LGA-124.881 Contract booklet.pdf

PDF 12 MB Posted

Attached to
LaGuardia Airport - Rehabilitation of Taxilane 0
Solicitation number
CONTRACT LGA-124.881
Issued by
Queens County, New York

About this file

This is a contract booklet for Construction Contract LGA-124.881 issued by The Port Authority of New York and New Jersey for the rehabilitation of Taxilane 0 at LaGuardia Airport in Queens, New York. The work consists of milling, excavating, paving, pavement markings, drainage systems, and related construction at Taxilane 0 and vicinity thereof. Bids are due by 2:30 PM EST on Thursday, November 5, 2026, and must be submitted electronically via the Bonfire platform at https://panynj.bonfirehub.com/portal/?tab=login. Prospective bidders must make proper arrangements with the Engineer at the construction site before inspection by contacting Joseph Lewis at (347) 392-1744 or jlewis@panynj.gov. Questions concerning the contract must be submitted to Alvin Chen at (212) 435-4636 or alchen@panynj.gov no later than 5:00 PM on the day which is 14 calendar days before the bid due date. The contract time to final completion is 596 calendar days. The Authority will accept bids until 90 days after opening, with award made to the responsible bidder submitting the lowest responsive, technically qualified bid.

The estimated contract price range is $5 million to $10 million. A bid bond in the amount of 5% of the total contract price is required. Liquidated damages for failure to complete on time are $3,000 per calendar day. Prevailing wage rates following Davis Bacon (Federal) standards apply. The project is anticipated to be funded in whole or in part by the Federal Aviation Administration (FAA) and is therefore subject to federal provisions including Title VI of the Civil Rights Act of 1964, the Airport and Airway Improvement Act of 1982, and other federal civil rights requirements. Bidders must meet specific prerequisite qualifications, including completion of at least two comparable contracts within an Air Operations Area (AOA) within the past ten years as a prime or general contractor, and the project manager and superintendent must each have a minimum of five years of construction experience on comparable contracts within an operating airport environment. A Background Qualification Questionnaire (BQQ) is required for subcontractors and vendors with anticipated subcontract values of $100,000 or greater. The contract is designated as Design-Bid-Build with compensation on a combination basis.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CA02124881

FAA

K.M.

LAGUARDIA AIRPORT

REHABILITATION OF TAXILANE 0

CONTRACT LGA-124.881

NOVEMBER 2026

This bid is not complete unless bidder's Signature appears on page 26 and Bid Forms in the

Information for Bidders are completed https://www.panynj.gov

COMMISSIONERS

Kevin J. O'Toole, Chairman Jeffrey H. Lynford, Vice Chairman

J. Christian Bollwage

Fanny Cedano

Marie Therese Dominguez

Leecia Eve

Elizabeth R. Fine

Winston Fisher

George Helmy

Joseph Kelley

Gary LaBarbera

Kevin P. McCabe

EXECUTIVE STAFF

Kathryn Garcia, Executive Director

Jean Roehrenbeck, Deputy Executive Director

Amy Fisher, General Counsel

Elizabeth McCarthy, Chief Financial Officer

James Heitmann, Chief Operating Officer

Derek H. Utter, Chief Development Officer

M. Rizwan Baig, Chief Engineer/Director

Luke S. Bassis, Chief Procurement Officer

John Gay, Inspector General

Edward Cetnar, Director, Public Safety Department

Jessica Gummerman, Secretary

Catherine Britell, Director, Tunnels, Bridges & Terminals Department

Clarelle DeGraffe, Director, Rail Transit Department

Sarah K. McKeon, Director, Aviation Department

Bethann Rooney, Director, Port Department

Jolene Yeats, Director, World Trade Center Department https://www.panynj.gov i

TABLE OF CONTENTS

ADVERTISEMENT ........................................................................................................................................A

CONTRACT INFORMATION SUMMARY ................................................................................................S

INFORMATION FOR BIDDERS

1. FORM AND SUBMISSION OF BIDS

2. PREREQUISITES

3. PAPERS ACCOMPANYING BIDS

4. QUALIFICATION INFORMATION

5. ACCEPTANCE OR REJECTION OF BID

6. RETURN OF CERTIFIED CHECKS

7. WEBSITE POSTINGS OF CONTRACT DOCUMENTS

8. DISPOSAL OF CONTRACT DOCUMENTS

9. AVAILABLE DOCUMENTS

10. DISADVANTAGED BUSINESS ENTERPRISES PROGRAM (DBE)

11. INSPECTION OF SITE

12. QUESTIONS BY BIDDERS

13. PREVAILING RATE OF WAGE CERTIFICATION

14. CERTIFICATION OF NO INVESTIGATION (CRIMINAL OR CIVIL ANTI-TRUST),

INDICTMENT, CONVICTION, SUSPENSION, DEBARMENT, DISQUALIFICATION,

PREQUALIFICATION DENIAL OR TERMINATION, ETC.; DISCLOSURE OF OTHER

REQUIRED INFORMATION

15. NON-COLLUSIVE BIDDING AND CODE OF ETHICS CERTIFICATION; CERTIFICATION

OF NO SOLICITATION BASED ON COMMISSION, PERCENTAGE, BROKERAGE,

CONTINGENT FEE OR OTHER FEE

16. BIDDER ELIGIBILITY FOR AWARD OF CONTRACTS - DETERMINATIONS BY AN

AGENCY OF THE STATE OF NEW YORK OR NEW JERSEY CONCERNING ELIGIBILITY

TO RECEIVE PUBLIC CONTRACTS

17. CONTRACTOR PERFORMANCE EVALUATIONS

18. THE EDWARD J. MALLOY CONSTRUCTION INITIATIVE FOR CONSTRUCTION SKILLS -

APPRENTICESHIP PROGRAM

19. CERTIFICATION OF PARTICIPATION IN A STATE-REGISTERED APPRENTICESHIP

PROGRAM

20. JOB MIX SUBMITTAL

21. BUY AMERICAN CERTIFICATE

22. BID FORMS

PART 1 - GENERAL CONTRACT PROVISIONS

FORM OF CONTRACT

ii

CHAPTER I - GENERAL PROVISIONS

23. DEFINITIONS

24. GENERAL AGREEMENT

25. AUTHORITY ACCESS TO RECORDS

26. INTEGRITY MONITOR

27. RENTAL OF CONSTRUCTION EQUIPMENT

28. EXEMPTION FROM NEW YORK STATE AND NEW YORK CITY SALES TAXES

29. CODE OF ETHICS FOR PORT AUTHORITY VENDORS

30. PERFORMANCE AND PAYMENT BOND

CHAPTER II - COMPENSATION AND PAYMENTS

31. UNIT PRICES AND LUMP SUM FOR UNCLASSIFIED WORK

32. ADJUSTMENTS OF LUMP SUM FOR UNCLASSIFIED WORK

33. COMPENSATION FOR EXTRA WORK

34. COMPENSATION FOR PREMIUM TIME

35. COMPENSATION FOR EMERGENCY DELAYS

36. MONTHLY PAYMENTS

37. PROMPT PAYMENT AND RETAINAGE

38. RELEASE OF MONIES PREVIOUSLY WITHHELD FROM MONTHLY PAYMENTS UPON

RENDITION OF A CERTIFICATE OF SUBSTANTIAL COMPLETION

39. FINAL PAYMENT

40. WITHHOLDING OF PAYMENTS

CHAPTER III - PROVISIONS RELATING TO TIME

41. TIME FOR COMPLETION AND LIQUIDATED DAMAGES

42. EXTENSIONS OF TIME

43. IDLE SALARIED MEN AND EQUIPMENT

44. DELAYS TO CONTRACTOR

45. CANCELLATION FOR DELAY

CHAPTER IV - CONDUCT OF CONTRACT

46. AUTHORITY OF DIRECTOR

47. AUTHORITY OF CHIEF ENGINEER

48. AUTHORITY AND DUTIES OF ENGINEER

49. NOTICE REQUIREMENTS

50. NON-DISCRIMINATION REQUIREMENTS

51. AFFIRMATIVE ACTION PROGRAMS

52. PREVAILING RATE OF WAGE

53. MINIMUM WAGE RATES

iii

54. EXTRA WORK ORDERS

55. PERFORMANCE OF EXTRA WORK

56. TITLE TO MATERIALS

57. ASSIGNMENTS AND SUBCONTRACTS

58. CLAIMS OF THIRD PERSONS

59. CERTIFICATES OF PARTIAL COMPLETION

60. CERTIFICATE OF SUBSTANTIAL COMPLETION

61. CERTIFICATE OF FINAL COMPLETION

62. NO GIFTS, GRATUITIES, OFFERS OF EMPLOYMENT, ETC

63. OBLIGATION TO REPORT

64. CONTRACTOR RESPONSIBILITY, SUSPENSION OF WORK AND TERMINATION

65. CONFLICT OF INTEREST

66. RIGHT TO AUDIT

CHAPTER V - WARRANTIES MADE AND LIABILITY ASSUMED BY THE CONTRACTOR

67. CONTRACTOR'S WARRANTIES

68. RISKS ASSUMED BY THE CONTRACTOR

69. NO THIRD PARTY RIGHTS

70. INSURANCE PROCURED BY THE AUTHORITY

71. INSURANCE PROCURED BY CONTRACTOR

CHAPTER VI - RIGHTS AND REMEDIES

72. RIGHTS AND REMEDIES OF AUTHORITY

73. TERMINATION FOR CONVENIENCE

74. CONTRACTOR'S DEFAULT

75. RIGHTS AND REMEDIES OF CONTRACTOR

76. PERFORMANCE OF WORK AS AGENT FOR CONTRACTOR

77. NO ESTOPPEL OR WAIVER

CHAPTER VII - FEDERAL AVIATION ADMINISTRATION REQUIREMENTS

78. FEDERAL AVIATION ADMINISTRATION REQUIREMENTS

CHAPTER VIII - MISCELLANEOUS

79. SUBMISSION TO JURISDICTION

80. PROVISIONS OF LAW DEEMED INSERTED

81. INVALID CLAUSES

82. NON-LIABILITY OF THE AUTHORITY REPRESENTATIVES

83. SERVICE OF NOTICES ON THE CONTRACTOR

84. MODIFICATION OF CONTRACT

iv

85. PUBLIC RELEASE OF INFORMATION

SPECIFICATIONS

DIVISION 01 - GENERAL PROVISIONS

86. CONSTRUCTION REQUIRED BY THE SPECIFICATIONS

87. AVAILABLE PROPERTY

88. CONSTRUCTION SITE SECURITY REQUIREMENTS

89. OPERATIONS OF OTHERS

90. LABOR ACTIONS

91. CONTRACTOR'S MEETINGS

92. CONTRACT DRAWINGS

93. REFERENCE DOCUMENTS

94. SHOP DRAWINGS, CATALOG CUTS AND SAMPLES

95. SUBSTITUTION

96. WORKMANSHIP AND MATERIALS

97. INSPECTIONS AND REJECTIONS

98. MANUFACTURERS' CERTIFICATION

99. NO RELEASE OF CONTRACTOR

100. ERRORS AND DISCREPANCIES

101. DIFFERING SUBSURFACE CONDITIONS

102. ACCIDENTS AND FIRST AID PROVISIONS

103. SAFETY PROVISIONS

104. SUSTAINABILITY REQUIREMENTS - INFRASTRUCTURE

105. REMOVAL AND DIVERSION OF CONSTRUCTION AND DEMOLITION MATERIALS

106. AIR QUALITY PROTECTION

107. DIESEL-POWERED EQUIPMENT

108. DAILY PROGRESS, EQUIPMENT AND LABOR REPORTS

109. LAWS AND ORDINANCES

110. EQUIPMENT INFORMATION SUBMITTALS

111. SIGNS

112. CONTRACTOR'S FIELD OFFICE AND REPRESENTATIVE

113. SURVEYS

114. TEMPORARY STRUCTURES

115. PERMIT AND REQUIREMENTS FOR WELDING

116. FINAL INSPECTION

117. WARRANTIES

v

118. UTILITY DATA COLLECTION

119. REQUIREMENTS FOR CRANES AND DERRICKS

120. TEMPORARY UTILITY SERVICES

121. TEMPORARY SANITARY FACILITIES

122. PROGRESS SCHEDULE

123. SCHEDULE OF VALUES

124. AIRPORT OPERATIONS AND CONDITIONS

125. AIRPORT CONSTRUCTION SAFETY REQUIREMENTS

126. HOURS OF WORK AND CONSTRUCTION STAGING

PART 2 - GENERAL CONSTRUCTION ITEMS

ITEM C-100 CONTRACTOR QUALITY CONTROL PROGRAM (CQCP)

ITEM C-102 TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION CONTROL

ITEM C-105 MOBILIZATION

ITEM C-110 METHOD OF ESTIMATING PERCENTAGE OF MATERIAL WITHIN SPECIFICATION LIMITS

(PWL)

PART 3 - SITEWORK

ITEM P-101 PREPARATION/REMOVAL OF EXISTING PAVEMENTS

ITEM P-152 EXCAVATION, SUBGRADE, AND EMBANKMENT

PART 4 - BASE COURSES

ITEM P-209 CRUSHED AGGREGATE BASE COURSE

PART 6 - FLEXIBLE PAVEMENTS

ITEM P-401 ASPHALT MIX PAVEMENT

PART 9 - MISCELLANEOUS

ITEM P-603 ASPHALT TACK COAT

ITEM P-605 JOINT SEALANTS FOR PAVEMENTS

ITEM P-620 RUNWAY AND TAXIWAY MARKING

PART 11 - DRAINAGE

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-751 MANHOLES, CATCH BASINS, INLETS AND INSPECTION HOLES

DIVISION 02 - EXISTING CONDITIONS

026100 OFF-SITE DISPOSAL OF EXCAVATED SOIL

DIVISION 03 - CONCRETE

033010 PORTLAND CEMENT CONCRETE

033110 CONCRETE REINFORCEMENT

DIVISION 33 - UTILITIES

334443 VORTEX TYPE HYDRODYNAMIC SEPARATOR

vi

Appendix 1 - Permits

Schedule of Minimum Wage Rates (FED NY)

A

ADVERTISEMENT

THE PORT AUTHORITY OF NEW YORK AND NEW JERSEY

The Port Authority of New York and New Jersey has temporarily ceased in-person public bid openings and will allow for the digital submission of bids using the Bonfire platform, located at the link below.

Bidders MUST register in order download Bid documents and associated information regarding the below referenced solicitation and in order to upload bid submissions.

Registration on Bonfire platform requires a separate and distinct registration from all other

Authority platforms.

Sealed bids for the following contract will be received by The Port Authority of New York and

New Jersey, until 2:30 PM on the date indicated.

The Authority shall accept only those bids in electronic format for which the submission or modification is completed at the time of the Bid Due Date. Bid submissions will be accepted by upload only, at https://panynj.bonfirehub.com/portal/?tab=login and must be uploaded and received by the Authority by

2:30 PM EST on the date indicated in order to be considered. Hand deliveries and mailed deliveries (e.g., UPS, USPS) will not be accepted. The Port Authority may request an original, signed paper submission at any time following the Bid Due Date. If requested, such original, signed paper submission must be identical to the electronic submission. In the event of a discrepancy, the electronic submission shall control.

Contract documents will no longer be available for purchase at the Contract Desk on the 1st Floor, 2 Montgomery Street, Jersey City. Prospective bidders may obtain contract documents by downloading the documents directly from the Bonfire platform, by logging in to Bonfire after completing a one-time new vendor registration. The contract documents will be made available electronically to the prospective bidder at no cost, as soon as they become available. For availability of contract documents, go to https://www.panynj.gov/port-authority/en/business-opportunities/solicitations-advertisements/Construction.html. Questions by prospective bidders concerning the contract should be directed only to the person whose name and phone number is listed.

Contract LGA-124.881 – LaGuardia Airport – Rehabilitation of Taxilane 0. Estimate Range: $5M -

$10M. Bids Due: Thursday, November 5, 2026. The work under this contract consists generally of milling, excavating, paving, pavement markings, drainage systems, and related work at Taxilane 0 and vicinity thereof at LaGuardia Airport, Queens, New York. This project may be Federally funded in whole or in part. Accordingly, all bidders and the successful Contractor will be required to comply with any and all required applicable federal provisions and requirements contained in this solicitation and resulting contract. For questions call Alvin Chen at (212) 435-4636 or e-mail – alchen@panynj.gov.

https://panynj.bonfirehub.com/portal/?tab=login https://www.panynj.gov/port-authority/en/business-opportunities/solicitations-advertisements/Construction.html https://www.panynj.gov/port-authority/en/business-opportunities/solicitations-advertisements/Construction.html

A1

This Contract contains the following Prerequisites:

A. The bidder must demonstrate the following:

1.) That the bidder has completed (or substantially completed) as a prime or general contractor at least two contracts of type, size and complexity comparable to the work of this Contract within an Air Operations Area (AOA) within the past ten years.

2.) That the bidder's full-time project manager and full-time Superintendent each have a minimum of five years of construction experience on contracts of type, size and complexity comparable to the work of this Contract within operating airport environment in areas within an active AOA.

A Bid submitted by a bidder who does not meet the prerequisite Qualification Information requirements will be considered non-responsive and the bidder's Bid will not be eligible for acceptance by the

Authority.

As a condition of a grant award, the Authority shall demonstrate that it complies with the provisions of

Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d et seq.) and implementing regulations

(49 CFR Part 21) including amendments thereto, the Airport and Airway Improvement Act of 1982

(49 U.S.C. § 47123), the Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.), Section 504 of the

Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), the Americans with Disabilities Act of 1990

(42 U.S.C. § 12101, et seq.), U.S. Department of Transportation and Federal Aviation Administration

(FAA) Assurances, and other relevant civil rights statutes, regulations, or authorities, including any amendments or updates thereto. This may include, as applicable, providing a current Title VI Program

Plan to the FAA for approval, in the format and according to the timeline required by the FAA, and other information about the communities that will be benefited and impacted by the project. A completed FAA

Title VI Pre-Grant Award Checklist is required for every grant application, unless excused by the FAA.

The Authority shall affirmatively ensure that when carrying out any project supported by this grant that it complies with all federal nondiscrimination and civil rights laws based on race, color, national origin, sex, creed, age, disability, genetic information, in consideration for federal financial assistance. The

Department’s and FAA's Office of Civil Rights may provide resources and technical assistance to recipients to ensure full and sustainable compliance with Federal civil rights requirements. Failure to comply with civil rights requirements will be considered a violation of the agreement or contract and be subject to any enforcement action as authorized by law.

Additionally, all bidders (including proposers, and respondents, as applicable) are notified that the Port

Authority will ensure that, with respect to any contract/agreement entered into pursuant to this advertisement, all businesses will be afforded full and fair opportunity to submit bids, proposals and responses, as applicable, in response to this invitation, and no businesses will be discriminated against on the grounds of race, color, national origin (including limited English proficiency), creed, sex, age or disability in consideration for an award.

THURSDAY, October 1, 2026

S

CONTRACT INFORMATION SUMMARY

THE PORT AUTHORITY OF NEW YORK AND NEW JERSEY

This summary is a brief listing of selected provisions of the Contract as of the "Date Prepared" below, for the convenience of prospective bidders. These summary pages are not part of the Contract, are not necessarily accurate or complete and may not necessarily remain up-to-date or reflect the actual Contract requirements, as Contract requirements may be modified by Addendum throughout the solicitation period.

Contract No. and Title: LGA-124.881 - Rehabilitation of Taxilane 0

Summary Description of Work: milling, excavating, paving, pavement markings, drainage systems, and related Work at Taxilane 0 and vicinity thereof at LaGuardia Airport, Queens, New York

1. Estimate Range $5M - $10M

2. Solicitation Type Advertised

3. Contractor Qualification Prerequisites Yes - as specified in the Advertisement and in the

Information for Bidders

4. Background Qualification Questionnaire

(BQQ) requirement

Yes

5. Contract Documents contain Protected

Information

No

6. Bidders Question submission deadline Yes - 14 days prior to Bid Date

7. Bid Bond requirement Yes - 5% of Total Contract Price

8. Performance and Payment Bond requirement

Determination will be made prior to award

9. Contract Type Design-Bid-Build

10. Compensation Type Combination

11. Contract time to Final Completion 596 Calendar Days

12. Term of Contract N/A

13. Interim Milestone Completions No

14. Liquidated Damages for failure to

Complete on time

Yes - $3000 per Calendar Day

15. Wage Rates Davis Bacon (Federal)

16. MBE/WBE Participation subcontracting goals

N/A

S

Contract No. and Title: LGA-124.881 - Rehabilitation of Taxilane 0

17. DBE Goals (Subcontracting or DBE self-performed)

N/A

18. Insurance provided by Contractor Commercial Automobile Liability Insurance

19. Permits to be obtained by Contractor No

20. Area Available for Contractor's Use Yes - Refer to Contract Drawing G002

21. Materials Furnished by the Authority No

22. Building Information Modeling (BIM) requirements

No

23. Construction Staging/Phasing requirements

Yes - Refer to Division 01 and Contract Drawings

24. Sustainability requirements/Infrastructure Yes - Refer to Division 01

25. External Funding anticipated Yes - FAA

26. Buy America, BABA, Made in America No

27. Buy American, BABA, Made in America Yes

28. Maintenance Agreement No

Date Prepared: October 1, 2026

CONTRACT LGA-124.881

INFORMATION FOR BIDDERS

1. FORM AND SUBMISSION OF BIDS

The Port Authority of New York and New Jersey, hereinafter called the "Port Authority" or "Authority", invites bids (Bids) in the annexed form. Bids will be received until 2:30 PM on Thursday, November 5, 2026 via digital submission of Bids, using the Bonfire platform, at the link provided below.

Bidders must register and create a free Bonfire account at the provided link in order to log in and download Bid documents and associated information, and in order to upload Bid submissions.

Registration on the Bonfire platform requires a registration that is separate and distinct from all other Port

Authority software platforms.

Bid submissions must be uploaded, submitted and finalized prior to the Closing Time of 2:30 PM EST.

Bidders are strongly urged to allow sufficient time of at least one (1) day prior to Bids Due Date (Close

Date) to begin the uploading process and finalizing the Bid submission. Bidders will receive an email confirmation receipt with a unique confirmation number once a Bid submission is finalized.

The Authority will accept only those Bids in electronic format for which the submission or submission modification is completed at the time of the Bids Due Date.

The electronic copy of the Contract booklet furnished to each prospective bidder in portable document format (PDF) for the bidder’s use shall be filled out and submitted in its entirety to the Authority by the date and time that Bids are due. Bid submissions will be accepted by upload only, at:

https://panynj.bonfirehub.com/portal/?tab=login and must be uploaded and received by the Authority by 2:30 PM EST in order to be considered. Hand deliveries and mailed deliveries (e.g., UPS, USPS) will not be accepted.

Bidders will be permitted to submit modifications to Bids or withdraw previously submitted Bids electronically up to, but not after, the time of the Bid Due Date. The Authority may request an original, signed paper submission at any time following the Bid Due Date. If requested, such original, signed paper submission must be identical to the electronic submission. In the event of a discrepancy, the electronic submission shall control.

Bid results will be posted to the Port Authority of New York and New Jersey's website as soon as they are available, at the following link:

https://www.panynj.gov/port-authority/en/business-opportunities/preliminary-bid-results.html

Bid submissions must include all required information, as required by the clause hereof entitled "Papers

Accompanying Bids".

The Bid must be submitted upon the blank form bound herewith and must give all information required.

The Bid must be signed and the acknowledgment taken on the appropriate form following the Bid.

This Contract may be executed in any number of counterparts, and each such counterpart hereof shall be deemed an original instrument, but all such counterparts together shall constitute but one Contract. This

Contract may be signed by a party, either by hand, or with an electronic signature affixed digitally and in each case, this Contract may be personally delivered or sent by email or other electronic means after execution. Any such means of execution and transmittal shall have the same binding and legal effect.

No effort is made to emphasize any particular provision of the Contract, but bidders must familiarize themselves with every provision and its effect.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fpanynj.bonfirehub.com%2Fportal%2F%3Ftab%3Dlogin&data=02%7C01%7Clcherilus%40panynj.gov%7C9935df53700348b4f5a708d85036ab26%7Cc4484a25d0d84ad0916aa889b6aa7a02%7C0%7C0%7C637347544142355710&sdata=InBu2wOoM2kvJGPNhgQbfshyx7u19JFDA7ki09nvhUw%3D&reserved=0 https://www.panynj.gov/port-authority/en/business-opportunities/preliminary-bid-results.html

This Contract is to be funded in whole or in part by a grant from the Federal Aviation Administration

(FAA) under an agreement between FAA and the Authority. As a result, this Contract is subject to the requirements set forth in Sections 10 through 90 of the Part 1 General Contract Provisions and in Chapter

VII of the Form of Contract entitled "Federal Aviation Administration Requirements".

Title VI Solicitation Notice: As a condition of a grant award, the Authority shall demonstrate that it complies with the provisions of Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d et seq.) and implementing regulations (49 CFR Part 21) including amendments thereto, the Airport and Airway

Improvement Act of 1982 (49 U.S.C. § 47123), the Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.), Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), the Americans with

Disabilities Act of 1990 (42 U.S.C. § 12101, et seq.), U.S. Department of Transportation and Federal

Aviation Administration (FAA) Assurances, and other relevant civil rights statutes, regulations, or authorities, including any amendments or updates thereto. This may include, as applicable, providing a current Title VI Program Plan to the FAA for approval, in the format and according to the timeline required by the FAA, and other information about the communities that will be benefited and impacted by the project. A completed FAA Title VI Pre-Grant Award Checklist is required for every grant application, unless excused by the FAA. The Authority shall affirmatively ensure that when carrying out any project supported by this grant that it complies with all federal nondiscrimination and civil rights laws based on race, color, national origin, sex, creed, age, disability, genetic information, in consideration for federal financial assistance. The Department’s and FAA's Office of Civil Rights may provide resources and technical assistance to recipients to ensure full and sustainable compliance with Federal civil rights requirements. Failure to comply with civil rights requirements will be considered a violation of the agreement or contract and be subject to any enforcement action as authorized by law.

2. PREREQUISITES

The bidder shall submit the information required in A. of the clause of the Information for Bidders entitled "Qualification Information" with his Bid.

Company brochures alone shall not be submitted for the purpose of demonstrating experience and technical expertise. Submittals must be tailored to the specific requirements of this Contract.

If the bidder cannot demonstrate that it meets all of the required prerequisite qualifications, then the bidder may, with others, form a joint venture. The prerequisites will be considered satisfied if the joint venture itself, or any of its participants individually, can meet the requirements. If a joint venture which has not been established as a distinct legal entity submits a Bid, it and all participants in the joint venture shall be bound jointly and severally and each such participant in the joint venture shall execute the Bid and do each act and thing required by this Contract. All joint venture bidders must provide documentation of their legal status.

A Bid submitted by a bidder who does not meet the Qualification Information requirements will be considered non-responsive and the bidder's Bid will not be eligible for acceptance by the Authority.

3. PAPERS ACCOMPANYING BIDS

Each Bid must be accompanied by the following papers, which, unless otherwise indicated, should be enclosed with the Bid:

A. All information required by and pertaining to paragraph A. of the clause in the

Information for Bidders entitled "Qualification Information".

B. The bidder's Bid Submission Checklist filled in on the form furnished herewith.

C. The bidder's Analysis of Bid filled in on the form furnished via Notice to Bidders.

D. The bidder's information filled in on the "BID", "Signature and Certificate of Authority", and "Acknowledgement" forms furnished herewith in the clause in the Information for

Bidders entitled "Bid Forms".

1.) If the bidder be a corporation, a statement of the names and residences of its officers, which should be included on the page following the Bid.

2.) If the bidder be a partnership, a statement of the names and residences of its members, indicating which are general and which are special partners, which should be included on the page following the Bid.

3.) If the bidder be an individual, a statement of his residence, which should be included on the page following the Bid.

E. Certified financial statements, including applicable notes, reflecting the bidder's assets, liabilities, net worth, revenues, expenses, profit or loss and cash flow for the most recent calendar year or the bidder's most recent fiscal year. Where such certified financial statements are not available, then either reviewed or compiled statements from an independent accountant setting forth the same information. Such statements shall show the financial position of the bidder as of a date more than forty-five (45) days prior to the date on which Bids are opened. The bidder shall also submit a statement in writing signed by a duly authorized representative of the bidder, that the present financial condition of the bidder is at least as good as that shown on the statements submitted.

1.) Where neither certified financial statements nor financial statements from an independent accountant are available, then financial statements containing the information described in the paragraph above, prepared directly by the bidder. Such financial statements must be accompanied by a signed copy of the bidder's most recent Federal income tax return and a statement in writing, signed by a duly authorized representative of the bidder, that such statements accurately reflect the current financial condition of the bidder.

F. Either the Bid Bond bound herewith, in the penal sum of five percent (5%) of the

Estimated Total Contract Price, duly executed by the bidder as principal and by one or more surety companies duly authorized to carry on the business of suretyship in the state(s) in which the construction site is located, whose names appear on the current list of the Treasury Department of the United States as acceptable as sureties upon federal contracts; or, in lieu of a Bid Bond;

A certified check, payable to the order of The Port Authority of New York and New

Jersey, in the same amount required in the immediately preceding paragraph, which check shall be placed in an envelope marked "Bid Security" and enclosed with the Bid.

G. A statement of work which the bidder has on hand, including any work on which a bid has been submitted, containing a description of the work, the dollar value, the location by city and state, the current percentage of completion and the expected date for completion.

H. The name and address of the bidder's chief banking representative handling the bidder's account filled in on the "Banking Information, Employer Identification Number and

Credit Service Account" form furnished herewith in the clause of the Information for

Bidders entitled "Bid Forms".

I. The bidder's Federal Employer Identification Number (i.e., the number assigned to firms by the Federal Government for tax purposes); the bidder's Dun and Bradstreet number, if any; the name of any other credit service to which the bidder has furnished information and the number, if any, assigned by such service to the bidder's account filled in on the

"Banking Information, Employer Identification Number and Credit Service Account" form furnished herewith in the clause of the Information for Bidders entitled "Bid

Forms".

J. The bidder's unit prices and the Lump Sum for Unclassified Work inserted in the form furnished herewith in the clause of the Information for Bidders entitled "Bid Forms".

The amounts must be given both in figures and in writing and, in case of discrepancy, the writing shall control. The unit prices must be extended and totaled. The Estimated Total for Classified Work and the Lump Sum for Unclassified Work must be entered in the recapitulation and totaled.

K. One copy of each addendum, if any, issued during the bidding period shall be initialed and included with the Bid, but any Bid submitted without such addendum initialed and attached will nevertheless be construed as though such addendum had been initialed and attached.

L. A Certification Regarding Lobbying Pursuant to 31 U.S.C. 1352 and a Certification regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion - Lower Tier

Covered Transactions, pursuant to Chapter VII of the Form of Contract entitled "Federal

Aviation Administration Requirements", on the form furnished herewith in the clause of the Information for Bidders entitled "Bid Forms".

M. A Certification Regarding Tax Delinquency and Felony Convictions, pursuant to Chapter

VII of the Form of Contract entitled "Federal Aviation Administration Requirements", on the form furnished herewith in the clause of the Information for Bidders entitled "Bid

Forms".

N. A Certification of Compliance with FAA Buy American Preference, pursuant to

Chapter VII of the Form of Contract entitled "Federal Aviation Administration

Requirements", on the form furnished herewith in the clause of the Information for

Bidders entitled "Bid Forms".

4. QUALIFICATION INFORMATION

A. Each bidder shall submit with his Bid the information requested in A.1) below in electronic format, either Microsoft Word or Adobe PDF. This information shall be presented in an organized fashion and shall be categorized and sub-categorized in exact accordance with the following paragraphs.

1.) The bidder must demonstrate to the satisfaction of the Authority that it, or the entity performing the applicable work, meets the minimum requirements stated below to the satisfaction of the Chief Engineer. If the bidder cannot demonstrate that it, and the entity performing the applicable work, meets all of the below mentioned qualifications, then the bidder may, with others, satisfy the requirements by forming a joint venture and demonstrate that the joint venture itself, or any of its participants individually, meet the requirements. The bidder may also qualify if the bidder or persons or entities owning and controlling the bidding firm shall have satisfactorily met, as owning and controlling another firm, the below mentioned requirements.

a. That the bidder has completed (or substantially completed) as a prime or general contractor at least two contracts of type, size and complexity comparable to the

Work of this Contract within an Air Operations Area (AOA) within the past ten years.

b. That the bidder's full-time project manager and full-time Superintendent each have a minimum of five years of construction experience on contracts of type, size and complexity comparable to the Work of this Contract within operating airport environment in areas within an active AOA.

B. At any time after the opening of Bids, the Chief Engineer may give oral or written notice to one or more bidders to attend a pre-award meeting and to furnish the Authority with information relating to his qualifications to perform the Work, including the following, which information shall be furnished within seven (7) days thereafter, or as otherwise indicated:

1.) A detailed list of all anticipated material suppliers and subcontractors and a detailed list of the plant and equipment which the bidder proposes to use, indicating which portions it already possesses.

2.) Detailed information relating to work which the bidder has completed for others, including personal and corporate references, sufficient to the Authority to determine the bidder's responsibility, experience and capacity to perform the Work. If required by the Chief Engineer, the foregoing information shall include information to demonstrate to the satisfaction of the Chief Engineer that the bidder has within the past five years been a contractor on at least one contract of the same general type, extent and complexity as the contract on which the Bid has been submitted, and completed the work skillfully, in a satisfactory manner and on time.

3.) Information to supplement a) data shown in the financial statements and the statement of work on hand required to be submitted with the Bid; and b) any statement submitted under the clauses hereof entitled "Certification of No

Investigation (Criminal or Civil Anti-Trust), Indictment, Conviction, Suspension, Debarment, Disqualification, Prequalification Denial or Termination, Etc.; Disclosure of Other Required Information", "Certification of Participation in a State-Registered

Apprenticeship Program" or "Non-Collusive Bidding and Code of Ethics

Certification; Certification of No Solicitation Based on Commission, Percentage, Brokerage, Contingent Fee or Other Fee".

4.) Moreover, in the event that the bidder's performance on a past Port Authority or

PATH contract or contracts has been rated less than satisfactory (e.g., received a

Performance Evaluation rating of Marginal or Unsatisfactory) within three years prior to submission of his Bid, the Chief Engineer, or his or her designee, may request the bidder furnish information demonstrating to the satisfaction of the Chief

Engineer, or his or her designee, that, notwithstanding such rating, the root cause of the adverse performance has been identified and definitively corrected or the circumstances giving rise to the rating have changed and will not reoccur.

5.) If the bidder has performed a contract for the States of New York or New Jersey, or any governmental entity within such States and has filed a questionnaire or other document required to be submitted in order for the bidder to qualify to perform the contract, the bidder may be requested by the Chief Engineer to submit the most recent completed questionnaire or other such document, or if the most recent completed questionnaire or other such document is not available, to submit a written statement indicating the approximate date of the contract and the name of the governmental entity which awarded them the contract.

6.) Any additional information relevant to the bidder's Bid including information to supplement the bidder's Analysis of Bid.

7.) The bidder shall submit a complete Background Qualification Questionnaire (BQQ), required for himself and all subcontractors and vendors known to the bidder at the time of submission of Bids, who will be providing services under this Contract, if the value of such subcontract is anticipated to be greater than or equal to $100,000. This document and instructions for submitting the completed BQQ to the Authority's

Office of Inspector General can be obtained at the Authority's website through the following link:

https://www.panynj.gov/port-authority/en/help-center/oig.html

In the event that any of the foregoing in B. above is requested and is not furnished within seven days thereafter or as otherwise indicated, or within such additional time as the Chief Engineer, in his sole discretion, may allow, the Authority may not be in a position to determine whether the bidder is qualified, whether the bidder understands the requirements of the contract or whether the bid is responsive and may, in its sole discretion, reject the bidder's Bid.

In the event that the Chief Engineer or his or her designee finds, in his or her sole discretion, that the bidder has not satisfactorily demonstrated that the circumstances surrounding a Marginal or

Unsatisfactory Performance Evaluation rating have been successfully mitigated, the Authority may determine that award to the bidder is not in the best interest of the Authority and may, in its sole discretion, remove the bidder from consideration for award. In making such a determination, the Chief

Engineer or his or her designee may initiate a hearing at which time the Contractor will have to demonstrate to a committee of Port Authority staff that the circumstances leading to the Marginal or

Unsatisfactory Performance Evaluation rating have been mitigated and that the factors that led to the rating are no longer applicable. The determination of the Chief Engineer or his or her designee will be conclusive.

The giving of such notice to the bidder in connection with any of the foregoing lists, statement or information shall not be construed as an acceptance of his Bid. However, the Authority reserves the right in its sole and absolute discretion, to accept the Bid of a bidder despite the fact that said bidder has not submitted any information, list or statement required pursuant to this Section within the above-stated time period.

5. ACCEPTANCE OR REJECTION OF BID

Within ninety (90) days after the opening of the Bids, the Authority will accept one of the Bids, if it accepts any. Award will be made to the responsible bidder that submits the lowest responsive, technically qualified Bid. The Authority reserves the unqualified right, in its sole and absolute discretion, to reject all

Bids or to waive defects in any Bids.

https://www.panynj.gov/port-authority/en/help-center/oig.html

The acceptance of a Bid will be made only by mailing to or delivering at the office designated in the Bid a notice in writing specifically indicating acceptance signed by an authorized representative on behalf of the

Authority who is at present the Authority's Chief Procurement Officer. No other act of the Authority, its

Commissioners, officers, agents, or employees shall constitute acceptance of a Bid. Such notice will state whether or not the Authority elects to require the bidder to furnish a Performance and Payment Bond.

Rejection of a Bid will be made only by either (a) a notice in writing specifically stating that the Bid is rejected, signed by an authorized representative on behalf of the Authority who is at present the

Authority's Chief Procurement Officer and mailed to or delivered at the office designated in the Bid or (b) omission by the Authority to accept a Bid within ninety (90) days after the opening of Bids; and no other act of the Authority, its Commissioners, officers, agents or employees shall constitute rejection of a Bid, including any counter offer or other act of the Authority, its Commissioners, officers, agents or employees.

In the event that a successful bidder defaults upon the Contract by failing to furnish a satisfactory

Performance and Payment Bond, if required, and the Authority terminates the Contract, the Authority reserves the option to accept the next lowest responsive, technically qualified Bid of any other bidder within ninety (90) days after the opening of Bids, in which case such acceptance shall have the same effect as to such next bidder as though he were the originally successful bidder.

6. RETURN OF CERTIFIED CHECKS

Within ten (10) days after the opening of the Bids the Authority will return all certified checks deposited by bidders, except those deposited by three bidders to be selected by the Authority, which will be returned within three days after one Bid is accepted by the Authority; or if a Performance and Payment Bond is required, within three days after a satisfactory Performance and Payment Bond is furnished to the

Authority; or if all Bids are rejected, not later than three days after such rejection. The return of a bidder's check shall not, however, be deemed to be a rejection of his Bid.

7. WEBSITE POSTINGS OF CONTRACT DOCUMENTS

Recipients of Contract documents marked Confidential (Privileged) may not post them or any of them to a website except in accordance with the Authority's prior written approval, which may require a written non-disclosure agreement.

Recipients of Contract documents not marked Confidential (Privileged) may not post them or any of them to a website unless the website (1) is non-public, (2) is password protected and (3) is accessible only to the recipient's prospective subcontractors and suppliers. Recipient's prospective subcontractors and suppliers shall also be deemed recipients and shall be required to conform to the terms of this numbered clause. Recipients shall be deemed to include both bidders and those who do not submit bids.

No later than 180 days after the date of receipt of Bids, all recipients shall remove all Contract documents from their websites.

8. DISPOSAL OF CONTRACT DOCUMENTS

All recipients of Contract documents, including bidders and those who do not bid and their prospective subcontractors and suppliers who may receive all or a part of the Contract documents or copies thereof, shall make every effort to ensure the secure and appropriate disposal of the Contract documents to prevent further disclosure of the information contained in the documents. Secure and appropriate disposal includes methods of document destruction such as shredding or arrangements with refuse handlers that ensure that third persons will not have access to the documents' contents either before, during, or after disposal. Documents may also be returned for disposal purposes to the Contract Desk on the 1st Floor, 2 Montgomery Street, Jersey City, NJ 07302 or the office of the Chief Procurement Officer, 4 World

Trade Center, 150 Greenwich Street, 21st Floor, New York, NY 10007.

9. AVAILABLE DOCUMENTS

Certain documents, specified below, are available for reference and examination by bidders by contacting

Jose Cartagena at (201) 395-3508 or email – jcartage@panynj.gov during regular business hours. These documents were not prepared for the purpose of providing information for bidders upon the present

Contract but they were prepared for other purposes, such as for other contracts or for design purposes for this or other contracts, and they do not form a part of this Contract. The Authority makes no representation or guarantee as to, and shall not be responsible for their accuracy, completeness or pertinence, and, in addition, shall not be responsible for the conclusions to be drawn therefrom. They are made available to the bidders merely for the purpose of providing them with such information as is in the possession of the Authority, whether or not such information may be accurate, complete or pertinent or of any value to the bidders. Questions concerning the content of the documents shall be submitted in accordance with the clause entitled "Questions by Bidders".

Said documents are as follows:

A. Drawings bearing the general title "THE PORT AUTHORITY OF NY & NJ -

LAGUARDIA AIRPORT – REHABILITATION OF TAXILANE 0", dated 08/19/2026, and are separately numbered and entitled as follows:

LGA-SL-491 PROJECT SITE MAP, BORING LOCATION PLAN, GENERAL NOTES,

LEGEND, ABBREVIATIONS & SYMBOLS, SOIL CLASSIFICATIONS

LGA-SL-492 PRESENTATION OF BORINGS

NOTE: For the bidder's convenience, Available documents will be transmitted with the

Contract documents, except for asterisked items which are available for examination by bidders as otherwise specified above.

10. DISADVANTAGED BUSINESS ENTERPRISES PROGRAM (DBE)

A. Policy

The requirements of 49 CFR Part 26 and any amendments thereto apply to this Contract, including the United States Department of Transportation (USDOT) Interim Final Rule issued on October 3, 2025, which removed race-and sex-based presumptions of social and economic disadvantage, and provides that no DBE goals may be set until a Unified

Certification Program (UCP) completes the reevaluation process delineated in 49 CFR

26.111. It is the policy of the Port Authority to practice nondiscrimination based on race, color, sex, or national origin in the award or performance of this Contract. The Port

Authority encourages participation by all firms qualifying under this solicitation regardless of business size or ownership.

B. Definitions

To avoid undue repetition, the following terms, as used in this numbered clause, shall be construed as follows:

1.) "Certification" means the process by which a business demonstrates to the

Authority's Office of Business Opportunity (OBO) or to a New York State Unified

Certification Program Certifying Partner (NYSUCP) or to a New Jersey Unified

Certification Certifying Partner (NJUCP) that it meets the requirements to be a DBE under USDOT regulations set forth in 49 CFR Part 26.

2.) "Disadvantaged Business Enterprise" or "DBE" is a for-profit small business concern

(a) that is at least 51% owned by one or more individuals who are socially and economically disadvantaged or, in the case of a corporation, in which at least 51% of the stock is owned by one or more such individuals; and (b) whose management and daily business operations are controlled by one or more of the socially and economically disadvantaged individuals who own it.

3.) "New York State Unified Certification Program Certifying Partners" include the Port

Authority of New York and New Jersey, Metropolitan Transportation Authority, the

Niagara Frontier Transportation Authority and the New York State Department of

Transportation.

4.) "New Jersey Unified Certification Program Certifying Partners" include the Port

Authority of New York and New Jersey, New Jersey Transit and the New Jersey

State Department of Transportation.

5.) "Socially and economically disadvantaged individual" means any individual who is a citizen (or lawfully admitted permanent resident) of the United States and who is:

a. Any individual that OBO or a NYSUCP or NJUCP Certifying Partner finds to be a socially and economically disadvantaged individual on a case-by-case basis.

b. Any individual who is a citizen (or lawfully admitted permanent resident) of the

United States and who a certifier finds to be socially and economically disadvantaged on a case-by-case basis. A determination that an individual is socially and economically disadvantaged must not be based in whole or in part on race or sex. For that reason, all applicants shall qualify as socially and economically disadvantaged if they can meet the relevant criteria described in §

26.67. Being born in a particular country does not, standing alone, mean that a person is necessarily socially and economically disadvantaged.

C. DBE Goal

DBE Participation Goal: In accordance with 49 CFR Part 26, as amended on October 3, 2025, there is no specific DBE contracting goal required for this Contract.

OBO is responsible administering the Authority's DBE Program. OBO may be contacted at the following email and address:

Contract No: LGA-124.881

Email: bus-diversity-compliance-management@panynj.gov

Address: The Port Authority of NY & NJ

2 Montgomery Street, 2nd Floor

Jersey City, NJ 07302

D. DBE Program

The Authority has established a DBE Program in accordance with applicable USDOT regulations in 49 CFR Part 26. The Authority receives Federal financial assistance from the Department of Transportation, and as a condition of receiving this assistance, the

Authority has signed an assurance that it will comply with these regulations

The Director of OBO has been delegated as the DBE Liaison Officer. In that capacity, the Director of OBO is responsible for implementing all aspects of the DBE Program.

Implementation of the DBE Program is accorded the same priority as compliance with all other legal obligations incurred by the Authority in its financial assistance agreements with the USDOT.

mailto:bus-diversity-compliance-management@panynj.gov

The Authority has disseminated this policy statement to the Board of Commissioners and all the components of the Authority's organization. The Authority has also disseminated this statement to DBE and non-DBE business communities that perform work for the

Authority on USDOT-assisted contracts through posting on the Authority website:

http://www.panynj.gov/business-opportunities/sd-getting-started.html

E. DBE Obligation

The successful bidder (Contractor), subrecipients or any of its subcontractors shall not discriminate on the basis of race, color, national origin, or sex in the performance of this

Contract. The Contractor shall carry out applicable requirements of 49 CFR Part 26, including any amendments thereto, in the award and administration of USDOT-assisted contracts. Failure by the Contractor or subcontractor to carry out these requirements is a material breach of this Contract, which may result in the termination of this Contract or such other remedy as the Authority deems appropriate, which may include, but is not limited to:

(1) Withholding monthly progress payments;

(2) Assessing sanctions;

(3) Liquidated damages; and/or

(4) Disqualifying the Contractor from future bidding as non-responsible.

Furthermore, the Contractor shall include the foregoing language of this subparagraph E.

in its subcontracts resulting from this Contract, and further agrees to provide the

Authority with copies of its subcontracts with its request for subcontractor approval, as well as upon request of the Authority.

F. Submission of DBE Utilization Plan

Not used.

G. Prompt Payment and Retainage

The successful bidder agrees to pay each subcontractor under this Contract for the satisfactory performance of its contract as provided in the clause in Chapter II of the

Form of Contract entitled "Prompt Payment and Retainage". Failure to comply with this provision may constitute a breach of contract, entitling the Authority to remedies provided herein, in addition to any other available remedy.

H. Credit Toward DBE Goal

Not used.

I. Contract Award

Not used.

J. DBE Modifications

Not used.

http://www.panynj.gov/business-opportunities/sd-getting-started.html https://www.ecfr.gov/current/title-49/subtitle-A/part-26

K. Office of the Inspector General

The Authority's Office of Inspector General (OIG) is responsible for investigating fraud and misconduct by Authority contractors, subcontractors, consultants, suppliers and others, including the DBE Program. Depending upon the dollar value of the construction project, and regulatory requirements, the OIG might engage the services of an Integrity

Monitor who reports to the OIG and assists in monitoring compliance governing the DBE

Program.

The OIG…