This is a Performance Work Statement (PWS) for lift station repairs at the 180th Fighter Wing facility in Swanton, Ohio.

The contractor shall replace one failed submersible pump with a new Gorman-Rupp SF Series pump Model SFV4D and one Allen-Bradley SMC Flex Soft Starter with a new like-for-like model at the main lift station (ID: #3 near Building 149). The scope includes removal and proper disposal of old components, professional installation of new equipment, complete system testing, and commissioning to ensure full operational functionality including pump alternation and controls. The contractor must provide all personnel, equipment, tools, materials, supervision, and quality control necessary to perform the work. Work shall be performed at Building 158, 180th Fighter Wing, 2660 S. Eber Road, Swanton, OH 43558, between 0700-1600 hours Monday through Friday, excluding U.S. federal holidays. The Period of Performance is 90 days after award. Required submittals include technical data sheets for both the pump and soft starter, as-built electrical drawings, operations and maintenance manuals, and an AF Form 3000 certification of compliance. The contractor must comply with installation security requirements, obtain base identification and vehicle passes, complete Antiterrorism Level I training within 15 calendar days, and comply with all applicable fire, traffic, safety, and security regulations. Performance will be evaluated against four key objectives: safe de-energization using Lock-Out/Tag-Out procedures (100% compliance), component installation per manufacturer guidelines (100% new and correctly installed), system functionality with 100% operational test pass rate, and full commissioning with stable operation. No Government Furnished Property, Materials, Equipment, or Services will be provided.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ver. October 2022

CUI

CUI

Warranty

PERFORMANCE WORK STATEMENT (PWS)

FOR

Lift Station Repairs

1.0 General:

1.1 Scope: The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified as Government Furnished, to perform the replacement of one (1) submersible pump and one (1) soft starter at the main lift station for the 180th Fighter Wing facility, as defined in this Performance Work Statement.

1.1.1 Objectives: The primary objective is to replace a failed submersible pump with a new Gorman-Rupp SF Series pump Model SFV4D to match existing and to replace the associated Allen-Bradley SMC Flex Soft Starter with a new, like-for-like model. This includes the removal and proper disposal of the old components, the professional installation of the new pump and soft starter, and complete system testing. The final objective is to commission the system, ensure it is fully operational, and that pump alternation and controls function as required.

1.2 Background: The main lift station (ID: #3 near, Bldg. 149) is a critical component of the facility's infrastructure. One of the existing submersible pumps has failed, and its associated Allen-Bradley SMC Flex Soft Starter has been identified for replacement. To ensure the operational reliability and redundancy of the lift station, these components must be replaced promptly to restore the system to full capacity and prevent potential service interruptions.

1.3 Period of Performance (PoP): The Period of Performance shall be 90 days after award.

1.4 General Information:

1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0700 - 1600 on Monday through Friday except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be in building 158 at the 180th Fighter Wing, 2660 S. Eber Rd., Swanton, OH 43558. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring

CUI

CUI

personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.1.1 Telework: Not Applicable.

1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall always carry proper identification with them and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.

1.4.2 Recognized Holidays: The following are recognized United States (US) holidays.

The contractor shall not perform services on these days unless otherwise approved in advance by the COR and the contracting officer. Requests to work holidays shall be made a minimum of 3 working days prior to the requested day(s).

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth National Independence Day: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Columbus Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day: December 25th

1.4.3 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures

CUI

CUI

itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS).

1.4.4 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.5 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, Headquarters Air Force (HAF) and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

a. The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

b. The contractor shall submit a written request on SFS FORM 77 to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid drivers license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.

c. During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

d. Reserved.

CUI

CUI

e. Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

f. Failure to comply with these requirements may result in withholding of final payment.

1.4.5.1. For Contractors Requiring Common Access Card (CAC). Not Required.

1.4.5.2 For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Air Force Instruction (AFI) 10-245, AFI 31-101 and Air Force Manual (AFMAN) 31-113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative)

1.4.5.3 Antiterrorism Awareness Level I Training (AT Level I). All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the unit AT Representative. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel.

1.4.5.4 Reserved.

1.4.5.5 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

http://jko.jten.mil/

1.4.5.6 Reserved

1.4.5.7 Reserved.

1.4.5.8 Reserved

1.4.5.9 Reserved

1.4.5.10 Reserved

1.4.5.11 Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/Signature Managers/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees’ initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) is located on the ADLS website and refresher OPSEC training is conducted annually (at Commander's Call). The contractor shall submit certificates of completion for each contractor employee to the COR within 15 calendar days after completion of training.

1.4.5.12 OPSEC Plan. Not Required.

1.4.5.13 Contracts that require Handling or Access to Classified Information: Not Required.

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control: Not Required

1.4.7 Special Qualifications: Reserved.

1.4.8 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5.

The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced.

The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

CUI

CUI

1.4.9 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO.

The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed.

1.4.10.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.11. Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at

FAR 22.17.

1.4.12 Contractor Travel: Not Applicable

1.4.13 Data Rights: Not Applicable

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost

CUI

CUI

or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Phase In / Phase Out Periods: Not Applicable

2.0 Definitions and Acronyms:

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

CUI

CUI

2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AEI Army Enterprise Infostructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense DSCA Defense Counterintelligence and Security Agency FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SCR Service Contract Reporting SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):

The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: None

3.2 Materials: None

3.3 Equipment: None

3.4 Services: None

3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E): RESERVED

5.0 Requirements: The contractor shall furnish all supervision, labor, materials, equipment, and supplies required to perform the work specified in this document in strict accordance with the specifications for this project and provide the government a complete and useable end product.

5.1 Main Lift Station Pump and Soft Starter Replacement:

5.1.1 Safely de-energize and perform Lock-Out/Tag-Out on all associated electrical systems for the main lift station before commencing work.

5.1.2 Remove the failed submersible pump from the wet well. The contractor shall be responsible for coordinating any necessary support, such as a crane or vactor truck, if required for the removal.

5.1.3 Remove the existing Allen-Bradley SMC Flex Soft Starter from the main control panel.

5.1.4 Install one (1) new Gorman-Rupp SF Series submersible pump. The model shall match the existing operational pump in the lift station (see attached SFEV4D Spec Sheet.pdf for specifications).

5.1.5 Install one (1) new soft starter. The contractor shall provide a new soft starter that is appropriately sized, fully compatible with the new Gorman-Rupp SFEV4D series pump, and serves as a direct replacement for the existing Allen-Bradley SMC Flex Soft Starter.

5.1.6 Perform all necessary electrical wiring and connections for the new pump and soft starter in accordance with the National Electric Code (NEC), manufacturer's instructions, and all applicable regulations.

5.1.7 Restore power and perform a system start-up. The contractor shall test all operational modes (e.g., Hand, Off, Auto), verify proper pump cycling, and confirm that the pump alternation sequence is functioning correctly.

5.1.8 The contractor shall be responsible for the removal and proper disposal of the old pump and soft starter in accordance with all environmental regulations.

5.2 Submittals: Submit technical data, catalog cut sheets, samples, test reports or other items as listed below:

5.2.1 Technical data/cut sheets for the new Gorman-Rupp submersible pump.

5.2.2 Technical data/cut sheets for the new soft starter.

CUI

CUI

5.2.3 As-built drawings – Provide an as-built drawing of new or modified electrical circuits.

5.2.4 Operations and maintenance manuals, and operating instructions for all installed equipment.

5.2.5 Submittals shall be provided with an AF Form 3000 filled out and signed by the contractor certifying the material is in compliance with the project requirements.

5.3 General:

5.3.1 Portable Toilet: Not applicable for this project – use facility bathrooms

5.3.2 Some of the work area is adjacent to the aircraft parking apron and is a secure restricted area.

5.3.3 Vehicles and equipment going onto the parking apron shall be inspected and checked for Foreign Object Debris (FOD) by the contractor prior to going on to the apron. All debris and objects which could become FOD shall be removed and properly disposed of or secured.

5.3.4 Smoking on base is only allowed in designated areas (smoking sheds are marked with signs).

5.3.5 The contractor shall verify existing dimensions and conditions prior to submitting a bid and again prior to beginning work.

5.3.6 The contractor shall provide the government project manager or COR 7 days written notice before performing any disturbance of the ground to a depth below 3”. The notice shall include a drawing of the area where the work is to be done.

Mark the work area and proposed excavations with white flags or marking paint if required by the government, so existing utilities can be properly identified before beginning any demolition or excavation. Contractor shall ensure an approved Air Force Form 103 Work Clearance is issued before beginning any excavations.

5.3.7 Provide a minimum of 7 days advance notice in writing to the Contracting Officer or COR prior to the shutdown of any building utility system, street, or parking lot.

5.3.8 The contractor shall insure that all work complies with all federal state and local laws and ordinances applicable to the construction of this project. Install all equipment according to the manufacturer’s written instructions. If a conflict is found, notify the Contracting Officer for resolution of the conflict prior to proceeding.

5.3.9 Prior to performing any operation requiring use of an open flame, or spark producing work obtain a burn permit from the base fire department (419-868- 4116). The contractor shall provide and maintain fire extinguishers and other safety equipment at the job site at all times as required to perform the work.

5.6 Service Contract Reporting: Reserved for projects over $3 million.

CUI

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication

Mandatory or Advisory

Website

Federal Acquisition Regulation Advisory https://www.acquisition.gov/?q=browsefar Defense Federal Acquisition

Regulation Supplement Advisory http://www.acq.osd.mil/dpap/dars/dfarspgi/current/in dex.html or https://www.acquisition.gov/dfars Joint Travel Regulation (JTR) Advisory https://www.defensetravel.dod.mil/site/travelreg.cfm

DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b)

01/23/2014 (Change 1:

07/28/2020)

Advisory http://www.esd.whs.mil/Directives/issuances/dodm

Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors

(paragraph 9)

August 2013 Advisory http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201 -2.pdf

DoDM 5200.2 Procedures for the DoD Personnel Security Program

(PSP)

04/03/2017 Advisory https://www.esd.whs.mil/Directives/issuances/dodm/

DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common

Access Card (CAC)

09/09/14 (Change 1:

05/04/2018)

Advisory https://www.esd.whs.mil/Directives/issuances/dodi/

Homeland Security Presidential Directive (HSPD)-12

Policy for a Common Identification Standard for Federal Employees and

Contractors

08/27/2004 Advisory https://www.dhs.gov/homeland-security-presidential-directive-12

DoDI 5400.11 Department of Defense Privacy and

Civil Liberties Programs

01/29/2019

Advisory https://www.esd.whs.mil/Directives/issuances/dodi/

DoD 5400.11-R Department of Defense Privacy

Program

05/14/2007 Advisory https://www.esd.whs.mil/Directives/issuances/dodm/

DoDD 8140.01 Cyberspace Workforce Management

10/05/2020

Advisory https://www.esd.whs.mil/Directives/issuances/dodd/

DoD 8570.01-M Information Assurance Workforce

Improvement Program

12/19/2005 (Change 4:

11/10/2015)

Advisory https://www.esd.whs.mil/Directives/issuances/dodm/

DoD 5220.22-M National Industrial Security Program

Operating Manual (NISPOM)

02/28/2006 (Change 2:

05/18/2016)

Advisory https://www.esd.whs.mil/Directives/issuances/dodm/

AFI 10-245

Antiterrorism

03/28/2013 (Certified current

03/30/2017)

Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

AFI 31-101

Security Forces Standards and

Procedures

08/18/2020 Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

AFMAN 31-113

Security Forces Standards and Procedures

03/05/2013 Change 1:

12/02/2015

Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131 https://www.acquisition.gov/?q=browsefar http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html https://www.acquisition.gov/dfars http://www.esd.whs.mil/Directives/issuances/dodm http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf https://www.esd.whs.mil/Directives/issuances/dodm/ https://www.esd.whs.mil/Directives/issuances/dodi/ https://www.dhs.gov/homeland-security-presidential-directive-12 https://www.dhs.gov/homeland-security-presidential-directive-12 https://www.esd.whs.mil/Directives/issuances/dodi/ https://www.esd.whs.mil/Directives/issuances/dodd/ https://www.esd.whs.mil/Directives/issuances/dodm/ https://www.esd.whs.mil/Directives/issuances/dodm/

CUI

CUI

AFPD 17-1

Information Dominance Governance and Management

04/12/2016 Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

AFMAN 17-1301

Computer Security (COMPUSEC) 02/12/2020 Advisory https://www.e-publishing.af.mil/Product-

Index/#/?view=pubs&orgID=10141&catID=1&series =-1&modID=449&tabID=131

AFI 10-701

Operations Security

7/24/2019 (Change 1:

06/09/2020)

Advisory https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&catID=1&series

=-1&modID=449&tabID=131

6.1 Applicable Forms: Forms applicable to the PWS are listed below:

Form Date Website AF Form 3000 Material Approval

Submittal Most recent version

CUI

TECHNICAL EXHIBIT 1

Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance

Objective Performance Standard Acceptable Quality

Levels (AQL) Surveillance Method / By

Whom

Safe De-energization

The lift station is safely de-energized using proper Lock-

Out/Tag-Out procedures before any work commences.

100% compliance with established LOTO safety protocols.

Visual inspection of LOTO application and verification log.

Component Installation

The new pump and soft starter are new and installed correctly per manufacturer guidelines and electrical codes.

100% of specified components are new and correctly installed.

Visual inspection and review of service report by COR.

System Functionality

The system starts successfully, runs without faults or leaks, and operates correctly in all modes (Hand, Off, Auto).

100% pass rate on operational tests.

Operational demonstration witnessed by COR.

Commissioning The lift station is fully operational, with pump alternation functioning correctly and meeting performance specifications.

100% system functionality with stable operation.

Commissioning test and review of system performance data by COR.

CUI

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title

Frequency Number of Copies

Medium/Format Submit To

5.1.7 Detailed Service &

Commissioning Report

Once, at with final report 1 Electronic Submission

(PDF)

COR

1.4.5.3 AT Level 1

Awareness Training Certificates

Provide within 15 calendar days after employee completes training.

1 Electronic Submission

COR

1.4.5.11

OPSEC

Training Certificates

Provide within 15 calendar days after employee completes training.

1 Electronic Submission

COR

1.4.10 Identification Media

Return within 14 days of employee’s departure from contract performance.

Original(s) Hard Copy KO

1.4.5.1. For Contractors Requiring Common Access Card (CAC). Not Required.