electrodes.
Welding of Splices. Splice welds shall be made using AISC approved pre-qualified full penetration welds, ground flush after welding.
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -8
Weld Finish. Welds shall in general be treated so that they will display good appearance and a surface suitable for painting. Welds shall be ground and blended to eliminate stress risers. All welds that require nondestructive examinations shall be dressed by chipping and grinding as required for good interpretation by the selected weld examination method. Final grinding marks shall be perpendicular to the weld axis.
Repair of Welds. Defects in welds shall be repaired and re-tested per AWS D1.1. Defective welds shall be repaired and re-inspected at no additional cost to the Government.
Stress Relief Heat Treatment. Where stress relief heat treatment is specified or shown on the Plans it shall be in accordance with the requirements of AWS D1.1 unless otherwise authorized or directed by the Engineer.
Inspector Qualification. All shop and field welding inspectors shall be qualified in accordance with the requirements of AWS QC1 and nondestructive testing personnel shall be qualified in accordance with the requirements of ASNT 01 for Levels I or II in the applicable nondestructive testing method. The inspector may be supported by assistant welding inspectors who are not qualified to ASNT 01, and assistant inspectors may perform specific inspection functions under the direct supervision of the qualified inspector.
Nondestructive Testing of Welds
1. General. The Contractor shall maintain an approved inspection system and perform required inspections in accordance with the Contractor’s approved welding procedures.
2. Examination of Welds. Examination of Welds shall be as follows:
a. All (100%) completed welds shall be cleaned and carefully examined for insufficient throat or leg sizes, cracks, undercutting, overlap, excessive convexity or reinforcement and other surface defects.
b. All fillet welds shall be given a complete (100%) non-destructive examination by liquid penetrant (PT) methods, as applicable.
c. All partial penetration welds shall be tested by PT method.
d. All full penetration welds other than butt welds shall be given non-destructive examination throughout their entire length by ultrasonic examination (UT), followed by radiographic examination (RT) if UT results are not clear, or by PT if RT is not feasible.
e. Butt welds shall be examined by UT or PT if UT is not feasible.
3. Acceptance Criteria. All welds shall comply with the requirements of AWS D1.1.
4. All welds found to be defective shall be repaired prior to stress relieving. Where stress relieving is required, non-destructive examination shall be performed after stress relieving.
5. Non-Destructive Testing Agency. The nondestructive examination of welds and the evaluation of examination tests as to the acceptability of the welds shall be performed by a testing agency or by the contractor using suitable equipment and qualified personnel.
Personnel performing nondestructive testing shall be qualified and certified in accordance with the requirements of AWS QC-1-88. Non-destructive testing personnel
"\\dowl.com\j\Projects\26\12494-01\81Specs\Mod14_LiftingBeam\40 05 59.16 - Steel Stoplogs.docx" 40 05 59.16 -9 shall be qualified Level II inspectors as qualified under a certified program meeting the guidelines of the American Society of Non-Destructive Testing (ANST) standard SNT- TC-1A. The company performing non-destructive testing shall have employed a Level III inspector as qualified under a certified program meeting the guidelines of SNT-TC- 1A to supervise the Level II inspectors. If requested by the Government, the Contractor shall submit, 14 days prior to beginning of testing, sufficient documentation demonstrating that the testing personnel are qualified.
6. Non-Destructive Testing Documentation. The Contractor shall maintain documentation of all visual and…